预应力混凝土连续箱梁挂篮施工

预应力混凝土连续箱梁挂篮施工
预应力混凝土连续箱梁挂篮施工

预应力混凝土连续箱梁挂篮施工

摘要:通过文塔大桥在施工中出现的跨径大、预埋多、线形、预应力张拉控制、各工序施工衔接顺序以及0#块和合拢段等关键部位的施工控制等角度出发,成功处理了挂蓝施工的难题,为以后碰到类似工程起到一定的借鉴与参考作用。

关键词:挂蓝施工0#块施工悬臂施工现浇段及合拢段施工

Abstract: through the WenTa bridge in construction of large span, buries appear more, linear, prestressed tension control, the process and construction cohesion order blocks and fold section, and other key parts of the construction control Angle, successfully deal with the problem of hang it blue construction for later encounter similar engineering plays a certain reference for action.

Keywords: hang blue construction; blocks 0 # construction; cantilever construction; cast-in-site segments and closed the construction period

1、工程概况

阳山文塔大桥主桥为预应力混凝土3跨连续梁,跨径布置为55m+90m+55m,单幅桥宽为12.25m,横截面左右幅均采用变截面的单箱单室截面,梁高由根部的5.0m高变到合拢段的2.5m高,箱梁顶板宽12.2m,厚28cm,箱梁底宽7.0m,底板厚度由根部的60cm变到合拢段的27cm,腹板为直腹板,厚度由根部的70cm变到合拢段的50cm。梁高按二次抛物线变化,采用纵、横、向预应力张拉。纵向采用ΦS15.2钢铰线作为预应力材料,锚具采用OVM15-9型、OVM15-12型、OVM15-15型、OVM15-17型、OVM15-20型,张拉控制力分别为1757KN、2344KN、2930KN、3320KN、3906KN,钢束张拉以张拉力为主,张拉力与伸长量双控,钢绞线张拉伸长量在10℅张拉控制应力时开始正式测量。横向采用3ΦS15.2钢铰线作为预应力材料,锚具为BM15-3型扁锚,单束张拉控制力为581.7KN,单端张拉,张拉应力控制,采用引伸量校核。主墩临时固结竖向预应力采用JL32精轧螺纹钢,标准强度fpk=930Mpa,张拉控制应力为500KN,以张拉力控制。上部连续箱梁纵向分为54个梁段(5.75m*4+3.5m*12+4m*24+3.75*4+9m*4+2m*6),最大节段重量为538t,上部构造C50混凝土数量为4531.04m3

2、0#块施工

0#块长5.75m,高5.0m,设1道横隔板,2个加劲肋,C50混凝土共224.12m3,节段须一次浇筑完毕,待混凝土强度达到设计强度95℅后,方可张拉预应力钢束。材料、设备竖向运输配1台25T吊车。

2.1临时支墩与托架

主桥0#块托架采用满堂支架施工,支架底坐落在承台上,用型钢作分配

连续梁挂篮施工安全要点

连续梁挂篮施工安全要 点 集团企业公司编码:(LL3698-KKI1269-TM2483-LUI12689-ITT289-

连续梁挂篮施工安全要点(1)采用桁架挂篮施工时,应遵守下列规定: ①挂篮组拼后,要进行全面检查,并做静载试验;挂篮两侧前移要对称平衡进行,大风、雷雨天气不得移动挂篮;挂篮移动到位以后要检查前后锚点、吊带、零号块临时锚固是否到位;挂篮移动中应设观察哨进行监护,并设限位装置。 ②进行零号块施工,并以斜托架做施工平台时,平台边缘应设安全防护设施。墩身两侧托架平台之间搭设的人行道必须连接牢固。 ③使用的机具设备(如千斤顶、滑车、手拉葫芦、钢丝绳等),应进行检查,不符合规定的严禁使用。 ④遇有大风及恶劣天气时,应停止挂篮行走作业。 (2)挂篮使用时,应经常检查后锚固筋、千斤顶、手拉葫芦、张拉平台等是否完好可靠。 (3)挂篮在安装、行走及使用中,应严格控制荷载,防止过大的冲击、振动。

(4)挂篮拼装及悬臂组装中,危险性较大,在高处及深水处作业时,应设置安全网,满铺脚手板,设置临时护栏。操作人员必须按规定佩戴安全防护用品,配备救生设施。 (5)自平桁式挂篮配重,宜用混凝土预制或钢件,不宜用水箱压重,以防水箱损坏泄漏,导致挂篮失衡倾覆。 (6)在底模荡移前,必须详细检查挂篮位置、后端压重及后吊杆安装情况是否符合要求。应先将上横梁两上吊带与底模下横梁连接好,确认安全后,方可荡移。 (7)挂篮行走时,要缓慢进行,速度应控制在0.1米/分钟以内。挂篮后部,各设一组溜绳,以保安全。滑道要铺设平整、顺直,不得偏移,并随时注意观察,发现问题及时处理。 (8)浇筑混凝土时,确认挂篮桁架后端,锚固在已完成的梁段上,并配重使之与浇筑的混凝土重力保持平衡状态。挂篮桁架行走和浇筑混凝土时,其稳定系数不得小于1.5。 (9)浇筑合龙段混凝土时,随浇筑进程,加载逐步撤出时,应自上而下进行。撤出压重时,应注意防止砸伤。

45+80+45m挂篮悬臂浇筑连续梁施工技术方案

1. 编制依据、编制范围及设计概况 1.1编制依据 1) 《公路工程技术标准》(JTG B01-2003); 2) 《公路钢筋混凝土及预应力混凝土桥涵设计规范》(JTG D62-2004); 3) 《公路桥涵设计通用规范》(JTG D60-2004); 4) 《公路桥涵地基与基础设计规范》(JTG D63-2007); 5) 《公路桥涵施工技术规范》(JTG/TF50-2011); 6) 《公路桥涵盆式橡胶支座》(JT/ T391-2009); 7) 《预应力混凝土用金属波纹管》(JG225-2007); 8) 《预应力混凝土用螺纹钢筋》(GB/T20065-2006); 1.2编制范围 施工里程为K1+910.96至K2+089.04引江济汉通航工程毛李公路桥 (45+80+45"预应 力混凝土连续箱梁。 1.3设计概况 江济汉通航工程毛李公路桥桥跨起终点桩号分别是K1+910.96和K2+089.04孔跨布置为(45+80+45",设计均采用挂篮悬浇法施工。 2. 工程综述 2.1工程概况 本标段为引江济汉通航工程施工W5-5标段,标段位于K46+570地处江汉平原。原属 长江二级阶地,地形平坦,地势开阔。 2.1.1 K46+570预应力连续梁简介 主桥上部节后为45+80+45m^跨预应力混凝土连续箱梁,根据设计平面图及桥面标高和路面标高推算及现场踏勘,本连续梁采用挂篮悬臂浇筑法施工。 梁体为单箱单室、变截面结构;连续梁全长170m计算跨度为45+80+45?箱梁根部 高度为4.8米,跨中高度为2.3米;箱梁根部地板厚60厘米,跨中底板厚32厘米,箱梁高度以及箱梁底板厚度按2.0次抛物线变化。箱梁腹板根部厚70厘米,跨中厚50厘米,箱梁顶宽9,5

连续梁挂篮施工工艺

中国中铁八局哈大客运专线项目部连续梁挂篮悬灌指导性施工工艺 目录 1、目的 (24) 2、编制依据 (24) 3、适用范围和特点 (24) 4、施工工艺流程 (24) 4.1、墩顶梁段施工工艺流程 (24) 4.2、悬臂浇筑施工工艺流程 (25) 4.3、合拢段施工工艺流程 (26) 5、施工方法及工艺要求 (27) 5.1挂篮设计 (27) 5.2施工方法 (28) 5.3质量要求及验收标准 (44) 6、箱梁施工的线型控制 (45) 6.1、立模预拱度计算 (45) 6.2、箱梁挠度观测 (46)

1、目的 明确连续梁悬灌施工工艺、操作要点和质量标准,规范和指导悬灌施工作业。 2、编制依据 《客运专线铁路桥涵工程施工质量验收暂行标准》 《客运专线铁路桥涵工程施工技术指南》 《施工图设计文件》 3、适用范围和特点 悬臂浇筑法适用于高墩、大跨径的连续梁、连续刚构,孔下不受通航、通行的限制,其特点是无须建立落地支架,无须大型起重及运输机具,主要施工设备是挂篮。在本项目用于鲅鱼圈特大桥275#~278#墩32+48+32m 跨鮁孔线、341#~346#墩45+3*70+45m跨沈大高速公路匝道、528#~531#墩48+80+48m跨沙鲅铁路连续梁。 挂篮是悬浇施工的主要设备,可在已经张拉锚固并与墩身连成整体的梁体上移动,每段绑扎钢筋、立模、浇筑混凝土、纵向预应力张拉都在挂篮内进行,完成本段施工后,挂篮对称向前各移动一节段。 挂篮吊架在浇筑梁段中所产生变形的调整,能通过调整前吊杆高度办法,或预压配重调整的办法来调整。 挂蓝承重系统有三角形构架、菱形构架、自锚式构架等,下文以三角形构架为例。 4、施工工艺流程 4.1、墩顶梁段施工工艺流程

连续梁菱形挂篮施工工法

连续梁菱形挂篮施工工法 近年来,科学技术的发展大大推动了桥梁设计施工的进步,其中预应力混凝土连续梁桥、刚构桥是采用较多的的桥梁型式。预应力混凝土连续梁桥、连续刚构桥一般跨度大而且跨江河、河谷,所以主要采用悬臂浇筑法施工。以往挂篮一般采用万能杆件、贝雷桁架、军便梁组拼而成,往往结构复杂、质量大、操作不方便;现在的连续梁、连续刚构桥箱梁截面多采用单箱双室或单箱多室截面,桥面宽度大,节段重量较重,要求每个节段全断面一次浇筑,对悬臂浇筑法施工提出了更高的要求,为满足施工需要,出现了各种新的悬臂浇筑法施工方法,其中菱形挂篮悬臂浇筑施工具有设备结构简单、节点少、变形小、操作方便等优点得到了较快的发展。 2.工法特点 2.0.1 在单箱双室(或单箱多室)宽幅箱梁的悬臂浇筑施工中,挂篮结构简单,主桁架杆件受力合理。混凝土应力及挠度变化稳定,节段施工横向稳定性好、抗风能力强,节段施工标高调整方便准确,易于控制桥梁线形。 2.0.2 箱梁采用菱形挂篮悬臂浇筑施工,底蓝及模板系统垂直悬吊在主桁悬臂端,挂蓝行走时,底蓝、外模板、内模滑梁升降同步就位,从而减少工序,缩短作业时间。 2.0.3模板和内外作业平台一次安装形成封闭整体,施工作业防护设施齐全,安全可靠。 2.0.4 菱形挂篮施工悬臂浇筑箱梁,施工作业空间宽敞,并在挂篮主桁上方设置遮阳雨棚,改善工人作业环境。 3.适用范围 本工法适用于预应力混凝土连续梁、连续刚构桥悬臂浇筑施工,尤其是单箱双室或单箱多室的宽幅箱形连续梁、连续刚构桥悬臂浇筑施工。

4.工艺原理 4.1 菱形挂篮的工艺原理: 4.1.1菱形挂篮的安装:在在墩身预埋件、临时支墩上安装三角托架形成工作平台施工0#梁段。0#梁段达到强度后在0#梁段顶面纵向对称安装菱形挂篮;挂篮前端悬吊形成的平台上进行下一个梁段的钢筋、模板、混凝土、预应力张拉、压浆施工。 4.1.2挂篮的移动:挂篮底部设有滑道,使挂篮能够沿桥梁纵向移动,滑道由精轧螺纹钢锚固在已浇注梁段;挂篮静止时后端由精轧螺纹钢锚固在已浇注梁段,移动时后端锚固在滑道上。完成一个梁段的施工后,挂篮后锚由锚固在已浇注梁段变为锚固在滑道上,对称将挂篮移动至下一个梁段直至循环完成所有悬臂节段的施工。 4.1.3合拢段施工:利用挂篮作吊架,在刚性锁定装置安装完毕后,拆除临时支墩释放梁体内部应力,两悬臂端平衡配重,夜间低温、无风的条件下进行合拢段混凝土浇筑,完成全桥梁体施工。 4.2 挂篮设计 4.2.1 挂篮的构造 挂篮主要由菱形主桁架系统、走行及锚固系统、提吊系统、底篮及模板系统、操作平台等六大部分组成,见4.2.1-1挂篮纵断面图及4.2.1-2挂篮横断面图。 滑道 外导梁 后锚 后下横梁 菱形架 前支腿 前下横梁 底纵梁侧模 螺旋千斤顶吊带0# 前上横梁

连续梁挂篮施工安全控制措施标准范本

解决方案编号:LX-FS-A71895 连续梁挂篮施工安全控制措施标准 范本 In the daily work environment, plan the important work to be done in the future, and require the personnel to jointly abide by the corresponding procedures and code of conduct, so that the overall behavior or activity reaches the specified standard 编写:_________________________ 审批:_________________________ 时间:________年_____月_____日 A4打印/ 新修订/ 完整/ 内容可编辑

连续梁挂篮施工安全控制措施标准 范本 使用说明:本解决方案资料适用于日常工作环境中对未来要做的重要工作进行具有统筹性,导向性的规划,并要求相关人员共同遵守对应的办事规程与行动准则,使整体行为或活动达到或超越规定的标准。资料内容可按真实状况进行条款调整,套用时请仔细阅读。 (1)挂篮上使用的所有配件、器具,必须符合国家质量检验标准及受力要求。 (2)施工过程中必须佩戴安全帽、安全带、穿防滑鞋,遵守项目部的相关规章制度。 (3)施工过程中,必须有一名经验丰富的、体力充沛的人员,进行协调统一指挥。 (4)砼浇筑前必须对挂篮上所有锚点及吊点进行检查,必须符合技术交底要求后,方可进行砼浇筑施工。 (5)挂篮应进行使用前的调试组拼,调试组拼

铁路桥梁连续梁挂篮施工技术研究

铁路桥梁连续梁挂篮施工技术研究 摘要挂篮施工作为铁路桥梁连续梁施工的重要内容,施工技术水平含量高,影响整个施工过程。施工中注意挂篮施工的每个细节,对可能出现的偏差做出正确调整,这对工程的顺利进行以及施工安全极为重要。施工中涉及的相关数据,专业人员一定要做好数据测算,保证数据精确性,对于减少挂篮偏差、管道预留孔位移等不利情况的产生有所帮助。 关键词连续梁;建设;铁路桥梁;挂篮;施工 1 连续梁挂篮施工技术综述 在铁路桥梁连续梁施工项目中,实现挂篮施工技术的应用,能够借助挂篮施工多样化形式来提升施工的效率与质量,而提高挂篮施工技术能够为确保施工的安全性,并实现对施工成本费用的有效控制提供保障,进而为提升铁路建设的综合效益奠定基础[1]。立足于铁路桥梁结构,将连续梁挂篮施工技术进行应用,需要着重强调整体结构的稳定性要符合建设设计要求,因此,对于施工单位而言,则就需要实现对结构各部分的承载力进行科学计算,进而优化相应的配置。 2 铁路桥梁连续梁施工中挂篮技术的控制要点 2.1 工程概况 以某铁路工程建设为例,这个连续箱梁主要是以单箱单变室作为其主要的横截面结构,如果该铁路所需要跨越的国道三段总长加起为103m的话,则该段的连续梁的总长则为120m。其中心支座距离两端则为0.9m,那么整个连续梁的三个支座的高度是以二次函数的抛物线的形式跨越國道。挂篮施工是预应力混凝土连续梁悬臂分段浇筑施工的一项主要设备,它以其所特有的高效率、低成本的特点。 2.2 挂篮系统的组成 在施工中通常所需要的挂蓝系统由五大部分组成。①承重系统:由三角形结合梁、前上横梁、后上横梁组成;②底模系统:由纵梁、前横梁、后下横梁以及模板组成;③侧模系统:由内外模支架、模板、吊梁、滑梁组成;④走行系统:由三角结合梁走行系统、侧模走行系统、内模走行系统组成;⑤锚固系统:由压紧器、锚固筋等组成。熟知挂篮系统的五大组成部分,有利于接下来的挂篮施工中挂篮的顺利组装[2]。 2.3 挂篮结构设计、选型以及制作 一是,设计结构和选型。实际建设铁路桥梁的时候,设计桥梁施工的最大荷载和最大承载力,经过大量实践可以发现自锚平衡式三角挂篮施工技术能够切实

连续梁挂篮施工组织设计方案

连续梁挂篮施工方案 1 编制依据 2 工程概况 3 施工技术方案 长阳大街连续梁采用轻型挂篮分段施工,先在主墩旁用碗扣式脚手架和型钢组成支架,预压后灌注0号段(连续梁0号段主墩顶预埋临时固结设备,设临时支座与0号段锁定,合拢后拆除临时锁定),在0号段上安装轻型挂篮,并进行预压,采用菱形挂篮灌注1号梁段,1号节块预应力施工结束后,挂篮前移,开始对称悬臂浇筑其它标准节块,并保证桥梁主墩的两个标准节块基本同步。 标准节块施工的同时,完成边跨现浇段的墩旁支架搭设、混凝土浇筑。在当日最低温度时,灌注中跨、边跨合拢梁段混凝土,形成连续梁。总体按照先边跨合拢后中跨合拢的步骤进行体系转换,完成连续梁的主体施工。 3.1 0#段施工方案 3.1.1 支架施工 (1)支架设计 针对现场情况,对0#段模板施工采用满堂支架的施工方法。在施工过程中,采用WDJ碗扣式脚手架做满堂支架。为确保支架的整体稳定性,立杆采用LG3000、LG1800 、LG1800三种形式交错搭设;横杆采用HG300、HG600、HG900三种形式,水平步高为0.6m。为满足整体稳定,设置纵横向剪刀撑,剪刀撑间距不大于6根立杆。根据荷载的分布情况及检算分别配置,立杆间距在箱梁翼缘板下2.7米范围

内采用90cm×60cm,在两侧腹板采用30cm×60cm,底板在箱梁中心线两侧1.8米范围内采用60cm×90cm。顶部采用可调范围为0~600mm 的可调托座和顶杆调整,顶杆采用DG600、DG900、DG1200三种形式,底部采用可调范围为0~300mm可调垫座调整。 (2)地基处理 碗扣式支架搭设前须进行地基处理。先清除支架范围内的树木等障碍物,将原状土用推土机整平,压路机压实,之后填筑40cm厚砂砾并压实,碾压稳定后,观察无辙痕、无沉降,再通过试验进行检测,压实度不小于93%。面层采用厚度20cmC20混凝土硬化,宽度为14m。(3)支架检算 详见满堂支架计算书。 (4)支架预压 在预压过程中,要根据施工过程的荷载情况进行布载,为减少对箱梁底模板的损伤,在支架搭设完成并铺设完方木、楞木,未铺底模前即对支架进行预压,预压采用在支架顶面堆码砂袋的方式,沙袋用吊车吊装,荷载分布与箱梁荷载分布相同。预压过程中加强布点量测工作,预压进行期间,以消除支架体系非弹性变形,检验基底承载力,量测沉降量,绘制沉降曲线图,待沉降趋于稳定后逐级卸载(持荷时间不小于72h), 当支架的沉降量较大时,要及时对支架进行调整。而后进行箱梁底模施工。底模铺设前根据预压结果和设计计算要求,确定预留拱度。 3.1.2 0#段梁体施工 (1)临时支座施工

连续梁挂篮施工安全要点(通用版)

连续梁挂篮施工安全要点(通 用版) Safety management is an important part of enterprise production management. The object is the state management and control of all people, objects and environments in production. ( 安全管理 ) 单位:______________________ 姓名:______________________ 日期:______________________ 编号:AQ-SN-0985

连续梁挂篮施工安全要点(通用版) (1)采用桁架挂篮施工时,应遵守下列规定: ①挂篮组拼后,要进行全面检查,并做静载试验;挂篮两侧前移要对称平衡进行,大风、雷雨天气不得移动挂篮;挂篮移动到位以后要检查前后锚点、吊带、零号块临时锚固是否到位;挂篮移动中应设观察哨进行监护,并设限位装置。 ②进行零号块施工,并以斜托架做施工平台时,平台边缘应设安全防护设施。墩身两侧托架平台之间搭设的人行道必须连接牢固。 ③使用的机具设备(如千斤顶、滑车、手拉葫芦、钢丝绳等),应进行检查,不符合规定的严禁使用。 ④遇有大风及恶劣天气时,应停止挂篮行走作业。 (2)挂篮使用时,应经常检查后锚固筋、千斤顶、手拉葫芦、

张拉平台等是否完好可靠。 (3)挂篮在安装、行走及使用中,应严格控制荷载,防止过大的冲击、振动。 (4)挂篮拼装及悬臂组装中,危险性较大,在高处及深水处作业时,应设置安全网,满铺脚手板,设置临时护栏。操作人员必须按规定佩戴安全防护用品,配备救生设施。 (5)自平桁式挂篮配重,宜用混凝土预制或钢件,不宜用水箱压重,以防水箱损坏泄漏,导致挂篮失衡倾覆。 (6)在底模荡移前,必须详细检查挂篮位置、后端压重及后吊杆安装情况是否符合要求。应先将上横梁两上吊带与底模下横梁连接好,确认安全后,方可荡移。 (7)挂篮行走时,要缓慢进行,速度应控制在0.1米/分钟以内。挂篮后部,各设一组溜绳,以保安全。滑道要铺设平整、顺直,不得偏移,并随时注意观察,发现问题及时处理。 (8)浇筑混凝土时,确认挂篮桁架后端,锚固在已完成的梁段上,并配重使之与浇筑的混凝土重力保持平衡状态。挂篮桁架行走

连续梁挂篮专项施工方案

挂篮悬浇专项施工方案

目录 一、工程概况 (1) 1.1第十三联连续刚构 (1) 1.2第十四联连续梁 (1) 二、编制目的及编制依据 (3) 2.1编制依据 (3) 2.2编制目的.................................................................................. 错误!未定义书签。 2.3适用范围 (4) 三、施工准备情况 (5) 3.1测量准备 (5) 3.2技术准备 (5) 3.3材料准备 (5) 3.4试验准备 (6) 3.5人员配置 (6) 3.6机械设备准备 (8) 3.7施工顺序及计划 (9) 四、施工工艺及方案 (10) 4.1主要施工技术方案 (10) 4.2施工方法 (11) 4.3工艺流程 (12) 4.4技术参数 (14) 4.5挂篮 (15) 4.5.1安装前准备 (15) 4.5.2挂篮拼装 (15) 4.5.3挂篮预压 (21) 4.5.4挂篮使用 (23)

4.5.5挂篮走行 (23) 4.5.6挂篮锚固 (25) 4.5.7 挂篮拆除 (25) 4.5.8 挂篮安全操作规程 (27) 4.6、1#块施工 (28) 4.6.1模板安装 (29) 4.6.2钢筋及预应力筋安装 (29) 4.6.3预应力安装 (31) 4.6.4混凝土浇筑 (32) 4.6.5预应力施工 (33) 4.6.6孔道压浆及封锚 (34) 4.6.7 1#块施工注意事项 (35) 4.7、模板工程 (35) 4.7.1施工准备 (35) 4.7.2模板施工及加固 (36) 4.8钢筋工程 (36) 4.8.1 普通钢筋加工及安装 (36) 4.9混凝土浇筑及养护 (39) 4.10预应力及压浆 (42) 4.11直线段现浇梁施工方案 (47) 4.11.1 边跨施工工艺流程 (47) 4.11.2 主线桥13联边跨现浇段支架设计方案 (48) 4.11.3 主线桥14联边跨现浇段支架设计方案 (50) 4.11.4 边跨现浇梁段模板工程 (52) 4.11.5 钢筋混凝土工程 (52) 4.12边跨合龙段施工 (52) 4.12.1 边跨合龙段 (52) 4.12.2 设平衡重 (53)

预应力混凝土连续箱梁挂篮施工

预应力混凝土连续箱梁挂篮施工 摘要:通过文塔大桥在施工中出现的跨径大、预埋多、线形、预应力张拉控制、各工序施工衔接顺序以及0#块和合拢段等关键部位的施工控制等角度出发,成功处理了挂蓝施工的难题,为以后碰到类似工程起到一定的借鉴与参考作用。 关键词:挂蓝施工0#块施工悬臂施工现浇段及合拢段施工 Abstract: through the WenTa bridge in construction of large span, buries appear more, linear, prestressed tension control, the process and construction cohesion order blocks and fold section, and other key parts of the construction control Angle, successfully deal with the problem of hang it blue construction for later encounter similar engineering plays a certain reference for action. Keywords: hang blue construction; blocks 0 # construction; cantilever construction; cast-in-site segments and closed the construction period 1、工程概况 阳山文塔大桥主桥为预应力混凝土3跨连续梁,跨径布置为55m+90m+55m,单幅桥宽为12.25m,横截面左右幅均采用变截面的单箱单室截面,梁高由根部的5.0m高变到合拢段的2.5m高,箱梁顶板宽12.2m,厚28cm,箱梁底宽7.0m,底板厚度由根部的60cm变到合拢段的27cm,腹板为直腹板,厚度由根部的70cm变到合拢段的50cm。梁高按二次抛物线变化,采用纵、横、向预应力张拉。纵向采用ΦS15.2钢铰线作为预应力材料,锚具采用OVM15-9型、OVM15-12型、OVM15-15型、OVM15-17型、OVM15-20型,张拉控制力分别为1757KN、2344KN、2930KN、3320KN、3906KN,钢束张拉以张拉力为主,张拉力与伸长量双控,钢绞线张拉伸长量在10℅张拉控制应力时开始正式测量。横向采用3ΦS15.2钢铰线作为预应力材料,锚具为BM15-3型扁锚,单束张拉控制力为581.7KN,单端张拉,张拉应力控制,采用引伸量校核。主墩临时固结竖向预应力采用JL32精轧螺纹钢,标准强度fpk=930Mpa,张拉控制应力为500KN,以张拉力控制。上部连续箱梁纵向分为54个梁段(5.75m*4+3.5m*12+4m*24+3.75*4+9m*4+2m*6),最大节段重量为538t,上部构造C50混凝土数量为4531.04m3 2、0#块施工 0#块长5.75m,高5.0m,设1道横隔板,2个加劲肋,C50混凝土共224.12m3,节段须一次浇筑完毕,待混凝土强度达到设计强度95℅后,方可张拉预应力钢束。材料、设备竖向运输配1台25T吊车。 2.1临时支墩与托架 主桥0#块托架采用满堂支架施工,支架底坐落在承台上,用型钢作分配

挂篮悬臂浇筑连续梁施工工艺

挂篮悬臂浇筑连续梁施工工艺 一、工法概述 1、工法简介 悬臂施工法是在桥墩两侧对称逐段就地浇筑混凝土,待混凝土达到一定强度后,张拉预应力筋,移动机具、模板继续施工。预应力混凝土连续梁桥采用悬臂施工的方法需在施工中进行体系转换,即在悬臂施工时,结构的受力状态呈T形刚构,悬臂梁,待施工合拢后形成连续梁。因此,在桥梁设计中在考虑施工过程的应力状态;要考虑由于体系转换及其他因素引起结构的次内力。内时为使施工受力与运营状态结构的受力尽量吻合,通常用悬臂施工的连续梁桥选取变截面梁。预应力混凝土连续梁桥在悬臂施工时,由于墩梁铰接而不能承受弯矩,因此,施工时要采取措施临时将墩、梁固结。待悬臂施工至少一端合拢后恢复原结构状态,这是连续梁采用悬臂施工法的一个特点。 悬臂施工法不需大量施工支架和临时设备,不影响桥下通航、通车,施工不受季节,河道水位的影响,并能大跨径桥上采用,因此得到广泛的使用。悬臂浇筑的施工方法是大跨连续梁桥的主要施工方法。 2、工法特点 1、易控制悬臂浇筑段标高偏差,能够随时纠正合拢段线形误差,保证弧状线形观感要求。 2、可以减少劳动强度、节省经济成本,施工速度快,能保证安全质量。 3、施工方法简单、易于施工人员掌握。 4、需要较完整的配套机械设备,机械化程度高。 5、有较好的社会效益和经济效益。 3、工法适用范围 1、适用于同类型墩高、大跨连续梁的悬浇施工。 2、适用于风力在10级以下的悬浇梁施工。 3、适用于工期紧,而且安全因素复杂的悬浇梁施工。 二、施工准备 2.1 技术管理 2.1.1施工前完成设计图纸会审和设计技术交底,施工方案和专项技术措施的审核、审批。 2.1.2对所用参与施工的人员进行技术培训和交底。 2.1.3 每分项工程施工前,必须经过工前检查,并签发检查合格证,由现场技术人员和安全员进行检查,并由施工负责人进行签认。 2.1.4 现场检查、测量的数据等检测应在专用记录本上及时做好记录并签字,数据信息要真实、完整、准确、清晰。

连续梁挂篮施工方法及施工工艺

连续梁挂篮施工方法及施工工艺 1.1挂篮设计 采用三角形挂篮以中墩为中心形成T构对称、平衡悬浇施工。中墩旁设置塔吊负责钢筋及小型机具、材料垂直运输,墩旁设置封闭之字梯供人员上下。 ⑴挂篮设计 根据混凝土悬臂浇注工艺及对挂篮设计的技术要求,综合各种形式的挂篮施工特点、用钢量、钢材种类、操作工艺等研究比选后,决定采用三角轻型挂篮施工,走行方式为无平衡重走行方式,使桁架走行时的稳定系数大于2.0,满足规范要求。满足挂篮下净高不小于1.5m。挂篮由承重系统、底模系统、模板系统(内、外)、走行系统、后锚固系统组成。 ①承重系统 每套挂篮由三片三角形组合梁组成,三角形组合梁由2根工字钢主梁和2根槽钢立柱、φ32的精轧螺纹钢斜拉带及联系角钢组成。三角形组合梁下设滑道,滑道下铺钢枕。 前上横梁:采用2根槽钢栓接于主梁前端上翼缘,横梁设翼缘侧模、底板、顶板竖向承重吊杆。同时设平联与主梁连接,防止失稳。 立柱:底部接主梁中部上翼缘,采用IV级精轧螺纹粗钢筋与主梁前后端斜拉,作为斜拉杆,横向设有平联相互连接,保证主梁稳定性。

b、底模系统 底模长1.0m在混凝土悬臂施工中承担钢筋混凝土重量及施工机具重量,并兼做施工操作平台。底模采用大块钢模板,模板平铺于底板纵梁上,纵梁在底板下采用2根槽钢。底板纵梁与前下横梁、后下横梁采用栓接,前下、后下横梁均采用2根槽钢。 c、模板系统(内、外) 外模用槽钢及角钢做骨架,其外围为大块钢模,钢模面板用5 mm热轧板,骨架与模板连接均采用焊接,侧模用滑梁悬吊,滑梁后设滑轮,以便滑梁、侧模同时滑出,内模采用槽钢和角钢做骨架,钢木组合模板,采用滑梁移动。 d、走行系统 分为三角形组合梁走行系统,侧模走行系统及内模走行系统三部分。 三角形组合梁走行系统:在每片梁中部设滑动点,后部设平衡导向滑轮,箱梁顶面上设滑道,向前滑移。 侧模走行:外模走行,在侧模滑梁上安装滚动轴,当松开后锚拴及支撑拆模时,在自重作用下,侧模落在滑梁上,与主梁、侧模、内模滑梁同时前进。 内模走行:放松内模后,内模板即落在滑梁上,与主梁、侧模、内模同时前进。 后锚拴采用Φ32精轧螺纹粗钢筋。作用是将挂篮承受的

连续梁挂篮施工安全控制措施(2021年)

连续梁挂篮施工安全控制措施 (2021年) Security technology is an industry that uses security technology to provide security services to society. Systematic design, service and management. ( 安全管理 ) 单位:______________________ 姓名:______________________ 日期:______________________ 编号:AQ-SN-0630

连续梁挂篮施工安全控制措施(2021年) (1)挂篮上使用的所有配件、器具,必须符合国家质量检验标准及受力要求。 (2)施工过程中必须佩戴安全帽、安全带、穿防滑鞋,遵守项目部的相关规章制度。 (3)施工过程中,必须有一名经验丰富的、体力充沛的人员,进行协调统一指挥。 (4)砼浇筑前必须对挂篮上所有锚点及吊点进行检查,必须符合技术交底要求后,方可进行砼浇筑施工。 (5)挂篮应进行使用前的调试组拼,调试组拼后,要进行仔细地检查各部件联接牢固情况,各接头焊缝是否合格,杆件是否变形等现象,各联接配件是否齐全,尺寸是否按设计要求,发现问题及时整改。

(6)及时准备机具设备并进行检查 ①千斤顶:在使用前应对各部位所使用的千斤顶大小,按技术要求准备好,并进行调试检查,不合格的千斤顶不能使用。 ②倒链:使用前要进行仔细地检查倒链的每一个链环接头是否会脱焊,各齿倒顺要灵活,吊重的吨位要符合设计要求,禁止使用小吨位的倒链代替大吨位使用,确保施工过程中的安全。钢丝绳的使用安全:在挂篮上各部位所使用的钢丝绳粗细要严格按照设计要求进行准备,不得任意使用不合格的钢丝绳。钢丝绳两头的吊环要用穿绳法,重要部位禁止使用U型卡做绳头吊环,防止使用过程中绳头滑脱,发生安全事故。 ③精轧钢及螺母:使用前精轧钢必须为新购合格的,并且不能存在变形。吊杆下吊点必须采用双螺母,螺母下端精轧钢必须留有2道以上的丝扣。 ④螺母垫片:螺母垫片必须采用2cm厚以上钢板或2根16以上槽钢制作的扁担梁,它们的长度必须大于挂篮各主横梁或压梁的宽度,不得局部受力。

连续梁采用挂篮施工安全控制要点示范文本

连续梁采用挂篮施工安全控制要点示范文本 In The Actual Work Production Management, In Order To Ensure The Smooth Progress Of The Process, And Consider The Relationship Between Each Link, The Specific Requirements Of Each Link To Achieve Risk Control And Planning 某某管理中心 XX年XX月

连续梁采用挂篮施工安全控制要点示范 文本 使用指引:此操作规程资料应用在实际工作生产管理中为了保障过程顺利推进,同时考虑各个环节之间的关系,每个环节实现的具体要求而进行的风险控制与规划,并将危害降低到最小,文档经过下载可进行自定义修改,请根据实际需求进行调整与使用。 第一节:一般规定 1.按照现行有关安全生产法律法规的规定,结合工程实 际和项目特点,明确施工安全责任,制定施工安全措施, 加强施工安全管理,有效预防事故发生。 2. 按设计施工,严格执行有关安全技术标准,将安全 技术措施纳入施工组织设计和施工方案,并在施工前向作 业人员进行安全技术交底。 3.对施工现场安全生产情况进行检查,制止违章作业, 清除现场安全隐患。 4.保证安全生产费用的足额投入,确保作业环境安全, 施工安全措施费用不得挪作他用。

5.发现施工现场情况与设计文件不符并影响施工安全时,应立即向有关单位报告,并及时采取安全防范措施。 6.发现重大安全隐患或发生安全事故后,立即启动应急预案,采取有效措施防止事故扩大,并按规定上报事故情况。 第二节:安全管理要点 1.安全管理组织机构:根据项目实际,编制项目相应的施工安全管理制度。坚持按照"管生产必须管安全,谁主管谁负责"的原则。 2.安全资源配置:根据项目施工实际,制定安全费用使用计划,专款专用,配置相应安全资源。 3. 安全管理目标:对安全管理目标要细化和分解责任到每一位领导干部和管理人员,明确责任、实行各级包保制,实现安全无事故目标。 4. 安全教育培训:三类管理人员要具有行业主管部门

【桥梁方案】某铁路桥56米连续梁菱形挂篮行走方案

新建XX铁路XX标段 XX特大桥 (40+56+40)m双线连续梁挂篮行走方案 编制单位:XX 单位主管:XX 技术负责人:XX 审核人:XX 编制人:XX 编制日期: XX年XX月XX日

目录 一、编制依据 (1) 二、工程概况 (1) 三、挂篮的设计情况及挂篮特点 (2) 四、挂篮前移施工 (3) 五、挂篮安全保证措施 (5)

显和特大桥(40+56+40)m连续梁 挂篮行走方案 一、编制依据 1、新建贵广铁路13标招标文件、补遗说明书及招标文件答疑书; 2、相关规范: (1)《高速铁路桥涵工程施工质量验收标准》TB10752-2010; (2)《铁路混凝土工程施工质量验收标准》TB10424-2010; (3)《铁路混凝土工程施工技术指南》铁建设(2010)241号; (4)《高速铁路桥涵工程施工技术指南》铁建设(2010)241号; (5)《铁路预应力混凝土连续梁(刚构)悬臂浇筑施工技术指南》 (TZ324-2010); 3、《有砟轨道预应力混凝土连续梁(双线)》跨度40+56+40m 图号:通桥(2008)2261A-VI 4、《中交四航局贵广铁路工程一项目经理部56m 跨挂篮图纸》 二、工程概况 显和特大桥为贵广线与南广线组合特大桥,起点部分为四线共 线,跨三水二桥南引桥连续梁后贵广线与南广线分道,变为两线桥; 南广线显和特大桥起讫里程桩号为NDK774+442.050-NDK776+049.49, 长度1607.44m,桥墩编号为1#~47#(对应贵广线14#~60#墩),南 广显和特大桥跨越三水大桥南引道处为(40+56+40)m的双线连续梁 结构,南广线连续梁桥墩编号为42#~45#,对应线路里程 NDK775+807.01~NDK775+944.61。 全桥共分34个梁段,中支点0号梁段长度8m,一般梁段长度分 为3.0m、3.5m,合拢段长2.0m,边跨直线段长11.6米。0#块采用的

48+80+48m连续梁挂篮施工专项方案

目录 1编制说明................................................... 错误!未指定书签。 1.1编制依据 ................................................. 错误!未指定书签。 1.2编制范围 ................................................. 错误!未指定书签。2工程概况................................................... 错误!未指定书签。 2.1连续梁工程概况 ............................................ 错误!未指定书签。 2.2连续梁线间距计算表......................................... 错误!未指定书签。 2.3梁横断面图................................................ 错误!未指定书签。 2.4连续梁整体布置立面图 ....................................... 错误!未指定书签。 2.5连续梁分节施工立面图 ....................................... 错误!未指定书签。 2.6连续梁建筑材料 ............................................ 错误!未指定书签。 2.7构造及其他................................................ 错误!未指定书签。 2.8水文、地质及气象条件 ....................................... 错误!未指定书签。3施工组织及安排.............................................. 错误!未指定书签。 3.1施工准备 ................................................. 错误!未指定书签。 3.2施工组织机构.............................................. 错误!未指定书签。 3.3工期安排 ................................................. 错误!未指定书签。4施工方案................................................... 错误!未指定书签。 4.1支座安装及设置临时固结施工 .................................. 错误!未指定书签。 4.20#块梁段施工.............................................. 错误!未指定书签。 4.3悬臂浇筑梁段施工........................................... 错误!未指定书签。 4.4钢筋安装 ................................................. 错误!未指定书签。 4.5混凝土施工................................................ 错误!未指定书签。 4.6各梁段混凝土浇筑施工注意事项................................. 错误!未指定书签。 4.7混凝土养护................................................ 错误!未指定书签。 4.8预应力施工及压浆........................................... 错误!未指定书签。

挂篮悬臂浇筑连续梁施工

挂篮悬臂浇筑连续梁施工工法..

挂篮悬臂浇筑连续梁施工工法 1 工法概述 本工法所述为三向预应力变截面连续混凝土箱梁。施工中在墩顶设临时支座使墩、梁固结,承台上对称设置两组钢管混凝土柱临时支撑梁体,采用支架 现浇0#块、挂篮平衡悬臂浇筑其余块件,最后在跨中合拢。 挂篮悬臂浇筑法适用于不受净空限制的高墩、大跨径的连续梁,连续刚构桥施工。 2 一般要求 2.1 技术管理 2.1.1 施工前完成设计图纸会审和设计技术交底,施工方案和专项技术措施的审核、审批。 2.1.2 对所用参与施工的人员进行技术培训和交底。 2.1.3 每分项工程施工前,必须经过工前检查,并签发检查合格证,由现场技术人员和安全员进行检查,并由施工负责人进行签认。 2.1.4 现场检查、测量的数据等检测应在专用记录本上及时做好记录并签字,数据信息要真实、完整、准确、清晰。 2.1.5 施工过程中及时进行阶段性技术分析总结。2.1.6 施工现场必须严格遵守业主和监理的现场管理要求。 2.2 作业人员 2.2.1 所有作业人员必须经过岗前技术培训,从事电工、高空作业、机械操作等特殊作业的施工人员必须持证上岗。 2.2.2 作业人员应着装整齐、佩戴安全帽进入施工现场,高空作业人员必须佩戴安全带。 2.2.3 作业人员身体健康,无妨碍施工的病症,严禁酒后作业。 2.2.4 作业人员必须遵守劳动纪律,服从统一指挥, 相互协调,严禁违章指挥、违章作业。 2.4.5 所有作业人员必须参加班前技术和安全交底,明确个人任务和职责,掌握操作要求,熟悉安全措施

等。 2.3 设备材料 2.3.1 施工机械应性能良好,定期进行保养和检查,确保正常使用。 2.3.2 主要施工机具设备和安全用具要由专人管理,定期进行性能检查、试验并标识,严禁超期使用。 2.3.3 主要施工机具应定机定人,严格执行交接班制度。接班时,必须对机具检查一次,并做好记录。 2.3.4 进场材料要有质量保证书,并按规定进行抽检试验。材料和施工机具应按规定分类存放,标识清楚,防止损伤、污染。 2.4 作业现场 2.4.1 作业现场布置整洁、合理,林区要有特殊防护措施。 2.4.2 场地应平整、坚实、不积水,符合装卸、搬运、消防等要求。 2.4.3 格遵守文明施工管理要求,现场实行封闭管理。 2.4.4 作业现场应设置有工棚、安全设施、标志、标识牌等。 2.4.3 作业现场紧临黄河大堤,作业现场的布置应精心策划,减少占用林地,施工尽量不破坏黄河大堤的护坡安全性。 2.4.5作业完成清理现场,恢复地貌。 2.5 文件资料 2.5.1 内业文件资料实行标准化管理,及时收集和整理相关施工项目的所有文件资料。 2.5.2 施工组织设计、工艺方案和标准化作业指导手册编写完毕后,经技术负责人审核,批准后实施。 2.5.3 施工过程中现场技术员做好工程日志记录,完整、准确、及时全面反映现场施工情况,做好资料整理与归档。 2.3.4 做好各种材料的质量记录和资料的整理与保存工作,做到各种证明、合格证(单)、验收、试验单据齐全,确保其可追溯和完整性。 2.3.5 施工过程中留取影像资料。 3 工法原理

挂篮悬浇连续梁桥的施工监控

第1题 施工监测一般要求什么时间进行 A.早晨日出之前 B.晚上太阳落山之后 C.没有要求随时都可以测 D.根据施工的进度确定 答案:A 您的答案:A 题目分数:7 此题得分:7.0 批注: 第2题 临时锚固一般何时拆除 A.全桥合拢之后 B.边跨合拢之后 C.中跨合拢之前 D.边跨合拢之前 答案:B 您的答案:B 题目分数:7 此题得分:7.0 批注: 第3题 挂篮一般由哪个单位设计? A.设计单位 B.监控单位 C.施工单位 D.业主委托第三方 答案:C 您的答案:C 题目分数:7 此题得分:7.0 批注: 第4题 立模标高的精度是多少? A.?5mm B.?10mm

D.-2mm,+5mm 答案:A 您的答案:A 题目分数:7 此题得分:7.0 批注: 第5题 立模标高中的预拱度数值是如何确定的 A.施工监控单位自己计算确定 B.由设计单位提供的数值确定 C.根据经验确定 D.施工监控单位计算后请设计单位确认后确定 答案:D 您的答案:D 题目分数:2 此题得分:2.0 批注: 第6题 桥梁施工监控工作开展过程中需要和哪些单位联系 A.建设单位 B.设计单位 C.监理单位 D.施工单位 E.质监站 答案:A,B,C,D 您的答案:A,B,C,D 题目分数:7 此题得分:7.0 批注: 第7题 挂篮预压的目的是什么? A.验证设计 B.消除非弹性变形 C.获取荷载-变形曲线 D.检验临时锚固的性能 答案:A,B,C 您的答案:A,B,C 题目分数:7

此题得分:7.0 批注: 第8题 施工控制的工作内容有哪些? A.有限元分析计算 B.通过立模指令指导现场施工 C.对施工监测数据进行分析,对现场的安全状况进行分析,及时预警 D.有异常情况时,及时组织各参建方共同商讨解决方案 答案:A,B,C,D 您的答案:A,B,C,D 题目分数:7 此题得分:7.0 批注: 第9题 施工监测的内容有哪些? A.梁体的应力 B.挂篮预压的变形观测 C.温度监测 D.梁体的变形观测 E.主墩的沉降观测 答案:A,B,C,D,E 您的答案:A,B,C,D,E 题目分数:7 此题得分:7.0 批注: 第10题 关于合拢段施工哪些说法是正确的? A.边跨合拢段施工时可以不进行配重 B.未来避免混凝土开裂,中跨预应力张拉要快,不宜进行分批张拉 C.合拢段施工的时机宜选择在一天当中温度最低的时段 D.中跨合拢段预应力张拉前主墩墩顶的支座的临时锚固要解除 E.边跨合拢段施工结束后,可以解除主墩的临时锚固 答案:D,E 您的答案:D,E 题目分数:7 此题得分:7.0 批注: