基础石方开挖施工方案
![基础石方开挖施工方案](https://img.360docs.net/imgd8/1pbkroyy07rd27ahvpiwsyl2evvlnywj-81.webp)
![基础石方开挖施工方案](https://img.360docs.net/imgd8/1pbkroyy07rd27ahvpiwsyl2evvlnywj-c2.webp)
目录
1.1施工条件 ------------------------------------------------------------------------------------------------------------------------ 2
1.1.1前言---------------------------------------------------------------------------------------------------------------------------- 2
1.1.2工程布置 ------------------------------------------------------------------------------------------------------------------- 2
1.1.3地质条件 ------------------------------------------------------------------------------------------------------------------- 2
1.1.4现场具备的条件------------------------------------------------------------------------------------------------------- 3
1.1.5项目制约条件 ----------------------------------------------------------------------------------------------------------- 3
1.2工作内容及要工程量---------------------------------------------------------------------------------------------------- 3
2、施工进度安排------------------------------------------------------------------------------------------------------------ 3
2.1施工总体安排---------------------------------------------------------------------------------------------------------------- 3
2.2石方开挖进度安排 ------------------------------------------------------------------------------------------------------- 3
2.3施工强度 ----------------------------------------------------------------------------------------------------------------------- 4
3、施工布置-------------------------------------------------------------------------------------------------------------------- 4
3.1 施工布置原则--------------------------------------------------------------------------------------------------------------- 4
3.2 石方开挖道路 -------------------------------------------------------------------------------------------------------------- 4
3.3 施工导流布置 -------------------------------------------------------------------------------------------------------------- 4
3.4施工供电与照明 ----------------------------------------------------------------------------------------------------------- 4
3.5施工供风 ----------------------------------------------------------------------------------------------------------------------- 4
3.6施工排水 ----------------------------------------------------------------------------------------------------------------------- 5
3.7开挖料的堆存 --------------------------------------------------------------------------------------------------------------- 5
3.8作业面布置 ------------------------------------------------------------------------------------------------------------------- 5
4、测量控制-------------------------------------------------------------------------------------------------------------------- 5
4.1施工放样------------------------------------------------------------------------------------------------------------------------ 5
4.2测量设备 ----------------------------------------------------------------------------------------------------------------------- 6
5、本方案引用标准和规程规范及资料------------------------------------------------------------------------ 6
6、表层清理-------------------------------------------------------------------------------------------------------------------- 6
6.1表层清理的要求 ----------------------------------------------------------------------------------------------------------- 6
6.2植被清理的施工程序和方法 --------------------------------------------------------------------------------------- 7
6.2.1施工程序 ------------------------------------------------------------------------------------------------------------------ 7
6.2.2施工方法------------------------------------------------------------------------------------------------------------------ 7
7、基础石方明挖------------------------------------------------------------------------------------------------------------ 8
7.1主要项目及工作内容---------------------------------------------------------------------------------------------------- 8
7.2开挖程序 ----------------------------------------------------------------------------------------------------------------------- 8
7.3施工准备 ----------------------------------------------------------------------------------------------------------------------- 8
7.4石方开挖技术要求 ------------------------------------------------------------------------------------------------------- 8
7.5石方开挖方法 --------------------------------------------------------------------------------------------------------------- 9
7.5.1开挖方式------------------------------------------------------------------------------------------------------------------- 9
7.5.2石方开挖边坡设计 -------------------------------------------------------------------------------------------------- 9
7.5.3基础开挖底面宽度 -------------------------------------------------------------------------------------------------- 9
7.5.5装药量控制 ------------------------------------------------------------------------------------------------------------ 10
7.5.6爆破器材选用--------------------------------------------------------------------------------------------------------- 12
7.5.7装药与封堵 ------------------------------------------------------------------------------------------------------------- 12
7.5.8钻爆施工----------------------------------------------------------------------------------------------------------------- 12
7.6石方开挖设备 --------------------------------------------------------------------------------------------------------------13
8、环境保护与文明施工----------------------------------------------------------------------------------------------- 13
9、质量标准及要求------------------------------------------------------------------------------------------------------- 13
9.1质量要求 ----------------------------------------------------------------------------------------------------------------------13
9.2开挖应注意的质量问题 --------------------------------------------------------------------------------------------- 14
10、安全防护措施 --------------------------------------------------------------------------------------------------------- 14
10.1劳动保护 -------------------------------------------------------------------------------------------------------------------- 14
10.2安全用电-------------------------------------------------------------------------------------------------------------------- 14
10.3 火工材料管理及爆破安全技术措施 -----------------------------------------------------------------------15
1、概述
1.1施工条件
1.1.1前言
依据朝阳市水利建筑设计院提供取水头部及中途加压泵站地质图和基础设计深度比较分析,中途加压泵站工程基岩埋置深度较深,基础开挖施工无石方开挖,取水头部基岩埋置深度较浅。因此,本工程基础石方开挖施工位于取水头部。
取水头部基础石方开挖部位,除泵房基础为基坑开挖外,截潜坝和渗渠为基槽开挖结构形式。
由于本工程提供的地质勘察资料的精度不够,石方开挖施工方案将受其影响。本方案亦是建立在此前提条件下编制的。待基础土方开挖揭露岩面线后,根据实际岩面高程随时调整石方开挖方法。
1.1.2工程布置
取水头部截潜坝、渗渠、头部一级泵站位于辽宁省朝阳市朝阳县朝阳县乌兰河硕乡黄道营子村大凌河干流上,取水头部中心为东经119°59′15",、北纬41°20′00",上游有上窝铺水文站,下游有朝阳水文站。截潜坝长431m,为混凝土地下暗渠结构;截潜坝上游辐射两条800m长渗渠与之相连。截潜坝上游左岸布置一级加压泵站,厂区内布置泵房、水锤室,附属用房等建筑物。
1.1.3地质条件
取水头部位于朝阳县乌兰河硕乡,黄道子村,大凌河河谷,截潜和取水建筑物位于河谷左侧,依傍左岸布设。截潜剖面长431m,渗渠自截潜坝沿河床两侧向上游弧形伸展,长0.60 km。地貌为河谷地貌,河床左侧为高漫滩。地表高程231.99~238.87m。河道左岸临近乡级公路和山体。
勘察主要揭遇地层有:粉土①层、圆砾②层、砂岩③层。其中,砂岩层埋深0~11.4m,位于高程225.91~231.5m之间。场区地下水埋深0.40~1.70m。
1.1.4现场具备的条件
目前,对于石方施工的现场条件,取水头部对外交通条件较好,三通一平已完成。除头部泵站厂房已完成表土开挖,具备石方开挖条件,其他部位因征地未完成不具备石方开挖条件,只能进行取水头部泵站厂房石方开挖施工。
1.1.5项目制约条件
依据合同总工期要求2011年11月1日前完工,头部基础开挖施工必须满足施工总进度要求。基础石方开挖直接制约总体工程施工进度,石方开挖必须满足总体工程施工进度要求,及早进行基础石方开挖是保证合同工期的关键。此外,基础施工设备进场,石方开挖前爆破手续完备等准备工作提前进行。
1.2工作内容及要工程量
根据合同文件中工程量清单内容,本项目石方明挖工程量15495m3。土石方明挖主要工程量见表1.2-1。
2.1施工总体安排
2011年5月27日开工,2011年11月1日完工。
2.2石方开挖进度安排
本项目石方开挖的进度安排如表2.2-1。
表2.2-1 石方开挖进度计划表
2.3施工强度
依据开挖工程量、进度安排,各部位开挖施工强度见表2.3-1
表2.3-1 土石方开挖强度表
3、施工布置
3.1 施工布置原则
施工布置遵守科学合理,各施工道路最短,工程量最少,压缩占地面积,同时又方便施工,不增加临时工程量,有利于环境保护,不影响或少影响相邻工程的施工,保证施工和工程安全等原则。
3.2 石方开挖道路
石方开挖施工区域内场内临时施工道路的布置,主要以满足方便石方开挖施工运输为目的,同时兼顾后续工序项目使用方便的形式布置。石方开挖作业区域至场区临时道路间的施工支路,依据现场情况就近连接。厂区主要临时干路见
3.3 施工导流布置
另见专项施工方案。
3.4施工供电与照明
石方开挖施工区域基坑排水和供风用电全部利用现场315KVA变压器供电。变压器到空压站及水泵间采用380/220V架空布线,选用75mm2橡胶电缆引至用电点。根据施工进度情况,拟在开挖区域布置3~5盏碘钨灯进行照明。其他临时性照明区域根据现场情况临时增加碘钨灯照明。
3.5施工供风
本工程施工供风主要为基础石方明挖开挖用风。
在开挖区域附近布置一台6m3移动式电动空压机供风。采用2″高压胶管供风。
主要供风设备和材料见表3.5-1。
3.6施工排水
基础石方开挖期间,主要考虑基坑内渗水及降雨排水。
基坑内渗水及降雨积水,在每个基坑开挖边线外配置二台6″潜水泵和二台2″潜水泵控制排水。
3.7开挖料的堆存
由于施工场地狭窄,开挖料现场无堆存场地,且不能直接用于回填使用,石方开挖料需运输至场外堆存。石方开挖料将运至监理人指定的弃料场堆存。
3.8作业面布置
根据施工进度安排,依据开挖段划分将本工程基础石方开挖项目基本划分为两个作业面进行开挖作业,各作业面单独布置,开挖穿插土方开挖进行同时作业。
4、测量控制
4.1施工放样
(1)施工测量放样贯穿整个施工过程,在施工程序上,可以直接由等级控制点(首级及加密控制点)直接施放,也可以由细部临时加密的等级较低的轴线、测站点来施放。根据不同精度要求以及是否方便操作来选择,重要部位直接采用首级控制点、加密网点进行放样。
(2)在本工程中将充分利用先进的仪器设备进行施工放样,主要采用的办法是全站仪光电测距极坐标法,根据不同情况辅以边角前方交会法,轴线交会法,以及测角前方交会法等。
(3)放样前根据设计图纸和有关资料及使用的控制点成果,准备好放样资料,绘制出放样草图,所有资料及草图均经两人独立校核。所有放样点线均有检核条件。现场取得的放样及检查验收资料,必须进行复核,确认无误后方能交付使用。
(4)做好土石分界测绘