新建额济纳至哈密铁路站前工程EHSG-1标段架桥作业指导书

编制:

审核:

审批:

中铁十四局集团有限公司额哈铁路项目部

目录

一适用范围````````````````````````````````````````````1二作业准备``````````````````````````````````````````````1三技术要求``````````````````````````````````````````````3 四工艺流程````````````````````````````````````````````5 五施工要求````````````````````````````````````````````````````````````````````````````5 六冬季施工措施```````````````````````````````````````````````````````````````````10 七质量控制及检验要求`````````````````````````````````````````````````````````12 八劳动力组织```````````````````````````````````````````````````````````````````````13 九机具配置```````````````````````````````````````````````````````````````````````14 十安全保证措施```````````````````````````````````````````````````````````````````14

架桥作业指导书

一适用范围

本方案适用于新建额济纳至哈密铁路EHSG-1标额济纳架桥作业。

二作业准备

2.1内业技术准备

①组织人员熟悉架设桥梁梁型,听取线下单位的施工交底。

②确定架桥机组装方案,龙门架支立点选择,编制架梁施工组织,确定架梁方向和顺序。

③根据工程进度情况,核实架梁进度计划,架梁作业施工组织设计编制,根据施组要求向梁片供应单位提供桥梁运输顺序要求等。

④人员培训,参加架梁的所有施工人员必须经过客运专线桥梁施工培训并对架桥机机械性能及施工技术细则熟悉和全面掌握后才能上岗操作。特殊工种人员必须进行强化培训,经考试合格后方可发证上岗。

2.2外业技术准备

①架桥机、运梁车、倒装龙门架现场组装完毕、调试合格,工作状态良好;

②支座十字线、孔跨距离、锚栓孔位置、孔径及深度、垫石平整度及标高复测,清除预留孔中的杂物;

③桥头线路加固,桥台、桥尾加固;

④桥梁质量检查合格;

⑤架桥机走行线路一切影响架桥机的障碍物调查和排除。

DJ180架桥机简介:

DJ180架桥机型单导梁架铺机用于架设公路桥梁40米及以下跨度预应力钢筋混凝土梁片、铁路桥梁32m及以下跨度预应力钢筋混凝土梁片、铺设25m铁路轨排。

该机由主机和机动运梁车两大部分组成。

机动运梁车技术参数——表1

.主机技术参数——表2

三技术要求

1由于桥台填土复杂,桥机在跨桥台作业中极易发生意外,对桥台进行加固可以有效防止发生桥台垮塌事故,架桥机作业前必须对桥台线路进行加固距桥台45m线路加固;

2在直线有效长度不小于80m的线路上组装架桥机,

3检查支座的规格、型号,认真检查支座外形、外观质量、注意配件是否齐全,在搬运过程中要轻取轻放,避免损伤支座,影响外观质量。向监理提交合格证书或质量保证书。

4安装支座

①、T梁外形尺寸和外观质量检查合格后,进行支座安装作业。

②、检查固定支座上下支座板对正情况以及调整活动支座上下座板纵向预留横向错动量。支座上下座板必须水平安装,固定支座上下座板应互相对正;活动支座上下座板横向应对正,在架梁施工过程中应根据支座安装施工温度与设计安装温度之差和梁体混凝土未完成收缩、徐变量及弹性压缩量调整活动支座上下座板纵向预留错动量。

③、根据桥图确定所需支座的类型(区分固定端、活动端),在倒装龙门架处安装支座。

四工艺流程

DJ180架桥机施工作业流程:

组装架桥机和支立倒装龙门架---架桥机桥台就位和龙门架倒装梁片----机动平车喂梁就位---架桥机吊梁、走梁、落梁---安支座、落梁就位---架桥机前移一跨。

五施工要求

5.1桥头线路加固:

(1)、压道前应详细了解路基的施工资料、填筑情况和填筑后沉落情况。

(2)、采用机车(轴重大于190KN)或超重车(轴重不小于30T)进行压道。

(3)、压道范围:前方压上桥台1m,后方压到大轴重最远停留处以远50m。采取拨道架梁时,除正线外应拨到计算拨道量处压道。所有大轴重通过或停留地段均应压到。

(4)、压道速度:宜为1~3Km/h,不得超过5Km/h,对大轴重经常停留地段,桥台尾与线路衔接和个别有疑问的薄弱处所,应放慢速度或较长时间地停在该处任其沉落。

(5)、压道次数:压到无显著下沉,最后三个往返的轨道沉降左右偏差不得大于2mm,总下沉量不大于5mm,压道不得少于三个往返,并且有专职安检人员、施工技术人员、施工负责人共同检查,随车压道。

(6)、压道时应注意路基四周变化情况,对有橡皮泥或翻浆冒泥现象的路基应采取特别加固的方法。压道时应有养路人员配合整道,认真捣固。比较松软的路基,在变形地段应起道捣实后再压。压道后或架梁过程中,当遇大雨或长期阴雨浸泡路基,或压道后很长时间未架梁及架梁的间隔时间很长,或经过路线大抬道等情况,均应重新压道。

5.2架桥机组装

(1)组装架桥机应选择在桥头路基上进行,直线有效长度不小于80m,组装场地应平整、夯实,不得有局部路基松软。

(2)横移轨道下方应用硬杂木支垫好,轨道铺设应克服桥台或路基横坡,要铺设水平。

(3)组装时对所有栓接螺栓上紧上牢,保证受力均匀。

(4)组装前应检查各联接部位有无损伤变形情况,各部螺栓和销子有无脱落、丢失、损坏等情况,应注润滑油部位是否已注润滑油或脂等,然后进行组装。

(5)组装时对各联接部位、运动机构有无不整洁,附有杂物情况,应进行认真检查清理干净后进行组装。

5.3架铺机经组装后全面检查。

⑴检查各部栓联紧固情况,对任何一个螺栓均不能忽视。

⑵液压系统油面高度是否符合要求。