CONSTRUCTION ORGANIZATION DESIGN
FRAME WORKS FOR
BASF THE/POLY-THF EQUIPMENT
1. Description
Nature of the works: Investor and owner of the works is BASF Chemical Co., Ltd. and TECHNIP TIANCHEN CHEMICAL ENGINEERING (TIANJIN)Co., Ltd. is responsible for general contract management.
Basis of the organization design:
Working drawings, design description and related standard atlas provided by TECHNIP TIANCHEN CHEMICAL ENGINEERING (TIANJIN)Co., Ltd.;
Topography of the construction site and existing buildings (structures) or to be built in the surroundings of the works;
Construction contract for the works;
Geological report;
National specifications, procedures, standards or codes for acceptance of works and Shanghai Municipal regulations and requirements in respect of building construction being currently effective.
2. Outline of the works
Outline of the works
The works is located within SCIP with building area of 3841.63m2 (occupies the land of 7329m2) and is one-story structural frame, reference to the schedule of works items for the details.
Table 1- Schedule of works items
The construction of the works will be commenced on June 6, 2003 and completed on Nov.15 2003 according to the works program, and its total construction period is 140 calendar days. It’s an isolated foundation of PHC piles and caps, with foundational depth of burial of 1.5~2.5m. The pile works has been completed. THF building’s length: 105.7m, width: 33.7m and story height: 11m; Poly-THF building’s length: 39.7m, width: 35.7m, and story height: 6.5m. The works’ level 100.00 is equal to the a bsolute level of 4.00.
All concrete for the works shall be commercial C30/C40 concrete.
Site condition
The construction site of the works is wide, power, water supply and drainage have provided, and the leveling has been completed, it has been get ready for commencement. Temporary power supply for construction has been solved through providing generator by the contractor as well as temporary water supply has been also connected to the site.
3. Construction arrangement
Construction organization management
Project methods will be conducted for the construction and we will establish a Project Department in charge of performing the contract in all respects, organizing, inducting managing, coordinating and controlling the construction.
The project Dept. will take scientific management, crack and highly effective team as well as reasonable structure as its principle to form a strong construction team for the works’ construction, meanwhile, accept the supervisions of owner and supervisors so to ensure the time and quality of the construction.
A project responsible system will be conducted for all works in respect of
production, technology, quality, cost and safety, with dynamic management and optimized combination in system. We intends to take corresponding measures as follows in the construction organization and arrangement:
3.1.1 In order to ensure the completion of the works in time, except preparation of
master program, sectional operation program will be worked out based thereon to control the construction progresses of sectional or sub-item works, organize labors in earnest, arrange overtime work and allocate labors as necessary to the extent that the construction progress is ensured without suspension and holdup in the work, and initiatives of all participates in the construction will be fully given play to, and the construction assigned us by the owner will be completed on or before the specified time.
3.1.2 Stress on planning management, properly work out month, week and day
work plans, set up a reliable materials and supporting system to the extent that the supply can be ensured and the transportation meets any requirement.
3.1.3 Fully use commercial concrete for the structure of the works, properly
coordinate with concrete suppliers, improve planning and allocation to ensure the construction demands, conduct transaction in the commercial concrete management market and conclude and sign contract in relation thereto.
3.1.4 Organization structure on the site: Establish a Project Management Dept. and