PM-EN(oct30)

合集下载
相关主题
  1. 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
  2. 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
  3. 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。

Total01-Jan-1528-Feb-17564 2 X 35 MW

2 X 35 MW COGENERATION POWER PLANT M/S PT. WILMAR ...01-Jan-1528-Feb-17564

A1020Basic Design Complete30-Apr-150 A1030Detail Design Complete30-Oct-150 A1040Boiler Erection & Installation start01-Jun-150 A1048Boiler 1 Hydraulic Test Complete02-Mar-160 A1049Boiler 2 Hydraulic Test Complete31-May-160 A1054Water Treatment Plant Commissioning complete31-May-160 A10566kV Power have provided(Purchaser's scope)16-Mar-160 A1059Boiler 1 Ignition07-Jul-160 A1060Boiler 2 Ignition07-Dec-160 A1065STG Erection & Installation start01-Jan-160 A10701# STG Synchronisation19-Sep-160 A10711# STG Full Load Operation30-Sep-160 A10722# STG Synchronisation15-Feb-170 A10802# STG Full Load Operation28-Feb-170 Engineeri

Engineering01-Jan-1530-Oct-15217 A1000Civil foundation load data - Boiler & Aux Columns30-Jan-150 A1005Civil foundation load data - ESP & Other30-Apr-150 A1010Civil foundation load data -STG & Aux30-Apr-150 E1000Basic Design01-Jan-15*28-Apr-1584 E1010Basic Design Review Meeting29-Apr-15*30-Apr-152 E1020Detail Design01-May-15*28-Oct-15129 E1030Detail Design Review Meeting29-Oct-15*30-Oct-152 Procurem

Procurement01-Jan-1530-Jun-16391 P1000MRQ:Long-Preriod equipment; return imformation fr...01-Jan-15*27-Feb-1542 P1010TBA/CBA/SBA:Long-Preriod equipment02-Feb-15*02-Apr-1544 P1020PO Issue(MRP):Long-Preriod equipment02-Mar-15*29-Apr-1543 P1030MRQ:Aux equipment; return imformation from supplier01-Apr-15*15-May-1533 P1040TBA/CBA/SBA:Aux equipment30-Apr-15*12-Jun-1532 P1050PO Issue(MRP):Aux equipment18-May-15*01-Jul-1533 P1055Anchor Bolt Deliver to site for Boiler 1&225-Mar-15*30-Apr-1527 P10581st Part of Steel Structure for Boiler 1 Deliver to site27-Apr-15*29-May-1525 P1060Deliver to Site:Long-Preriod equipment01-Oct-15*30-Jun-16196 P1070Deliver to Site:Aux equipment01-Jan-16*30-Jun-16130 Constract

Constraction02-Feb-1528-Feb-17542 C0960Design & constraction Civil Foundation Boiler & Aux ...02-Feb-15*30-Jun-15107 C0970Design & constraction Civil Foundation ESP & Other...01-May-15*30-Sep-15109 C0980Design & constraction 1# STG Pedestal,TG Building...01-May-15*31-Dec-15175 C0990Design & constraction 2# STG Pedestal,TG Building...01-May-15*29-Jan-16196 C1000Civil Foundation Boiler & Aux Columns complete01-Jun-15*01-Jun-151 C1005Civil Foundation ESP & Other Auxiliaries complete01-Oct-15*01-Oct-151Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

28-Feb-17, Total

28-Feb-17, 2 X 35 MW Basic Design Complete

Detail Design Complete

Boiler Erection & Installation start

Boiler 1 Hydraulic Test Complete

Boiler 2 Hydraulic Test Complete

Water Treatment Plant Commissioning complete

6kV Power have provided(Purchaser's scope)

Boiler 1 Ignition

Boiler 2 Ignition

STG Erection & Installation start

1# STG Synchronisation

1# STG Full Load Operation

2# STG Synchronisatio

2# STG Full Load Op

30-Oct-15, Engineering

Civil foundation load data - Boiler & Aux Columns

Civil foundation load data - ESP & Other

Civil foundation load data -STG & Aux

Basic Design

Basic Design Review Meeting

Detail Design

Detail Design Review Meeting

30-Jun-16, Procurement

MRQ:Long-Preriod equipment; return imformation from supplier

TBA/CBA/SBA:Long-Preriod equipment

PO Issue(MRP):Long-Preriod equipment

MRQ:Aux equipment; return imformation from supplier

TBA/CBA/SBA:Aux equipment

PO Issue(MRP):Aux equipment

Anchor Bolt Deliver to site for Boiler 1&2

1st Part of Steel Structure for Boiler 1 Deliver to site

Deliver to Site:Long-Preriod equipment

Deliver to Site:Aux equipment

28-Feb-17, Constract Design & constraction Civil Foundation Boiler & Aux Columns(Purchaser's scope)

Design & constraction Civil Foundation ESP & Other Auxiliaries(Purchaser's scope)

Design & constraction 1# STG Pedestal,TG Building & EOT Crane(Purchaser's scope)

Design & constraction 2# STG Pedestal,TG Building & EOT Crane(Purchaser's scope)

Civil Foundation Boiler & Aux Columns complete

Civil Foundation ESP & Other Auxiliaries complete

实际尚需关键尚需工作

里程碑

汇总

Page 1 of 2 2 X 35 MW COGENERATION POWER PLANT

M/S PT. WILMAR NABATI INDONESIA

相关文档
最新文档