充电桩项目预算测算报告(2)

充电桩项目预算测算报告(2)

充电桩项目预算测算报告(2)充电桩项目预算测算报告(2)一、项目概述二、预算测算1.设备采购预算根据市场调研和项目需求,我们计划购买30个充电桩设备。

每个充电桩的价格为5000元,共计预算为150,000元。

2.基础设施建设预算为了确保充电桩设备的正常运行,我们需要进行一系列基础设施建设工作,包括电力改造、土建工程等。

根据初步评估,我们估计这些工程的总费用约为60,000元。

3.运营成本预算4.员工薪酬预算为了保障项目的日常运营,我们需要聘请2名专职员工,负责充电桩的维护和管理工作。

根据行业平均薪水水平和工作强度,我们预计每个员工的年薪为50,000元。

因此,员工薪酬预算为100,000元。

5.保险预算为了降低项目运营风险,我们计划购买保险来覆盖充电桩设备的损失和责任。

根据保险公司的报价,我们估计每年的保险费用为10,000元。

6.其他费用预算除了上述所列的费用之外,项目中还会涉及其他费用,如市政审批费用、宣传费用等。

初步估计这些费用约为20,000元。

三、总体预算将以上各项预算加总,得出充电桩项目的总体预算如下:设备采购预算:150,000元;基础设施建设预算:60,000元;运营成本预算:150,000元;员工薪酬预算:100,000元;保险预算:10,000元;其他费用预算:20,000元。

总体预算为:490,000元。

四、风险评估在项目预算测算过程中,我们也对潜在的风险因素进行了评估。

主要的风险因素包括市场需求不及预期、设备故障率高、竞争加剧等。

针对这些风险,我们制定了相应的风险应对措施,如营销策略的灵活调整、提高设备的质量控制、加强与相关合作伙伴的合作等。

五、结论根据上述预算测算和风险评估,我们得出充电桩项目的总体预算为490,000元。

这一预算将用于购买设备、进行基础设施建设、支付运营成本、员工薪酬、购买保险以及其他相关费用。

通过合理的费用控制和风险应对,我们将确保项目的顺利开展和可持续运营。

电动车充电站安装工程合同(2024版)一

电动车充电站安装工程合同(2024版)一

20XX 专业合同封面COUNTRACT COVER甲方:XXX乙方:XXX电动车充电站安装工程合同(2024版)一本合同目录一览1. 工程概况1.1 项目名称:电动车充电站安装工程1.2 项目地点:市区路号1.3 工程规模:共计个充电桩1.4 工程预算:总金额为万元2. 合同主体2.1 甲方:市区路号房屋所有人2.2 乙方:电动车充电站建设有限公司3. 工程内容3.1 乙方负责在甲方提供的场地内进行电动车充电站的安装工作3.2 包括但不限于:充电桩的安装、接通电源、调试及验收等4. 工程进度4.1 工程预计开始时间为2024年月日4.2 工程预计结束时间为2024年月日5. 工程质量5.1 乙方应确保充电站的安装工程质量,符合国家相关法律法规及行业标准5.2 乙方应提供充电站设备的合格证明及质保书6. 工程款项6.1 甲方应按照双方约定的付款进度,向乙方支付工程款项6.2 付款方式:银行转账7. 违约责任7.1 如乙方未按约定时间完成工程,应向甲方支付违约金,违约金为合同总金额的1%7.2 如甲方未按约定时间支付工程款项,应向乙方支付滞纳金,滞纳金为应付款项的1%8. 争议解决8.1 对于因履行本合同而产生的任何争议,双方应通过友好协商解决8.2 如协商不成,任何一方均有权向合同签订地人民法院提起诉讼9. 合同的生效、变更和解除9.1 本合同自双方签字(或盖章)之日起生效9.2 任何一方不得单方面变更或解除本合同,除非经双方协商一致10. 保密条款10.1 双方在合同履行过程中所获悉的对方的商业秘密和机密信息,应予以严格保密11. 合同的转让11.1 未经对方书面同意,任何一方不得将本合同的权利和义务全部或部分转让给第三方12. 法律适用12.1 本合同的签订、履行、解释及争议解决均适用中华人民共和国法律13. 其他约定13.1 本合同一式两份,甲乙双方各执一份13.2 本合同未尽事宜,可由双方另行签订补充协议,补充协议与本合同具有同等法律效力14. 签字盖章14.1 甲方(盖章):14.2 乙方(盖章):14.3 签订日期:2024年月日第一部分:合同如下:第一条工程概况1.1 项目名称:电动车充电站安装工程1.2 项目地点:市区路号1.3 工程规模:共计个充电桩1.4 工程预算:总金额为万元第二条合同主体2.1 甲方:市区路号房屋所有人2.2 乙方:电动车充电站建设有限公司第三条工程内容3.1 乙方负责在甲方提供的场地内进行电动车充电站的安装工作3.2 包括但不限于:充电桩的安装、接通电源、调试及验收等第四条工程进度4.1 工程预计开始时间为2024年月日4.2 工程预计结束时间为2024年月日第五条工程质量5.1 乙方应确保充电站的安装工程质量,符合国家相关法律法规及行业标准5.2 乙方应提供充电站设备的合格证明及质保书第六条工程款项6.1 甲方应按照双方约定的付款进度,向乙方支付工程款项6.2 付款方式:银行转账第七条违约责任7.1 如乙方未按约定时间完成工程,应向甲方支付违约金,违约金为合同总金额的1%7.2 如甲方未按约定时间支付工程款项,应向乙方支付滞纳金,滞纳金为应付款项的1%第八条争议解决8.1 对于因履行本合同而产生的任何争议,双方应通过友好协商解决8.2 如协商不成,任何一方均有权向合同签订地人民法院提起诉讼第九条合同的生效、变更和解除9.1 本合同自双方签字(或盖章)之日起生效9.2 任何一方不得单方面变更或解除本合同,除非经双方协商一致第十条保密条款10.1 双方在合同履行过程中所获悉的对方的商业秘密和机密信息,应予以严格保密10.2 保密期限自本合同签订之日起算,至合同终止或履行完毕之日止第十一条合同的转让11.1 未经对方书面同意,任何一方不得将本合同的权利和义务全部或部分转让给第三方第十二条法律适用12.1 本合同的签订、履行、解释及争议解决均适用中华人民共和国法律第十三条其他约定13.1 本合同一式两份,甲乙双方各执一份13.2 本合同未尽事宜,可由双方另行签订补充协议,补充协议与本合同具有同等法律效力13.3 本合同的修改和补充,应采用书面形式,经甲乙双方共同签署第十四条签字盖章14.1 甲方(盖章):14.2 乙方(盖章):14.3 签订日期:2024年月日第二部分:其他补充性说明和解释说明一:附件列表:附件1:项目地点地形图详细要求:地形图应包括充电站建设区域的详细地形、高程、水文等信息,以便乙方进行工程设计和规划。

充电桩项目预算测算报告(2)

充电桩项目预算测算报告(2)

充电桩项⽬预算测算报告(2)充电桩项⽬预算测算报告规划设计 / 投资分析⼀、预算编制说明本预算报告是xxx集团本着谨慎性的原则,结合市场和业务拓展计划,在公司预算的基础上,按合并报表要求编制的,预算报告所选⽤的会计政策在各重要⽅⾯均与本公司实际采⽤的相关会计政策⼀致。

本预算周期为5年,即2019-2023年。

⼆、公司基本情况(⼀)公司概况顺应经济新常态,需要公司积极转变发展⽅式,实现内涵式增长。

为此,公司要求各级单位通过创新驱动、结构优化、产业升级、提升产品和服务质量、提⾼效率和效益等路径,努⼒实现“做实、做强、做⼤、做好、做长”的发展理念。

公司主要客户在国内、国外均衡分布,没有集中度过⾼的风险,并不存在对某个或某⼏个固定客户的重⼤依赖,公司采购的主要原材料市场竞争充分,供应商数量众多,在采购⽅⾯具有⾮常⼤的⾃主权,项⽬承办单位通过供应商评价体系与部分供应商建⽴了长期合作关系,不存在对单⼀供应商依赖的风险。

未来,公司计划依靠⾃⾝实⼒,通过引⼊资本、技术和⼈才等扩⼤⽣产规模,以“⾼效、智能、环保”作为产品发展⽅向,持续加强新产品研发⼒度,实现⾏业关键技术突破,进⼀步夯实公司技术实⼒,全⾯推动产品结构升级,优化公司利润来源,提⾼核⼼竞争能⼒,巩固和提升公司的⾏业地位。

(⼆)公司经济指标分析在新能源电池技术仍在发展阶段的今天,作为新能源汽车的动⼒输出保障,充电设施建设的完善与否直接关乎到了新能源汽车究竟能开多远,更关乎新能源汽车产业到底能⾛多好。

⾃2014年起,我国开始全⾯开放新能源汽车相关基础设施建设的市场准⼊,⼤⼒推进社会资本投资充电桩建设。

2015年被看作是中国新能源汽车产业发展的元年,新能源汽车的⽕热,同样也带动了充电基础设施⾏业的快速发展。

2015年11⽉17⽇,由国家发改委、国家能源局、⼯信部、住建部四部委联合颁布了《电动电动汽车基础设施发展指南(2015-2020年)》,该指南提出,按照适度超前原则明确充电基础设施建设⽬标,计划到2020年新增分散式充电桩超过480万个,以满⾜新能源汽车的充电需求。

充电桩安装工程合同范本标准

充电桩安装工程合同范本标准

充电桩安装工程合同范本标准甲方:(详细填写甲方信息,包括单位名称、注册地址、邮政编码、法定代表人、联系电话等)乙方:(详细填写乙方信息,包括单位名称、注册地址、邮政编码、法定代表人、联系电话等)一、工程概况1. 项目名称:充电桩安装工程2. 项目地点:(填写充电桩安装位置)3. 总使用功率:(填写充电桩总功率)4. 项目工期:自合同签订之日起,至竣工验收合格为止。

二、工程内容1. 乙方负责为甲方在项目地点进行充电桩的安装工作,包括但不限于:a. 充电桩的土建施工、机电设备安装;b. 充电桩的接线、调试;c. 充电桩的相关设备采购、安装调试;d. 充电桩系统的联网调试。

2. 具体工程内容及实施方案详见工程设计文件。

三、合同价款及付款方式1. 合同价款为(填写具体金额),包括设备采购、施工费用、运输费用、调试费用等。

2. 付款方式:a. 甲方按以下约定的支付比例向乙方支付合同价款:- 合同签订后,甲方向乙方支付合同总价款的20%作为定金;- 甲方验收合格后,向乙方支付合同总价款的50%;- 合同竣工后,经双方共同验收合格后,甲方支付剩余合同价款的30%。

b. 乙方完成阶段性工作后,向甲方提交相应的支付申请,甲方在7个工作日内予以支付。

3. 合同价款不包括增值税,若相关法规要求甲方向乙方支付增值税,则增值税由甲方负责支付。

四、工期保证1. 甲、乙双方应共同按照约定的工期完成工程。

2. 若由于甲方原因导致工期延误,甲方应向乙方按照日计算,支付工程合同价款的0.1%作为违约金。

3. 若由于乙方原因导致工期延误,乙方应向甲方按照日计算,支付合同价款的0.1%作为赔偿金。

五、质量保证及维修保养1. 乙方提供的充电桩设备及施工服务在安装验收后享有一年质量保证期。

2. 乙方应将充电桩的用户使用手册以及售后服务电话提供给甲方,并提供维修保养支持。

六、合同变更和解除1. 合同变更:任何一方变更合同内容,应经双方协商一致,并签署书面变更协议。

安装充电桩报告表

安装充电桩报告表

安装充电桩报告表1. 引言随着电动车的普及和市场需求的增加,充电桩的安装变得愈发重要。

本文将介绍如何编写一份安装充电桩报告表,以便记录、管理和跟踪充电桩的安装过程。

2. 报告表的目的安装充电桩报告表的目的是为了记录充电桩的安装过程,包括位置选择、电源接入、硬件安装等等。

通过报告表,我们可以清晰地了解每个步骤的具体情况,以便日后维护和管理。

3. 编写报告表的步骤步骤一:选择安装位置选择合适的位置是安装充电桩的首要任务。

需要考虑以下几个因素:•充电桩的可见性和易用性:确保充电桩的位置对用户来说易于找到和使用。

•电源接入的便捷性:选择距离电源接入点较近的位置,以减少电线的长度和安装成本。

•停车空间的合理布局:确保充电桩周围有足够的停车空间,以便用户停车充电。

在报告表中,记录选择的充电桩位置和相关考虑因素。

步骤二:准备电源接入在选择好安装位置后,需要准备电源接入。

具体步骤如下:1.确认电源接入能力:联系电力公司或专业人员,确认该位置是否满足充电桩所需的电源容量。

2.安装电源接入设备:根据电力公司或专业人员的要求,安装电源接入设备,如电源线、电源箱等。

在报告表中,记录电源接入的准备过程和具体步骤。

步骤三:硬件安装在准备好电源接入后,可以进行充电桩的硬件安装。

具体步骤如下:1.安装支架:根据充电桩的类型和规格,选择合适的支架,并按照厂家提供的安装说明进行安装。

2.连接电源线:将准备好的电源线连接到充电桩的电源输入端,并确保连接牢固、接线正确。

3.固定充电桩:将充电桩固定在支架上,并进行必要的调整和固定。

在报告表中,记录硬件安装的具体步骤和注意事项。

步骤四:测试和调试完成硬件安装后,需要进行充电桩的测试和调试。

具体步骤如下:1.供电测试:确认电源接入正常,并检查充电桩是否能够正常供电。

2.充电功能测试:使用合适的电动车测试充电桩的充电功能,确保充电桩能够正常充电。

3.网络连接测试(可选):如果充电桩需要连接网络进行管理和监控,进行网络连接测试,确保连接正常。

电动车充电站车棚改造安装预算表

电动车充电站车棚改造安装预算表

规格型号
40*80 ≧6平方 ≧1.5平方 ≧2.5平方
86型
直径≧20毫米 32A三相 亚克力3㎜ 10路
注: 1、本报价不包含土建、配合费、防火费用、脚手架费用; 2、因市场行情波动较大,此报价在三日内有效.
山西小斑马网络有限公司 二0一七年十一月十九日
电动车充电站工程预算表
工程 名称:车棚改造加装电站
序号
项目名称

材料部分
1 方钢
2 电源线
3 电源线
4 电源线
5 插座含专用底盒
6 防水罩
7 PVC线管
8 漏保含箱子9 pvc二维码来自10 小斑马智能充电站
11 附材
12 安装费
二 直接费合计
三 其他
四 工程造价
五 工程单套造价
工程量 单位 单价
0.5 400.0 600.0 100.0
50 20 30 2 50 5 1.00 200.00
T 3200.00
M 3.00
m
1.00
m
2.00
套 7.00
个 17.00
根 6.50
个 70.00
个 6.00
台 1000.00
批 500.00
台 5.00
(一+二+三)x5%
总价/6
合价
1600.00 1200.00 600.00 200.00 350.00 340.00 195.00 140.00 300.00 5000.00 500.00 1000.00 11425.00 571.25 11996.25 1999.38

充电桩安装工程合同范本(2024版)

充电桩安装工程合同范本(2024版)

充电桩安装工程合同范本(2024版)合同编号:__________根据《中华人民共和国合同法》及相关法律法规的规定,甲乙双方在平等、自愿、公平、诚实信用的原则基础上,就甲方委托乙方进行充电桩安装工程的事宜,经友好协商,达成如下协议:一、工程概述1.1 工程名称:充电桩安装工程1.2 工程地点:__________1.3 工程内容:根据委托方的要求,承包方负责进行充电桩的安装工作,包括设备采购、安装、调试及验收等。

二、合同价格2.1 本工程的合同总价为人民币__________元整(大写:__________元整),包括所有工程费用、材料费用、人工费用、税费等。

2.2 甲方应按照双方约定的付款方式及时支付合同款项。

具体付款方式如下:(1)合同签订后____个工作日内,甲方支付合同总价款的____%;(2)工程验收合格后,甲方支付合同总价款的____%;(3)剩余的合同总价款,在保修期满后____个工作日内支付。

三、工程进度3.1 承包方应按照双方约定的工程进度计划进行施工。

工程进度计划如下:(1)工程启动:合同签订后____个工作日内;(2)工程完成:合同签订后____个工作日内;(3)工程验收:工程完成后____个工作日内。

3.2 甲方应按照约定提供施工所需的现场条件,包括但不限于施工场地、电源、水源、交通等。

四、工程质量4.1 承包方应按照国家标准、行业标准和甲方的要求进行施工,确保工程质量。

4.2 工程验收不合格的,承包方应按照甲方的要求进行整改,直至验收合格。

4.3 工程验收合格后,承包方应承担____个月的质保期。

质保期内,因施工质量原因导致的设备故障,承包方负责免费维修或更换。

五、违约责任5.1 任何一方违反本合同的约定,导致合同无法履行或者造成对方损失的,应承担违约责任,向对方支付违约金,违约金为合同总价款的____%。

5.2 因不可抗力导致合同无法履行或者部分履行,经双方协商一致可以解除合同。

充电桩项目预算测算报告

充电桩项目预算测算报告

充电桩项目预算测算报告1.引言2.需求分析根据市场调研和用户需求分析,该充电桩项目计划在城市及主要道路设置充电桩站点,并提供24小时全天候充电服务。

具体需求如下:-充电桩总数:100个-充电功率:每个充电桩最小功率为3.7千瓦,最大功率为22千瓦-充电接口:适应各种电动车充电接口标准-充电方式:支持直流快速充电和交流慢速充电-充电费用:按电量计费,提供便捷的支付方式3.技术方案针对以上需求,我们将采用以下技术方案:-充电桩类型:组合使用快速充电桩和慢速充电桩-充电桩数量分布:在城市及主要道路设置10个充电桩站点,每个站点配备10个充电桩(6个快速充电桩和4个慢速充电桩),确保充电桩的覆盖范围和充电速度-充电桩供电方式:接入电网供电,并配备必要的电力传输设备,如变压器和充电机变换器- 支付方式:通过手机App或刷卡支付的方式进行充电费用结算4.预算测算4.1材料和设备费用-充电桩设备:100个充电桩设备乘以单个充电桩设备的价格,包括充电机、电缆、充电枪等。

-电力传输设备:根据供电要求购买变压器和充电机变换器。

-其他材料:如地基、充电桩基座、安装螺栓等。

4.2人工费用-设计人工费:充电桩站点规划和布局设计工作。

-安装人工费:充电桩设备的安装和调试。

-运维人工费:充电桩设备的定期检修和维护工作。

4.3运营费用-电力费用:根据每个充电桩的平均充电功率和每度电的价格,估算每个充电桩的每月用电费用。

-维护费用:包括定期维护、故障修理和零部件更换等费用。

-运营管理费用:包括充电桩站点运营管理人员工资、物业管理费等费用。

5.预算总结综合考虑以上费用,我们对充电桩项目的预算进行了测算,总额为X 万元。

其中,设备和材料费用占比约为XX%,人工费用占比约为XX%,运营费用占比约为XX%。

6.结论和建议根据该预算测算报告,我们可以得出该充电桩项目在预算方面的投入情况。

在实施过程中,建议加强与供电部门的合作,确保项目的电力接入可靠稳定。

(完整版)充电桩项目安装工程施工方案

(完整版)充电桩项目安装工程施工方案

充电桩项目安装工程施工方案XXXXXXXXXXXXXXXXXXXXXXXXX有限公司1.编制目的和依据1.1编制目的为确保工期、质量及安全、成本及文明工地条件,编制出有针对性的施工组织设计(方案),以指导施工顺利地完成本工程项目的安装。

大力推广应用新技术、新工艺、新材料,控制工程成本,缩短工期,创建优质工程为目的。

2.2编制依据本工程施工组织设计编制依据是根据国家现行规范、规程、质量标准,业主提供施工图纸、施工合同,并结合以往施工同类工程特点、经验、我公司施工能力、技术装备状况编制。

主要编制依据办公楼电气部分施工图纸建筑工程施工质量验收统一标准 GB 50300-200 建筑电气工程施工质量验收规范 GB 50303-2002 1kV及以下配线工程施工与验收规范 GB 50575-2010 电力建设施工质量验收及评定规程第1部分:土建工程 DL5210.1-2005 智能建筑工程质量验收规范 GB50339-2003 2.工程概况工程范围包括:充电设备安装,配电柜安装、电缆敷设、充电系统防雷、接地系统及安全措施。

供电电源:220v/380v低压侧供电电源由箱式变电站引来。

导线的选择及敷设:低压配干线: YJV-3*120+2由箱式变电站低压配电柜至充电桩主配电箱。

低压配电支线:YJV-3*10+2由配电箱至充电桩,YJV-3*2.5由配电箱至充电桩照明。

数据线缆-六类由配电箱至充电桩。

3.主要项目施工方法和技术措施3.1一般规定3.1.1建筑电气装置1kv以下配电系统,必须符合设计要求,满足计量、维护管理、供电运行的安全性及可靠性,确保使用功能。

3.1.2建筑电气1kv及以下配线工程所需的器材,必须符合国家现行的技术标准和施工规范的有关规定。

3.1.3技术文件应齐全①器材的型号、规格及外观质量应符合设计要求,国家现行规范与技术标准的规定。

②每批检查合格证有生产许可证编号,按GB5023.1-5023.7—97标准生产的应有安全生产认证标志;③外观检查:包装完好,抽检的电线绝缘层完整无损,厚度均匀。

充电桩安装工程2024年

充电桩安装工程2024年

充电桩安装工程2024年甲方(委托方):_______乙方(施工方):_______合同编号:_______**签订日期:**2024年_______月_______日签订地点:_______第一条项目概况1.1 项目名称:_______1.2 项目地点:_______1.3 项目内容:本项目包括但不限于充电桩的采购、安装、调试及相关配套设施的建设。

具体内容详见附件一《工程量清单》。

1.4 工程期限:自合同签订之日起至_______年_______月_______日止。

第二条工程质量2.1 工程质量标准应符合国家及行业相关标准,具体标准详见附件二《质量标准》。

2.2 乙方应严格按照设计图纸和施工技术规范进行施工,确保工程质量达到甲方要求。

2.3 甲方有权对工程质量进行监督和检查,乙方应予以配合。

第三条工程价款及支付方式3.1 工程总价款为人民币_______元(大写:_______元整)。

3.2 支付方式:a. 合同签订后_______日内,甲方向乙方支付工程总价款的_______%作为预付款。

b. 工程进度达到_______%时,甲方向乙方支付工程总价款的_______%。

c. 工程竣工验收合格后_______日内,甲方向乙方支付工程总价款的_______%。

d. 质保期满后_______日内,甲方向乙方支付工程总价款的_______%。

第四条工程进度4.1 乙方应根据合同约定的工程期限,合理安排施工进度,并及时向甲方报告工程进度情况。

4.2 因乙方原因导致工程延期的,乙方应承担相应的违约责任。

4.3 因不可抗力或甲方原因导致工程延期的,工程期限相应顺延,双方应协商解决。

第五条材料设备供应5.1 乙方负责采购符合设计要求和质量标准的材料和设备。

5.2 乙方应向甲方提供材料和设备的质量证明文件,并接受甲方的检查和验收。

5.3 甲方有权对乙方采购的材料和设备进行抽查,如发现不符合要求的,乙方应及时更换。

最新自行车棚电瓶充电桩安装工程预算表

最新自行车棚电瓶充电桩安装工程预算表

工程款合计(大写):注:总价超过最高限价75000元的为无效报价,报价品牌在备注栏推荐品牌上选择打钩。

报价人(盖章):附图:初中英语八大时态综合时态练习( )1. What _____ you _____ over the weekend?A. will; doB. does; doC. did; doD. were,; doing( )2. Xiao Li usually _____ to school by bike last year.A. goesB. wentC. will goD. is going( )3. What _____ in our town 100 years from now?A. happenedB. is happenedC. has happenedD. will happen( )4. Mr. Smith _____ to see you in an hour.A. cameB. has comeC. will comeD. comes( )5. _____ you _____ from your parents recently?A. Did; hearB. Have; heardC. Do; hearD. Will; hear ( )6. We _____ TV at home this time last night.A. were watchingB. watchedC. have watchedD. would watch ( )7. We _____ over 1500 English words by the end of last month.A. have learnedB. had learnedC. will learnD. learnt ( )8. She _____ in Shanghai for ten years since 1992.A. has livedB. had livedC. livedD. will live( )9. She _____ in Shanghai for ten years.A. has livedB. had livedC. livedD. will live( )10. We all know that the earth _____ round the sun.A. goesB. wentC. is goingD. will go( )11. “Where are the boys?”“They _____ soccer on the playground.”A. playB. are playingC. were playingD. played( )12. Look! Lucy _____ under the tree.A. readsB. is readingC. was readingD. read( )13. He _____ more than 200 model cars in the last five years.A. has collectedB. had collectedC. collectedD. will collect( )14. Jim _____ a letter to his parents at 7:30 last night.A. had writtenB. wroteC. would writeD. was writing ( )15. The Smiths _____ in Beijing since two weeks ago.A. stayedB. were stayingC. would stayD. have stayed ( )16. “When _____ you _____ the bike?”“Last Monday.”A. have; boughtB. did; buyC. will; buyD. do; buy( )17. Look! The boy _____English now.A. likesB. likedC. is likingD. was liking( )18. Most students in our class _____ TV twice a week.A. watchB. watchedC. will watchD. are watching ( )19. How soon _____ they _____ back from work?A. do; comeB. did; comeC. have; comeD. will; come ( )20. “Where _____ you _____ Mr. Li?”“In his office, half an hour ago.”A. will; seeB. did; seeC. have, seenD. do; see ( )21. I _____ a new dictionary. Look! It’s very useful.A. boughtB. will buyC. have boughtD. would buy。

充电站施工工程预算方案(2篇)

充电站施工工程预算方案(2篇)

第1篇一、项目背景随着新能源汽车的快速发展,充电基础设施建设已成为推动产业发展的关键环节。

本充电站施工工程预算方案旨在为我国某地区新建一座充电站提供详细的预算计划,确保项目顺利实施,提高投资效益。

二、项目概述1. 项目名称:某地区充电站建设项目2. 项目地点:某地区3. 项目规模:建设50个充电桩,包括直流快充桩和交流慢充桩4. 项目周期:预计6个月5. 项目总投资:约1000万元三、预算编制原则1. 符合国家相关法律法规和行业标准2. 保证预算的准确性和合理性3. 综合考虑市场行情和价格波动4. 确保项目顺利进行四、预算编制内容1. 工程费用(1)土建工程费用土建工程包括充电站场地平整、建筑物建设、室外配套设施等。

预算费用如下:- 场地平整:30万元- 建筑物建设:200万元- 室外配套设施:100万元- 合计:330万元(2)电气安装工程费用电气安装工程包括电缆敷设、设备安装、配电室建设等。

预算费用如下:- 电缆敷设:100万元- 设备安装:200万元- 配电室建设:100万元- 合计:400万元(3)智能化系统费用智能化系统包括充电桩控制系统、监控报警系统、数据传输系统等。

预算费用如下:- 充电桩控制系统:100万元- 监控报警系统:50万元- 数据传输系统:50万元- 合计:200万元2. 设备购置费用设备购置包括充电桩、变压器、电缆、配电设备等。

预算费用如下:- 充电桩:500万元- 变压器:100万元- 电缆:100万元- 配电设备:100万元- 合计:800万元3. 人员费用人员费用包括施工人员工资、管理人员工资、技术支持人员工资等。

预算费用如下:- 施工人员工资:100万元- 管理人员工资:50万元- 技术支持人员工资:50万元- 合计:200万元4. 其他费用其他费用包括设计费、监理费、验收费、保险费、绿化费等。

预算费用如下:- 设计费:30万元- 监理费:20万元- 验收费:10万元- 保险费:10万元- 绿化费:5万元- 合计:75万元五、预算汇总根据以上预算编制内容,本充电站施工工程预算汇总如下:- 工程费用:730万元- 设备购置费用:800万元- 人员费用:200万元- 其他费用:75万元- 合计:1705万元六、预算执行与控制1. 加强预算执行管理,确保各项费用合理使用2. 定期对预算执行情况进行检查,及时发现和解决问题3. 加强与供应商的沟通协调,确保设备、材料价格合理4. 严格控制人工成本,提高劳动生产率5. 加强施工现场管理,确保工程质量七、结语本充电站施工工程预算方案为项目顺利实施提供了详细的预算计划。

电动自行车车棚安装施工方案

电动自行车车棚安装施工方案

目录第一章工程概况 (2)第一节工程说明 (2)第二节编制依据 (2)第二章管理体系与保证措施 (3)第一节人员配备、劳动力计划及保证措施 (3)第二节材料采购计划 (4)第三章进度计划与保证措施 (5)第一节施工进度控制措施 (5)第二节工期进度保证措施 (5)第四章质量保证措施 (6)第一节材料采购阶段质量保证措施 (6)第二节施工安装阶段质量保证措施 (7)第五章施工方案与技术措施 (8)第一节材料供应 (8)第二节加工制作 (8)第三节构件涂装工艺及技术措施 (9)第四节保护、运输及仓储和施工 (11)第五节材料的检查、检验 (11)第六节材料的保管及检查 (12)第七节现场安装方案 (12)第六章安全保障措施 (21)第一节编制原则及施工安全管理目标 (21)第二节施工安全管理体系 (21)第三节安全管理制度 (23)第四节分项工程安全技术措施 (25)第七章与甲方及物业在维保方面的配合 (31)附表: (32)一、拟投入本工程的主要机械设备表 (33)二、劳动力计划表 (33)第一章工程概况第一节工程说明一、工程说明1、工程名称:配建项目电动自行车车棚施工工程。

2、工程地点:3、建筑面积:808.06平方米4、施工工期:计划工期60日历天5、质量要求:合格二、工程内容:地块自行车棚施工,包括自行车棚基础、结构施工以及为完成施工内容而发生的障碍物拆除、施工垃圾清运、成品保护等工作内容。

车棚采用160、100、80的圆钢管组合焊接,顶面篷布采用PVDF材质膜结构。

车棚采用160X100X5X5mm及80X50X4X4方钢管焊接,顶面采用8+1.52PVB+8钢化玻璃盖板、硅酮结构胶粘固。

所有金属构件表面两遍金属面氟碳漆喷涂。

隔板采用40X40X3X3mm方钢管,3mm厚造型钢板。

背板钢支架采用80X50X4X4mm方钢及20X20X2角钢焊接,背板采用1.2mm厚造型钢板及2厚钢板造型装饰扣板,背板面板采用5mm厚钢化玻璃。

2024年充电桩安装工程合同范本(2篇)

2024年充电桩安装工程合同范本(2篇)

2024年充电桩安装工程合同范本合同编号:【合同编号】甲方:【甲方名称】地址:【甲方地址】统一社会信用代码:【甲方统一社会信用代码】乙方:【乙方名称】地址:【乙方地址】统一社会信用代码:【乙方统一社会信用代码】鉴于甲、乙双方在充电桩安装工程方面具有相应的技术能力和经验,并经友好协商,达成如下合作意向,特订立本合同:第一条合同目的本合同的目的在于约定甲方委托乙方进行充电桩安装工程,并明确双方在工程过程中的权利义务。

第二条工程范围1. 甲方委托乙方进行充电桩安装工程,包括但不限于充电桩设备的选型购买、工程设计、设备安装、系统调试等。

2. 具体的工程范围、规模、进度等事项详见附件《充电桩安装工程方案》。

第三条工程费用1. 本工程总投资为【投资金额】。

2. 工程费用的支付方式为【支付方式】,具体的支付比例和节点详见附件《工程费用支付计划表》。

3. 甲方应按照支付计划表的约定,按时支付相应的工程款项给乙方。

第四条工期1. 工程的施工周期为【XX】个月。

2. 自本合同签订之日起,乙方应按照工期计划,按时完成工程,并保证工程的质量。

第五条质量保证1. 乙方保证在工程施工过程中,严格按照相关法律法规和标准要求进行操作,保证工程质量符合相关规定。

2. 工程完工后,乙方提供一年的免费质量保修期,保证设备的正常运行。

第六条知识产权1. 本合同中涉及的所有技术和知识产权归属甲方所有。

2. 乙方在执行本合同过程中所产生的一切技术和知识产权均归属甲方所有。

第七条保密条款1. 甲乙双方在本合同履行过程中,对获取的对方商业秘密及其他保密信息应严格保守,不得向任何第三方披露。

2. 乙方不得将甲方的商业秘密及其他保密信息用于其他目的,包括但不限于用于与甲方竞争或泄露给其他竞争对手。

第八条违约责任1. 任何一方违反本合同约定的内容,应承担相应的违约责任。

2. 违约方应在收到对方书面通知后【XX】天之内进行整改,如逾期未整改的,守约方有权解除合同。

电动车充电站安装工程合同(2024版)版

电动车充电站安装工程合同(2024版)版

20XX 专业合同封面COUNTRACT COVER甲方:XXX乙方:XXX电动车充电站安装工程合同(2024版)版本合同目录一览1. 工程概述1.1 工程名称:电动车充电站安装工程1.2 工程地点:_______1.3 工程日期:自合同签订之日起至____年__月__日2. 合同双方2.1 甲方名称:_______2.2 甲方地址:_______2.3 乙方名称:_______2.4 乙方地址:_______3. 工程内容3.1 充电站设计:根据甲方要求,设计符合相关规范的充电站方案3.2 充电站设备采购:按照设计方案,采购所需的充电设备3.3 充电站安装:按照设计方案和规范要求,进行充电设备的安装工作3.4 充电站验收:工程完成后,进行验收,确保充电站正常运行4. 合同价格4.1 合同总价:人民币____元(大写:____元整)4.2 支付方式:合同签订后__日内,甲方支付乙方合同总价__%;工程验收合格并交付使用后,甲方支付乙方合同总价__%5. 工程进度5.1 设计阶段:自合同签订之日起__日内完成充电站设计方案5.2 采购阶段:自设计方案确定之日起__日内完成设备采购5.3 安装阶段:自设备到达施工现场之日起__日内完成充电站安装5.4 验收阶段:自充电站安装完成后__日内进行验收6. 质量保证6.1 乙方保证所提供的设备符合国家相关标准和规范6.2 乙方负责充电站安装过程中的质量控制,确保工程质量6.3 工程验收合格后,乙方提供__年的质保服务7. 售后服务7.1 乙方负责对甲方进行充电站操作和维护的培训7.2 乙方在质保期内,对充电站设备进行维护和维修7.3 乙方在质保期内,对充电站设备进行升级和更新8. 合同的变更和解除8.1 合同的变更:合同履行过程中,如需变更,双方协商一致后签订补充协议8.2 合同的解除:因不可抗力或其他不可预见的原因导致合同无法履行,双方协商一致后解除合同9. 违约责任9.1 甲方未按约定时间支付合同款项,乙方有权暂停工程进度,甲方需支付违约金9.2 乙方未按约定时间完成工程,甲方有权要求乙方支付违约金9.3 乙方提供的设备不符合国家相关标准和规范,甲方有权要求乙方更换或修复10. 争议解决10.1 双方在履行合同过程中发生的争议,通过友好协商解决10.2 如协商不成,任何一方均有权向合同签订地的人民法院提起诉讼11. 合同的生效、变更和解除11.1 本合同自双方签字盖章之日起生效11.2 本合同的变更和解除,必须经双方协商一致,并以书面形式签订补充协议12. 其他约定12.1 双方应遵守国家相关法律法规,不得从事违法经营活动12.2 双方应保守合同中的商业秘密,未经对方同意不得向第三方披露13. 合同附件13.1 充电站设计方案13.2 充电站设备清单13.3 充电站施工图纸14. 合同份数14.1 本合同一式两份,甲乙双方各执一份,具有同等法律效力第一部分:合同如下:第一条工程概述1.1 工程名称:电动车充电站安装工程1.2 工程地点:_______1.3 工程日期:自合同签订之日起至____年__月__日第二条合同双方2.1 甲方名称:_______2.2 甲方地址:_______2.3 乙方名称:_______2.4 乙方地址:_______第三条工程内容3.1 充电站设计:根据甲方要求,设计符合相关规范的充电站方案3.2 充电站设备采购:按照设计方案,采购所需的充电设备3.3 充电站安装:按照设计方案和规范要求,进行充电设备的安装工作3.4 充电站验收:工程完成后,进行验收,确保充电站正常运行第四条合同价格4.1 合同总价:人民币____元(大写:____元整)4.2 支付方式:合同签订后__日内,甲方支付乙方合同总价__%;工程验收合格并交付使用后,甲方支付乙方合同总价__%第五条工程进度5.1 设计阶段:自合同签订之日起__日内完成充电站设计方案5.2 采购阶段:自设计方案确定之日起__日内完成设备采购5.3 安装阶段:自设备到达施工现场之日起__日内完成充电站安装5.4 验收阶段:自充电站安装完成后__日内进行验收第六条质量保证6.1 乙方保证所提供的设备符合国家相关标准和规范6.2 乙方负责充电站安装过程中的质量控制,确保工程质量6.3 工程验收合格后,乙方提供__年的质保服务第七条售后服务7.1 乙方负责对甲方进行充电站操作和维护的培训7.2 乙方在质保期内,对充电站设备进行维护和维修7.3 乙方在质保期内,对充电站设备进行升级和更新第八条合同的变更和解除8.1 合同的变更:合同履行过程中,如需变更,双方协商一致后签订补充协议8.2 合同的解除:因不可抗力或其他不可预见的原因导致合同无法履行,双方协商一致后解除合同第九条违约责任9.1 甲方未按约定时间支付合同款项,乙方有权暂停工程进度,甲方需支付违约金9.2 乙方未按约定时间完成工程,甲方有权要求乙方支付违约金9.3 乙方提供的设备不符合国家相关标准和规范,甲方有权要求乙方更换或修复第十条争议解决10.1 双方在履行合同过程中发生的争议,通过友好协商解决10.2 如协商不成,任何一方均有权向合同签订地的人民法院提起诉讼第十一条合同的生效、变更和解除11.1 本合同自双方签字盖章之日起生效11.2 本合同的变更和解除,必须经双方协商一致,并以书面形式签订补充协议第十二条其他约定12.1 双方应遵守国家相关法律法规,不得从事违法经营活动12.2 双方应保守合同中的商业秘密,未经对方同意不得向第三方披露第十三条合同附件13.1 充电站设计方案13.2 充电站设备清单13.3 充电站施工图纸第十四条合同份数14.1 本合同一式两份,甲乙双方各执一份,具有同等法律效力第二部分:其他补充性说明和解释说明一:附件列表:附件一:充电站设计方案详细要求和说明:本附件应包括充电站整体设计方案,包括但不限于充电设备的选型、布局、电气系统设计、防雷及安全防护措施等。

2024年充电桩建设安装工程合同模板

2024年充电桩建设安装工程合同模板

2024年充电桩建设安装工程合同模板本合同目录一览第一条合同主体及定义1.1 合同双方1.2 充电桩建设安装工程1.3 合同文件第二条工程范围与内容2.1 工程概述2.2 充电桩设备及参数2.3 施工地点与期限第三条合同价格与支付3.1 合同总价3.2 支付方式3.3 支付条件第四条工程质量与标准4.1 质量要求4.2 检验标准4.3 质量保证第五条施工许可与手续5.1 施工前的许可5.2 施工中的监管5.3 施工后的验收第六条技术支持与服务6.1 技术培训6.2 售后服务6.3 技术更新第七条合同的变更与解除7.1 变更条件7.2 解除条件7.3 变更或解除的程序第八条违约责任8.1 违约行为8.2 违约责任8.3 违约赔偿第九条不可抗力9.1 不可抗力的定义9.2 不可抗力的后果9.3 不可抗力的处理第十条争议解决10.1 争议的解决方式10.2 仲裁程序10.3 法律适用第十一条合同的生效、终止与失效11.1 合同的生效条件11.2 合同的终止条件11.3 合同的失效条件第十二条保密条款12.1 保密信息12.2 保密义务12.3 保密期限第十三条法律、法规与合规13.1 法律法规的遵守13.2 合规要求13.3 合规审查第十四条其他条款14.1 合同的补充14.2 合同的转让14.3 附件清单第一部分:合同如下:第一条合同主体及定义1.1 合同双方1.2 充电桩建设安装工程1.3 合同文件本合同文件包括:合同协议、工程量清单、技术参数、图纸、说明书、补充协议等,上述文件一经签署即构成本合同不可分割的一部分,具有同等法律效力。

第二条工程范围与内容2.1 工程概述本工程包括但不限于充电桩的设备采购、运输、安装、调试、验收、培训、售后服务等。

2.2 充电桩设备及参数乙方应按照甲方提供的技术参数和图纸要求,提供符合国家标准和行业规定的充电桩设备。

2.3 施工地点与期限施工地点:甲方指定的地点。

施工期限:自合同签订之日起至工程验收合格之日止。

电动车充电桩车棚施工合同

电动车充电桩车棚施工合同

电动车充电桩车棚施工合同甲方(以下简称“业主”):乙方(以下简称“施工方”):根据《中华人民共和国合同法》及相关法律法规的规定,甲乙双方在平等、自愿、公平、诚信的原则基础上,就甲方委托乙方进行电动车充电桩车棚施工事宜,达成如下协议:一、工程概况1.1 工程名称:电动车充电桩车棚施工工程1.2 工程地点:____________(具体位置见附件一)1.3 工程规模:车棚面积为____平方米,充电桩数量为____个(具体位置和数量见附件二)1.4 工程预算:人民币(大写):____元整(小写):____元1.5 工程质量标准:符合国家相关法律法规及行业标准。

二、合同工期2.1 工期自双方签订合同之日起计算,施工期为____天。

2.2 施工方应当按照约定的工期完成工程。

如因施工方原因导致工程延期,施工方应当承担相应的违约责任。

三、施工内容3.1 施工方应当按照甲方提供的施工图纸和技术要求进行施工。

3.2 施工方应当负责车棚的设计、材料采购、施工、验收等一切相关工作。

3.3 施工方应当保证施工过程中的人员安全、质量安全、施工安全。

四、材料和设备4.1 施工方应当根据工程需要,采购符合国家标准的材料和设备。

4.2 施工方应当在施工前将材料和设备的样品报甲方审查,甲方同意后方可进行采购。

4.3 施工方应当对所采购的材料和设备进行质量检验,确保质量合格。

五、工程款支付5.1 双方约定采用以下付款方式:(1)合同签订后,甲方支付施工方工程预算的30%作为预付款;(2)工程进度达到50%时,甲方支付施工方工程预算的30%;(3)工程验收合格后,甲方支付施工方工程预算的20%。

5.2 施工方应当提供正规发票,甲方按照约定时间支付工程款。

六、工程验收6.1 工程完成后,施工方应当组织自检,自检合格后向甲方申请验收。

6.2 甲方收到申请后,应当在约定的时间内组织验收。

验收合格的,双方签署验收报告。

6.3 验收不合格的,施工方应当按照甲方的要求进行整改,直至达到验收标准。

充电桩成本构成核算表

充电桩成本构成核算表

充电桩成本构成核算表
充电桩成本构成核算表主要用于详细列出充电桩的各项成本,以便于企业进行全面成本控制和盈利分析。

下面是一个充电桩成本构成核算表的范例,供您参考:
注:
1.充电桩设备购置费:购买充电桩设备的费用,单价乘以数量得出总价。

2.安装施工费:安装充电桩所需的人工费用,单价乘以数量得出总价。

3.土地租赁费:租赁用于安装充电桩的土地的费用,按年计算。

4.电力接入费:将充电桩接入电网所需的费用,单价乘以数量得出总价。

5.运营维护费:充电桩日常运营和维护的费用,按年计算。

6.管理费用:管理充电桩项目的费用,按年计算。

  1. 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
  2. 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
  3. 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。

精品文档自行车棚电瓶充电桩安装工程报价单
序号项目名称项目特征计量
工程量
综合单价合价
单位( 元 )
备注
( 元 )
1 配线 6 平方毫米铜芯线套管安装米360 推荐品牌:菊花、蓝天、正泰、
六环
2 配线 2.5 平方毫米铜芯线套管安装米480 推荐品牌:菊花、蓝天、正泰、
六环
3 配线普通网线套管安装米150 推荐品牌:菊花、蓝天、正泰
4 配管20PVC线管安装(有铝合金扁管的应安装管内,其他
米400
推荐品牌:中财、公元、伟星、明装)高丰
40×100 铝合金扁管,壁厚不小于 2.5 ,安装时两根拼
5 铝合金扁管安装接,包含拼接及固定在车棚内所需要的所有附件和安米110 1 推荐品牌:凤铝、亚铝、广成
装费用。

(工程量栏目中的数量为两根拼接后的长度)
简要说明:
(1)箱体尺寸为:高 360* 宽 260* 厚 120(单
位;MM);
(2)箱体颜色材质:环保绿,冷轧钢板外表抛
6 投币机安装光处理后喷塑;台 4
( 3)固定方式:壁挂式;
(4)一台投币机带10 个插座,分别可以单独投币充
电。

包含安装及所有附件,详见样品图(仅供参考)。

推荐品牌:公牛、正泰、德力7 普通插座安装普通 2+3 孔插座安装 , 安装在铝合金扁管上。

只40
西
8 刷卡主机安装联网主机。

由浙江正元供货,必须与学院现有一卡通
台 1 联网,包含安装及所有附件。

9 刷卡插座安装刷卡插座安装,安装在铝合金扁管上(由浙江正元供
只70 货,必须与学院现有一卡通联网)。

10 配电箱不锈钢明装箱,固定安装在车棚内。

只 3
12 漏保安装40A 单相漏保,安装在配电箱内。


推荐品牌:公牛、正泰、德力6
西
13 小计
14 税金
合计
工程款合计(大写):
注:总价超过最高限价75000 元的为无效报价,报价品牌在备注栏推荐品牌上选择打钩。

报价人(盖章):
附图:。