西罗园二区商住楼
消防系统设备安装工程
施工组织设计
北京中消伟业安全技术工程有限公司二零零四年三月二十五日
施工组织设计(计划书)审批表
施工组织设计(计划书)审批会签表
前言
西罗园二区商住楼是公司在北京投资兴建大型住宅小区。该工程建成后将在丰台区发展起到举足轻重的作用,故该工程消防系统设备及安装质量的优劣显得十分重要。
本次工程图纸中所涉及的消防系统设备安装工程,为我公司之施工项目。根据业主在招标书中的要求,我们依据设计图纸,编制了“西罗园二区商住楼消防系统设备安装工程施工组织设计”书。概述了工程项目的专业特点、施工前的准备工作、施工安排布署和要求、详细的工程施工方案和机具计划表、主要的施工方法和施工依据、工程质量和安全保证措施以及对业主应尽的义务。
为圆满完成本工程,我们将按照已获得ISO-9000质量保证体系认证的要求,对工程的投标、施工管理、交付及服务进行全过程的质量管理和控制,严格恪守本公司的质量方针和质量目标,即信守合同,精心施工,保证质量,竭诚服务。工程一次验收合格率100%,保证本投标项目达到国家颁布的有关施工及验收的优良标准,并积极配合总包工程做好各项工作。
鉴于时间仓促,本施工计划书在编写的内容方面还不尽完善,有待于今后在各项具体施工方案和技术措施中加以补充。
目录
第一章工程概况 ··························································· 1.1 第二章施工项目工程特点 ··············································· 2.1
一、火灾自动报警系统及其联动系统 ····························· 2.1
二、室内消火栓系统 ·················································· 2.1
三、自动喷水灭火系统 ··············································· 2.2第三章施工准备工作 ····················································· 3.1
一、人员准备 ··························································· 3.1
二、设备选型、主材的审定 ········································· 3.1
三、现场临时设施 ····················································· 3.2
四、技术准备工作 ····················································· 3.2 第四章施工进度计划 ····················································· 4.1
一、工程进度计划 ····················································· 4.1
二、劳动力计划 ························································ 4.1
三、施工机具计划 ····················································· 4.1 第五章主要施工方法和技术措施 ······································ 5.1
一、火灾自动报警系统及其联动控制系统 ······················· 5.1
二、自动喷水、消火栓灭火系统 ··································· 5.8 第六章施工执行的规程、规范、技术标准和图集 ················· 6.1 第七章工程质量管理和工程综合管理措施 ·························· 7.1
一、工程质量管理 ····················································· 7.1
二、成品保护措施 ····················································· 7.4
三、消防措施 ··························································· 7.5
四、现场保卫措施 ····················································· 7.5
五、安全生产措施 ····················································· 7.6
六、雨季施工措施 ····················································· 7.7 第八章工程档案 ··························································· 8.1 第九章竣工交接与服务承诺 ············································ 9.1
一、质量目标 ··························································· 9.1
二、工程的服务与承诺 ··············································· 9.1
三、竣工图编制移交 ·················································· 9.1 附表:
附表一:管理人员组织结构表
附表二:劳动力需用计划表
附表三:施工机具计划表
附件四:报警设备简介