工程管理专业英语专业版

合集下载
  1. 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
  2. 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
  3. 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。

9.1第一段Construction planning is a fundamental and challenging activity in the management and execution of construction projects. It involves the choice of technology, the definition of work tasks, the estimation of the required resources and durations for individual tasks, and the identification of any interactions among the different work tasks. A good construction plan is the basis for developing the budget and the schedule for work. Developing the construction plan is a critical task in the management of construction, even if the plan is not written or otherwise formally recorded. In addition to these technical aspects of construction planning, it may also be necessary to make organizational decisions about the relationships between project participants and even which organizations to include in a project. For example, the extent which sub-construction will be used on a project is often determined during construction planning.

在施工项目的管理和执行中,施工计划是一项基本的并且具有挑战性的活动。它涉及到技术的选择,工作任务的定义、每一个任务所需资源和维持时间的估算,以及不同工作任务之间相互作用的识别等工作。一个好的施工计划是制定工作计划和工作进度的基础。确定施工计划是管理当中的一项重要工作,即使这个施工计划不是书面的或其他正式记录的形式。除了施工计划技术层面的问题之外,项目组织关于项目参与方之间的沟通和联系所作出的有管决策也是十分重要的。例如,分包商在一个项目中所承担的范围通常是在施工计划期间决定的。

四 In developing a construction plan, it is common to adopt a primary emphasis on either cost control or on schedule control as illustrated in Fig. 9-1. Some projects are primarily divided into expense categories with associated costs. In these cases, construction planning is cost or expense oriented. Within the categories of expenditure, a distinction is made between costs incurred directly in the performance of an activity and indirectly for the accomplishment of the project. For example, borrowing expenses for project financing and Project Management for Construction: Construction Planning overhead items are commonly treated as indirect costs. For other projects, scheduling of work activities over time is critical and is emphasized in the planning process. In this case, the planner insures that the proper precenes among activities are maintained and that efficient scheduling of the available resources prevails. Traditional scheduling procedures emphasize the maintenance of task precedences (resulting in critical path scheduling procedures) or efficient use of resources over time (resulting in job shop scheduling procedures). Finally, most complex projects require consideration of both cost and scheduling over time, so that planning, monitoring and record keeping mustconsider both dimensions. In these cases, the integration of schedule and budget information is a major concern. In this chapter, we shall consider the functional requirements for construction planning such as technology choice, work breakdown, and budgeting. Construction planning is not an activity which is restricted to the period after the award of a contract for construction. It should be an essential activity during the facility design. Also, if problems arise during construction, re-planning is required

在制定一项施工计划时,通常在成本控制或进度控制中采用如图9-1所示的主要的重点。一些项目被主要地分为费用类别以及相关成本。在这些情况下,施工计划是成本或费用导向的。

相关文档
最新文档