35kv集电线路监理细则
(整理)35KV变电站监理细则
云南省牛栏江-滇池补水工程施工供电工程35kV变电站工程建设监理实施细则云南恒诚建设监理咨询有限公司云南省牛栏江-滇池补水工程施工供电监理部2009年11月目录1、监理依据 (1)2、工程控制与协调 (1)2.1 质量控制的内容和方法 (1)2.1.1 目的和适应范围 (1)2.1.2 引用的文件 (1)2.1.3 目标和原则 (2)2.1.4 职责 (2)2.1.5 工作程序 (3)2.2 进度控制的内容和方法 (8)2.2.1 编制变电站工程进度横道图 (8)2.2.2 编制变电站工程进度网络图 (9)2.2.3 控制进度的方法 (9)2.3 进度控制的内容和方法 (12)2.4 安全控制的内容和方法 (15)2.5 合同管理的内容和方法 (15)2.6 信息管理的内容和方法 (17)2.6.1 信息管理所涉及的单位 (17)2.6.2 信息管理的内容 (17)2.6.3 信息管理的要求 (17)2.6.4 信息管理的办法 (17)2.6.5 信息传递的方式 (18)2.6.6计算机信息管理的一般配置 (18)2.7 组织协调的内容和方法 (19)2.7.1监理单位与各有关单位之间的关系 (19)2.7.2协调工作方法 (20)3、监理措施 (21)3.1 主要监理工作的执行程序 (21)3.1.1 施工招标工作程序 (21)3.1.2 征地与交桩程序 (22)3.1.3 四通一平验收程序 (22)3.1.4 开工条件审查程序 (23)3.1.5 施工图会审程序 (24)3.1.6 设计修改程序 (25)3.1.7 整改、停工、复工程序 (25)3.1.8 驻厂监造工作程序 (26)3.1.9 超限设备运输工作程序 (26)3.1.10 现场开箱检验工作程序 (27)3.1.11 计划管理程序 (28)3.1.12 统计程序 (28)3.1.13 土建施工质量验评程序 (29)3.1.14 电气质量验评程序 (30)3.1.15 工程验收程序 (31)3.1.16 变电工程达标投产检查程序 (32)3.2 施工工程中的监理工作 (33)3.2.1 监理作业明细表 (33)3.2.2 监理工程师的受权范围 (33)3.2.3 分项工程的检查项目 (34)3.2.4 监理预检 (35)3.2.5 监理报告 (35)3.2.6 监理月报 (36)4、工程质量验评 (36)4.1 变电工程土建施工质量检查与评定管理细则 (36)4.1.1 变电工程土建施工质量管理细则 (36)4.1.2 四通一平工程质量验收办法 (40)4.1.3控制楼基础验评办法 (42)4.1.4 主控楼主体工程质量验评办法 (43)4.1.5 主控楼装饰工程及所属区性建筑验评办法 (45)4.2 变电工程电气部分的质量检验和评定办法 (48)4.2.1 引用文件 (48)4.2.2 工程质量监督体系和质量等级评定的组织 (48)4.2.3 质量验评工作的范围和时间 (48)4.2.4 质量验评工作的程序 (48)4.2.5 《变电站工程电气质量验评方案》的编制 (49)4.2.6 《变电站工程电气质量验评范围划分表》的编制 (50)5、工程验收 (55)5.1 变电工程验收 (55)5.1.1 验收的范围 (55)5.1.2 验收的依据 (55)5.1.3 验收的组织 (56)5.2 竣工资料的归档内容和技术要求 (57)5.2.1 档案内容 (57)5.2.2 归档分工及技术要求 (59)5.2.3 装订规格与交接时间 (59)5.3 启动期间的监理工作 (60)5.3.1 启动验收委员会的工作内容 (60)5.3.2 监理工作 (60)6、变电工程达标投产检查(预检或复检)方案 (61)6.1 检查依据 (61)6.2 检查时间 (61)6.3 检查的组织 (61)6.4 检查的内容 (61)6.5 检查程序 (61)7、附录 (62)附录A:变电站工程电气监理工作明细表 (62)附录B:变电站工程土建监理工作明细表 (66)附录C:变电站监理作业卡 (70)1、监理依据1.1 本工程《建设监理合同》。
35KV线路监理细则
华能内蒙古茂明风电场二期49.5MW项目监理处35KV集电线路监理实施细则内蒙古康远工程建设监理有限责任公司华能内蒙古茂明风电场项目监理处二0一0年八月审批:总监理工程师:日期:编制:专业监理工程师:日期:目录一、工程概况二、监理依据三、监理范围四、监理目标五、监理措施六、监理方法华能内蒙古茂明风电场二期49.5MW项目工程监理处35kV集电线路监理实施细则一、工程概况:1、工程名称:华能内蒙古茂明风电场二期49.5MW项目工程监理处。
2、工程建设地点:包头市北部达茂旗境内风电场距白云鄂博矿区约25KM,南距包头130KM,距220KV望海变电站直线距20KM处。
3、工程建设规模:集电线路经过现场初步勘测确定,两回主干线大至为由西北向西南走向。
该集电线路分为FJ810KW 3回路支线,全线采用直埋电缆及光缆敷设,最终电缆进入升压站本期35kV间隔。
全部采用电缆ZC-YJY23-26/35型电缆,及GYTA53-6A1a型光缆,总长度25km。
4、工程计划工期:自2010年8月15日开工至2010年11月30日竣工。
5、参建单位:建设单位:华能包头风力发电有限公司设计单位:内蒙古电力勘测设计院监理单位:内蒙古康远工程建设监理有限责任公司施工单位:昌邑市电力工程有限公司质量监督单位:内蒙古电力质检站6、工程特点:华能内蒙古茂明风电项目(49.5MW)工程,位于包头北部达茂旗境内,风电场距白云鄂博矿区约25KM,南距包头130KM,距220KV望海变电站直线距20KM,二期场址范围约27KM海拔平均高程约1600M,场址周围地势较平坦,为广阔的荒漠草原。
二期建设规模为49.5MW,共安装33台风机,风机单机容量为1500KW,轮毂高度65M。
220KV升压站位于二期工程西南侧约2KM,升压站电压等级为220KV。
风力发电机出口电压690V,经35/0.69KV箱式变压器升压至35KV架空集电线路输送至风电场220KV变电站的35KV侧。
35kV送电线路工程监理实施细则
山东物流园仓储贸易区金杨万华木业35KV电力线路工程安全质量控制监理实施细则编制人:审核人:河南卓越监理工程有限公司2014年6月21日目录1工程概况 ........................................................................................................... - 3 -1.1工程参建单位.. (3)2监理范围、监理依据及监理目标......................................................................... - 3 -2.1监理范围 (3)2.2监理依据 (3)2.3监理目标 (5)3监理工作控制的要点及方法................................................................................ - 5 -3.1施工现场监理人员必须严格管控下列违章行为:. (5)4项目监理部工作内容.......................................................................................... - 6 -4.1施工准备阶段监理工作.. (6)4.2监理部对施工安全监督及控制措施 (7)4.3施工用电 (7)4.4气焊及电焊工作 (7)4.5高处作业(凡在高度基准面2米以上有可能坠落的高处进行的作业都应视为高处作业。
) (8)5施工实施阶段监理工作....................................................................................... - 8 -5.1工程分解情况 . (8)5.2施工现场监理人员质量控制 (9)5.2.1进场原材料控制........................................................................................................................ - 9 -5.2.2架空电力线路使用的线材,架设前应进行外观检查,应符合下列规定:................................. - 9 -5.2.3金具组装配合应良好,安装前应进行外观检查,且应符合下列规定: .................................... - 9 -5.2.4 土石方分部工程....................................................................................................................... - 9 -5.2.5 基础分部工程......................................................................................................................... - 10 -5.2.6架线分部工程 ......................................................................................................................... - 11 -5.2.7接地工程................................................................................................................................. - 12 -5.2.8工程交接验收 ......................................................................................................................... - 13 -6附表:............................................................................................................. - 14 -7质量控制点检查方式:..................................................................................... - 15 -35kV送电线路安全质量控制监理实施细则1工程概况1.1工程参建单位工程名称:建设单位:设计单位:施工单位:监理单位:2监理范围、监理依据及监理目标2.1监理范围根据监理合同签订的监理服务范围及所授权限:对工程质量、安全、进度、投资(或仅限于工程量的控制)及有关合同管理,组织开展监理工作。
35千伏电力工程监理实施细则
35千伏电力工程监理实施细则一、项目背景35千伏电力工程是电力系统中的重要组成部分,它负责将发电厂或变电站产生的35千伏电能输送到各用户端。
为保证工程的质量和安全,监理工作必不可少。
本细则旨在规范35千伏电力工程监理实施的具体细节,以确保工程的顺利进行。
二、监理组织1.监理委员会:由项目建设单位、设计单位、施工单位和监理单位等相关单位组成,负责监督工程进展。
2.监理组织:由建设单位聘请的专业监理单位组成,负责实施工程监理。
三、监理职责1.质量监理:监督工程施工过程中的质量控制,包括原材料质量检验、施工工艺合理性等方面的监督。
2.进度监理:监督工程施工进度,确保按照合同约定的时间节点完成工作。
3.安全监理:监督工程施工过程中的安全措施,确保施工人员的安全。
4.费用监理:监督工程施工中的费用使用情况,确保经济合理性。
5.法律监理:监督工程施工中的法律法规遵守情况,确保合法合规。
四、监理内容3.施工进度评估:评估施工进度是否符合合同约定的时间节点。
4.施工质量评估:评估施工过程中的质量控制情况,包括原材料检验、施工工艺。
5.施工安全评估:评估施工过程中的安全措施是否到位。
6.施工费用评估:评估施工中的费用使用情况,确保合理性。
7.施工法律评估:评估施工过程中的法律法规遵守情况。
8.竣工验收:参与工程的竣工验收,确保工程质量达到规定标准。
五、监理报告1.监理日志:监理人员应当每天对施工情况进行记录,包括工作内容、遇到的问题等。
2.监理报告:监理人员应当定期向建设单位提交监理报告,内容包括施工进度、质量、安全等方面的评估和建议。
六、监理权力1.监理人员有权进入工程施工现场进行检查和监督。
2.监理人员有权要求施工单位配合检查和提供相关资料,如发现问题,有权要求施工单位立即进行整改。
七、监理奖惩1.如果监理人员发现施工单位存在严重违规行为,可以向建设单位建议停工或处罚施工单位。
2.如果施工单位未按照监理要求进行整改,监理人员可以向建设单位建议解除合同或采取其他措施。
35KV工程施工监理实施细则(新)
内蒙古华电二连浩特城市风光互补电场一期49.5MW风电场工程35kV集电线路工程监理实施细则内蒙古康远工程建设监理有限责任公司内蒙古华电二连浩特城市风光互补电场工程项目监理处二O一一年四月审批栏批准:年月日审核:年月日编制:年月日目录内蒙古华电二连浩特城市风光互补电场一期49.5MW风电场工程建设35KV集电线路工程(一)基础工程监理实施细则1 目的: (1)2 适用范围: (1)3 监理工作主要依据: (1)4 基础和接地工程设计特点: (1)5监理工作控制要点及目标值: (2)6. 监理工作方法: (5)7. 监理措施: (7)8 监理工作流程图: .........................................................................................内蒙古华电二连浩特城市风光互补电场一期49.5MW风电场工程35kV集电线路工程基础工程监理实施细则1 目的:为了对线路工程建设质量进行有效的监理,确保工程质量符合设计图纸文件、施工验收规范及本工程监理规划的要求,实现工程达标投产和创优,为业主提供满意的服务,特制订本细则。
2 适用范围:本细则适用于本工程35kV集电线路的基础和施工质量管理的监控管理。
3 监理工作主要依据:3.1 本工程建设《监理规划》;3.2 项目法人与各承包商签订的工程建设合同;3.3 已批准的工程初步设计、施工图设计及工程变更文件;3.4 GB50319—2005《建设工程监理规范》;3.5 《GBJ233—90》110~500kV架空电力线路施工及验收规范》;3.6 DL/T5168—2002《110~500kV架空电力线路工程施工质量及评定规程》;3.7 《输变电工程达标投产考核评定标准》3.8 《国家电力公司送变电优质工程评选办法》;3.9 本工程相关的原材料、产品的技术标准;3.10 GB50204-2010《混凝土结构工程施工及验收规范》;3.11 CECS40:《混凝土预制混凝土构件质量控制规程》;3.12 公司质量管理体系文件、《监理工作程序》、《监理工作制度》。
35KV永久供电线路工程施工监理实施细则
35kV永久供电线路工程监理实施细则编号:*****目录35kV永久供电线路工程 (1)监理实施细则 (1)一、工程概况 (1)二、总则 (1)三、施工技术方案审批程序 (1)四、施工过程监理 (2)五、施工质量控制 (5)5.1 原材料及器材检验应符合下列要求 (5)5.2 电杆基坑及基础埋设应符合下列规定 (6)5.3 电杆组立与绝缘子的安装应符合下列规定 (6)5.4 拉线安装应符合下列规定 (7)5.5 现浇砼铁塔基础应符合下列规定 (7)5.6 混凝土浇筑质量应符合下列规定 (8)5.7 铁塔组立 (9)5.8 导线的架线,除应符合单元工程质量检验标准外,还应符合下列要求 (9)5.9 35kV线路上的电气设备安装应符合下列要求 (10)5.10 35kV电力接户线的安装 (10)5.11接地工程的施工应符合下列规定 (10)5.12 架空电力线路的试验项目 (11)5.13 其他 (11)六、工程项目划分、质量评定及验收 (11)七、工程计量与支付 (13)八、施工过程单元质量评定表 (13)一、工程概况*****工程****35kV永久供电线路I标包括:黄河北岸工程、**段、**段、**1段,合同编号**,全线长**km。
**段设计桩号为Ⅳ0+000~Ⅳ**+**,全线长**km。
导线采用LGJ-120/20钢芯铝绞线,地线型号为GJ-35型镀锌钢绞线,地线在各降压站出口约1—1.5千米处架设,其中跨越**段导线采用LGJ-185/30钢芯铝绞线,地线型号为GJ-50型镀锌钢绞线。
全线共用杆塔**基,其中铁塔**基,水泥杆**基,线路总长**km,经过降压站7座;全线共需完成混凝土基础**m3,铁塔组立**吨;线路走径共钻越500kV线路2次,220kV线路3次,110kV线路3次,跨越35kV线路3次,跨越10kV线路12次,380V线路3次,通讯线路17次,跨越公路桥17次。
二、总则2.1 本细则适用于****段35kV永久供电线路工程,主要包括施工技术方案审批程序、施工过程监理、施工质量控制、工程项目划分及质量评定与验收、工程计量与支付以及施工过程监理实施表格等6个部分。
kv集电线路监理细则
大唐齐齐哈尔碾子山风电场工程35kv集电线路工程监理实施细则黑龙江正信建设工程监理有限公司2011年3月20日目录1.监理依据 (1)2.监理范围 (1)3.监理目标 (1)4.质量控制 (1)4.1 施工阶段质量控制程序 (1)4.2质量控制的一般原则 (3)4.3 各分部工程质检内容及要求 (5)4.3.1 基础施工 (5)4.3.2 杆塔组立 (8)4.3.3 架线施工 (9)4.3.4 接地工程 (10)5.进度控制 (10)6. 投资控制 (12)7. 安全控制 (12)8. 监理方法 (12)附表1:工程项目质量检查验收分级项目表 (14)附表2:输电线路工程施工项目监理质量管理点明细表…17-1835kv集电线路工程监理实施细则(审批页)批准:(总监理工程师)年月日审核:(总监代表或专业组长)年月日编制:(专业监理工程师)年月日1 监理依据1.1建设工程监理规范(GB50319―2000)1.2 本工程建设监理规划1.3国家和地方政府的法律、法规及电力行业的有关政策规定和技术规范、标准、规程验评标准等。
1.4“大唐黑龙江新能源开发有限公司”与“黑龙江正信建设工程监理有限公司”签订的《大唐齐齐哈尔碾子山风电场工程建设监理合同》及《大唐齐齐哈尔碾子山风电场工程建设监理合同〉补充协议》1.5已批准的施工图设计及设计修改通知单等有关设计技术文件和工程协调会等施工过程文件1.6输变电工程达标投产考核评定标准(2000年版)1.7电力线路线路工程110kV~500kV线路施工质量检验及评定标准1.8 OPGW工程施工质量检验及评定标准工程1.9政府批准的工程建设文件1.10制造厂提供的商品说明书及安装工作指导书1.11业主对工程质量、进度等提出的要求1.12 为实现大唐新能源开发有限公司对大唐齐齐哈尔碾子山风电场工程建成精品工程的目标,贯彻落实企业各项规章制度及强制性条文。
2 监理范围35KV集电线路建设的设计、施工、调试、竣工验收及保修过程的质量、进度、投资、安全控制,工程建设合同管理、信息管理,协调甲乙方间的关系。
35kV直埋电缆工程监理实施细则(集电线路)
目录一、工程概况及特点 (2)1.1工程概况 (2)1.2工程建设相关单位 (2)1.3专业工程特点 (2)二、监理工作范围和目标 (2)2.1监理范围 (2)2.2监理工作目标 (3)三、监理工作依据 (3)四、关于质量、进度、投资、安全控制 (3)五、各项工作流程 (5)5.1施工监理工作流程 (5)5.2单位工程监理及质量控制流程 (5)5.3施工图会审流程 (5)5.4原材料构配件及设备质量签认流程 (6)5.5隐蔽工程、分项工程认签流程 (6)5.6工程量计量流程 (6)5.7质量事故处理流程 (7)5.8工程停、复工流程 (7)5.9工程设计变更流程 (8)5.10工程竣工验收流程 (8)六、质量控制方针 (9)6.1保证项目 (9)6.2基本要求 (9)一、工程概况及特点1.1工程概况双城万隆49.5MW风电项目位于黑龙江省哈尔滨市双城区北约30km的永胜乡以南2公里,风电场处于丘陵地带与冲积平原的交汇处,为平原风电场。
地表植被为荒地、耕地和林地,地势较为平坦,场地地面高程123.10~129.40m,区内皆为草甸、沼泽。
整个风电场区域面积约27km²。
双城万隆风电场拟建15台单机容量为3200kW的风力发电机组和1台单机容量为1500kW的风力发电机组,总容量为49.5MW,每台风机配置一台箱式变电站。
双城万隆风电场35kV集电线路工程分为A、B两个回路,其中A回路带8座风机(A线:W19、W15、W3、W14、W01、W02、W03、X12),线路总长6.278km,B回路带8座风机(B线:W04、W05、W06、W07、W08、W09、W10、W11),线路总长4.833km。
两条回路电缆直埋敷设长度共计14.21km。
本期35kV电缆线路中箱式变电站至线路终端(转角)塔采用FS-YJL Y63-26/35kV-1×95mm²铝芯电力电缆,塔上加35kV跌落式熔断器。
35KV集电线路监理细则
宁夏恒安监理公司风电项目专业监理实施细则编号:XX FD/HA-B-001-2012恒安监理风电工程35KV集电线路监理实施细则(项目监理机构名称)(加盖项目监理机构公章)年月宁夏恒安监理公司风电项目专业监理实施细则批准:(总监理工程师)年月日审核:(总监代表或专业组长)年月日编写:(专业监理工程师)年月日宁夏恒安监理公司风电项目专业监理实施细则目次1工程概况及特点 ·············································································································1.1工程概况 ··············································································································1.2工程特点 ··············································································································2编制依据 ······················································································································3监理目标 ······················································································································3.1质量控制目标 ········································································································3.2进度控制目标 ········································································································3.3造价控制目标 ········································································································4监理工作流程及重点工作 ·································································································4.1质量控制流程及重点工作 ·························································································4.2进度控制重点工作 ··································································································4.3造价控制重点工作 ··································································································5监理工作内容、措施及方法 ······························································································5.1作业人员控制 ········································································································5.2材料、设备控制 ·····································································································5.3施工机具、检测、计量器具的控制 ·············································································5.4作业方案(措施)的控制 ·························································································5.5作业过程控制 ········································································································5.6作业环境控制 ········································································································6质量通病防治专项措施 ····································································································7质量控制标准及验评 ·······································································································8附件·····························································································································附件1:质量控制流程图(略)························································································附件2:W、H、S点的设置(略) ···················································································附件3:有关监理过程控制、检查、记录表(略) ·······························································宁夏恒安监理公司风电项目专业监理实施细则35KV集电线路监理实施细则1工程概况及特点1.1 工程概况【编写说明】本部分描述的工程概况应在《监理规划》的描述基础上继续细化,侧重从专业层面多使用数据对本专业工程进行描述,而不能像监理规划中那样仅对工程总体情况作概述。
kv集电线路监理细则
k v集电线路监理细则公司内部编号:(GOOD-TMMT-MMUT-UUPTY-UUYY-DTTI-大唐齐齐哈尔碾子山风电场工程35kv集电线路工程监理实施细则黑龙江正信建设工程监理有限公司2011年3月20日目录1.监理依据 (1)2.监理范围 (1)3.监理目标 (1)4.质量控制 (1)4.1 施工阶段质量控制程序 (1)4.2质量控制的一般原则 (3)4.3 各分部工程质检内容及要求 (5)4.3.1 基础施工 (5)4.3.2 杆塔组立 (8)4.3.3 架线施工 (9)4.3.4 接地工程 (10)5.进度控制 (10)6. 投资控制 (12)7. 安全控制 (12)8. 监理方法 (12)附表1:工程项目质量检查验收分级项目表 (14)附表2:输电线路工程施工项目监理质量管理点明细表…17-1835kv集电线路工程监理实施细则(审批页)批准:(总监理工程师)年月日审核:(总监代表或专业组长)年月日编制:(专业监理工程师)年月日1 监理依据1.1建设工程监理规范(GB50319―2000)1.2 本工程建设监理规划1.3国家和地方政府的法律、法规及电力行业的有关政策规定和技术规范、标准、规程验评标准等。
1.4“大唐黑龙江新能源开发有限公司”与“黑龙江正信建设工程监理有限公司”签订的《大唐齐齐哈尔碾子山风电场工程建设监理合同》及《大唐齐齐哈尔碾子山风电场工程建设监理合同〉补充协议》1.5已批准的施工图设计及设计修改通知单等有关设计技术文件和工程协调会等施工过程文件1.6输变电工程达标投产考核评定标准(2000年版)1.7电力线路线路工程110kV~500kV线路施工质量检验及评定标准1.8 OPGW工程施工质量检验及评定标准工程1.9政府批准的工程建设文件1.10制造厂提供的商品说明书及安装工作指导书1.11业主对工程质量、进度等提出的要求1.12 为实现大唐新能源开发有限公司对大唐齐齐哈尔碾子山风电场工程建成精品工程的目标,贯彻落实企业各项规章制度及强制性条文。
35KV变电站监理标准
35KV变电站监理标准1. 引言本文档旨在规范35KV变电站的监理工作,确保工作的顺利进行和施工质量的保证。
2. 变电站监理范围监理工作的范围应包括以下内容:- 设计方案的审查和确认- 施工过程的监督和检查- 材料和设备的验收- 安全和环保控制的监管- 工期管理和进度控制- 质量管理和质量检查- 合同和支付管理3. 监理人员要求监理人员应具备以下条件:- 具备相关专业知识和经验,熟悉35KV变电站的施工和运行要求- 具备良好的沟通和协调能力,能够与各方合作,并解决问题- 具备较强的法律意识和风险识别能力,能够及时做出决策和处理纠纷- 具备独立工作能力和承压能力,能够按时完成工作任务4. 监理工作流程监理工作的流程应包括以下步骤:1. 设计审查:对变电站的设计方案进行审核和确认,包括结构、电气和设备等方面的设计是否符合相关标准和规范。
2. 施工监督:对变电站的施工过程进行监督和检查,确保施工质量和进度符合要求。
3. 材料验收:对使用的材料进行验收,确保其符合规定的质量标准和技术要求。
4. 设备验收:对安装的设备进行验收,包括设备的功能和性能测试,确保设备可以正常运行。
5. 安全和环保监管:监督和检查变电站的安全和环保控制措施,确保施工过程不会对环境造成污染,且符合相关法律法规要求。
6. 工期管理:对施工进度进行管理和控制,确保施工进度符合合同约定的要求。
7. 质量管理:监督和检查施工质量,包括材料和工程质量的控制和管理。
8. 合同和支付管理:监督和管理合同履行和支付情况,确保各方按照合同约定履行义务。
5. 监理结果和报告监理人员应及时提供监理报告,内容包括以下方面:- 设计审查意见和结论- 施工监督检查结果和问题整改情况- 材料和设备验收意见和结论- 安全和环保监管情况- 工期管理和进度情况- 质量管理和检查结果- 合同和支付管理情况6. 附则本标准适用于35KV变电站的监理工作,监理人员应按照本标准中规定的要求进行工作,确保监理工作的有效进行和施工质量的控制。
【细则】35KV变电所安装监理实施细则
【关键字】细则35/10KV变电所安装监理实施细则一、工程概况1、工程名称:银星一井煤矿35/10KV变电所安装工程2、建设单位:银星煤业集团有限责任公司3、设计单位:中煤武汉煤炭设计院4、监理单位:宁夏灵州工程监理咨询公司5、施工单位:宁夏宁通电力有限公司6、建设地点:灵武市白土岗镇宁夏银星煤业有限责任公司银星一井35/10KV变电所电气安装工程,该工作内容按施工设计中所涉及的主要设备变电器、高低压开关、高压成套电容补偿装置有关技术设计资料施工。
本安装工程包含:主变压器SZ11-10000/35 35±3*2.5%/10.5KV 10000KV A3台,电力变压器S11-M800/10 10/0.4KV A 2台,自动跟踪补偿消弧线圈成套装置FRD-XHC-10/10-75型2套,35KV 高压柜KYN61-40.5型13台、10KV高压柜KYN28A-12(Z)42台、主控室装置及保护屏11面、电容器室柜子14面、干湿滤波电抗器6台、3500avr电抗2台、380V低压柜GCS型11台及母线桥、电缆桥架、穿墙套管。
支柱绝缘子、电力电缆、控制电缆、电缆支架、等电力试验的调试安装。
本变电所设防雷直击保护设施独立避雷针4座(其中h1、h2高为25米,h3、h4高为30米)使整个变电所处于防雷保护范围之内,独立避雷针设置有独立的接地装置,主接地网用-50*5镀锌扁钢,接地极选用L50*5 L=2500镀锌角钢。
1、银星一井编制《银星一井煤矿施工组织设计》及修订补充文件;2、银星一井35/10KV变电所电气安装设计施工图纸;3、本项目的《建设工程委托监理合同》4、《银星一井煤矿监理规划》(机电安装);5、《建设工程监理规范》(GB50319-2000);6、《煤矿安全规程》2005版7、《建筑施工安全检查标准》(JGJ59-99)8、《工程建设标准强制性条文》9、《煤矿安装工程质量检检验评定标准》(MT5010-95)10、《电气装置安装工程高压电气施工及验收规范》(GBJ147-90)11、《电器装置安装工程母线装置施工及验收规范》(GBJ149-90)12、《电气装置安装工程电缆线路施工及验收规范》(GB50168-92)13、《电气装置安装工程接地装置施工及验收规范》(GB50169-92)14、《电气装置安装工程盘、柜机二次回路接线施工及验收规范》(GB50171-92)15、《电气装置安装工程电气设备交换试验标准》16、设备安装工程施工除按照本标准有关规定外;必须按照产品技术文件的规定;工程施工设计施工图纸及有关设计说明,并进行安装工程质量的检验评定;本项目的招、投标文件;经国家及自治区批准的现行材料单价、预算定额及有关建设(施工)的管理办法。
- 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
- 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
- 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。
35kv集电线路监理细则大唐齐齐哈尔碾子山风电场工程35kv集电线路工程监理实施细则黑龙江正信建设工程监理有限公司2011年3月20日目录1.监理依据 (1)2.监理范围 (1)3.监理目标 (1)4.质量控制 (1)4.1 施工阶段质量控制程序 (1)4.2质量控制的一般原则 (3)4.3 各分部工程质检内容及要求 (5)4.3.1 基础施工 (5)4.3.2 杆塔组立 (8)4.3.3 架线施工 (9)4.3.4 接地工程 (10)5.进度控制 (10)6. 投资控制 (12)7. 安全控制 (12)8. 监理方法 (12)附表1:工程项目质量检查验收分级项目表 (14)附表2:输电线路工程施工项目监理质量管理点明细表…17-1835kv集电线路工程监理实施细则(审批页)批准:(总监理工程师)年月日审核:(总监代表或专业组长)年月日编制:(专业监理工程师)年月日1 监理依据1.1建设工程监理规范(GB50319―2000)1.2 本工程建设监理规划1.3国家和地方政府的法律、法规及电力行业的有关政策规定和技术规范、标准、规程验评标准等。
1.4“大唐黑龙江新能源开发有限公司”与“黑龙江正信建设工程监理有限公司”签订的《大唐齐齐哈尔碾子山风电场工程建设监理合同》及《大唐齐齐哈尔碾子山风电场工程建设监理合同〉补充协议》1.5已批准的施工图设计及设计修改通知单等有关设计技术文件和工程协调会等施工过程文件1.6输变电工程达标投产考核评定标准(2000年版)1.7电力线路线路工程110kV~500kV线路施工质量检验及评定标准1.8 OPGW工程施工质量检验及评定标准工程1.9政府批准的工程建设文件1.10制造厂提供的商品说明书及安装工作指导书1.11业主对工程质量、进度等提出的要求1.12 为实现大唐新能源开发有限公司对大唐齐齐哈尔碾子山风电场工程建成精品工程的目标,贯彻落实企业各项规章制度及强制性条文。
2监理范围35KV集电线路建设的设计、施工、调试、竣工验收及保修过程的质量、进度、投资、安全控制,工程建设合同管理、信息管理,协调甲乙方间的关系。
3监理目标3.1质量目标:工程建设质量达到国家电力公司电网建设分公司关于“输变电工程创一流考核评定标准”的要求。
分项工程合格率100%,分项工程创优率100%。
不发生重大质量事故。
实现工程高水平达标投产,创电力行业优质工程,争创国家级优质工程。
3. 2进度目标:认真管理和执行工程进度计划,在无不可抗拒因素影响前提下,保证工程阶段性目标的实现,线路施工总工期控制为194个工作日,确保工程按期竣工。
3.3投资控制:按合同中条款中执行。
3. 4安全目标:贯彻“安全第一,预防为主”的方针,杜绝死亡事故和人身、设备、交通等安全事故。
3.5环保控制:工程开工前必须熟悉设计说明书和招标文件,了解、环保有关要求、制定相应的措施尽可能在工程竣工且恢复地表原貌。
力争作到绿色环保工程。
4.质量控制:4.1 施工阶段质量控制监理程序4.2 质量控制的一般原则4.2.1 审查、熟悉施工图纸,积极参加施工图会审和技术交底,提出监理意见并形成纪要。
4.2.2 对主要材料(铁塔、导地线、OPGW、金具、绝缘子等)的质量控制主要通过审查供应商的资质(营业执照、企业资质证书、有关许可证)及到达现场的材料的检验。
对施工承包商报审的《主要材料、构配件及设备供应商资质报审表》及《工程材料/构配件/设备进场报审表》签署监理意见。
4.2.3 对水泥、砂石及基础钢材(包括接地装置)的质量,检查供货单位的资质、产品合格证;审查承包商选择的对上述材料进行抽检复试的试验单位及实验人员的资质并认可,监督和见证施工承包商对上述材料抽检复试。
4.2.4 把好材料进场验收的质量和数量关,督促施工承包商按质量验收规范和计量检测规定对材料的质量和数量进行验收(包括品种、规格、型号、数量、外观、出厂合格证明等),并检查施工承包商的验收记录。
不符合设计图纸规格要求或质量不合格的材料不得进场。
4.2.5 对材料存储、保管与发放进行检查,确定是否造成质量下降或损失。
4.2.6 对施工组织设计进行审查(其要点是质量保证体系、人员配备、施工技术方案、W点H点S点的划分确定、工机具、质量标准等),合格后予以批准。
4.2.7 对施工技术方案措施进行审查(包括对施工质量的保证、施工安全可靠及技术的先进性等)后在《特殊施工技术方案措施报审表》上由监理工程师及总监理师会同签署审查意见。
4.2.8 对施工承包商上报的《特殊工种/特殊作业人员报审表》及《主要测量计量器具/试验设备检验报审表》进行检查认可。
4.2.9 由设计院提出的设计变更,经审查提出监理意见,上报业主批准后监督贯彻执行。
4.2.10 由施工单位提出的设计变更,施工单位先与设计单位研究后,经监理单位进行核实签署意见并上报业主批准后监督贯彻执行。
4.2.11 工程施工分项工程、分部工程及单位工程完成后监理人员进行预验收,对发现的缺陷或质量问题在《分项工程质量报验申请表》、《分部(子分部)工程质量报验单》及《单位(子单位)工程质量报审表》上签署监理意见,并附《监理工程师通知单》通知施工承包商进行整改。
整改后,施工承包商填报《监理工程师通知回复单》,监理人员进行复查并签署复查意见。
最后报请项目法人进行竣工验收。
4.2.12 审查施工承包商的竣工资料。
4.2.13 施工中发生质量事故,应由施工承包商先填报《工程安全/质量事故报告单》,经组织有关单位调查、分析研究后,填报《工程安全/质量事故处理方案报审表》,上述报告分别经设计单位、监理、项目法人审查认可后由施工承包商进行处理。
处理后填报《工程安全/质量事故处理结果报验表》经监理单位查验认可。
4.2.14 发生下列情况之一,且经监理工程师通知施工承包商整改无效时,总监理工程师可在征得业主同意后签发《工程暂停令》。
4.2.14.1 不经审查的设计图纸施工。
4.2.14.2 特殊工种无证操作4.2.14.3 发现不合格材料、半成品、构配件或机具设备有问题。
4.2.14.4 隐蔽工程未经验收签证。
4.2.14.5 上道工序未经检验签证,便进入下道工序。
4.2.14.6 发现不合格项及质量问题整改不力。
4.2.14.7 发生重大质量、安全事故、危及环保及职业健康。
4.2.15 对停工的工程需要复工时,施工承包商应填报《工程复工申请表》经监理检查认可后,方可复工。
4.2.16 正式竣工验收4.2.16.1 竣工验收报验条件·施工承包商已进行了“三级自检”;·施工承包商已按消缺方案对工程缺陷处理完毕并经复查合格;·竣工验收资料已全部整理准备齐全(签证齐全、编目齐全);·影响线路运行安全的通道障碍处理完毕。
如符合以上条件,施工承包商可填写《交付中间验收交接表》报监理单位审核,然后报项目法人审批。
4.2.16.2 验评办法·竣工验收由项目法人组织、质监中心站、监理单位、设计承包商、施工承包商及运行单位共同参加。
·检查验收分内业资料检查和外业现场检查;·质量检验和评定按GBJ233-90《110-500kV架空送电线路施工及验收规范》和《110-500kV架空电力线路工程施工质量检验及评定标准》DL/T6168―2002进行。
·线路经竣工验收应符合已颁布的现行规范、验评标准,质监中心站对工程质量予以评定、项目法人、运行、监理、设计承包商、施工承包商等单位应在竣工验收书上签字。
4.2.17 工程试运行阶段4.2.17.1 督促施工承包商配合线路试验的进行,并及时处理各种突发事故。
4.2.17.2 参与工程投产前的下列试验活动:·测定线路绝缘电阻;·核对线路相位;·测定线路参数的高频特性;·电压由零升至额定值;·以额定电压对线路进行冲击合闸试验;·带负荷试运行。
4.2.17.3 对投产前的各种试验进行签证。
4.2.18 工程项目保修阶段监理。
4.2.18.1 审核施工承包商的《工程保修证书》;4.2.18.2 回访了解工程投运后保修阶段的质量状况;4.2.18.3 对出现的质量缺陷,确定责任方;4.2.18.4 督促施工承包商对施工保修期内的质量问题进行处理;4.2.18.5 对设计原因引起的质量问题,在经过项目法人与设计承包商认可后,协助处理;4.2.18.6 对保修期间发生的质量问题及修复结果,提出监理意见并以书面资料报工程有关单位。
4.3 各分部工程施工质检内容及要求4.3.1 基础施工基础工程是送电线路中的重要隐蔽工程,因此也是监理工作的重点。
现场监理人员必须做到跟踪、旁站监理。
4.3.1.1 送电线路路径、塔位复测监理4.3.1.1.1 线路路径、塔位复测由施工承包商进行,监理工程师可随机抽检其结果。
当发现超过允许偏差时,请其重测。
4.3.1.1.2 基础分坑及开挖工程监理4.3.1.1.2.1 普通铁塔基础分坑时应注意设计给定的施工基面及坑位附近的地形条件,保证基础的边坡稳定。
4.3.1.1.2.2 分坑前施工技术人员应核对基础施工图与铁塔加工图的有关尺寸是否相符,尤其是插入式角钢基础。
分坑时要特别注意不等高腿,尤其是四腿皆不等高的基础间的高差及根开,依据施工承包商编制的分坑手册(或作业指导书)进行检查。
4.3.1.1.2.3 分坑时,基础中心桩位和控制桩必须明确、稳固,基础验收前不准丢失。
无论等高或不等高腿基础,都必须控制单腿及整基基础的扭转。
4.3.1.1.2.4 基础开挖时,监理工程师应根据不同的基础形式,不同的地质条件进行巡视检查,基坑开挖结束时进行验坑。
4.3.1.1.2.4.1 普通土坑开挖时应按土质留有偏坡,坑口周边及坑底留有操作余度。
基坑形状力求规整、坑底平坦。
坑外土应有组织堆放,不得随意扬弃、占用农田及破坏环境。
4.3.1.1.2.4.2 地下水位很高或流砂坑开挖时,应采取降低水位、挡土板、投石压砂等措施完成基坑开挖工作。
监理人员应强调安全施工,防止坑壁坍塌伤人。
当挖掘工作实在困难,不能达到要求坑深,施工承包商要求减少坑深或改变设计时,监理人员应视情况及时向总监理师报告。
在没有得到肯定答复时,施工人员、监理人员无权改变设计,现场停工待命。
4.3.1.1.2.4.3 检查施工基面、风偏坡面及对地开方后净值。
4.3.1.1.2.4.4 基坑未经监理人员验坑,施工人员不得进行基础浇制。
4.3.1.2 基础浇制4.3.1.2.1 基础施工前监理人员检查的内容:4.3.1.2.1.1 原材料(钢材、水泥、砂、石、水)的检验。
在施工承包商提供化验单的基础上,以抽检及现场检查为主,发现不合格的材料,应责令施工人员停止使用,进行处理和更换。