中国牛人外文翻译
- 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
- 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
- 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。
ORIGINAL PAPER
Stability assessment of a slope under a transformer substation using numerical modelling
H.J.Li •F.C.Dai •W.C.Li •L.Xu •
H.Min
Received:2April 2010/Accepted:26July 2010/Published online:17September 2010ÓSpringer-Verlag 2010
Abstract This paper presents an analysis of the defor-mation mechanism and stability assessment of a slope in Yunnan Province,China.Field investigations indicated that the deformation of the slope was caused by the com-bined effects of the unfavorable topographical,geological and hydrogeological conditions and the placement of man-made fill.The stability of the slope was assessed by 3D numerical modeling which showed that the factor of safety of the slope was 1.1in the natural state but reduced to 1.03after fill was placed.Pile reinforcement was undertaken,which raised the factor of safety to 1.27.
Keywords Fill slope ÁDeformation mechanism ÁNumerical modelling ÁStrength reduction
Re
´sume ´L’article pre ´sente une analyse du me ´canisme de de
´formation et une e ´valuation de la stabilite ´d’une pente dans la province de Yunnan,en Chine.Les travaux de
terrain ont indique
´que la de ´formation de la pente re ´sultait d’effets combine
´s en rapport avec des conditions topo-graphiques,ge
´ologiques et hydroge ´ologiques de ´favorables et la construction d’un stabilite
´de la pente a e
´te ´e ´value ´e a `l’aide d’une simulation nume ´rique 3D qui a montre
´que le facteur de se ´curite ´de la pente valait 1,1en conditions naturelles mais passait a
`1,03apre `s construction du remblai.Des renforcements par pieux ont e
´te ´re ´alise ´s,ce qui a fait passer le coefficient de se
´curite ´a `1,27.Mots cle
´s Remblai sur pente ÁMe ´canisme de de
´formation ÁSimulation nume ´rique ÁDiminution de re
´sistance Introduction
In order to develop the provincial economy and satisfy the need for power,a 220kV transformer substation was constructed in Yanjin,located in northeastern Yunnan Province,PR China.The construction of the transformer substation commenced in November 2004,and the site was filled in March 2005.The total volume of cut and fill was 152,000m 3.The compaction was accomplished using a sheeps-foot roller with a layer thickness of 200mm.
During heavy rainfall between July 18and July 20,2005,a creeping slide was observed in the slope at the northwest of the construction site.It led to tensile cracks in the retaining wall with a maximum crack width of 20cm.Meanwhile,the foundation of the 110kv framework located on the top of the slope subsided by 29cm.The moving slope was 340m long and 100m wide.The unstable slope threatened the safety of the transformer substation,the end tower of the 110kv power output and the lives and prop-erties of the residents nearby.After deformation,the fill slope was reinforced immediately with 23rectangular piles in the northwest of the site and 41circular piles in two rows at the northwestern corner of the site.Each rectangular pile
H.J.Li (&)
Institute of Mine Safety Technology,China Coal Research Institute,
Beijing 100013,People’s Republic of China e-mail:geolhj@
F.C.Dai ÁW.C.Li ÁL.Xu
Institute of Geology and Geophysics,
Chinese Academy of Sciences,P.O.Box 9825,Beijing 100029,People’s Republic of China H.Min
Institute of Rock and Soil Mechanics,Chinese Academy of Sciences,
Wuhan 430071,People’s Republic of China
Bull Eng Geol Environ (2011)70:385–394DOI 10.1007/s10064-010-0318-7