2006-06-26 Reported: Bill.Bin 20-28
Volumetric Shrinkage at Ejection
case1 case2
The Volumetric shrinkage at ejection result can be used to detect sink marks on the model. Volumetric shrinkage should be uniform across the whole part to reduce warpage. High shrinkage values could indicate sink marks or voids inside the part. Volumetric shrinkage can be controlled by the use of packing profiles.
2006-06-26
Reported: Bill.Bin
4-28
Part infomatiom
Thickness distribution
2006-06-26
Reported: Bill.Bin
5-28
Cooling system design
All case is base 2d mold design.
2006-06-26 Reported: Bill.Bin 19-28
Temperature mold
case1 case2
The temperature mold result shows the average temperature of the plastic mold interface at the top side, of the mold element during the cycle time . The result displays in the mold surface has a small range..
Runner system design
case2 Move gate
case2 is reviser runner system (move gate )
2006-06-26 Reported: Bill.Bin 8-28
Fill Time
case1
case2
The fill time result shows the position of the flow front at regular , as the cavity fills. Each color contour represent the parts of the mold Which were being filled at same time. .The fill time is about 5.6 second in the model . No racetrack effect occur. Air trap appear on the last filled area. Do set enough vent over there.
2006-06-26 Reported: Bill.Bin 16-28
ClaBiblioteka Baidup force: XY Plot
case1 case2
The result shows the pressure and clamp force at various times during the filling and packing phases of the analysis.
Mold Flow Report
1. Project Summary--------------------------------------------------------------------------2 2. Plastic material information ---------------------------------------------------------- 3 3. Analysis purpose & Process condition ------------------------------------------- 4 4. Part information, Runner and cooling system design ---------------------6~8 5. Analysis result--------------------------------------------------------------------------9~27 6. Conclusion & suggestion ------------------------------------------------------------- 28
2006-06-26 Reported: Bill.Bin 10-28
Pressure at V/P switchover
case1 case2
The result shows the pressure distribution through the flow path inside the mold at the Switchover point from velocity to pressure control.
Pressure at injection location :XY Plot
case1
case2
The result shows the pressure and clamp force at various times during the filling and packing phases of the analysis.
2006-06-26 Reported: Bill.Bin 17-28
circuit coolant temperature
case1 case2
The cooling analysis screen output contains the change in coolant temperature from coolant-into coolant-out If the increase is unacceptable (greater than 2-3 deg.c)
case1
case2
2006-06-26
Reported: Bill.Bin
2-28
Material Property
ABS Polylac PA-737 Manufacturer : Chi Mei Corporation PA1. Melt Density : 2. Solid Density : 3. Ejection Temperature 4. Recommended Mold 6. Filler unfilled 200deg.C 0.96055g/cu.cm 1.0494g/cu.cm 90 deg.C 60 deg.C 8. Melt Temperature Maximum 9. Mold Temperature Minimum 240 deg.C 40deg.C
2006-06-26 Reported: Bill.Bin 13-28
Weld line
case1
case2
Notice the positions of the weld lines, which may affect the qualing of the part appearance but which maybe affect the part structural functions. .
5. Recommended Melt Temperature 220deg.C 7. Melt Temperature Minimum
P-V-T
2006-06-26 Reported: Bill.Bin
Viscosity vs Shear rate
3-28
Process setting
Analysis purpose: improve warpage Analysis Project: Cooling + flow + Warpage Process setting
Mold Temperature:60/65℃ Melt Temperature: 220℃ Fill Time: automatic Cooling time:60S V/P switch-over: 99% of filled volume pack
case1
case2
80%V/P 10S
80%X0.3+0X1.5+6X60%+12X100%S
2006-06-26 Reported: Bill.Bin 18-28
Time to freeze
case1 case2
The result shows the thickness of the frozen. A higher value represents a thicker frozen layer, while low value means a thinner polymer melt (flow )layer Cooing channel need to near sprue , for reduce cycle time.
2006-06-26 Reported: Bill.Bin 9-28
Fill Time
case1
case2
The fill time result shows the position of the flow front at regular , as the cavity fills. Each color contour represent the parts of the mold Which were being filled at same time. .The fill time is about 5.6 second in the model . No racetrack effect occur. Air trap appear on the last filled area. Do set enough vent over there.
2006-06-26
Reported: Bill.Bin
1-28
Mold Flow Report
Mold NO:B10274 : Prepared by: Bill.Bin Cavity number:1*2 Analysis purpose : improve warpage。 Analysis Project: Cool +Fill +Pack + Warp Case1 is the 3D design. Case2 is revise mold design and modified the process condition.
2006-06-26 Reported: Bill.Bin 11-28
Air Trap
case1
case2
The air traps are show in pink node
2006-06-26 Reported: Bill.Bin 12-28
Air Trap
case1
case2
The air traps are show in pink node
2006-06-26 Reported: Bill.Bin 6-28
Runner system design
case1
Ø12mm Ø10~2.8mm
Ø8mm
Ø2.8~8mm Ø10mm
Case1 is base 2d mold design ,
2006-06-26 Reported: Bill.Bin 7-28
10. Mold Temperature Maximum 80deg.C 11. Maximum Shear Rate 12. Maximum Shear Stress 13. Thermal conductivity 14. Measured MFR 50000 1/s 0. 5 Mpa 0.19(k)w/m.c 3 g/10min(5kg/200.C))
2006-06-26 Reported: Bill.Bin 14-28
波前温度
case1
case2
The melt temperature is 220℃, this themperature at flow front is allow.
2006-06-26 Reported: Bill.Bin 15-28