课设翻译-有道翻译
- 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
- 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
- 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。
2.12 Perceptions of Owners and Contractors
Although owners and contractors may have different perceptions on project management for construction, they have a common interest in creating an environment leading to successful projects in which performance quality, completion time and final costs are within prescribed limits and tolerances. It is interesting therefore to note the opinions of some leading contractors and owners who were interviewed in 1984.
From the responses of six contractors, the key factors cited for successful projects are:
∙well defined scope
∙extensive early planning
∙good leadership, management and first line supervision
∙positive client relationship with client involvement
∙proper project team chemistry
∙quick response to changes
∙engineering managers concerned with the total project, not just the engineering elements.
Conversely, the key factors cited for unsuccessful projects are:
∙ill-defined scope
∙poor management
∙poor planning
∙breakdown in communication between engineering and construction
∙unrealistic scope, schedules and budgets
∙many changes at various stages of progress
∙lack of good project control
The responses of eight owners indicated that they did not always understand the concerns of the contractors although they generally agreed with some of the key factors for successful and unsuccessful projects cited by the contractors. The significant findings of the interviews with owners are summarized as follows:
∙All owners have the same perception of their own role, but they differ significantly in assuming that role in practice.
∙The owners also differ dramatically in the amount of early planning and in providing information in bid packages.
∙There is a trend toward breaking a project into several smaller projects as the projects become larger and more complex.
∙Most owners recognize the importance of schedule, but they adopt different requirements in controlling the schedule.
∙All agree that people are the key to project success.
From the results of these interviews, it is obvious that owners must be more aware and involved in the process in order to generate favorable conditions for successful projects. Design professionals
and construction contractors must provide better communication with each other and with the owner in project implementation.
3. The Design and Construction Process
3.1 Design and Construction as an Integrated System
In the planning of facilities, it is important to recognize the close relationship between design and construction. These processes can best be viewed as an integrated system. Broadly speaking, design is a process of creating the description of a new facility, usually represented by detailed plans and specifications; construction planning is a process of identifying activities and resources required to make the design a physical reality. Hence, construction is the implementation of a design envisioned by architects and engineers. In both design and construction, numerous operational tasks must be performed with a variety of precedence and other relationships among the different tasks.
Several characteristics are unique to the planning of constructed facilities and should be kept in mind even at the very early stage of the project life cycle. These include the following:
∙Nearly every facility is custom designed and constructed, and often requires a long time to complete.
∙Both the design and construction of a facility must satisfy the conditions peculiar to a specific site.
∙Because each project is site specific, its execution is influenced by natural, social and other locational conditions such as weather, labor supply, local building codes, etc.
∙Since the service life of a facility is long, the anticipation of future requirements is inherently difficult.
∙Because of technological complexity and market demands, changes of design plans during construction are not uncommon.
In an integrated system, the planning for both design and construction can proceed almost simultaneously, examining various alternatives which are desirable from both viewpoints and thus eliminating the necessity of extensive revisions under the guise of value engineering. Furthermore, the review of designs with regard to their constructibility can be carried out as the project progresses from planning to design. For example, if the sequence of assembly of a structure and the critical loadings on the partially assembled structure during construction are carefully considered as a part of the overall structural design, the impacts of the design on construction falsework and on assembly details can be anticipated. However, if the design professionals are expected to assume such responsibilities, they must be rewarded for sharing the risks as well as for undertaking these additional tasks. Similarly, when construction contractors are expected to take over the responsibilities of engineers, such as devising a very elaborate scheme to erect an unconventional structure, they too must be rewarded accordingly. As long as the owner does not assume the responsibility for resolving this risk-reward dilemma, the concept of a truly integrated system for design and construction cannot be realized.