夜间施工申请表

合集下载

建筑工地夜间施工证明

建筑工地夜间施工证明

建筑工地夜间施工证明
一、办理依据
《中华人民共和国环境噪声污染防治法》、《山东省环境噪声污染防治条例》。

二、办理条件
因特殊需要必须在夜间连续作业的,需完成夜间施工申请表等相关材料。

1、确因工艺需要或其他特殊原因,必须夜间(22时至次日6时)施工;
2、因抢险、抢险等应急施工及其他特殊原因确需夜间施工;
3、市政工程(道路、桥梁、地下管网等)建设确需夜间施工;
4、项目所处地比较敏感,必须进行公示;
5、连续作业前3天申报。

三、办理程序
1、受理;
2、现场勘察;
3、出具证明。

四、提交材料
1、施工单位提报关于夜间连续施工作业的申请报告(1份);
2、施工工程初次申请夜间施工审批的,需提交工程施工进度表(原件及复印件各1份);
3、县级以上人民政府或者有关主管部门的证明(原件1份);
4、授权委托书(原件1份);
5、公众意见表(原件1份)。

五、办理期限
2个工作日。

六、收费依据及标准
不收费。

建筑工地夜间施工许可证办理流程

建筑工地夜间施工许可证办理流程

建筑工地夜间施工许可证办理流程下载温馨提示:该文档是我店铺精心编制而成,希望大家下载以后,能够帮助大家解决实际的问题。

文档下载后可定制随意修改,请根据实际需要进行相应的调整和使用,谢谢!并且,本店铺为大家提供各种各样类型的实用资料,如教育随笔、日记赏析、句子摘抄、古诗大全、经典美文、话题作文、工作总结、词语解析、文案摘录、其他资料等等,如想了解不同资料格式和写法,敬请关注!Download tips: This document is carefully compiled by theeditor.I hope that after you download them,they can help yousolve practical problems. The document can be customized andmodified after downloading,please adjust and use it according toactual needs, thank you!In addition, our shop provides you with various types ofpractical materials,such as educational essays, diaryappreciation,sentence excerpts,ancient poems,classic articles,topic composition,work summary,word parsing,copy excerpts,other materials and so on,want to know different data formats andwriting methods,please pay attention!夜间建筑工地施工许可证的办理流程详解在城市的发展进程中,建筑工地的夜间施工已经成为一种常态。

夜间和特殊时期建筑施工作业核准依据

夜间和特殊时期建筑施工作业核准依据

夜间和特殊时期建筑施工作业核准依据、规定和程序一、法律依据(一)《中华人民共和国环境噪声污染防治法》第二十九条在城市市区范围内,建筑施工过程中使用机械设备,可能产生环境噪声污染的,施工单位必须在工程开工十五日以前向工程所在地县级以上地方人民政府环境保护主管部门申报该工程的项目名称、施工场所和期限、可能产生的环境噪声值以及所采取的环境噪声污染防治措施的情况。

第三十条在城市市区噪声敏感建筑物集中区域内,禁止夜间进行产生环境噪声污染的建筑施工作业,但抢修、抢险作业和因生产工艺上要求或者特殊需要必须连续作业的除外。

因特殊需要必须连续作业的,必须有县级以上人民政府或者其有关主管部门的证明。

前款规定的夜间作业,必须公告附近居民。

第五十六条建筑施工单位违反本法第三十条第一款的规定,在城市市区噪声敏感建筑物集中区域内,夜间进行禁止进行的产生环境噪声污染的建筑施工作业的,由工程所在地县级以上地方人民政府环境保护行政主管部门责令改正,可以并处罚款。

)《建筑施工场界环境噪声排放标准》(GB12523-90)1、适用范围本标准适用于城市建筑施工期间施工场地产生的噪声。

2、标准值2.1 不同施工阶段作业噪声限值列于下表:等效声级Leq[dB(A)]2.2 表中所列噪声值是指与敏感区域相应的建筑施工场地边界线处的限值。

2.3 如有几个施工阶段同时进行,以高噪声阶段的限值为准。

3、监测方法本标准的建筑施工场地边界线处的等效声级测量应按GB12524《建筑施工场界噪声测量方法》进行。

二、相关要求(一)管理职能分工1、对建筑施工的建设和施工单位执行环境保护法律制度的日常监督检查,由工地所在地辖区环保部门负责。

跨区工程项目由市环保局施工噪声管理办公室监督检查。

2、对夜间施工噪声污染扰民投诉的查处,按照属地管理原则由工地所辖区环保局负责。

跨区域工程项目夜间施工投诉和多次反映强烈的投诉原则上由市环保局环境监察支队负责查处。

3、按照全市集中统一管理的要求,市施工噪声管理办公室可以对全市范围内违法施工噪声扰民行为进行查处。

杭州市建设工地夜间施工作业意见书

杭州市建设工地夜间施工作业意见书
施工工艺
连续施工涉及的机械设备名称、数量等
3、连续作业施工方案及施工时间
连续作业施工方案
审批情况
连续作业施工时间
4、连续作业施工审核及备案情况
监督科室意见
监督 科
备注:办理时需携带经审批的连续作业施工方案(方案交监督科室,由科室留存)
杭州市建设工地夜间施工作业意见书
工程名称
施工单位项目经理联系电话 Nhomakorabea建设单位
工程地址
夜间施工项目
工程量
申请作业时间
年 月 日 时至 月 日 时(共 小时)
申请夜间施工理由
申请单位(盖章)
年 月 日
建设单位意见
建设单位(盖章)
年 月 日
建设工程质量
安全监督站意见
(盖章)
年 月 日
建设行政
主管部门意见
(盖章)
年 月 日
施工工艺连续作业申请表
1、工程基本情况
工程名称
地 点
建筑面积、结构类型
建设单位
施工单位
监理单位
建设单位项目负责人、电 话
施工围墙外50米内建筑物情况(道路、公建、居住区)

项目经理、电话

项目总监、电话
西
工地值班电话

2、因生产工艺上要求必须连续作业或者特殊需要情况说明
连续施工作业部位
连续作业涉及的

夜间施工许可证

夜间施工许可证

夜间施工许可证
一、事项名称夜间施工许可证二、设定行政审批的法律依据
1、《四川省建筑管理条列》第 4 条、第47条
2、《成都市建筑施工现场监督管理规定》第九条三、行政审批数量及方式
无审批数量限制〜申请方式为直接向本机关申请四、行政审批条件(前置条件)无
五、申请材料
1、夜间施工的书面申请
2、《建筑工程施工许可证》
3、施工进度表
4、施工扬尘、噪声污染控制措施
5、相关施工图纸
6、监理单位、商品混泥土供应商单位证明
7、工程周边的居委会、小区物业或有关单位同意夜间施工的证明材料
六、申请表格
表格可在区政务中心建设局 6 号窗口免费领取七、行政审批程序第一步:申请人持相关材料向区政务中心建设局6号窗口提出申请〜由窗口工作人员进行初审后受理第二步:对申请人提出符合条件的工程〜派出工作人员到施工现场给予核定第三步: 在承诺期限内〜经审查符合法定条件、标准的〜依法作出准予许可证
的书面决定〜由负责施工许可证办理的工作人员答复申请人
八、行政审批时限
法定时限:20 个工作日, 承诺时限:2 个工作日九、行政审批收费标准及依据无
十、行政审批年审或年检
审批
十一、事项类别
行政许可事项
十二、事项类型
承诺件
十三、目前是否在中心办理是
十四、是否网上预审。

夜间加班工程施工规范标准

夜间加班工程施工规范标准

一、前言夜间加班工程施工是指在正常工作时间以外,为满足工程进度要求,安排在夜间进行的施工作业。

为确保夜间加班工程施工的安全、质量、进度,特制定本规范标准。

二、适用范围本规范标准适用于所有夜间加班工程施工项目,包括但不限于建筑、市政、交通、水利等行业。

三、夜间加班工程施工要求1. 申报与审批(1)夜间加班工程施工需由施工人员向项目经理申报,填写《夜间施工作业申请表》。

(2)项目部专职安全员对现场施工工作面进行检查,确保具备夜间施工作业条件。

(3)项目经理审批通过后,方可进行夜间加班工程施工。

2. 施工组织与管理(1)制定夜间加班工程施工组织方案,明确施工任务、人员、材料、设备等。

(2)设置夜间施工负责人,负责施工现场的组织、协调、监督工作。

(3)加强对夜间施工人员的培训,提高其安全意识和操作技能。

3. 施工安全(1)严格执行安全操作规程,确保施工安全。

(2)加强施工现场安全管理,设置安全警示标志,配备必要的安全防护设施。

(3)加强施工现场照明,确保夜间施工区域照明充足。

(4)加强施工人员健康管理,确保夜间施工人员休息充足。

4. 施工质量(1)严格按照施工图纸和规范要求进行施工,确保工程质量。

(2)加强对施工过程的质量控制,及时发现并处理质量问题。

(3)做好施工记录,确保施工过程可追溯。

5. 施工进度(1)根据工程进度要求,合理安排夜间加班工程施工计划。

(2)加强施工人员协调,确保夜间加班工程施工顺利进行。

(3)加强施工现场管理,提高施工效率。

四、夜间加班工程施工保障措施1. 物资供应保障(1)确保夜间加班工程施工所需物资及时供应。

(2)加强物资储备,避免因物资短缺影响施工进度。

2. 照明保障(1)确保夜间施工区域照明充足,满足施工需求。

(2)定期检查照明设备,确保其正常运行。

3. 通讯保障(1)确保夜间施工区域通讯畅通,便于施工人员联系。

(2)设置临时通讯设施,确保施工人员随时保持联系。

五、结语夜间加班工程施工规范标准旨在确保夜间加班工程施工的安全、质量、进度。

夜间施工审批工作流程

夜间施工审批工作流程

夜间施工审批工作流程
一、出具证明的条件
满足以下条件之一的建筑施工作业可出具夜间连续施工作业证明:
1、有可能危及人民生命财产安全的抢修、抢险作业,必须昼夜连续施工的。

2、因生产工艺上要求或特殊需要必须连续作业的。

二、出具证明的程序
1、建筑施工单位应当提前2日提出申请;
2、现场勘验;
3、提出申请次日下午15:30出具证明;
4、备案公告。

三、办理时限二日内办结。

附:办理夜间建筑施工证明登记表
青岛市环境保护局黄岛分局办理夜间建筑施工证明登记表。

上海市夜间施工申请需递交的材料

上海市夜间施工申请需递交的材料

夜间施工申请需要递交的材料
首次申请需递交的材料
(一)相关单位(包括建设单位、承包施工单位、工程转包单位的营业执照复印件,工程项目的《建筑工程施工许可证》;
(二)建筑工地总平面布置图(包括周边敏感建筑物分布情况)和施工布置图(包括施工设备布置情况);
(三)施工进度计划表(需建设单位、施工单位、监理单位共同盖章);
(四)现场夜间连续施工的具体时间和工程量(需建设单位、施工单位、监理单位共同盖章);
(五)建设工程安全质量监督部门提供的该项工程属于允许夜间施工的特殊工序的证明(见附件7);
(六)施工单位与周边敏感建筑物住户或当地居委会签订的《夜间建筑施工谅解协议》;
(七)排污申报登记材料和依法缴纳排污费的证明材料;
(八)夜间文明施工承诺书;
(九)夜间施工噪声污染控制措施(需建设单位、施工单位、监理单位共同盖章)。

深圳夜间施工申请流程

深圳夜间施工申请流程

深圳夜间施工申请流程深圳市建设工程夜间施工作业申请核发管理流程:一、施工单位申请核发作业证明的,应当在施工作业前5个工作日向工程所在地的核发机构提交以下材料:(一)填写申请表,并由建设单位现场负责人签字,施工单位、监理单位盖章;(二)建设项目证明材料,包括:建设单位、监理单位、施工单位的营业执照复印件,《建筑工程施工许可证》或者《开工备案表》,建筑施工合同复印件;(三)提交项目立项部门出具的国家、省、市重大项目证明复印件,特殊需要的证明材料;或需提交工程监理单位按照《连续施工意见书出具工作指引》等规定出具的连续施工意见书;(四)施工现场环境噪声防治方案,按照市生态环境局制定的《施工现场(夜间作业期间)环境噪声防治方案编制要点》编写,并由建设单位现场负责人签字,施工单位、监理单位盖章。

同一工地的施工单位再次申请核发作业证明的,无需提交第一款第二项规定的材料。

二、按照本办法第六条规定申请延长连续作业时长的,施工单位除提交第九条第一款第一、三、四项规定的材料外,还应当提交下列材料中的任一项材料:(一)具有相应资质的检测机构出具的上一次中午或者夜间作业期间施工场界噪声达标监测报告(包括昼间和夜间);(二)与施工场界外200米内所有住宅小区的业主委员会或者所有受影响居民签订的《建设工程夜间施工作业谅解协议》。

申请人可以在政务服务网站提出申请,深圳市一窗综合服务受理平台自动接收相关材料;或者直接向工程所在地核发机构提出申请。

核发机构自收到申请材料之日起2个工作日内,对申请材料进行初审,符合条件的,予以受理。

申请材料不齐全或者不符合法定形式的,应当一次性告知申请人需要补正的全部内容;不能按要求补正的,不予受理。

核发机构应当自受理申请之日起1个工作日内进行审核,符合条件的,向申请人核发作业证明;不符合条件的,不予核发作业证明,并及时告知申请人不予核发的理由。

夜间加班申请表雨

夜间加班申请表雨

工程名称:山东华威保安集团安防电子产品综合楼编号:
致监理单位:山东博仲项目管理有限公司
现有基础分部分项工程需夜间加班施工,准备工作有:人员、材料、机械设备、照明设施等,
将于今天下班前就绪,加班时间至止。

施工负责人、技术员、
值班人。

请监理工程师检查工作情况,并批准加班申请。

承包单位:曲阜华兴建筑有限公司
项目经理:陈卫国
日期:2014年月日
监理工程师意见:
经检查加班准备工作已就绪/未就绪,具备/不具备夜间加班条件,故同意/不同意夜间加班。

监理方将有夜间值班。

请予以监督。

总监代表:
日期:2014年月日
工程名称:曲阜滨河花苑楼编号:
致监理单位:山东齐鲁城市建设管理有限公司
现有分部分项工程需夜间加班施工,准备工作有:人员、材料、机械设备、照明设施等,将于今天下班前就绪,加班时间18:00 至止。

施工负责人、技术员、值班人。

请监理工程师检查工作情况,并批准加班申请。

承包单位:济宁鸿祥建筑工程有限公司
项目经理:王磊
日期:2014年月日
监理工程师意见:
经检查加班准备工作已就绪/未就绪,具备/不具备夜间加班条件,故同意/不同意夜间加班。

监理方将有夜间值班。

请予以监督。

总监代表:
日期:2014年月日。

夜间施工许可证明办理流程

夜间施工许可证明办理流程

夜间施工许可证明办理流程英文回答:Nighttime construction permits are required in manycities to ensure that construction activities do notdisrupt the peace and quiet of the surrounding neighborhoods during nighttime hours. The process of obtaining a nighttime construction permit may vary depending on the specific city or municipality, but generally, it involves the following steps:1. Determine the need for a nighttime construction permit: Before starting any nighttime construction activities, it is important to determine if a permit is required. This can usually be done by contacting the local city or municipality's building department or permit office.2. Gather the necessary documentation: Once it is established that a nighttime construction permit is required, gather all the necessary documentation. This mayinclude project plans, construction schedule, noise mitigation measures, and any other relevant information.3. Fill out the permit application: Obtain the nighttime construction permit application form from the local building department or permit office. Fill out the application form completely and accurately, providing all the required information.4. Submit the application: Submit the completed permit application along with the necessary documentation to the building department or permit office. Pay any applicable fees at this time.5. Review and approval process: The building department or permit office will review the application and documentation to ensure compliance with local regulations and noise restrictions. They may also conduct site visits or request additional information if necessary. Once the application is approved, the nighttime construction permit will be issued.6. Compliance with permit conditions: It is importantto comply with all the conditions and requirements of the nighttime construction permit. This may include adhering to specific working hours, implementing noise mitigation measures, and ensuring minimal disruption to thesurrounding community.7. Renewal or extension of permit: If the construction activities extend beyond the initial permit duration, it may be necessary to apply for a permit renewal or extension. This process typically involves submitting a request to the building department or permit office, along with any additional documentation or information required.In summary, the process of obtaining a nighttime construction permit involves determining the need for a permit, gathering necessary documentation, filling out the application, submitting it to the building department or permit office, undergoing the review and approval process, complying with permit conditions, and potentially renewingor extending the permit if needed.中文回答:夜间施工许可证明办理流程因城市或地区而异,但一般包括以下步骤:1. 确定是否需要夜间施工许可证明,在开始任何夜间施工活动之前,需要确定是否需要申请许可证明。

夜间施工许可证明办理流程

夜间施工许可证明办理流程

夜间施工许可证明办理流程英文回答:Nighttime construction permits are required in many cities and municipalities to ensure that construction work does not disturb residents during the night. The process for obtaining a nighttime construction permit may vary depending on the specific regulations and requirements in your area.1. Research local regulations: The first step is to research and understand the specific regulations and requirements for nighttime construction permits in your area. This can usually be done by visiting the website of your city or municipality and looking for information on construction permits.2. Complete application form: Once you have familiarized yourself with the regulations, you will need to complete an application form for a nighttimeconstruction permit. This form will typically ask for information such as the location of the construction site, the type of work being done, the proposed hours of construction, and any plans for noise mitigation.3. Submit supporting documents: Along with the application form, you may be required to submit supporting documents such as construction plans, noise mitigation plans, and any necessary permits or licenses. These documents will vary depending on the nature of the construction project.4. Pay fees: There may be fees associated with obtaining a nighttime construction permit. The amount of the fees will depend on the size and scope of the construction project. These fees are typically paid at the time of submitting the application.5. Review and approval process: Once your application and supporting documents have been submitted, they will be reviewed by the relevant authorities. This review process typically involves assessing the potential impact of thenighttime construction on nearby residents and determining whether the proposed measures for noise mitigation are sufficient.6. Issuance of permit: If your application is approved, you will be issued a nighttime construction permit. This permit will outline the approved hours of construction and any specific conditions or requirements that must be followed.7. Compliance and inspections: Once the permit is issued, it is important to ensure compliance with the approved conditions and requirements. Regular inspections may be conducted to ensure that the construction work is being carried out in accordance with the permit.It is worth noting that the process for obtaining a nighttime construction permit can be time-consuming and may require careful planning and coordination with the relevant authorities. It is important to start the application process well in advance of the planned construction start date to allow for any necessary reviews and approvals.中文回答:夜间施工许可证明是许多城市和市政当局要求的,以确保夜间施工不会打扰居民。

夜间连续施工作业证明

夜间连续施工作业证明
夜间连续施工作业证明夜间施工证明连续作业施工方案夜间施工时间夜间施工照明车夜间施工夜间施工照明灯夜间施工许可证夜间移动施工照明灯夜间施工方连续施工作业证明
审批依据:
《中华人民共和国环境噪声污染防治法》、《青岛市环境噪声管理规定》
审批程序:
需要提交材料:
申请报告(内容包括施工单位夜间连续施工作业的原因及时间)。
(以上材料原件或复印件均需加盖公章或由法人或委托代理人签字生效)
核准时限:
自受理申请之日起5个工作日。
有关说明
1.因特殊需要必须在夜间连续作业;2.完成了夜间施工申请表等相关材料。
  1. 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
  2. 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
  3. 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。

建筑工地夜间施工作业申请表
编号:
申请材料:
建设单位、施工单位营
业执照复印件
工地设备布置图
工地周边地形图
特殊需要连续施工的证
明材料:
注:本表一式四份。

嘉定区环保局、嘉定区环境监察支队、环保办、申请单位各持一份。

填报要求
1、建设施工单位应填报本表。

2、当排污单位排放污染物需作改变或者发生污染事故等造成污染物排放紧急变化的,必须分别在改变3日前或变化年3日内填报相应的《排放污染物月变更申报表(试行)》,履行变更申报手续。

3、必须用钢笔填报,蓝、黑墨水均可,书写工整、清晰,填报数据一律用阿拉伯数字,文字说明一律用汉字,涂改后必须签章有效。

4、本表须按“填表说明”如实规范填写,于各项栏目不得空缺,如属于“无”、“零”、“未检出”、“未测”、“不明”等,应用文字注明。

5、本表一式两份,每份需加盖公章,于建设施工项目动工15日前报环境监察机构,环境监察机构审核后退申报单位一份。

6、排污者申报的相关数据经环境监察机构核定后,将作为征收排污费与其他环境监督管理事项的依据。

7、填表说明:
(1)施工单位名称:填写建设施工单位名称,应与单位公章一致。

(2)法定代表人:由《法人单位代码证书》中的法定代表人签章认可。

没有法定代表人的由单位实际负责人签章认可。

(3)法人代码:按照技术监督部门颁发的《法人单位代码证书》上的代码填写。

(4)施工负责人:建设施工项目的具体负责人。

(5)身份证号码:施工负责人的身份证号码。

(6)联系人:本单位与当地环境监察机构的联系人。

(7)联系电话:指本单位负责环保工作的工作人员对外联系的电话号码(含地区码)。

(8)传真:指本单位对外联系的传真号码(含地区码)。

(9)邮政编码:指办公通讯地址所在地区的邮政编码。

(10)通讯地址:指邮政部门认可的单位环保联系人的办公通讯地址。

(11)施工场所地址:填写建设施工场所具体地址。

(12)施工场所中心经、纬度:填写施工场所的地理位置的中心经、纬度。

(13)工程项目名称、施工许可证号码、施工场地面积:按照施工许可证填写。

(14)工地类型:选择建筑工地、拆迁工地、市政工地、园林绿化、其他工地填写。

(15)施工人员数:填写本工地施工期内参与正常施工的管理人员和工人总数。

(16)施工单位开户银行、帐号:填写施工单位财务基本帐户的信息。

(17)开工时间、竣工时间:按施工许可证上的开工时间、竣工时间填写。

(18)场界噪声值:对应表中施工阶段的名称由施工单位按以往经验分昼夜填写边界噪声值。

昼夜时间的划分按《中华人民共和国噪声防治法》的规定划分昼间为6—22点。

(19)施工时间:按施工组织设计或施工方案上的时间确定。

(20)主要施工机械名称/数量:指挖掘设备、运输车辆、打桩机、搅拌机、浇筑设备、塔吊(卷扬机)、振动设备、木工机械、金属建材加工机械等。

(21)施工场所平面及测点示意图:施工场地平面图要求
①标明施工场地周围环境情况;
②标明场界准确位置及相对位置;
③标明准确方向、方位;
④标明主要参照物;
⑤施工进行后,噪声监测点等其他内容可后补。