Type Test Report for HIVERT-Y 6kV 96A System 合康高压变频器测试报告(英文版)
- 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
- 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
- 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。
Reference No.: 2003 Electrical Test 018
Tian Jin Test Institute for Generating & Distribution & Electric Control Equipment
China National Center for Quality Supervision and Test of Electrical Control and
LV Distribution Equipment (CECDE)
1DPH 0HGLXP 9ROWDJH 9DULDEOH )UHTXHQF\ 'ULYH
7\SH +,9(57 <
&RQVLJQPHQW 8QLW :XKDQ +LFRQLFV 7HFKQRORJ\ &R /WG
.LQG RI 7HVW &RQVLJQPHQW 7HVW
China National Center for Quality Supervision and Test of Electrical Control and LV Distribution Equipment
TESTING REPORT
Reference No.: 2003 Electrical Test 018 7RWDO 3DJHV 3DJH
Name
Medium Voltage Variable Frequency Drive Trademark / Type
HIVERT-Y06/096Rated Voltage: 6000V Capacity: 1000kVA Main
Technical
Data
Rated Current: 96A Kind of Test
Consignment Test Consignment
Unit
Wuhan Hiconics Technology Co., Ltd. Address of
Consignment
Unit
4th Floor 3 Yejin Rd., Qinshan District, Wuhan Production
Unit
Wuhan Hiconics Technology Co., Ltd. Address of
Production
Unit
4th Floor 3 Yejin Rd., Qinshan District, Wuhan Sampling
Place
/Sampler /Sample Provider Qiuquan Chen Sampled
Quantity
/Sampling Basic /Production Date on-site Sampling
Date
/Arrival Date Sample No.
2003DK005Letter of Authorization 2003-Z018Inspection
Basis
Q/HC02-2002 Technical Condition of HIVERT-Y Range Medium Voltage Variable Frequency Drive Inspection
Date March 4, 2003 - March 8, 3003
Inspection
Conclusion
According to 18 inspection items, the product complies with
the inspection basis. Therefore, the consignment Test is passed. Issue Date: March 11, 2003
Remarks For inspection items, see page 2.
Approver ˖ Auditor ˖ Editor:
China National Center for Quality Supervision and Test of Electrical Control and LV Distribution Equipment
TESTING REPORT
Reference No.: 2003 Electrical Test 018
Summary Sheet of Inspection Item and Conclusions7RWDO 3DJHV 3DJH
No. Inspection/Test
Item Conclusion
Page
1General Examination (Clearance and Creepage
Distance, Safety Grounding, etc.)
Check out 3-4
2 Protection Level Test Check out 5
3 Insulation
Resistance Test Check
out
6 4 Light-load
Test Check
out 7
5 Load
Test Check
out 9
6 Rated Output V oltage Test Check out 8
7 Unbalance Level of Output V oltage Test Check out 8
8 Harmonic Content of Output V oltage and Current Test Check out 10-17
9 Harmonic Content of Input V oltage and Current Test Check out 18-24
10 Rated Output Frequency Test Check out 8
11 Adjustable Range of Frequency Test Check out 25
12 Precision Test of Frequency Stability Check out 26
13 Frequency Resolution Test Check out 27
14 Continuously Running Test Check out 28
15 Startability
Test Check
out 29-30
16 Efficiency
Test Check
out 31
17 Power Factor Test Check out 31
18 Cooling Performance Test Check out 32
Auditor˖Xia Liu Editor: Shumin Liu