抗拔桩声测管埋设技术交底
- 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
- 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
- 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。
桩号
桩底标高桩顶标高桩长笼长声测管长度声测管根数
KB19 4.56622.76618.219.2619.263KB22 4.87223.07218.219.2619.263KB23 5.18423.38418.219.2619.263KA497.50123.70116.217.2617.263KB28 5.82424.02418.219.2619.263KB30 5.82424.02418.219.2619.263KB33 5.82424.02418.219.2619.263KB44-4.88524.91529.831.0431.043KB47-4.6525.1529.831.0431.043KA63-2.19425.60627.829.0429.043KB59-3.97225.82829.831.0431.043KB61-3.74126.05929.831.0431.043KB70-3.28726.51329.831.0431.043KA72 5.0226.9221.922.9622.963KB73 3.24827.14823.925.1425.143KB75 3.24827.14823.925.1425.143KB78 3.70327.60323.925.1425.143KB82-0.72127.87928.629.8429.843KB86-0.18128.41928.629.8429.843KA87 3.08929.69826.627.8427.843KA909.77829.37819.620.6620.663KB1018.29129.89121.622.8422.843KA9710.54730.14719.620.6620.663KB1098.80320.40321.622.8422.843KB1149.27630.87621.622.8422.843KA105
11.575
31.175
19.6
20.66
20.66
3
1、应埋设声测管的工程桩:桩径大于800mm且小于或等于1600mm时不得少于3根声测管。
2、声测管的规格:采用外径为50mm、壁厚不小于2.5mm的钢管,底部应下至孔底、上部管口高度同主筋。
3、埋设要求:声测管连接处应光滑过渡,捆扎在钢筋笼内侧,上下口用堵头密封。
4、埋设过程中,须边下管边及时灌注清水。
5、埋设2根声测管的按对称布置,埋设3根 声测管的布置示意图如下:
编制: 工班负责人: 工区经理:
三期抗拔桩
江北工区二期、三期抗拔桩声测管技术交底
二期抗拔桩
备注
1905