供应链管理第三版unit8习题与答案
- 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
- 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
- 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。
Chapter 8
Aggregate Planning in the Supply Chain
True/False
1.The goal of aggregate planning is to satisfy demand in a way that
minimizes profit.
Answer: False
Difficulty: Easy
2.Aggregate planning is a process by which a company determines
levels of capacity, production, subcontracting, inventory, stockouts,
and even pricing over a specified time horizon.
Answer: True
Difficulty: Moderate
3.Aggregate planning solves problems involving aggregate decisions
rather than stock keeping unit (SKU) level decisions.
Answer: True
Difficulty: Easy
4.Traditionally, much of aggregate planning is focused within an
enterprise and may not always be seen as a part of supply chain
management.
Answer: True
Difficulty: Moderate
5.Aggregate planning is an important supply chain issue because, to
be effective, it requires inputs from throughout the supply chain, but
its results have little impact on the supply chain.
Answer: False
Difficulty: Moderate
6.Short-term production serves as a broad blueprint for operations
and establishes the parameters within which aggregate planning decisions are made.
Answer: False
Difficulty: Easy
7.The aggregate planning problem is concerned with determining the
production level, inventory level, and capacity level (internal and
outsourced) for each p eriod that maximizes the firm’s profit over the
planning horizon.
Answer: True
Difficulty: Moderate
8.To create an aggregate plan, a company must specify the planning
horizon for the plan and the duration of each period within the planning horizon.
Answer: True
Difficulty: Easy
9.A planning horizon is usually between three and five years.
Answer: False
Difficulty: Moderate
10. A poor aggregate plan can result in improved sales and
profits if the available inventory and capacity are unable to meet
demand.
Answer: False
Difficulty: Easy
11. A poor aggregate plan may result in a large amount of
excess inventory and capacity, thereby raising costs.
Answer: True
Difficulty: Moderate
12.The aggregate planner must make a trade-off between
capacity, inventory, and backlog costs.
Answer: True
Difficulty: Moderate
13.An aggregate plan that increases one cost typically
results in the increase of the other two.
Answer: False
Difficulty: Moderate
14.The time flexible strategy is where the production rate is
synchronized with the demand rate by varying machine capacity or hiring and laying off employees as the demand rate varies.
Answer: False
Difficulty: Hard
15.The time flexible strategy is where workforce (capacity)
is kept stable but the number of hours worked is varied over time in an effort to synchronize production with demand.
Answer: True
Difficulty: Moderate