某港改建码头毕业设计1 总平面布置某港改建码头是河口港码头,平面布置与工艺设计按《海港总平面设计规》和《河港总平面设计规》的有关规定确定。

根据水文、地质、地形、货种、装卸工艺及施工条件等因素综合分析,采用高桩码头结构型式(上层土为淤泥)。

码头前沿大致平行于黄浦江主流向,由于码头前江面宽约500米,水域面积不大,为了不使水流结构发生变化选用顺岸式。

码头前沿布置在规划前沿线,考虑到当地陆域面积紧,采用满堂式,1#和2#码头连片布置,拆掉原有的防洪墙,将后桩台至陆地之间的短距离水域用当地廉价的砂石料抛填,当汛期来临时,码头停止作业,采用堆沙包的方法来防汛。

由资料得到的水位值:设计高水位:高潮位累积频率曲线的10%处————3.75 m设计低水位:高潮位累积频率曲线的90%处————1.22 m极端高水位:高潮位累积频率曲线的2%处————4.63m极端低水位:高潮位累积频率曲线的98%处————0.60 m1.1一头总平面布置1.1.1停靠方式停靠方式采用两点系泊(如图),受力系船柱数目根据船长查得为n=2,系船柱间距最大为20m,最少系船柱个数为6个。

1.1.2一头主要尺度的拟定1.1.2.1 泊位长度L=L+2d单个泊位长度:bL————单个泊位长度(m)bL————设计船长(m),L=82.6m;d————富裕长度(m),按《海港总平面设计规》查表取值为8~10mL=82.6+2×(8~10)=98.6~102.6m,取码头长度为118m, 已有岸线满足要求.b1.1.2.2泊位宽度为了不占用主航道,泊位宽度:B=2bb————设计船宽(m),b=13.6mB=2×13.6=27.2m,取28m1.1.2.3 码头前沿顶高程(按有掩护港口的码头计算)基本标准:E=HWL + 超高值(1.0~1.5)复核标准:E=极端高水位+超高值(0~0.5)E————码头面高程(m)HWL————设计高水位(m)基本标准:E=3.75+(1.0~1.5)=4.75~5.25 m复核标准:E=4.63+(0~0.5)=4.63~5.13 m由资料知,当地万吨级泊位的码头面标高一般为+4.8m,所以取E=4.8m1.1.2.4码头前沿设计水深D=T+Z1+Z2+Z3+Z4H- Z1Z2 =K%4D————码头前沿设计水深(m)T————设计船型满载吃水(m),T=4.47m;Z1————龙骨下最小富裕深度(m),查得Z1=0.2mZ 2————波浪富裕深度(m ),K ————系数,顺浪取0.3,横浪取0.5%4H ————码头前的允许波高(m )由于地处黄浦江中,码头前江面宽度只有500米,波浪主要为顺浪,查《港口规划与布置》得3000吨级的杂货船的允许波高为%4H =0.8m ,所以:Z 2 =0.3⨯0.8-0.2=0.04 mZ 3————船舶因配载不均而增加的船尾吃水值(m ),杂货船可不计,Z 3=0 m ;Z 4————备淤富裕深度(m ),Z 4=0.5mD=4.47+0.2+0.04+0+0.5=5.21m,所以码头前沿水底高程=设计最低水位-码头前沿设计水深=1.22-5.21=-3.99m,由于码头前沿布置在规划前沿线处,且规划挖至-9.0m ,所以水深条件肯定满足。

重力式码头毕业设计

重力式码头毕业设计

第1章编制说明1.1 编制依据1、xxxx有限公司设计的《xxxxx工程重件码头工程施工图》;2、xxxx一期工程重件码头工程设计交底纪要;3、xxxx一期工程重件码头工程施工合同;1.2编制说明xxx一期工程重件码头工程施工组织设计的编写遵循合同文件及设计交底纪要要求、施工技术规范和工程质量检验评定标准,遵循的主要技术规范、标准和法规如下:《海港总平面设计规范》(JTJ211-99)《港口工程地基规范》(JTJ250-98)《海港水文规范》(JTJ213-98)《港口及航道护岸工程设计与施工规范》(JTJ300-2000)《重力式码头设计与施工规范》(JTJ290-98)《港口工程质量检验评定标准》(JTJ221-98)及其局部修订《水运工程混凝土质量控制标准》 JTJ269-96《港口工程混凝土结构设计规范》JTJ167-98《水运工程混凝土施工规范》 JTJ268-96《水运工程混凝土试验规程》 JTJ270-98《水运工程测量规范》(TJT203-94)《港口工程荷载规范》(JTJ215-98)《建筑设计防火规范》(GB50016-2006)《港口消防监督实施办法》《港口工程劳动安全卫生设计规定》(JT320-1997)《港口设施维护技术规程》(JTJ289)表1-1第2章工程概况2.1 工程基本情况2.1.1工程地点:xxxxx。

2.1.2工程内容、范围及结构型式根据xxxx一期工程重件码头工程合同文件,重件码头工程范围为:沉箱码头、翼墙、码头后方陆域形成、重件码头道路外侧护岸、码头供电照明设备基础、码头道路及堆场、港池、回旋区及航道疏浚、助航设施的采购与安装、码头给水管道采购和安装、码头供电照明设备采购与安装。

重件码头泊位总长109.5m。

装卸作业区的宽度范围是50m,码头陆域纵深67m。

主体结构长80m,顶高程7.5m,前沿底标高为-7.8m。

码头面西侧设两座系船墩,前沿线长29.5m。

毕业设计---5万吨级货物装配码头设计

毕业设计---5万吨级货物装配码头设计

毕业设计---5万吨级货物装配码头设计介绍本文档旨在提供关于设计一座5万吨级货物装配码头的毕业设计的详细信息。

通过这份文档,您将了解到设计该码头所需考虑的关键因素以及相关的技术要求。

设计要求装卸能力设计的货物装配码头应具备每年装卸5万吨货物的能力。

这包括不同类型的货物,如散装物、集装箱和重型货物等。

可靠性和安全性码头必须设计为稳定、结构牢固,能够承受恶劣天气和海洋环境条件。

安全方面的考虑非常重要,包括货物装卸过程中的人员、设备和货物的安全。

功能性码头应具备高效的装卸能力,能够满足货物装卸的时间要求。

同时,应考虑到货物储存和临时存放的需求。

环境影响码头设计应考虑减少对环境的不良影响,采取合适的措施来保护自然资源和水域生态系统。

技术要求供电系统码头应配备可靠的供电系统,以确保连续的电力供应,并满足各种设备的功率需求。

水域结构码头的水域结构应设计为坚固、稳定,能够承受电动起重机和其他装卸设备所造成的荷载。

码头设备适当的装卸设备是保证码头高效运营的关键。

应根据货物类型和装卸需求选择适当的设备,如起重机、堆高机和运输设备等。

储存和堆放区域码头应设计具有足够的储存和堆放区域,以便在装卸过程中灵活安排货物的存放。

计划和时间表以下是完成毕业设计的预计时间表:1. 调研和需求分析:2周2. 设计方案制定:3周3. 技术细节和设备选择:2周4. 施工图设计和评估:4周5. 最终设计报告和展示准备:2周以上时间表仅供参考,实际时间可能会根据项目的具体要求而有所调整。

结论通过本文档,您已经了解到设计一座5万吨级货物装配码头的关键要求和技术要求。

希望这份文档能帮助您顺利完成毕业设计,并设计出一个高效、可靠和安全的码头。

如有任何问题或需要进一步的辅助,请随时联系我。

1000DWT集装箱码头结构设计毕业设计

1000DWT集装箱码头结构设计毕业设计

1000DWT集装箱码头结构设计毕业设计目录摘要....................................................................................................................................... 错误!未定义书签。

ABSTRACT .......................................................................................................................... 错误!未定义书签。

资料.................................................................................................................................................................... 1自然条件.................................................................................................................................................... 11 地理位置........................................................................................................................................ 12 气象资料........................................................................................................................................ 23 水文资料........................................................................................................................................ 44 泥沙运动........................................................................................................................................ 75 地质条件.................................................................................................................................... 11营运资料................................................................................................................................................ 12吞吐量预测.................................................................................................................................... 12船型................................................................................................................................................ 121 总平面设计.............................................................................................................................................. 141.1 平面布置的一般规定..................................................................................................................... 141.2 泊位数的确定................................................................................................................................. 141. 泊位数目的计算....................................................................................................................... 141.3 码头水域布置。

集装箱码头毕业设计

集装箱码头毕业设计

集装箱码头毕业设计
集装箱码头是现代物流的重要组成部分,其良好的运营管理和高效的操作能力对于保障国际贸易的顺畅进行有着至关重要的作用。

因此,集装箱码头的设计需要充分考虑其功能、流程、安全等方面的要素,同时也需要与现代化的技术手段相结合,以提高其运营效率和安全性。

在集装箱码头毕业设计中,需要考虑以下几个方面:
1. 布局设计:集装箱码头需要合理的布局设计,以保证各种物流流程的顺畅进行,并且充分利用场地资源,提高吞吐量。

2. 设备选型与规划:集装箱码头需要各种设备,例如起重机、堆垛机、吊车等,需要选用具有高效、安全性好的设备,并且合理规划设备的数量和位置。

3. 货物流程管理:集装箱码头的运营需要严格的货物流程管理,例如装卸、堆存、运输等环节需要保证操作规范、安全、高效。

4. 安全管理:集装箱码头的安全管理需要注意各种风险,例如货物的安全、设备的安全、工人的安全等,需要制定相应的安全规章制度,加强安全培训和检查。

设计一个高效、安全、现代化的集装箱码头,不仅需要对物流产业的深入了解和把握,还需要运用现代化的计算机技术、物流管理理论等手段,从整体上规划、设计、管理码头。

通过毕业设计,学生能够更好地掌握物流学科知识,提高自己的综合能力。

- 1 -。

扶壁码头毕业设计模板

扶壁码头毕业设计模板

扶壁码头毕业设计模板扶壁码头毕业设计模板毕业设计是每个大学生必经的一道坎,它不仅是对我们四年学习成果的总结,也是对我们能力的一次检验。

在选择毕业设计题目时,我经过一番思考,决定选择扶壁码头作为我的设计模板。

扶壁码头是一种可以安全靠岸的码头结构,它具有一定的创新性和实用性,适用于各种不同的水域环境。

下面,我将详细介绍我设计的扶壁码头模板及其特点。

一、设计理念在设计扶壁码头模板时,我注重结构的稳定性和安全性。

扶壁码头采用了坚固的混凝土结构,能够承受大风大浪的冲击,保证码头的稳定性。

同时,为了增加码头的安全性,我在设计中加入了护栏和防滑设施,防止人员在码头上滑倒或意外坠入水中。

二、结构设计扶壁码头的结构设计主要包括桩基、码头平台和护栏。

桩基是码头的承重结构,我采用了混凝土桩作为扶壁码头的基础,以确保码头的稳定性。

码头平台是人员活动的区域,我设计了宽敞平整的码头平台,方便人员上下船和进行其他活动。

护栏是为了保护人员的安全,我选择了坚固的金属护栏,并在上面加入了防滑条,以增加人员在码头上的安全性。

三、适用环境扶壁码头模板适用于各种不同的水域环境,包括海洋、河流和湖泊等。

无论是在海边的旅游景点,还是在内陆的渔村,扶壁码头都能够提供一个安全可靠的靠岸场所。

同时,扶壁码头的模板设计可以根据不同的环境需求进行调整,适应不同地区的气候和水流条件。

四、创新性与实用性扶壁码头模板的创新之处在于其结构的稳定性和安全性。

相比传统的木质码头,扶壁码头采用了混凝土结构,更加坚固耐用。

同时,扶壁码头还加入了护栏和防滑设施,提高了人员在码头上的安全性。

这种创新的设计不仅能够满足人们对于码头的基本需求,还能够提供更高的安全保障。

扶壁码头模板的实用性主要体现在其适用性和可扩展性上。

扶壁码头适用于各种不同的水域环境,可以满足不同地区的码头需求。

此外,扶壁码头的模板设计可以根据实际需要进行调整和扩展,满足不同规模和功能的码头建设。

总结:通过对扶壁码头毕业设计模板的详细介绍,我们可以看出其具有稳定性、安全性、创新性和实用性等特点。

高桩码头毕业课程设计

高桩码头毕业课程设计

高桩码头毕业课程设计一、课程目标知识目标:1. 让学生掌握高桩码头的基本结构及其功能,理解其设计原理;2. 使学生了解高桩码头建设的关键技术,掌握其施工流程;3. 帮助学生了解我国高桩码头的发展历程,认识其在国民经济中的重要作用。

技能目标:1. 培养学生运用所学知识分析和解决实际工程问题的能力;2. 提高学生团队协作和沟通能力,能在项目中进行有效的分工与合作;3. 培养学生运用现代信息技术收集、整理和分析相关信息的能力。

情感态度价值观目标:1. 培养学生对港口工程及高桩码头建设的兴趣,激发其学习热情;2. 增强学生的社会责任感,使其认识到高桩码头建设对环境保护的重要性;3. 引导学生树立正确的价值观,认识到工程建设的经济效益与社会效益的统一。

分析课程性质、学生特点和教学要求,本课程旨在帮助学生全面掌握高桩码头相关知识,将理论联系实际,提高学生的工程素养。

课程目标分解为具体学习成果,以便后续教学设计和评估。

在教学过程中,注重培养学生的实践能力、创新能力和团队协作精神,为我国高桩码头建设培养高素质的工程技术人才。

二、教学内容本课程教学内容主要包括以下几部分:1. 高桩码头概述:介绍高桩码头的基本概念、结构特点、分类及功能,对应教材第一章内容。

2. 高桩码头设计原理:讲解高桩码头的设计原理、设计方法及设计要点,对应教材第二章内容。

3. 高桩码头施工技术:阐述高桩码头的施工流程、关键技术及质量控制,对应教材第三章内容。

4. 高桩码头建设案例分析:分析国内外典型高桩码头工程案例,了解其设计、施工及管理经验,对应教材第四章内容。

5. 高桩码头发展与展望:介绍我国高桩码头的发展历程、现状及未来发展趋势,对应教材第五章内容。

教学内容安排和进度如下:第一周:高桩码头概述第二周:高桩码头设计原理第三周:高桩码头施工技术第四周:高桩码头建设案例分析第五周:高桩码头发展与展望在教学过程中,注重理论与实践相结合,提高学生对高桩码头工程的认识,培养其解决实际问题的能力。

集装箱码头设计毕业设计

集装箱码头设计毕业设计

集装箱码头设计毕业设计集装箱码头设计毕业设计一、引言集装箱码头作为现代物流运输的重要环节,对于国家经济发展和贸易往来起着至关重要的作用。

随着全球贸易的不断增长,集装箱码头设计也日益受到重视。

本文将探讨集装箱码头设计的关键因素和挑战,并提出一些建议。

二、集装箱码头设计的关键因素1.地理位置集装箱码头的地理位置对于物流运输的效率和成本起着决定性的作用。

码头应该位于交通便捷的地区,方便货物的进出。

此外,码头附近的水深、水流、风向等自然条件也需要考虑,以确保船只的安全进出。

2.码头设施码头设施的完善程度直接影响着码头的运营效率。

包括码头的装卸设备、堆场、仓库、道路等。

合理规划和布局这些设施,可以提高码头的货物吞吐量和作业效率。

3.信息化管理随着物流行业的发展,信息化管理在集装箱码头设计中扮演着越来越重要的角色。

通过引入先进的信息技术,可以实现货物跟踪、作业计划、库存管理等的自动化和智能化,提高物流效率和减少错误。

4.环境保护在集装箱码头设计中,环境保护是一个不可忽视的因素。

码头的建设应该符合环境保护的要求,减少对周边环境的污染。

同时,可以考虑利用可再生能源和节能技术,减少能源消耗和碳排放。

三、集装箱码头设计的挑战1.规划和布局集装箱码头的规划和布局需要综合考虑多个因素,如地理条件、交通网络、市场需求等。

这需要设计师具备全面的知识和技能,并进行科学的分析和决策。

2.装卸设备选择集装箱码头的装卸设备种类繁多,如起重机、堆高机、输送带等。

设计师需要根据码头的规模和货物类型选择合适的设备,以满足码头的作业需求。

3.运营效率提升随着物流行业的竞争加剧,提升运营效率成为集装箱码头设计的重要目标。

设计师需要优化作业流程,减少作业时间和成本,提高货物吞吐量。

4.安全管理集装箱码头的安全管理是一个复杂而严峻的挑战。

设计师需要考虑货物的安全存储和运输,防止事故和损失的发生。

同时,还需要制定应急预案,应对突发事件。

四、集装箱码头设计的建议1.综合规划在集装箱码头设计中,需要进行全面的规划,综合考虑各种因素。

港口码头设计毕业设计论文

港口码头设计毕业设计论文

港⼝码头设计毕业设计论⽂第⼀章设计背景1.1 ⼯程概述该码头,位于⼴西防城港,防城港市位于⼴西南部边陲,南临北部湾,北连南宁市,东接钦州,西邻越南(位置⾃定),码头可顺岸式布置或凸堤式布置,可利⽤岸线长300~400⽶。

1.2设计原则(1)总体设计应该与国家、地⽅经济发展和总体部署保持⼀致,严格按照国家和⾏业有关⼯程建设法规、政策和规定实施。

(2)结合国情,采⽤成熟的技术、设备和材料,使⼯程设计安全可靠、使⽤⽅便、总造价低、施⼯进度快、⼯程量少,获取较多的社会利益和经济效益。

(3)保护⼯程区域⽣态环境,不占⽤⼟地,⽅便管理,节省投资。

1.3设计依据(1)设计任务书:《⼴西港⼤宇集团建材码头设计施⼯》。

(2)相关规范标准:(3)设计参考书:1.4设计任务本⼯程主要设计内容包括:⽔域、陆域总平⾯布置、码头和接岸结构、堆场和辅建区建;构筑物包括变电所、轨道梁、排⽔管沟、灯塔基础等,还有配套的供电、给排⽔、消防、通信、控制、节能、环保等。

第⼆章设计资料2.1⽓象2.1.1⽓温年平均⽓温22.2℃,⽉平均最⾼⽓温28.4℃(出现在7⽉),极端最⾼⽓温为35.4℃(出现在1979年9⽉19⽇),⽉平均最低⽓温为14.2℃(1⽉),极端最低⽓温2.8℃(1977年1⽉31⽇)。

各⽉平均⽓温见表2-1。

表2-1 各⽉平均⽓温表2.1.2降⽔年平均降⽔量为2359.9mm,年最⼤降⽔量为3111.9mm(1973年),年最⼩降⽔量为1745.6mm(1974年)。

降⽔量都集中在6~9⽉,该4个⽉的降⽔量占全年降⽔总量的71%,其中以8⽉份降⽔量最为集中,达528.7mm,⽽11⽉⾄翌年3⽉,这5个⽉的降⽔量只占全年降⽔总量的6.4%,其中以2⽉份降⽔量最⼩,仅有23.9mm。

各⽉平均降⽔量见表2-2。

表2-2 各⽉平均降⽔量表⽇最⼤降⽔量为337.9mm(在1980年9⽉3⽇),⽇降⽔量⼤于25mm的⽇数平均为27天。

码头毕业设计

码头毕业设计

码头毕业设计码头毕业设计700字一、设计需求现代社会中,码头作为货运物流的重要阵地,承担着大部分货物的进出口任务。

为了提高货物的装卸效率,减少人力成本,提高作业效率,设计一个智能化的码头运输系统十分重要。

二、设计方案1. 系统结构该智能码头运输系统由以下几个组成部分构成:- 货物运输机器人:主要用于货物的装卸和运输。

可以自动辨识货物的类型、大小和重量,并进行适当的操作。

- 控制中心:用于监控和控制货物运输机器人的运行。

可以实时获取货物的位置和状态,并对其进行远程操作。

- 数据分析模块:用于对码头运输系统的运行数据进行分析和处理,以优化运输效率和降低成本。

2. 系统功能- 货物装卸功能:货物运输机器人可以自动进行货物的装卸操作,无需人工干预。

只需将货物放在指定位置,机器人即可自动完成装卸任务。

- 运输功能:货物运输机器人可以将货物从码头运送到指定位置,实现物流的自动化。

- 远程操控功能:控制中心可以对货物运输机器人进行远程操作,实现对机器人的精确控制和指导。

- 数据分析功能:通过对运输数据的分析,可以发现运输效率的瓶颈和不足之处,以便进行优化。

3. 技术实现- 视觉识别技术:利用计算机视觉技术,让货物运输机器人能够准确识别货物的类型、大小和重量,并作出相应的操作。

- 自动控制技术:通过控制中心对货物运输机器人进行远程操作,实现对机器人的精确控制。

- 数据分析技术:对运输数据进行统计和分析,找出问题所在,并提出解决方案。

三、设计效果通过引入智能码头运输系统,可以大大提高码头的货物装卸效率,减少人力成本,并实现物流的自动化。

同时,通过对运输数据的分析和处理,可以优化运输效率,进一步降低成本。

四、结语智能码头运输系统是现代社会对于物流行业的重要需求之一。

希望通过这个设计方案,能够为码头的货物装卸工作提供便利和高效的解决方案,推动物流行业的发展。

xxx码头毕业设计开题报告

xxx码头毕业设计开题报告

xxxxxxx
2014届毕业生毕业设计(论文)题目:xx港5万吨级高桩码头设计
院(系)别土木工程学院
专业港航专业
班级港口
学号 xxxxxxxxxxx
姓名 xxxxxx
指导教师 xxxxxxx
二○一四年六月
xxxxxxxxx
2014届毕业生毕业设计(论文)
任务书
题目:xxxxxxxxxx5万吨级高桩码头设计
专业:港口航道与海岸工程
班级:xxxxxxxxx
学号:xxxxxxxxx
姓名:xxxxxxx
指导教师:xxxxxxx
完成日期:2014年xx 月xxxxx 日
设计任务书
xxxxxxxxx
2014届毕业生毕业设计(论文)
开题报告
题目:xxxxxxxxxxx
专业:港口航道与海岸工程
班级:10级
学号:xxxxxxxxxxx
姓名:xxxxxxxx
指导教师:xxxxxxxx
2014年x月xxx 日
开题报告书
xxxxxxxxxx本科生毕业设计 (论文)
中期检查表
设计题目:黄骅港一期5万吨级高桩码头设计。

(整理)高桩码头本科毕业设计

(整理)高桩码头本科毕业设计

精品文档精品文档毕业设计说明书东疆港区集装箱码头2号泊位设计梁板式高桩码头结构学生姓名 高杰专业名称 港口航道与海岸工程专业班级06级港口工程2班 指导教师吕美君 高级工程师土木工程系 2010年 6 月20日学 号06260209精品文档精品文档东疆港区集装箱码头2号泊位工程设计梁板式高桩码头结构Dongjiang Port No.2 Container Terminal BerthDesignBeam Piling Wharf Structure精品文档精品文档摘要本次设计的港址是位于天津港东疆港区。

码头类型为集装箱码头。

根据设计工艺要求,码头总长度为660米,码头前沿停泊水域宽70米,最大可安全地停靠第三代集装箱船。

仓库和堆场面积及分布根据货物量决定。

码头前沿设计水深13.11米。

码头分为10段,每段长63m。

前方桩台长30m,后方桩台长38m。

该码头为整体装配梁板式高桩码头。

面板采用预制板,搭接在纵梁上。

纵梁分为装卸桥轨道梁、一般纵梁和边纵梁,纵梁搭在桩帽上。

纵梁按刚性支撑连续梁计算。

横向排架间距为7米,横梁采用钢筋混凝土叠合梁。

重点部分是横向排架计算,采用桩两端为铰接柔性桩台的计算方法。

对横梁、面板进行内力、配筋计算和抗裂验算。

桩采用的是预制预应力空心方桩,对桩的承载力进行验算。

关键词:集装箱;高桩码头;结构布置;横向排架精品文档精品文档ABSTRACTThe design of the port site is located in Tianjin Dongjiang Port.The type of pier is container terminal. According to the design process requirements,the pier is 660 meters in length ,the water front parkof the pier is 70 meters,calling at maximum security to the third generation of container ships. Warehouse and yard area and volume of distribution of the decision of the goods.The front design depth of the pier is 13.11 meters,but just 12.5m is required,so not digging it.The pier assembly as a whole beam piling wharf. Panel is prefabricated panels, overlapping in the longitudinal beam. Stringer into crane beam, the general longitudinal and side rails, rails resting on pile cap. Due to time constraints of the design only to go out and cantilever crane track the specific parts and general longitudinal calculation. Longitudinal support beam by rigid calculation. Transverse distance of 7 meters of reinforced concrete beams using composite beam. Personal key part of Transverse using pile hinged at both ends of the calculation method for the specific calculations, see later. Pile with the precast hollow, because the design of the relatively long pile, the pile of reinforced concrete need to do further research, so do not go into detail here, piles of Reinforcement.KEY WORDS:Container; piled wharf; Plane Layout; lateral row frame精品文档目录第1章设计背景 (1)1.1工程概述 (1)1.2 设计原则 (1)1.3 设计依据 (1)1.4 设计任务 (1)第2章设计资料 (3)2.1 地形条件 (3)2.2 气象条件 (3)2.3 水文条件 (3)2.4 泥沙条件 (6)2.5 地质条件 (6)2.6 地震条件 (7)2.7 荷载条件 (7)2.8 施工条件 (7)第3章设计成果 (8)3.1 总体设计成果 (8)3.2 结构方案成果 (8)3.3 施工图设计成果 (8)3.4 关键性技术要求 (8)3.5 设计成果评价 (9)第4章总平面设计 (10)4.1 工程规模 (10)4.2 布置原则 (10)4.3 设计船型 (10)4.4 作业条件 (10)4.5 总体尺度 (11)4.5.1 码头泊位长度 (11)4.5.2 码头前沿高程 (11)4.5.3 码头前沿停泊水域尺度 (12)4.5.4 码头前船舶回旋水域尺度 (12)4.5.5 陆域设计高程 (12)4.5.6 航道设计尺度 (12)4.6平面方案比选 (12)精品文档精品文档4.7 装卸工艺设计 (13)第5章结构选型 (14)5.1 结构型式 (14)5.2 结构布置 (14)5.3 构造尺度 (14)5.4 作用分析 (15)5.4.1永久作用 (15)5.4.2可变作用 (15)5.4.3偶然作用 (19)第6章结构设计 (20)6.1 面板设计 (20)6.1.1计算原则 (20)6.1.2计算参数 (21)6.1.3作用分析 (21)6.1.4作用效应计算 (22)6.1.5作用效应组合 (24)6.1.6验算及配筋 (25)6.1.7抗裂验算 (27)6.2 纵梁设计 (27)6.2.1计算原则 (28)6.2.2计算参数 (28)6.2.3作用分析 (29)6.3 横向排架 (30)6.3.1计算原则 (30)6.3.2计算参数 (30)6.3.3作用分析 (32)6.3.4作用效应计算 (32)6.3.5作用效应组合 (44)6.3.6验算及配筋 (46)6.3.7抗裂验算 (48)6.4 基桩设计 (49)6.4.1计算原则 (49)6.4.2计算参数 (49)6.4.3作用效应计算 (49)6.4.4作用效应组合 (51)6.4.5桩身强度验算 (51)精品文档精品文档致谢 (52)参考资料及设计规范 (53)外文资料及译文 (55)毕业设计任务书 (66)设计进度计划表 (73)精品文档精品文档精品文档第1章设计背景1.1工程概述规划建设中的天津港东疆港区位于天津港东北部,北临永定新河口,南临天津港主航道,西临规划反“F”航道,东临渤海湾海域,为浅海滩涂人工造陆形成的三面环海半岛式港区。

毕业设计---5万吨级港口码头设计

毕业设计---5万吨级港口码头设计

毕业设计---5万吨级港口码头设计1. 引言本文档旨在对一座5万吨级的港口码头进行设计,以满足现代港口运输需求并提升港口的运作效率和安全性。

2. 设计需求该港口码头设计应满足以下需求:- 容纳5万吨级船只,提供足够的对接和停泊空间- 提供装卸货物的设施和设备,以支持高效的货物运输- 考虑船只进出港口时的安全性- 提供足够的储存空间,以便临时存放货物- 保证设计符合现行港口安全标准和环保要求3. 港口布局设计3.1 码头结构根据5万吨级船只的需求,设计一个坚固、稳定的码头结构,能够承受大型船只的靠泊和货物装卸作业。

建议采用混凝土桩和钢结构搭建码头,以确保结构的稳定性和耐久性。

3.2 航道和船坞考虑到船只进出港口的安全性,需要设计一个宽敞而深度适宜的航道,以方便船只的进出并确保航行安全。

此外,设计一个船坞用于船只的停泊和装卸货物。

3.3 装卸设施和设备为了高效运输货物,港口码头需要配备现代化的装卸设施和设备。

建议设置多个装卸平台和起重机,以支持同时进行多个装卸作业,并能够处理各种类型和大小的货物。

3.4 货物存储区为了满足大量货物的储存需求,设计一个宽敞的货物存储区,以便临时存放货物。

建议根据货物类型和特性,设置不同的存储区域,以确保货物的分类储存和管理。

4. 安全和环境考虑设计过程中应严格遵守现行的港口安全标准和环保要求。

确保港口设施和设备的安全性,包括防护措施、紧急救援设备和安全标识等。

此外,减少港口运营对周边环境的影响,采取合适的环保措施,如噪音和污染的控制。

5. 结论通过对5万吨级港口码头的设计,可以提升港口的运作效率和安全性,满足现代港口运输需求。

合理的港口布局、先进的装卸设施和设备,以及严格的安全和环保措施,将使该港口成为一座先进、高效和可持续发展的港口码头。

注:本文档为设计建议,具体实施时请遵循相关法律和规定。

沉箱码头毕业设计

沉箱码头毕业设计

沉箱码头毕业设计一、选题背景沉箱码头是一种新型的港口工程,相比传统的码头,它具有更高的自动化程度和更快的装卸速度,能够大大提高港口运营效率。

因此,在当前全球经济发展和物流需求日益增长的背景下,沉箱码头成为了一个备受关注的热门话题。

二、选题意义作为一个新兴领域,沉箱码头在我国尚未得到广泛应用,但是其前景十分广阔。

因此,通过本次毕业设计,我们可以深入了解沉箱码头的技术原理和应用场景,并且探索如何在实际应用中克服各种困难和挑战。

同时,在毕业设计过程中,我们还可以提高自己的综合能力和创新能力,并且为未来从事相关行业做好准备。

三、研究内容与方法1. 研究内容本次毕业设计主要涉及以下方面:(1)沉箱码头技术原理:深入了解沉箱码头的工作原理、结构组成及其特点等方面。

(2)设计方案:根据实际需求,制定适合不同规模、不同场地的沉箱码头设计方案。

(3)系统实现:通过编程、模拟等方式,实现沉箱码头的自动化控制系统。

(4)性能测试:通过实验室测试和现场试验,对沉箱码头的各项性能进行评估。

2. 研究方法本次毕业设计主要采用以下研究方法:(1)文献调研:通过查阅相关文献,深入了解沉箱码头的技术原理及其应用情况。

(2)软件仿真:运用MATLAB等软件,对沉箱码头进行仿真模拟,验证设计方案的可行性和有效性。

(3)硬件实现:采用单片机、传感器等硬件设备,搭建沉箱码头自动化控制系统,并进行调试和优化。

(4)现场试验:在实际场地上进行测试和评估,并对系统进行改进和优化。

四、预期成果本次毕业设计预期达到以下成果:(1)深入了解沉箱码头的技术原理及其应用情况;(2)制定适合不同规模、不同场地的沉箱码头设计方案;(3)完成沉箱码头自动化控制系统的开发和调试;(4)对沉箱码头的各项性能进行评估,并提出改进方案。

五、实施计划本次毕业设计的实施计划如下:1. 第一阶段(1月-3月):调研和设计(1)文献调研:深入了解沉箱码头的技术原理及其应用情况,了解国内外相关研究现状。

毕业设计---5万吨级散货码头设计

毕业设计---5万吨级散货码头设计

毕业设计(论文)铁山港5万吨级散货码头设计学生姓名:学号:2008班级专业:港口航道与海岸工程指导教师:铁山港50000吨级散货码头设计摘要铁山港区距北海市近40公里,距合浦县城廉州镇40多公里,距自治区首府南宁市250公里,距广东省湛江市约150公里,距海南省首府海口市124海里。

铁山港区是西南最便捷的出海通道之一,是广西以及大西南连接广东、福建陆路经济走廊的重要交通枢纽。

本设计主要根据铁山港自然条件、运营、船型等资料,设计若2个5万吨级散货泊位。

主要设计内容包括:对码头环境进行分析,包括地理、水文、气候、风况等进行分析;对码头进行总平面布置,包括码头陆域、水域的平面布置及生产生活辅助区布置;对散货泊位进行装卸工艺流程的设计,确定码头的主要经济技术指标;对码头进行结构设计,包括方块、沉箱方案的拟定及比较,最终确定为沉箱方案,进行结构计算和配筋计算。

关键词:总平面布置;装卸工艺;结构设计;配筋计算THE DESIGA OF TIESHANPORT’S 50000DWT BULK TERMINALABSTRACTTieshan port is nearly 40 kilometers away from Beihai City, the distance between the city of Hepu County is about 40 kilometers, 250 km away from Nanning, capitalof the autonomous and Zhanjiang City (Guangdong Province) about 250 km away. From the capital of Hainan Province,Haikou City,the distance is 124 miles. Tieshan port is the most convenient access to the sea southwest of Guangxi and the Big Southwest, is connected to land in Fujian, Guangdong Economic Corridor of important traffic hub.According to the native condition opertion factor and transport means, this project will design four ten thousad ton class berths, one of them is used for the bulk cargo. Cheif design content: the analysis to mative tendition of harbour, which include geography hydrdogy, weather, wind etc; The overall plan design covers the surfowe design of the wharfs land and water. The living assistance arrangement etc: The design of cargo-handing technology tarft flow program of bunk cargo berth, which is used for determining key index sign of the economy technique; Construction design including the determination and comparion coutrete block and contrete caisson plan; The later choosed, along with structure caulation and steels arranging accout.Key word:Overall plan arrangement; Cargo-handing technology; Construction design; Steels arranging account目录第一章总论 (1)第二章工程设计自然条件 (3)2.1 工程地理位置 (3)2.2 气象 (3)2.2.1 气温 (3)2.2.2 降雨 (3)2.2.3 雾 (4)2.2.4 风况 (4)2.2.5 湿度 (5)2.3 水文 (5)2.3.1 潮汐 (5)2.3.2 波浪 (7)2.3.3 潮流 (8)2.4 地形、地貌与工程泥沙 (8)2.4.1 地形、地貌 (8)2.4.2 工程泥沙 (8)2.5 工程地质 (9)2.5.1 地质特征概述 (9)2.5.2 岩土物理力学指标 (11)2.5.3 基础适宜性及地基持力层选择 (12)2.5.4 疏浚岩土工程特性评价 (12)2.6 地震 (13)第三章船型资料与吞吐量 (14)3.1 船型资料 (14)3.2 吞吐量资料 (14)3.3 北海港港区分布及泊位情况 (14)第四章装卸工艺 (16)4.1 装卸工艺的设计原则及一般要求 (16)4.1.1 设计原则 (16)4.1.2 一般要求 (16)4.2 机械设备选型 (17)4.3 装卸工艺及流程 (17)4.4 机械数量的确定 (17)4.4.1 移动式装船机 (18)4.4.2 桥式卸船机 (18)4.5 装卸工人数和司机人数的确定 (19)4.5.1 港口装卸工 (19)4.5.2 装卸机械司机人数 (19)4.6 主要技术经济指标 (20)4.6.1 散货码头泊位数 (20)4.6.2 库场面积 (21)4.6.2 设计堆场通过能力 (22)4.6.3 装卸一艘船所需时间 (23)4.6.5 库(场)面积 (23)第五章总平面布置 (24)5.1 港区布置原则 (24)5.2 高程及水深的确定 (25)5.2.1 设计水位及水位差 (25)5.2.2码头前沿设计高程 (25)5.2.3码头前沿设计水深 (25)5.2.4 码头前沿水底高程 (26)5.3 总平面布置 (26)5.3.1水域布置 (26)5.3.2 陆域布置 (27)第六章结构方案的拟定 (30)6.1结构比选 (30)6.2沉箱结构 (31)第七章沉箱码头的验算 (32)7.1 设计条件 (32)7.1.1 设计船型 (32)7.1.2 结构安全等级 (32)7.1.3 建筑物尺度 (32)7.1.4 自然条件 (32)7.2 作用分类与计算 (33)7.2.1 结构自重力(永久作用) (33)7.2.2 土压力标准值计算 (39)7.2.3 堆货荷载产生的土压力(可变作用) (42)7.2.4 码头前沿堆货引起的竖向作用(可变作用) (42)7.2.5 门机荷载产生的土压力作用(可变作用) (43)7.2.6 船舶系缆力(可变作用) (44)7.2.7 波浪力(可变作用) (46)7.2.8 贮仓压力(永久作用) (55)7.2.9 施工期沉箱沉放时面板所受水压力计算 (57)7.2.10 码头荷载标准值汇总 (58)7.3码头稳定性验算 (58)7.3.1 作用效应组合 (58)7.3.2 码头沿基床顶面抗滑稳定性验算 (59)7.3.3 码头沿基床顶面的抗倾稳定性计算: (60)7.3.4 基床承载力验算 (63)根据《重力式码头设计与施工规范》 (63)7.3.5 地基承载力的验算 (65)第八章沉箱结构内力计算 (70)8.1 承载力极限状态下的内力计算 (70)8.1.1 沉箱前壁板 (70)8.1.2 沉箱前底板计算 (71)8.1.4 内力计算 (72)8.2 正常使用极限状态下的内力计算 (74)8.2.1 沉箱前壁板 (74)8.2.2 沉箱底板计算(短暂状况) (75)8.2.3 内力计算 (76)8.3 配筋的计算 (77)8.4 构件裂缝宽度验算 (80)8.4.1 矩形截面受弯构件最大裂缝宽度计算公式 (80)8.4.2 对沉箱前壁板进行裂缝宽度验算 (80)参考文献 (85)结束语 (86)第一章总论北海市铁山港区东邻广东省湛江市,南临北部湾,西部为北海市区,北部为灵山县、浦北县。

纳溪沟码头毕业设计

纳溪沟码头毕业设计

. . ..交通学院河海学院港口、海岸及近海工程专业2011级毕业设计资料河海学院港工教研室二○一五年三月主城港区洋世达公司纳溪沟码头工程设计资料一、地理位置市公路运输(集团)公司纳溪码头一期工程,位于南岸区鸡冠石镇纳溪沟。

该码头位于朝天门下游12km的长江南岸(右岸),在规划的主城区边沿地带,距规划的中央商务区(CBD)南岸片区边缘约1km,距渝黔高速公路黄桷湾立交约5km。

纳溪沟位于弹子石中央商务区和茶园工业园区的连接地段,后方有弹子石~广阳坝公路通过。

二、营运资料1、货运任务该码头工程营运的货种有散货70万吨/年,件杂25万吨/年及多用途泊位货35万吨/年。

2、设计船型根据调查目前长江上运输船舶的实际,并结合长远发展,设计船型其设计基本尺度如下表1。

表1 设计船型基本尺度三、自然资料1、气象⑴风况风向:常风向为北风,北东北,频率6~15%风速:最大风速26.7m/s(1981.5.10)瞬间最大风速:27.0m/s(1961.8.4)定时(2分钟)最大风速:20m/s(1949.5.16)本地大风强度不大,并且频率较低,加之受川江峡谷地形影响,对船舶靠离码头和航行影响不大。

⑵降水多年平均降雨量:1082mm (1916年)历年最大降雨量:1353.9mm (1970年)历年最少降雨量:911.7mm (1971年)年最多雨日174d(1974年),年最少雨日139d(1978年),日最大降雨量192.9mm(1956年6月25日)⑶雾况根据1979年~1989年11年的资料统计,其雾状特征值如下:年平均发生天数40.0d最大年发生天数61.0 d(1979年)最大月平均发生天数6.4 d(1月份)最长延时47hr40min(1986年)因轻雾对船航行影响很少,上述特征值主要是指中雾和浓雾。

⑷气温极端最高气温:44.0℃极端最低气温:-2.5℃历年平均气温:18.5℃历年月平均最高气温:28.1℃(8月)历年月平均最低气温:7.2℃(1月)根据上述自然状况进行分析,港口不可作业天数见下表2。

杭州余杭港方块式码头毕业设计

杭州余杭港方块式码头毕业设计

第一篇绪论交通运输是社会经济的主要组成部分,是生产与消费的纽带,是商品流通人们交往的基础条件。

港口是一个国家和地区经济发展的重要依托。

港口是具有水陆联运设备和条件,供船舶安全进出和停泊的运输枢纽,是水陆交通的集结点和枢纽,工农业产品和外贸进出口物资的集散地,船舶停泊、装卸货物、上下旅客、补充给养的场所。

在未来一个时期,中国的港口仍处于大建设、大发展阶段。

我们政府已把交通运输业列为优先发展的产业,我国将进一步完善港口布局,重点建设集装箱、煤炭、进口油气和铁矿石中转的运输系统,扩大港口吞吐能力。

同时这些大建设、大发展也对港口建设和管理提出了更高的要求。

杭州港余杭港区仁和石化作业区南港区块项目位于杭州市北部余杭区仁和镇的东侧,京杭运河的西岸。

为了改变泊位吨级小、泊位数量少、港口发展长期滞后于腹地经济发展与运量增长速度的现状,杭州余杭港进行扩建,拟建1000吨级以上泊位若干个,主要货种为集装箱。

第二篇自然条件2.1 地形、地貌杭州港余杭港所处河面宽度约为100m,作业区陆域范围内除少量农居外,其余均为鱼塘和农田(非保护耕地),地势平坦,高程为1.87m-2.98m(黄海高程),该区域两岸植被较好,雨天地表径流造成的水土流失比较轻微,河道水流平稳,正常水位期基本无流速,泥沙来源极少,河床来源极少,河床冲淤变化较小,河道基本稳定。

2.2 地质条件2006年11月,由江西金新勘测工程有限公司杭州分公司对该项目所在位置地质进行了详勘,按照地基土的时代成因、物理力学性质特征差异,现基本确定有以下土质:1素填土2粉质粘土3淤泥质粘土4粉质粘土5粉质粘土6粉质粘土7粉质粘土8砾砂详细工程地质特征见表12.3气象,气温,降水,风况,雾况,雷暴,地震工程区域位于东亚季风区,气候温和湿润,日照充足,雨量充沛,四季分明。

春季温暖多雨,夏季炎热湿润,盛行SE风,6~7月为梅雨期,8月下旬至9月中旬是台风季节,此季节多阵雨,偶有冰雹、龙卷风和伏旱。

相关主题
  1. 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
  2. 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
  3. 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。

基本要求
★ 码头毕业设计基本要求
设计条件分析:熟悉设计资料的主要特点,明确它们对设计
的影响,选择合理的方法确定有关计算参数,然后进行概括、
系统地整理。 码头平面设计:合理地确定有关设施的规模及主要尺度,选
择合理的装卸工艺,进行总平面布置。
码头结构初步设计:选择合理的码头结构型式,拟定2个可 行方案进行比选,确定推荐方案。 指定构件的技术设计:初步设计的基础上,对推荐方案的指 定构件进行技术设计。要求自编电算程序进行结构内力分析。
谢谢大家
码头工程毕业设计
鲁子爱
2015年3月
内容提要
内 容 提 要
毕业设计的目的和任务 ★ 码头工程毕业设计的基本要求 ★ 码头工程毕业设计的基本方法与步骤


设计条件分析 码头平面设计 码头结构初步设计 指定构件技术设计 计算书、说明书、图纸
目的任务
★ 毕业设计的目的和任务
性质:毕业设计是完成高等学校专业教育的最后一个很重要

装卸工艺设计
码头泊位:长度、宽度
主要设施规模 锚地:锚泊方式、锚泊位尺度 平面尺度设计 防波堤长度


竖向尺度设计 回旋水域:回旋圆直径
平面布置
库场:长度、宽度
生产辅助设施:占地面积
码头平面设计
★ 码头平面设计

装卸工艺设计


主要设施规模
平面尺度设计 水域:船舶停泊水深、航行水深
设计条件分析
★ 设计条件分析

使用条件 气象:风雨雾温 → 平面布置、作业天数、施工


自然条件 水文:水位、水(潮)流、波浪、泥沙
施工条件 地形:地形图 → 平面布置:前沿、驳岸、引桥
地质:土质、地质剖面图 → 结构型式、岸坡 → 主要尺度、荷载、淤积分析
设计条件分析
★ 设计条件分析

基本要求
★ 码头毕业设计基本要求
设计说明书:说明设计条件、设计依据、设计方法和主要设
计成果、施工注意事项等,如初步设计中结构选型、各方案的
主要技术经济指标等,技术设计中结构计算图式的确定、内力 分析方法及主要工况的计算结果、强度计算方法与结果等。条
理清楚、层次分明。
设计计算书:主要计算内容的具体计算过程与结果。方法合 理、计算正确。
的实践性教学环节,它不同于设计部门的设计,也不是几个课 程设计的简单组合,而是一个本专业教学性质的综合设计。
目的:巩固所学过的理论知识,并得到一定程度的加深和扩
展,进一步提高计算、编写说明书及绘图的技能,培养自学能 力、运用所学知识去分析问题和解决问题的能力。 任务:在老师指导下独立完成一个具体工程的设计任务,一 般包括设计条件分析、平面设计、初步设计、技术设计、编写 设计说明书和计算书、绘制有关设计图纸。

码头泊位数量 锚地、回旋水域规模 库场面积:货物堆存量、拆码垛工
装卸工艺设计
主要设施规模 艺、堆存高度(货种、地基承载力) 平面尺度设计 生产辅助设施:流动机械库、机修


竖向尺度设计 车间、工属具仓库、办公楼、停车场
平面布置

职工数量:司机、工人、管理人员
码头平面设计
★ 码头平面设计


竖向尺度设计
平面布置
→确定各水域底高程
陆域:码头前沿高程、场地高程、
场区排水 防波堤:顶高程、挡浪墙顶高程
码头平面设计
★ 码头平面设计

装卸工艺设计


主要设施规模 码头前沿线位置
平面尺度设计 陆域驳岸线位置


竖向尺度设计 仓库、堆场布置
平面布置
道路、铁路布置
生产辅助设施布置
总平面布置图
图纸:不少于3张,至少1张运用计算机绘图。
设计条件分析
★ 设计条件分析

使用条件


自然条件
施工条件
设计条件分析
★ 设计条件分析

使用条件 货物:货种、流向、吞吐量 → 规模、工艺

自然条件 船舶:船型及尺度 → 主要尺度、荷载
机械:可供选择的装卸运输机械及其性能 施工条件 →工艺、码头荷载
装卸工艺设计
主要设施规模 根据货种及流向、机械的适应性和作 平面尺度设计 业效率等,合理地选择装卸船机的数量 按相互协调原则配备水平运输机械及
库场作业机械(类型、数量)
计算通过能力、投资、能耗等 分析所设计装卸工艺的优缺点
码头平面设计
★ 码头平面设计
使用条件 施工机械:性能 → 设计方案、施工工期


自然条件 材料供应:主要工程材料来源
施工条件
→ 设计方案的实施、工程投资 三通一平:水、电、路、场地
码头平面设计
★ 码头平面设计

装卸工艺设计


主要设施规模
平面尺度设计


竖向尺度设计
平面布置
码头平面设计
★ 码头平面设计

根据码头通过能力要求、货物类型 及流向等营运资料,科学合理地设计 装卸工艺(必要时进行多方案比选):
相关文档
最新文档