关于我国海底隧道建设若干工程技术问题的思考
郭陕云
(中铁隧道集团有限公司,河南洛阳
471009)
摘要:结合国内外海底及水下隧道建设的实例,从海底隧道的工程准备、技术方法、方案比选、风险管理、工程理念等方面进行论述。提出海底隧道项目应从长计议、及早打算、周密安排,才能少走弯路,不失时机;对沉埋法、暗挖法、盾构法修筑海底隧道的优缺点进行分析,提出采用建议及应当注意和研究的问题;从线位和线形、线数和断面、附属及运营设施、建造方式等方面对海底隧道工程方案进行比选,提出建议;提出我国海底隧道采用风险管理的建议;进一步强调要树立正确的工程建设理念。关键词:海底隧道;工程准备;技术方法;方案比选;风险管理;工程理念中图分类号:U459.5
文献标识码:B
Co mments on So me Engi n eeri n g and Technology Issues
Rel ated to Buildi n g Sub 2sea Tunnels i n Chi n a
G UO Shan 2yun
(China R ail w ay Tunnel Group Co .,L td .,L uoyang 471009,Henan,China )
Abstract:On basis of case hist ories of sub 2sea tunnels and sub 2water tunnels in China and f oreign countries,the author makes s ome co mments on sub 2sea tunnels in res pect of engineering p reparati ons,technical methods,op ti on selecti on,risk manage ment and engineering concep t .The author states that for sub 2sea tunnel works,future issues should be p r op 2erly considered and early p reparati ons and water 2tight arrange ment should be made s o as t o avoid det ouring course and not t o l ose any opportunity .After analyzing the advantages/disadvantages of s ome popular constructi on methods for sub 2
sea tunnels,such as i m mersed tube method,drill and blastmethod and T BM (Tunnel BoringMachine )method,the au 2thor makes s ome suggesti ons on the selecti on of the p r oper constructi on methods f or sub 2sea tunnels and p r ovides s ome t op ics t o which s pecial attenti on should be paid and /or researches should be made .The author als o makes s ome advices on the op ti on selecti on of sub 2sea tunnels in ter m s of l ocati on and alignment,tube numbers and cr oss 2secti on,auxiliary and operati on facilities and constructi on methods .The author suggests that risk manage ment should be intr oduced int o the manage ment of the sub 2sea tunnel works in China .The author finally e mphasizes that rati onal engineering concep t should be established in the m ind of the decisi on 2makers .
Key words:sub 2sea tunnel;engineering p reparati on;technical method;op ti on selecti on;risk manage ment;engineer 2ing concep t
0引言
厦门东通道翔安隧道的建设开启了我国大陆方面海底隧道的先河,使得我国众多隧道建设工作者和有关专家、学者的多年梦想成真。我们由衷地敬佩福建省及厦门市相关主管领导的勇气和魄力,并感谢他们为中国水下隧道的建设和发展所做出的努力和贡献。翔安隧道将作为中国大陆第一座海底隧道载入史册。我曾有幸多次参加厦门东通道的技术方案征询和论证会,并于2004年3月参与并主持了中国土木工程学会隧道及地下工程分会和厦门市路桥建设总公司联合举
办的厦门东通道海底隧道修建技术高级专家研讨会,所以对翔安隧道修建技术方案前后形成的过程有着部分的了解。因此也催使我对海底隧道建设的工程技术问题有着个人粗浅的认识和想法。
1工程准备
人类要用水下隧道穿越海域的思想始于19世纪
的欧洲拿破仑时代,英法海峡隧道自1800年曾两次动工开挖后又停了下来。正因为人们有了这百年的热望和向瀚海天堑挑战的勇气,才产生出了当今为世人所骄傲的“世纪杰出工程”。日本于20世纪40年代建
收稿日期:2007-05-29
作者简介:郭陕云(1958-),中国土木工程学会隧道及地下工程分会理事长,教授级高级工程师。
第27卷 第3期2007年6月 隧道建设Tunnel Constructi on
27(3):1~5
June,2007