工程变更通知(ECN)生成作业指导-中英文对照
- 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
- 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
- 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。
Revision History
Approved DCN on File in Document Control
1.0 SCOPE 范围
1.1 This work instruction is used in generating Engineering Change Notice (ECN) applicable to
product documentation.
该作业指导书适用于产品文件的工程变更通知(ECN)的生成。
1.2 This work instruction can be used during the initial release, revision and obsolescence of a
product document.
该作业指导可用于产品文件初次发行,修订以及废止。
2.0 ASSOCIATED DOCUMENTS 相关文件
2.1 DC20001 - Document Control Procedure
DC20001 -文件控制程序
2.2 DC30001 – Work Instruction for Document Naming
DC30001 –文件命名作业指导
2.3 DC30002 – Work Instruction for Document Change Notice (DCN) Generation.
DC30002 –文件更改通知(DCN)生成作业指导
3.0 SAFETY REQUIREMENTS 安全要求
3.1 Not applicable. 不适用
4.0 GENERAL REQUIREMENTS 一般要求
4.1 An overview of the Engineering Change Notice (ECN), Temporary Engineering Change
Notice (TECN) generation flow is found in Attachment 1 and 2.
工程变更通知(ECN)以及临时工程变更通知(TECN)生成流程总括可参照附件1和附件2。
4.2 Initiator to fill up an ECN form. For the ECN form, refer to Form DC30003_A and Form
DC30003_B in case additional page/s is required (see Attachment 3-A and 3-B).
发起人填写ECN表格。
关于ECN表,参考Form DC30003_A 和Form DC30003_B
附页以防需要更多的附页(参考附件3-A和附件3-B) 。
4.2.1 Refer to Table 1 below for guidance on important details needed in filling up an ECN /
TECN form for Products Documentation.
填写生产文件ECN / TECN表格所需重要细节,请参照下表1作为指导。
4.2.2 Refer to Table 2 below for guidance in filling up the Affected Document column.
填写受影响文件栏参照下表2作为指导
4.3 For manual entry and signature, use black or blue pen only. Pencil is not allowed.
针对手写输入和签名,只可使用黑色或蓝色钢笔,不允许使用铅笔。
4.4 URGENT ECN / TECN 紧急ECN / TECN;
4.4.1 An URGENT ECN / TECN is deemed effective upon approval of the CEO and or his
deputies.
紧急ECN / TECN经CEO 和/或他的代理人批准后即生效。
4.5 An ordinary ECN / TECN shall be routed by the initiator for approval within 2 working days.
常规的ECN / TECN在2个工作日内由发起人跟进安排签名批准。
4.6 DCC shall provide ECN / TECN number once the approval process is complete.
如批准程序完成,DCC应提供ECN / TECN编号。
4.7 Changes affecting suppliers 影响供应商的变更;
4.7.1 DCC shall send the approved copy of the ECN / TECN to the initiator and relevant
internal purchaser.
DCC应将批准的ECN / TECN复件发给发起人及内部采购。
4.7.2 Implementation of the change(ECN / TECN) at the supplier site shall be validated by
the QA Engineer.
由供应商一方执行的(ECN / TECN) 变更应由QA工程师进行验证。
4.8 To extend the TECN after the expiry date, the initiator needs to issue another TECN,
otherwise initiator may consider issuing an ECN.
TECN期满后如需延期,发起人需重新发起另一个TECN,否则发起人应考虑发行ECN。
4.9 Cost Impact. 价格影响
4.9.1 The initiator of ECN is responsible for the determining the cost impact of the change. It
shall be clearly stated “none” in the ECN/TECN; if there is nothing foreseen.
工程变更通知(ECN) 的发起人负责判定变更价格影响。
如没有任何预见,则清楚地在
ECN/TECN上描述为“none”(没有)
4.9.2 Should there be unforeseen cost impact determined by the internal purchaser and
supplier, the recipient of such feedback, shall inform the CEO. 若内部采购及供应商判
定的价格变更影响为无法预见,接受该反馈的人应通知CEO。
4.10 Implementation of the change(ECN / TECN) in SUNMING shall be validated by
the QA Engineer.
由SUNMING执行的(ECN / TECN) 变更应由QA工程师进行验证。
(Attachment 1)
附件1
Engineering Change Notice (ECN) Generation Flow 工程变更通知(ECN)生成流程图
(Attachment 2)
附件2
Temporary Engineering Change Notice (TECN) Generation Flow 临时工程变更通知(TECN)生成流程图
(Attachment 3-A)
附件3-A
Engineering Change Notice (ECN) Form 工程变更通知(ECN)表
(Attachment 3-B)
附件3-B
Engineering Change Notice (ECN) Supplementary Sheet 工程变更通知(ECN) 附加表
(Attachment 4)
附件4
Major and Minor Category 主要和次要类别。