拉法基水泥集团--设备调试说明33
- 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
- 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
- 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。
Test & Commissioning
No Load T est: Individual Equipment
Palletizer No of
pages
/ Equipment Item:
Issue Date: 29th Oct. 2008 Rev: R00 Item N°
MPT - Single Machine Electrical Protection Interlock Test; MPT - 单机设备保护联锁测试
Lubrication A nd checking before starting
润滑和启动前检查
Lubrication 润滑All elements or components are added right lubrication oil before starting. And the right label should be near the lubrication point.
在启动前,所有的部件已经正确添加了润滑油。并且已润滑标签应
当贴在润滑点附近。
□
Security 安全检查No debris inside of packer.
检查内部无杂物。
All safety device installed like coupling guard
所有安全防护装置安装到位。
□
□
Mechanical check and adjustment
机械检查和调整Manually run the machine before normal running to make sure it
run smoothly and no friction and touch.
运转前先手动盘车,要求会专体转动灵活,不允许有摩擦、卡碰等
现象。
Inspecting the bolt tighten of driving wheel, reducer;
检查驱动电机减速机的固定螺栓是否紧固。
Check and tighten all the bolts.
检查并拧紧各联接螺栓;
Check the compressed air piping, check the pressure of compressed air system and no leakage on the piping
检查压缩空气管线,检查管路压力及无漏气
□
□
□
Key Point for Individual Test
单机试车期间检查内容
(1) The duration of individual test should be
单机试车运转时间为:
2hours
(2) Following items should be checked during the individual test:
单机试车期间,下列项目应当检查:
❑The equipment rotates smoothly without any abnormal vibration or sound.
设备转动平稳,无异常振动和杂音;
❑Be sure that all joint and seal places are secured without air and oil leakage.
各联接部位和密封部位,密封良好,不得有漏风、漏油现象。□□
单机试车记录
Register of Individual Test Running Current
运行电流
A Ambient temperature:
环境温度:
0C
Checking items 检查内容Unit
Results
记录结果
0.5h 1h 2h
Motor bearing temperature 电机轴承温度0C
R
L
Reducer shell temperature
减速机外壳温度
0C Rotor bearing temperature
转子轴承温度
0C
Checking items and standard 检查内容和质量标准
Result 检查结果
Lubrication 润滑No leakage
有无漏油现象
Yes No
□□
noise 杂音
No surprised noise
有无杂音和异常声音
Yes No
□□Comments and Updating Punch Lists
S OLVED
Y ES/N O
D AT
E S IGNATURE
Conclusion:
Accept:
Y es No
□□Accept:
Y es No
□
Accept:
Y es No
□□
Accept:
Y es No
□□
Date: Date : Date: Date:
Contractor: Test Engineer : Contractor:
NLT Manager
Lafarge:
Test Engineer:
Lafarge:
NLT Manager: