Geotechnical Monitoring of Excavation Work: An Internship Report.
Introduction.
This report presents the findings of an internship at [Company Name], where the intern participated in the geotechnical monitoring of an excavation project. The project involved the excavation of a deep foundation pit for a new building in downtown [City Name]. The intern's responsibilities included installing and monitoring instrumentation, collecting and analyzing data, and providing recommendations to the project team.
Methodology.
The geotechnical monitoring program included the
following:
Installation of piezometers to monitor groundwater levels.
Installation of inclinometers to measure lateral movement of the excavation walls.
Installation of extensometers to measure vertical movement of the excavation floor.
Daily monitoring of instrumentation readings.
Weekly analysis of data and generation of reports.
Results.
The results of the geotechnical monitoring program showed that the excavation work was progressing safely and without any significant geotechnical issues. The groundwater levels remained stable throughout the excavation process. The lateral movement of the excavation
walls was within the allowable limits. The vertical movement of the excavation floor was also within the allowable limits.
Recommendations.
Based on the results of the geotechnical monitoring program, the intern made the following recommendations:
Continue with the current monitoring plan.
Increase the frequency of inclinometer readings if lateral movement increases.
Install additional instrumentation if any unexpected geotechnical conditions are encountered.
Conclusion.
The geotechnical monitoring program played a critical role in ensuring the safety of the excavation work and the adjacent structures. The intern's work contributed to the
successful completion of the project.
中文回答:
基坑监测实习报告。
前言。
本报告介绍了实习生在 [公司名称] 参加基坑开挖工程岩土监
测的调研结果。
该项目包括为 [城市名称] 市中心一座新建筑开挖
一个深基坑。
实习生的职责包括安装和监测仪器、收集和分析数据,并向项目团队提供建议。
方法。
岩土监测计划包括以下内容:
安装测压计以监测地下水位。
安装测斜仪以测量开挖侧壁的横向位移。
安装伸缩计以测量开挖底板的竖向位移。
日常监测仪器读数。
每周分析数据并生成报告。
结果。
岩土监测计划的结果表明,开挖工作正在安全进行,没有出现
任何重大岩土问题。
整个开挖过程中,地下水位保持稳定。
开挖侧
壁的横向位移在允许范围内。
开挖底板的竖向位移也在允许范围内。
建议。
根据岩土监测计划的结果,实习生提出了以下建议:
继续执行当前监测计划。
如果横向位移增加,增加测斜仪读数频率。
如果遇到任何意外岩土条件,安装额外的仪器。
结论。
岩土监测计划在确保开挖工作和周围建筑物的安全方面发挥了至关重要的作用。