螺杆泵调试程序
- 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
- 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
- 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。
CONTENTS
1. PURPOSE ...........................................................................................................
2. CODES AND STANDARDS .............................................................................
3. DOCUMENTS AND DRAWINGS ..................................................................
4. ENVIRONMENT AND SAFETY ....................................................................
5. RESOURCE REQUIREMENT ........................................................................
6. COMMISSIONING ...........................................................................................
7. AFTER TEST CHECK .....................................................................................
COMMISSIONING PROCEDURE FOR
SCREW PUMP
螺杆泵调试程序
1.PURPOSE
目的
The following provides the commissioning procedures for the inspection, testing and commissioning of screw pump xx project, verify the equipment can also achieves its design intent and operability as specified in the technical contract after transportation and installation.
本调试程序包括淡螺杆泵的检查、测试以及调试,以确保该设备在经历运输和安装后,各项功能指标符合技术合同中的设计目的和操作要求。
2.CODES AND STANDARDS
依据的准则和标准
3.DOCUMENTS AND DRAWINGS
参考的文件与图纸
4.ENVIRONMENT AND SAFETY
环境和安全
●Commissioning work should be prepared to prevent frostbite when the environment
temperature is below 5℃.
当环境温度低于五度是要有防冻措施
●Ensure the commissioning area is cleaning.
确保调试区域整洁
●Ensure the place of caution brand is marked.
调试区域要悬挂警示牌
5.RESOURCE REQUIREMENT
调试资源
5.1PERSONNEL ORGANIZATION
人员组织
●Commissioning manager arrange the work. His job consists of putting up the
commissioning inform, holding a commissioning warming-up meeting include of JSA.
调试经理负责安排,包括调试安排的通知,主持召开包括JSA在内的调试准备会议。
●The main commissioning engineer (MCE) is mechanical engineer, the assistant
commissioning engineers are electrical commissioning engineer, instrument commissioning engineer and piping engineer.
机械工程师作为主调工程师,辅调工程师包括电器工程师、仪表工程师和工艺工程师。
●All participants must obey the order of MCE.
所有参加调试人员必须听从主调工程师指挥。
●People partake in commissioning on site: commissioning engineers, Owner, Third party,
inspector, Vendor service, QHSE.
参加调试的人员包括:调试工程师、业主、第三方、检验、厂家、QHSE
5.2TOOLS AND TEMPORARY EQUIPMENT
调试工具和临时设备
●Megger (0-500M)
兆欧表
●Voltage meter (0-500V)
电压表
●Multi meter
万用表
●Anemometer (0-20m/s)
风速仪
●Infrared thermometers
红外线测温仪
●Tachometer(3500rpm)
转速仪
●Vibration meter
振动表
●Noise meter
噪音仪
●Clamp on ampere meter (0-500A)
钳形电流表
●Interphone
对讲机