120KV变电站主变吊装施工方案
主变压器安装施工方案..
主变压器安装施工方案一、前言在电力系统中,主变压器是一个至关重要的设备,它起着电压变换和功率传递的作用。
主变压器的安装施工对电力系统的正常运行至关重要,下面将介绍主变压器的安装施工方案。
二、安装前准备在进行主变压器的安装之前,需要进行以下准备工作: 1. 检查主变压器的设备清单,确保所有零部件齐全; 2. 确定主变压器的安装位置,并进行现场勘察; 3.准备好必要的安装工具和设备; 4. 制定详细的安装计划,包括吊装、配线等方面的安排。
三、主变压器吊装主变压器的吊装是整个安装过程中最关键的环节之一,下面是吊装的具体步骤:1. 搭建起吊装置,确保吊装设备符合要求,吊装绳索牢固可靠; 2. 检查主变压器的吊装位置和吊点,确保吊装过程中不会造成损坏; 3. 采取适当的吊装方法,稳定主变压器的位置,慢慢提升主变压器至安装位置; 4. 在吊装的过程中,需要有专人指挥,确保吊装过程安全可靠。
四、主变压器接地主变压器的接地是保证安全的关键步骤,接地的方法如下: 1. 清理接地位置,确保接地环境干净整洁; 2. 检查接地线的连接情况,确保接地线接触良好; 3. 使用万用表进行接地测试,检验接地是否正常; 4. 完成接地后,对接地部分进行标识,方便后续维护管理。
五、主变压器油浸主变压器通常采用油浸式设计,进行油浸的步骤如下: 1. 清洗主变压器油箱,确保油箱内部干净; 2. 倒入变压器油,同时检查油位是否达标; 3. 对油浸后的主变压器进行静态试验,确保油浸效果良好; 4. 在油箱周围设置油漏检测器,定期检测漏油情况。
六、主变压器连接主变压器连接是主变压器安装的最后一步,连接步骤如下: 1. 将主变压器的高低压侧线路连接至相应的绝缘子; 2. 进行连接线路的绝缘测试,确保线路连接安全可靠; 3. 对主变压器进行二次接地,确保设备接地良好; 4. 完成主变压器连接后,进行设备的整体检查,确认无误后进行通电试运行。
结语以上就是关于主变压器安装施工方案的详细介绍,主变压器的安装需要严格按照规范操作,确保安全可靠。
变电站主变安装施工方案
一、工程概况本工程为XX变电站主变安装工程,工程内容包括主变设备的安装、调试及验收。
主变设备为XX型,容量为XX兆伏安。
工程地点位于XX市XX区XX变电站内。
二、施工组织机构1. 项目经理:负责整个项目的组织、协调、指挥和监督。
2. 技术负责人:负责施工过程中的技术指导和质量监督。
3. 施工班组长:负责班组施工的具体安排和执行。
4. 质量监督员:负责对施工过程进行质量监督。
5. 安全员:负责施工过程中的安全监督。
三、施工进度计划1. 施工准备阶段:10天2. 设备运输及进场阶段:5天3. 设备安装阶段:30天4. 调试阶段:15天5. 验收阶段:5天四、施工技术方案1. 设备安装(1)按照设备厂家提供的安装说明书进行安装。
(2)安装过程中,严格按照施工规范和操作规程进行。
(3)安装过程中,对设备进行检查,确保设备安装质量。
2. 调试(1)按照设备厂家提供的调试规范进行调试。
(2)调试过程中,对设备进行测试,确保设备性能符合要求。
(3)调试完成后,对设备进行试运行,确保设备运行稳定。
五、施工安全措施1. 施工人员必须佩戴安全帽、安全带等防护用品。
2. 施工现场设置安全警示标志,确保施工安全。
3. 施工过程中,严格遵守操作规程,防止误操作。
4. 定期对施工现场进行安全检查,及时发现并排除安全隐患。
六、施工质量保证措施1. 严格按照国家相关标准和规范进行施工。
2. 对施工人员进行技术培训,提高施工人员的技术水平。
3. 对施工过程进行质量监督,确保施工质量。
4. 对设备进行严格检查,确保设备质量。
七、施工环境保护措施1. 施工过程中,采取有效措施减少施工噪声和粉尘污染。
2. 施工现场设置围挡,防止施工垃圾和废水外溢。
3. 施工结束后,及时清理施工现场,恢复原状。
八、施工总结1. 施工过程中,严格按照施工方案进行施工,确保施工质量。
2. 施工过程中,加强安全管理,确保施工安全。
3. 施工结束后,对施工过程进行总结,为今后的施工提供借鉴。
吊车安装变压器施工方案
一、工程概况本工程涉及吊车安装变压器,旨在确保变压器安装过程的安全、高效和准确。
变压器是电力系统中重要的设备,其安装质量直接影响到整个电力系统的稳定运行。
本方案针对变压器吊装安装过程,详细阐述施工步骤、安全措施及质量控制要点。
二、施工准备1. 技术准备(1)熟悉变压器安装图纸、说明书及施工规范;(2)掌握吊车操作规程和安全注意事项;(3)对参与施工人员进行技术培训,确保其具备相应技能。
2. 材料准备(1)变压器、吊车、叉车、地牛车等设备;(2)安全带、安全帽、防护眼镜等安全防护用品;(3)吊装工具、紧固件等辅助材料。
3. 人员准备(1)组建施工队伍,明确各岗位责任;(2)配备专业的吊装、电工、技术人员;(3)成立安全监督小组,负责现场安全监督。
三、施工步骤1. 变压器检查(1)检查变压器外观,确保无损伤;(2)检查变压器内部接线,确保接线正确;(3)检查变压器油位、油质,确保油质符合要求。
2. 吊装准备(1)确定吊装位置,确保吊装过程安全;(2)检查吊车性能,确保吊装过程稳定;(3)安装安全防护设施,如围栏、警示标志等。
3. 变压器吊装(1)使用折臂吊车将变压器吊至二级平台;(2)使用叉车将变压器从二级平台转移到三级平台;(3)用地牛车将变压器挪动到安装位置。
4. 变压器就位(1)将变压器平稳放置在基础上;(2)调整变压器水平,确保安装精度;(3)检查变压器接地,确保接地良好。
5. 接线及调试(1)按照图纸要求,进行变压器内部接线;(2)调试变压器,确保其正常运行。
四、安全措施1. 严格遵循吊装操作规程,确保吊装过程安全;2. 施工现场设置安全警示标志,提醒人员注意安全;3. 施工人员必须佩戴安全防护用品,如安全带、安全帽等;4. 施工过程中,加强现场安全巡查,及时发现并消除安全隐患。
五、质量控制要点1. 严格按照施工规范和图纸要求进行施工;2. 选用合格的材料和设备,确保施工质量;3. 施工过程中,加强质量控制,确保变压器安装精度;4. 施工完成后,进行验收,确保变压器安装质量符合要求。
变电工程吊装方案
变电工程吊装方案一、引言变电工程作为电力系统中重要的一部分,涉及到电力设备的安装及维护,其中涵盖了各种各样的工艺、技术、设备等。
在变电站建设或改造中,变电设备的吊装是一个关键的环节,直接关系到工程的进度和安全。
因此,在进行变电工程吊装方案制定时,需要严谨、合理地考虑整个工程的实际情况和变电设备的特点,全方位地综合考虑吊装工艺、吊装设备、安全措施等因素,以确保吊装工程的顺利进行和安全完成。
本文将结合具体的变电工程吊装实例,对吊装方案的制定进行详细的阐述,旨在为相关工程人员提供参考和指导。
二、变电设备吊装特点与难点1. 变电设备吊装特点(1)大体积、重量变电设备通常具有较大的体积和重量,如变压器、开关柜等,其吊装需用吊车和专业吊装设备进行,吊装过程需要具备较高的承载能力。
(2)重心不稳定变电设备由于结构特性,其重心通常不稳定,吊装过程要求吊装人员具备较高的操作技能和经验,以确保吊装过程的安全。
2. 变电设备吊装难点(1)吊装空间狭小变电站常常位于城区及狭小场地,吊装空间较为狭小,不利于吊装作业进行。
(2)周边环境复杂变电站周边环境复杂,如地质条件不稳定、地下管线众多、建筑物密集等,这些因素增加了吊装作业的难度和风险。
因此,对于变电设备的吊装工程,需要谨慎制定吊装方案,并且制定合理的安全措施以应对各种吊装难点,确保吊装过程的稳定、快速和安全。
三、变电设备吊装方案制定1. 吊装前的准备工作(1)初步设计方案在编制吊装方案前,需对变电设备进行详细的测量和分析,以确定合理的吊装方案。
同时,需考虑吊装现场周边环境和设备状态等因素,进行初步设计方案的制定。
(2)现场勘察在初步设计方案确定后,需进行现场勘察工作,全面了解吊装现场的地形、使用情况、周边环境和设备情况等,验证初步设计方案的可行性,及时发现问题并进行调整。
2. 吊装方案的制定(1)设备吊装流程根据现场勘察结果和变电设备的实际情况,制定合理的设备吊装流程,包括:吊装前的准备工作、吊装设备和工艺选择、吊装现场的布置、吊装操作步骤及注意事项等内容。
变电站现场吊装方案
变电站工程构架吊装方案审批:审核:编制:目录一、施工依据: (3)二、安装前的准备: (3)三、预埋件施工: (4)四、安装工艺流程: (5)五、立柱的安装: (5)六、钢梁安装: (6)七、构件的连接和固定: (6)九、质量保证措施: (8)构架吊装方案本工程为工程变电站钢构工程,所用各种钢结构及钢板等均为热浸镀锌处理过的材料组成,其质量要求应符合现行国家标准《梁装前钢材表面锈蚀等级和除锈等级》(GB8923-1988)的规定。
在现场加工制作安装,构架整体如下:人字柱共8组,每组高度10.50米,钢立柱共3根,每根高度为3米。
其中人字柱相连接钢架共8根,4根长度为8米,4根长度为11米,4根长度为8米跨度为8米,4根长度为11米跨度为11米。
一、施工依据:1.设计图纸2.钢结构施工质量验收规范………………………………………GB50205——20013.钢结构焊接规程………………………………………………………JGT81——914.钢结构高强螺栓连接技术施工及验收规程…………………………TGT82——915.钢结构用大六角头高强螺栓连接付…………………………GB3632—3633—836.碳钢焊条………………………………………………………………GB5117—857.碳素钢埋弧自动焊剂…………………………………………………GB5293—858.涂漆表层高级除锈镀锌磁性粉质量验收规范……………………GB/T12754—91二、安装前的准备:1、对本工程的图纸进行仔细阅读,熟悉业主及设计要求。
2、根据本工程的工程量编制施工时间计划及资源调配计划。
3、复验预埋基础,其轴线、水平线、水平度、预埋基础位置及覆出长度,超出允许偏差时,做好技术处理。
4、经纬仪进行对基础标高复测,并取相对标高尺寸校对。
5、施工前,应检查钢构件在堆放、吊运过程中是否变形,如变形则必须校正后,方可进行安装。
6、施工流程:施工基础放线→人字柱钢柱结构安装→钢梁安装→完工清场。
变电所变压器吊装施工方案
变电所变压器吊装施工方案1. 引言本文档旨在描述变电所变压器吊装施工方案。
变电所变压器作为变电站的核心设备,其安全、稳定地进行吊装工作非常关键。
本方案将对吊装施工的流程、要求以及注意事项进行详细介绍。
2. 吊装施工流程吊装施工是变电所变压器安装的关键环节,正确的施工流程将确保吊装过程顺利、安全。
以下是吊装施工的详细流程:1.准备工作:–清理吊装现场,确保周围环境整洁,移除障碍物。
–检查吊装设备的工作状况,确保吊装设备完好。
–确定吊装人员的职责,并进行必要的培训。
2.就位固定:–使用合适的固定点将吊车就位,并按照规定的固定方式固定吊车。
–根据变压器的尺寸和重量,合理选择吊装工具和吊装方式。
3.配置吊具:–根据变压器的重量和形状,选择合适的吊具,如吊索、吊钳等。
–检查吊具的工作状况,确保吊具完好并无损坏。
4.吊装准备:–检查变压器的悬挂点、连接螺栓等关键部位,确保没有松动或损坏。
–进行必要的预处理,如将变压器进行防锈处理,以保护设备表面。
5.吊装操作:–由专业人员操作吊车,根据安全标准和吊装要求,将变压器吊起并悬挂在预定位置。
–控制吊车的移动和高度,确保变压器平稳吊装至预定位置。
–保持沟通畅通,吊车操作人员与指导人员紧密协作,确保吊装过程安全。
6.防护措施:–在吊装过程中,设置临时安全警戒线,确保施工区域的安全。
–接地变压器,并采取必要的雷击防范措施。
7.吊装完成:–完成吊装后,对变压器进行检查,确保变压器吊装安全、完整。
–拆除吊装设备和吊具,并进行必要的维护保养。
3. 注意事项在进行变电所变压器吊装施工时,需要注意以下事项:•按照吊装施工方案进行操作,确保吊装过程安全、规范。
•保持吊装现场整洁,确保周围环境安全。
•严格遵守各项操作规程和安全操作程序。
•吊装设备必须经过专业人员检查合格后方可使用。
•变压器的重心要与吊挂点平衡,避免重心不稳引起的倾斜或意外事故。
•在吊装过程中,保持沟通畅通,与吊车操作人员紧密配合。
变电站一次设备吊装方案及流程
变电站一次设备吊装方案及流程一、变电站一次设备吊装的前期准备。
1.1 设备检查。
咱们在吊装变电站一次设备之前啊,可得好好检查一下设备。
这就好比咱出门旅行前检查行李一样,要仔仔细细。
看看设备有没有损坏的地方,零件是不是齐全。
要是设备本身就有问题,那吊装过程中出岔子的概率可就大大增加了。
这设备检查可不能走马观花,得像啄木鸟找虫子那样认真。
1.2 场地准备。
场地也很关键啊。
吊装场地得宽敞、平坦,不能坑坑洼洼的。
就像咱们跳舞得有个平整的舞台一样。
周围不能有太多障碍物,不然吊车的施展空间就受限了。
而且要考虑到设备的放置位置,得规划好,不能到时候手忙脚乱,像没头的苍蝇似的。
二、吊装方案的制定。
2.1 选择合适的吊车。
这吊车的选择可大有学问。
要根据设备的重量、尺寸来选。
如果设备很重,你却选个小吊车,那就是小马拉大车,根本干不了这活。
反之,设备很轻却用个大吊车,那也是浪费资源,就像高射炮打蚊子。
要做到恰到好处,不多不少。
2.2 确定吊装点。
吊装点的确定那也是重中之重。
这就如同挑担子,得找准平衡点。
找不准的话,设备在吊装过程中就可能倾斜,那可就危险了。
得按照设备的结构和重心来确定吊装点,可不能瞎蒙,不然就会捅娄子。
2.3 制定安全措施。
安全措施是必须的。
吊装这活儿啊,就像在走钢丝,容不得半点马虎。
要给工作人员配备好安全帽、安全带等防护装备。
还要考虑到天气因素,如果风很大或者天气不好,那就得暂停吊装,这叫识时务者为俊杰。
三、吊装流程。
3.1 吊车就位。
吊车先开到指定的位置,就像士兵站好岗一样。
要停稳当了,不能摇摇晃晃的。
司机要把吊车的各个部件都检查一遍,确保没有问题,这就叫磨刀不误砍柴工。
3.2 设备挂钩。
变电站一次设备的吊装工作啊,是个细致活,需要咱们各个环节都做到位,可不能敷衍了事。
每个步骤都像是拼图的一块,缺了哪块都不行。
只有这样,才能顺利完成吊装任务,确保变电站的正常建设和运行。
变压器吊装方案及安全预案
一、前言变压器是电力系统中重要的电气设备,其吊装作业对施工安全有着重要影响。
为确保变压器吊装作业安全、顺利进行,特制定本方案及安全预案。
二、变压器吊装方案1. 施工准备(1)检查吊车及吊装设备是否完好,确保其符合吊装要求。
(2)检查变压器基础,确保其符合设计要求。
(3)组织施工人员学习吊装方案和安全预案,提高安全意识。
2. 吊装步骤(1)将变压器吊装到吊车指定位置。
(2)调整吊车,使变压器平稳地悬吊在空中。
(3)检查吊装设备、吊车及变压器连接是否牢固。
(4)指挥吊车缓慢将变压器移至基础。
(5)在变压器就位后,检查基础与变压器的连接是否牢固。
3. 吊装注意事项(1)吊装过程中,吊车司机应密切观察变压器状态,确保其平稳悬挂。
(2)吊装过程中,禁止施工人员靠近吊装区域。
(3)吊装完成后,检查变压器基础与变压器的连接是否牢固。
三、安全预案1. 人员安全(1)施工人员应穿戴安全帽、安全带等防护用品。
(2)吊装过程中,施工人员应站在安全位置,禁止靠近吊装区域。
(3)施工人员应遵守吊装作业规程,不得擅自操作吊装设备。
2. 设备安全(1)吊装设备应定期检查、维护,确保其安全可靠。
(2)吊装过程中,吊车司机应密切观察变压器状态,确保其平稳悬挂。
(3)吊装完成后,检查吊装设备、吊车及变压器连接是否牢固。
3. 环境安全(1)吊装过程中,禁止在吊装区域附近进行其他作业。
(2)吊装完成后,清理现场,确保无安全隐患。
四、应急处理1. 人员受伤(1)立即停止吊装作业,组织人员将受伤人员送往医院。
(2)对现场进行安全检查,确保无安全隐患。
2. 设备故障(1)立即停止吊装作业,通知设备维修人员进行检查。
(2)根据设备故障情况,采取相应措施,确保吊装作业安全进行。
(3)设备故障排除后,重新进行吊装作业。
五、总结本方案及安全预案旨在确保变压器吊装作业安全、顺利进行。
在吊装过程中,严格执行各项安全措施,确保人员、设备、环境安全。
同时,做好应急处理工作,确保突发事件得到及时有效处置。
变电站吊车专项方案
一、背景随着我国电力事业的快速发展,变电站建设规模不断扩大,变电站设备也越来越大型化、复杂化。
为提高变电站建设效率,降低施工风险,确保施工安全,特制定本专项方案。
二、适用范围本方案适用于变电站内采用吊车进行设备安装、调试、维修等施工活动。
三、施工组织1. 施工单位应成立吊车专项施工小组,负责吊车施工的组织、协调和监督工作。
2. 吊车施工小组应由项目经理、技术负责人、安全员、施工员等组成。
3. 施工前,施工单位应进行吊车施工安全教育和培训,确保施工人员掌握吊车操作规程和安全注意事项。
四、施工准备1. 施工单位应根据吊车作业需求,选择合适的吊车设备,并确保吊车设备符合相关技术标准和安全要求。
2. 对吊车设备进行全面的检查、试验,确保其性能良好,安全可靠。
3. 施工现场应设置明显的警示标志,并做好现场围挡、隔离措施,防止无关人员进入施工区域。
4. 施工单位应制定详细的吊装作业方案,明确吊装作业流程、作业人员职责、安全措施等。
五、施工流程1. 吊装前,对吊车设备进行检查,确保吊车设备状态良好。
2. 吊装作业前,施工人员应进行现场勘查,确定吊装位置、吊点、吊装路线等。
3. 吊装作业过程中,严格按照吊装作业方案进行操作,确保吊装过程安全、稳定。
4. 吊装完成后,对吊装设备进行检查,确认吊装作业质量。
六、安全措施1. 施工单位应制定吊车施工安全措施,包括吊车设备安全、人员安全、作业环境安全等方面。
2. 吊车设备操作人员必须具备相应的资质和技能,严格遵守操作规程。
3. 施工现场应配备必要的安全防护设施,如安全带、防护网、警示标志等。
4. 施工过程中,应密切关注吊装设备状态,发现异常情况立即停止作业,进行排查和处理。
5. 吊装作业过程中,施工人员应保持高度警惕,严格遵守安全操作规程,确保施工安全。
七、总结本方案旨在确保变电站吊车施工安全、高效、顺利进行。
施工单位应严格按照本方案执行,确保施工质量和安全。
在施工过程中,如遇特殊情况,应立即上报,并采取相应措施进行处理。
变电站构支架吊装施工方案
变电站构支架吊装施工方案一、施工方案编制依据本施工方案依据《电力建设工程施工安全技术规程》、《变电站建设工程施工及验收规范》等国家及行业相关标准、规范进行编制。
同时,结合本工程的具体特点和实际情况,确保施工过程的科学性、安全性和经济性。
二、工程概况与特点本工程为变电站构支架吊装施工,涉及大量高空作业和重型构件吊装。
工程的主要特点包括:构支架结构复杂、尺寸大、重量重,吊装高度高,施工难度大,对安全和质量要求高。
三、作业人员组织安排为确保施工顺利进行,将组织专业的吊装作业队伍,包含项目经理、安全监督员、吊装操作员、技术工人等。
所有作业人员必须持有相应的特种作业操作证,并经过培训合格后方可上岗。
四、机具计划与选择根据工程特点和吊装需求,选择适合的重型塔吊、吊索具、平衡梁等机具设备。
设备进场前进行严格检查,确保性能良好。
同时,制定机具设备使用、维护和保养计划,确保施工过程中的机具设备始终处于良好状态。
五、作业前准备与条件作业前,需完成施工现场的安全设施搭设,包括安全网、警示标志、防护栏等。
同时,对吊装区域进行清理,确保无障碍物。
此外,还需进行技术交底和安全教育,确保所有作业人员明确任务和安全要求。
六、施工工序与质量控制吊装施工按照以下工序进行:吊装设备检查→构件吊装前准备→吊装作业→吊装后检查。
在施工过程中,实行全过程质量控制,确保每个环节的施工质量符合设计要求。
七、安全技术措施与要求吊装作业过程中,严格执行安全操作规程,确保作业人员安全。
设置专职安全监督员,对施工现场进行实时监控,及时发现和纠正安全隐患。
对吊装设备进行定期检查和维护保养,确保其安全可靠。
在吊装区域设置警戒线,禁止非作业人员进入。
加强与气象部门的沟通,及时掌握天气变化,合理安排施工时间。
八、环境保护与文明施工严格遵守环境保护法规,减少施工过程中的噪音、粉尘和废水排放。
合理利用资源,减少材料浪费,提高施工效率。
保持施工现场整洁有序,实现文明施工。
变压器吊装施工方案
变压器吊装施工方案一、项目概述根据工程要求,本次施工方案为变压器的吊装工程。
变压器为重型设备,需要采取合适的吊装方式和措施,并保证施工安全。
本方案主要包括吊装前准备工作、吊装方案设计、操作方案制定、安全措施等内容。
二、吊装前准备工作1.组织筹备:成立吊装施工小组,负责组织各项工作。
2.确定吊装时间:根据施工进度和天气情况,确定最适宜的吊装时间。
3.确定吊装地点:根据变压器的尺寸和重量,选择合适的吊装地点,并进行现场勘察和测量,确保吊装设备的稳固性。
4.准备吊装设备:根据变压器的重量和尺寸,选择适当的吊装设备和吊装工具,如吊车、起重机械、吊钩、吊索等。
三、吊装方案设计根据变压器的重量、尺寸和施工现场的条件,制定合适的吊装方案。
1.吊装点的确定:根据变压器的结构特点,选择适当的吊装点,并确保吊装点的牢固性和稳定性。
2.吊装方式的选择:根据变压器的重量和尺寸,选择合适的吊装方式,如单点吊装、双点吊装、多点吊装等。
3.吊装工具的选择:根据吊装方式和施工现场条件,选择合适的吊装工具,如吊具、吊钩、吊索等。
4.吊装参数计算:根据变压器的重量和施工现场的条件,计算吊装参数,如起吊力、起吊高度、吊装角度等。
四、操作方案制定根据吊装方案设计,制定具体的操作方案,并进行必要的安全措施。
1.吊装设备的安装和调试:对吊装设备进行安装和调试,确保其正常运行。
2.吊装现场的准备:对吊装现场进行清理和整理,确保施工现场的安全和无碍。
3.吊装人员的培训:对吊装人员进行安全培训,包括吊装操作流程和安全注意事项等。
4.吊装作业的组织:根据操作方案,对吊装作业进行组织和调度,确保各项工作的顺利进行。
5.安全措施的落实:对吊装现场进行安全措施的落实,如设置安全警示标志、划定作业区域、限制人员通行等。
五、安全措施1.吊装人员必须具备相关操作证书和经验,且经过专业培训。
2.各项吊装设备必须经过检测和试运行,确保安全可靠。
3.吊装现场必须设置专人负责,且装备必要的安全设备,如安全网、安全带等。
变电站新建工程构架吊装专项施工方案范本
变电站新建工程构架吊装专项施工方案范本喀什莎车北郊220 千伏变电站新建工程构架吊装专项施工方案新疆送变电__ 公司二零二一年三月12喀什莎车北郊220千伏变电站新建工程构架吊装专项施工方案批准:年月日审核:年月日年月日年月日编写:年月日年月日3目录一、编制依据················································································································································ 4 二、工程概述················································································································································ 4 2 2. .1 1构架工作量 (5)······························································································································································· 7 2 2. .2 2构、支架安装特点························································································································· 7 2 2. .3 3施工计划安排 (7)三、施工流程及工艺要求····························································································································· 7 3 3. .1 1 施工准备········································································································································· 8 3 3. .2 2基础复测和技术交底··················································································································· 11 3 3. .3 3 现场到货验收及保管··················································································································· 12 3 3. .4 4构件排杆、组装··························································································································· 13 3 3. .6 6构、支架组装的地面验收············································································································ 15 3 3. .7 7构、支架吊装······························································································································· 15 3 3. .8 8构、支架的调整、校正··············································································································· 19 3 3. .9 9混凝土灌浆养护··························································································································· 19 3 3. .10拆除拦风绳................................................................................................................................. 19 3 3. .1 11 接地线制作. (20)四、施工质量要求 (2)0 4 4. .1 1质量检查 (2)0 4 4. .1 1. .2 2组装前检查······························································································································· 20 44. .2 2质量保证措施 (21)五、安全文明施工 (2)3 5 5. .1 1施工工机具检查及保养··············································································································· 23 5 5. .2 2吊装作业安全文明施工··············································································································· 23 5 5. .3 3现场安全监护······························································································································· 24 5 5. .4 4现场指挥 (2)4 5 5. .5 5施工作业环境······························································································································· 24 5 5. .6 6高空作业及高空作业人员············································································································ 24 5 5. .7 7危险源辨识 (25)5 5. .8 8现场安全文明布置....................................................................................................................... 25 六、标准工艺应用.. (2)6 七、质量通病防治措施 (30)八、强制性条文实施管理 (30)九、安全文明施工、环境保护措施及绿色施工························································································· 31 9 9. .1 1施工作业安全技术措施··············································································································· 31 9 9. .2 2现场文明施工措施······.。
主变吊装方案
主变吊装方案随着电力行业的发展,主变吊装成为电力工程中的重要环节。
本文将为您详细介绍一种主变吊装方案,以确保施工顺利进行。
一、工程概况本工程涉及主变吊装,主变容量为XX千伏安,重量约为XXX吨。
吊装高度为XX米,吊装现场地形平坦,不涉及特殊复杂条件。
二、方案介绍根据工程概况,我们设计了以下主变吊装方案:1. 前期准备在正式吊装前,必须进行充分的前期准备。
这包括了以下几个方面:(1)施工现场的准备,包括地面平整、道路畅通等。
(2)吊装设备的检查和保养,确保吊车、钢丝绳等设备的正常工作。
(3)组织吊装人员进行安全培训,确保吊装操作的安全性。
2. 吊装过程在开始吊装前,需要确定吊装方向和吊装点。
吊装过程中应注意以下事项:(1)使用符合国家标准的专业吊装设备,确保其具备足够的吊装能力和稳定性。
(2)根据主变的特点,合理选择合适的吊装索具,在吊装点固定牢固,避免发生滑脱等事故。
(3)由专业吊装人员操作吊车进行吊装,确保吊装过程平稳无误。
(4)随时监测吊装过程中的重量和位置,确保吊装过程安全可靠。
3. 吊装安全吊装安全是吊装工程的核心问题,必须做好以下几个方面的工作:(1)制定详细的吊装方案,确保吊装过程的顺利进行。
(2)严格遵守操作规程,包括吊装人员的装备要求、作业程序、信号传递等。
(3)加强现场安全管理,设立警戒线并进行标识,保证吊装现场的安全区域。
(4)安装必要的监测系统,对吊装过程中的重量、倾斜度等进行实时监控。
三、应急措施在吊装过程中,我们必须考虑到意外情况的发生,制定相应的应急措施:(1)建立健全的应急救援机制,配备必要的急救设备和人员。
(2)提前做好风险评估,避免意外发生。
(3)吊装现场设置紧急停止按钮和紧急疏散通道,确保人员的安全。
四、总结通过以上方案,我们可以确保主变吊装工作的安全、顺利进行。
在吊装过程中,各方面的准备工作十分重要,吊装人员的专业技能和经验也至关重要。
我们将严格按照方案进行施工,确保主变的安全吊装。
主变安装施工技术方案
主变安装施工技术方案一、工程概况本工程为一座电力变电站的主变安装工程。
主变的安装是电力变电站工程中非常重要的一环,关系到电力系统的稳定运行和供电质量。
本文将介绍主变安装施工技术方案,以确保施工过程的安全和有效性。
二、施工准备1.施工组织设计:明确施工组织机构及负责人员,落实人员职责和工作任务。
合理安排施工进度,确保施工进度的顺利进行。
2.施工人员培训:对施工人员进行必要的技术培训,提高其安全意识和操作技能,要求施工人员按要求进行个人防护。
3.材料准备:根据工程设计要求,采购所需的主变设备和施工材料,确保施工的顺利进行。
三、安装工艺流程1.地基处理:按照设计要求进行地基处理,包括基础开挖、回填、压实等工作。
确保基础的稳固和可靠。
2.主变吊装:选取合适的吊装工具和设备,按照设计要求进行主变的吊装。
吊装过程中要注意吊装点的稳固和吊装的平稳。
3.主变与设备的连接:按照设计要求,对主变与周围设备进行连接,包括电缆的接线、接地、粘接等工作。
确保连接的牢固和可靠。
4.主变绝缘:对主变进行绝缘处理,包括绝缘漆的涂刷和绝缘罩的覆盖等。
确保主变的绝缘性能符合要求。
5.精调和调试:对已安装的主变进行精调和调试,包括参数调整、回路测试和工作试验等。
确保主变的正常运行和工作性能符合要求。
6.安全监测和保护措施:在施工过程中,要加强对安全监测和保护措施的落实。
包括设立安全警示标志、进行质量检查和安全巡查等。
四、施工安全措施1.设立警示标志:在施工区域设置明显的警示标志,告知他人不得进入施工区域,确保施工现场的安全。
2.严格个人防护:施工人员要戴好安全帽、安全鞋,佩戴好防护手套和护目镜等,确保施工人员的安全。
3.安全操作规程:制定详细的安全操作规程,对施工人员进行安全培训,确保施工过程中的安全操作。
4.安全监测:对施工现场的安全状况进行定期监测,发现问题及时采取措施进行处置。
5.紧急救援预案:制定紧急救援预案,明确应急救援措施和人员职责,确保在紧急情况下能够及时采取措施保障人员安全。
120KV变电站主变吊装施工方案
变压器吊装方案一、概况刚果(金)卡莫亚铜钴矿一期工程,是一个采、选联合工程,设计规模为采选矿石量3000T/D,达产年产硫化铜钴精矿5.09万吨,氧化铜钴精矿2.61万吨。
120KV变电站主变裸重为30970千克。
其外形尺寸为6125x2150x3180。
由于现场起吊设备起重能力及场地因素限制,单台吊车无法吊装,我部特编制此吊装方案使用两台吊车配合吊装。
二、机具设备单数量备注序号设备或机具名称型号位1 1#汽车吊50吨辆 12 2#汽车吊25吨辆 13 卡环10吨个 44 钢板夹5吨个 25 钢丝绳Φ32 根 46 钢板20*1500*2000 块87 枕木300*300*1500 根30三、人员配置序号工种单位数量备注1 工长人 12 技术员人 13 汽车吊司机人 24 起重工人 15 现场安全员人 16 钳工人 6四、吊装准备1、120KV变电站全部用土方回填,地面全部推平夯实以便一台50吨和一台25吨汽车吊站位。
2、在主变旁边吊车起吊时支腿站立部位铺设好8块20*1500*2000钢板。
4、将主变慢慢转运至基础旁边。
5、将枕木全部搬运至基础旁,吊车站位下支腿时增大受力面积。
五、吊装方法1、两台吊车就位在基础旁边,1号吊车回转半径为5.5m,主臂伸长18.8m,此种情况下吊车最大起重量为27.3吨。
2号吊车回转半径5m,主臂伸长10.5m,此种情况下吊车最大起重量为20t。
可以起吊裸重为30t的主变。
(如图一)图一2、两台吊车在起重工指挥下,慢慢起吊至主变的混凝土平台边上,此时1号吊车吊住一侧在空中不动,回转半径5.5m,主臂18.8m,可以起吊27.3吨,2号吊车回转半径5m主臂伸10.5m,可以起吊20t。
3、两台吊车在起重工指挥下慢慢将主变往基础方向送,直至就位在主变基础上,再将两台吊车松钩收车。
六、安全措施1、现场施工人员必须安要求穿戴好劳动防护用品;2、吊具(钢丝绳、卡环、钢板夹等)全部由现场指挥人员亲自检查一遍;3、地面上用于增大受力面积的钢板枕木必须摆放好,现场指挥人员亲自检查;4、起吊时由专业起重工统一指挥。
主变压器吊装安装施工方案(最新版本)
1#主变安装施工方案批准:日期:年月日审核:日期:年月日编写:日期:年月日南源电力科技股份建阳白茶铺llOkV变电站工程项目部2014年1月—、适用围 (3)二、编制依据 (3)三、作业流程 (3)四、工艺流程说明及主要质量控制要点 (4)五、危险点辨识及预控措施 (14)六、工艺质量要求 (15)七、质量通病防治措施 (17)八、强制性条文 (17)九、质量验评及质量控制方式 (19)1. 适用围本施工方案适用于建阳白茶铺llOkV变电站工程,安装主变压器一台,容量50MVA.主变安装技术比较复杂,工艺要求较髙,必须严格按照设计图纸、GBJ148-90《电气装置安装工程电力电抗器、油浸电抗器、互感器施工及验收规》及厂家技术要求施工。
本文根据设计图纸及厂家提供的mokv电力变压器使用说明书》及相关规并结合施工现场情况编制。
表1主变主要技术参数表向施工人员作技术,安全交底,施工人员必须严格执行。
2.编制依据3. 作业流程图3-1主变安装作业流程图4. 工艺流程说明及主要质量控制要点4. 1作业准备4.1.1现场布置包括变压器油过滤及真空处理设施、附件和吊车等布置(附图2:现场布宜示意图)。
4.1. 2技术准备变压器试验合格证明书(包括电气试验、附件试验和变压器汕):变压器安装说明书:施工图纸;变压器保管记录,包括充干燥气体保管压力(气体保管压力一般为0・01〜0.03MP&,气体的露点应低于70°C)记录和运输过程冲击记录仪记录数据检查(三维冲击记录均必须小于3g)°施工组织机构如下:1)项目负责人:髙欣2)监理工程师:庄建淸3)质检员:黄承林4)现场安全负责人:峰5)起重负责人:金家伟6)吊罩技术负责人:杜洪松7)电气工作班成员:杜洪松胡显军培刚唐伦杰庆奎黄斌建华8)工器具管理员:黄从陆材料准备4. 1. 5主要工器具及仪器准备施工电源布置由于滤油机的加热功率大,对电源的稳宦性可靠要求较髙,特别是在主变真空注油阶段。
主变吊装方案
主变吊装方案1. 引言主变是电力系统中重要的设备之一,其安装过程中的吊装环节尤为重要。
正确的吊装方案能够确保主变的安全运输和安装,并减少不必要的损坏风险。
本文将介绍一种主变吊装方案,包括吊装前的准备工作、吊装过程中的注意事项和吊装方法。
2. 吊装前的准备工作在正式进行主变吊装之前,需要进行一系列的准备工作,以确保吊装过程的安全性和顺利进行。
2.1. 吊装计划在吊装前,应编制详细的吊装计划。
吊装计划应包括以下内容:•吊装时间和地点•主变的重量、尺寸和重心位置•使用的吊装设备和工具•吊装过程中的安全措施•吊装人员的职责分工吊装计划应经过相关部门的审核和批准,并在吊装前由吊装人员进行检查和确认。
2.2. 吊装设备的检查和准备在吊装前,需要对吊装设备进行检查和准备。
主要包括以下内容:•检查起重机械和吊具的工作状态,确保其符合吊装要求•根据主变的重量和尺寸,确定合适的吊装设备和吊具•检查吊装设备的负荷绳、钢丝绳等承重部位,确保其完好无损•对吊装设备进行必要的润滑和维护,保证其正常运行2.3. 吊装区域的准备吊装区域的准备工作主要包括以下内容:•清理吊装区域,确保没有杂物和障碍物影响吊装操作•检查吊装区域的地基承载能力,确保能够承受主变的重量•设置警示标志和临时隔离措施,确保吊装区域的安全3. 吊装过程中的注意事项在主变吊装过程中,需要注意以下事项,以确保吊装过程的安全性和顺利进行。
3.1. 重心的确定和控制主变在吊装过程中,其重心位置的确定和控制非常重要。
在吊装前,应通过详细的测量和计算,确定主变的重心位置。
在吊装过程中,应通过合理的吊装点位选择和吊装绳索的调整,控制主变保持平衡状态,避免因重心偏移导致的意外情况发生。
3.2. 安全距离的保持在吊装过程中,吊装人员需要保持与正在吊装的主变保持安全距离。
吊装人员应站在安全区域内,不得站在主变下方或工作范围内。
这样可以避免在意外情况下对吊装人员造成伤害,并确保吊装操作的安全。
主变吊装方案2022
主变吊装方案20221. 引言主变吊装是电力工程中的一项重要任务,主要用于变压器的安装和维护。
随着电力行业的发展,变压器的规格和重量不断增加,提出了更高的要求和挑战。
为了保证主变吊装的安全和高效,需要制定详细的吊装方案。
本文将重点介绍主变吊装方案2022,包括吊装前的准备工作、吊装方案的设计和实施、以及吊装后的相关操作和注意事项。
2. 吊装前的准备工作在进行主变吊装之前,需要进行一系列的准备工作,以确保吊装的安全和顺利进行。
2.1. 工作团队组建组建一支合适的工作团队是吊装前的第一步。
团队成员应包括有经验的吊装工程师、吊装操作人员、监控人员等。
各个成员应熟悉工作流程和安全规范,并具备相关的资质证书。
2.2. 吊装前的检查和准备在吊装前,需要对吊装设备和工作场地进行检查和准备。
包括但不限于:•检查起重机械和吊装设备的性能和安全状况,确保其符合相关标准和要求;•检查吊装设备的超载保护装置,确保其正常工作;•清理和整理工作场地,确保没有障碍物和安全隐患。
2.3. 监测和测量在吊装前,需要进行相关的监测和测量工作,以确保吊装过程中的安全和可控。
这些监测和测量包括:•对吊装设备进行负荷测试,确保其能够承受吊装任务的重量和负荷;•对主变进行重量和中心重任的测量,以确定合适的吊装方案。
3. 吊装方案的设计和实施设计合理的吊装方案是吊装工作的核心。
吊装方案应根据具体的情况和要求进行设计,并符合相关的标准和规范。
下面是吊装方案设计和实施的一般步骤:3.1. 吊装方案设计吊装方案设计应考虑以下因素:•变压器的重量和尺寸;•吊装设备的能力和限制;•工作场地的布置和条件;•安全风险的评估和控制。
根据以上因素,设计出合理的吊装方案,包括吊装设备的选择、吊装方法和步骤等。
3.2. 吊装方案实施吊装方案实施是吊装工作的关键环节。
在实施吊装方案时,需要注意以下问题:•操作人员应具备相关的技能和经验,熟悉吊装设备的操作步骤和安全规范;•操作人员应进行有效的沟通和协作,确保吊装工作的同步进行;•在吊装过程中,要时刻关注变压器的运动状态和安全情况,并及时调整吊装设备的操作;•吊装完成后,要进行相关的检查和测试,确保变压器的安装质量和性能。
一次设备吊装搬运施工方案
kV变电站一次设备吊装、搬运方案工程项目部20 年月日批准:审核:编制:时间:年月日目录一、设备参数: (1)二、吊装技术参数选择及计算 (1)三、质量保证体系 (2)四、安全技术措施及风险分析 (2)五、劳动力组织 (4)一、设备参数:2.1为便于安装就位变压器,在设备安装的正式轨道外组对一对临时轨道。
临时轨道制作方法:① 将轨道外安装临时轨道场地平整。
并铺设道木垫平。
② 使用δ=16的钢板铺设一块2.6米×2.6米的平台。
③ 在钢板上使用φ20的圆钢焊接二根临时轨道,临时轨道同轨道间距2米2.2 本次吊装采用 T 汽车吊单车吊装就位。
①卸车载荷计算:120吨汽车吊: 120吨汽车吊,主臂长度18.8m ,吊装半径7.18m ,额定载荷50000Kg ,吊车载荷45000Kg ,负荷率为90.0%。
②摆放就位于临时轨道载荷计算:120吨汽车吊: 120吨汽车吊,主臂长度18.8m ,吊装半径4.25m ,额定载荷82000Kg ,吊车载荷45000Kg ,负荷率为54.8%。
③吊装钢丝绳选用:采用一对Φ36-6×37+1FC 、长度为12m 的钢丝绳进行吊装,钢丝绳最小破断拉力为562KN ,钢丝绳双股使用,共计四股受力,每股受力108KN 。
吊车钢丝绳安全系数minF F 拉=η=562/108= 5.2>4,故主吊车钢丝绳满足使用要求。
④卡杆分析设备规格:长5692×宽2700×高3608 主吊车型号:120吨汽车吊 主车工况:支腿全伸,侧面吊装 设备重量:43.2吨吊装重量:45吨(设备重量+平衡梁重量+钩头索具重量)最大吊装半径:7.18米主臂长:18.8米额定载荷:50000KG最大负荷率:90.0%由图可见设备吊装高度足够且不会卡杆2.3变压器安装就位于临时轨道后,在对应的墙壁上开洞,使用10吨倒链安装就位于总降压变压器室内。
三、质量保证体系1、所有新购买的吊装索具,必须出示相应的合格产品证明。
- 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
- 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
- 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。
变压器吊装方案
一、概况
刚果(金)卡莫亚铜钴矿一期工程,是一个采、选联合工程,设计规模为采选矿石量3000T/D,达产年产硫化铜钴精矿5.09万吨,氧化铜钴精矿2.61万吨。
120KV变电站主变裸重为30970千克。
其外形尺寸为6125x2150x3180。
由于现场起吊设备起重能力及场地因素限制,单台吊车无法吊装,我部特编制此吊装方案使用两台吊车配合吊装。
二、机具设备
单
数量备注
序号设备或机具名称型号
位
1 1#汽车吊50吨辆 1
2 2#汽车吊25吨辆 1
3 卡环10吨个 4
4 钢板夹5吨个 2
5 钢丝绳Φ32 根 4
6 钢板20*1500*2000 块8
7 枕木300*300*1500 根30
三、人员配置
序号工种单位数量备注
1 工长人 1
2 技术员人 1
3 汽车吊司机人 2
4 起重工人 1
5 现场安全员人 1
6 钳工人 6
四、吊装准备
1、120KV变电站全部用土方回填,地面全部推平夯实以便一台50吨和一台25吨汽车吊站位。
2、在主变旁边吊车起吊时支腿站立部位铺设好8块
20*1500*2000钢板。
4、将主变慢慢转运至基础旁边。
5、将枕木全部搬运至基础旁,吊车站位下支腿时增大受力面积。
五、吊装方法
1、两台吊车就位在基础旁边,1号吊车回转半径为5.5m,主臂伸长18.8m,此种情况下吊车最大起重量为27.3吨。
2号吊车回转半径5m,主臂伸长10.5m,此种情况下吊车最大起重量为20t。
可以起吊裸重为30t的主变。
(如图一)
图一
2、两台吊车在起重工指挥下,慢慢起吊至主变的混凝土平台边上,此时1号吊车吊住一侧在空中不动,回转半径5.5m,主臂18.8m,可以起吊27.3吨,2号吊车回转半径5m主臂伸10.5m,可以起吊20t。
3、两台吊车在起重工指挥下慢慢将主变往基础方向送,直至就位在主变基础上,再将两台吊车松钩收车。
六、安全措施
1、现场施工人员必须安要求穿戴好劳动防护用品;
2、吊具(钢丝绳、卡环、钢板夹等)全部由现场指挥人员亲自
检查一遍;
3、地面上用于增大受力面积的钢板枕木必须摆放好,现场指挥人员亲自检查;
4、起吊时由专业起重工统一指挥。