2017冬季施工措施

  1. 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
  2. 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
  3. 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。

目录

第一章编制依据:·····································

······1 第二章工程概况······································

········1 一、工程概况······································

·········1 二、工程简介······································

·········1 三、方案编制目的:·····································

····2 第三章总体部署······································

·········2 一、施工准备······································

·········3 二、现场准备······································

·········3 三、技术准备······································

·········4 四、材料准备······································

·········4 第四章冬季施工措施······································

·5 一、砌筑工程······································

·········5 二、装修工程······································

(6)

1、抹灰工程

·····································

(6)

2、厨房卫生间防水工程

·······························

(7)

3、地砖工程

4、涂料工程

·····································

(8)

5、栏杆工程

·····································

(9)

6、屋面工程

·····································

(10)

7、外墙保温

·····································

(10)

8、门窗工程

·····································

(11)

第五章施工现场及生活区水电防护································11 第六章质

量保证措施······································

·12 一、组织管理框架······································

········12 二、质量管理措施······································

········13 第七章安全文明施工措施······································

·14 一、安全组织框架······································

(14)

二、安全技术管理措施

·································

(14)

郑州航空港区安置区工程冬季施工方案

第一章编制依据:

1、《施工组织设计》;

2、工程合同及相关文件;

3、《关于开展 2017 年冬季“三防”工作的通知》;

4、《建筑施工手册第五版》;

5、《混凝土结构施工及验收规范》(GB50204-2011);

6、《建筑工程施工质量验收统一标准》(GB50300-2013);

7、《建筑工程冬期施工规程》(JGJ/T104-2011 );

8、郑州新郑当地气温资料及历史数据。

第二章工程概况

一、工程概况

工程名称:郑州新郑综合保税区合村并城建设项目安置区工程施工地点:郑州航空港区规划郑港四路与郑港五街交叉口施工单位:中建六局集团有限公司

二、工程简介

1、本工程为 4 栋 11 层住宅楼和地下车库,地上十一层,地下一层 , 最大建筑高度为

36.705m,另在楼群中间有独立的地下车库。其中 5# 楼建筑面积为 11995.77m2 , 6# 楼建筑

面积为 4631.22 m2 , 7# 楼建筑面积为 9966m2, 8#楼建筑面积为 9115.85m2 ,地下车库建筑

面积

5600 ㎡。

2、工程目前施工情况:装饰装修阶段。

3、本年度冬期施工涉及的分项工程有:填充墙砌筑、通风道安装、

门窗安装、墙面抹灰、外墙保温、楼地面和厕浴间防水、屋面工程、地下室装修等。

三、方案编制目的:

1、加强冬期施工技术管理,提高技术管理水平。

2、确保施工质量,避免由于技术措施不当引起不必要的返工、返

修、资源浪费。

3、确保施工安全,达到国家、地方、公司规定的目标。

4、采取正确的冬期施工技术措施。

5、保证施工进度计划的顺利实施。

第三章总体部署

本工程 2016 年 10 月正式进入装饰装修施工, 2017 年 1 月完成全部装饰装修工程量,并

做完竣工验收。 2016 年 12 月将进入冬季施工(具体时间视当地气温确定),施工部位包

括:内外墙抹灰、二遍腻子、填充墙砌筑、厨房卫生间防水、屋面工程(防水卷材、保温板

及保护层、坡屋面挂瓦)、外墙保温工程(外墙抹灰、涂料及部分保温板粘贴)、门窗工程

(窗扇、玻璃安装)、室外回填土工程、地面工程(公共部分贴地砖等)、内墙涂料、栏杆扶

手工程等。

2