矿山场地平整及土石方工程开工手续流程
下载温馨提示:该文档是我店铺精心编制而成,希望大家下载以后,能够帮助大家解决实际的问题。
文档下载后可定制随意修改,请根据实际需要进行相应的调整和使用,谢谢!
并且,本店铺为大家提供各种各样类型的实用资料,如教育随笔、日记赏析、句子摘抄、古诗大全、经典美文、话题作文、工作总结、词语解析、文案摘录、其他资料等等,如想了解不同资料格式和写法,敬请关注!
Download tips: This document is carefully compiled by theeditor.
I hope that after you download them,they can help yousolve practical problems. The document can be customized andmodified after downloading,please adjust and use it according toactual needs, thank you!
In addition, our shop provides you with various types ofpractical materials,such as educational essays, diaryappreciation,sentence excerpts,ancient poems,classic articles,topic composition,work summary,word parsing,copy excerpts,other materials and so on,want to know different data formats andwriting methods,please pay attention!
矿山场地平整及土石方工程开工手续流程详解
矿山场地平整和土石方工程是矿业开发的重要环节,但在此之前,必须完成一系列的开工手续。
这些手续既是对法律法规的遵守,也是保障工程安全、环保和合规的重要步骤。
下面,我们将详细阐述这一流程。
1. 项目立项:首先,企业需要向相关部门提交项目建议书,阐明矿山开采的必要性和可行性,包括地质勘查报告、环境影响评估等,获得立项批准。
2. 环评审批:在立项后,需进行环境影响评价。
编制环评报告,提交环保部门审批,确保工程不会对周边环境造成重大影响。
通过环评后,会获得环评批复。
3. 土地使用审批:根据矿山所在地的土地性质,可能需要向土地管理部门申请土地使用权,或者进行土地征收、租赁等手续。
4. 安全许可:向安全生产监督管理部门提交安全预评价报告,获得安全生产许可证。
这是保证矿山开采安全的重要步骤。
5. 规划许可:向城乡规划部门申请建设工程规划许可证,明确工程的具体位置、规模和建设要求。
6. 施工图审查:设计单位完成施工图设计后,需提交相关部门进行审查,确认其符合相关技术标准和规范。
7. 施工招标:公开或邀请招标,选择具有相应资质的施工单位,签订施工合同。
8. 开工报告:向工程所在地的建设行政主管部门提交开工报告,获得开工令,标志着工程正式进入施工阶段。
以上就是矿山场地平整及土石方工程的开工手续流程,每个步骤都需要严谨对待,以确保工程的顺利进行。
同时,企业在执行过程中还应严格遵守相关法律法规,做到合法合规,保护好生态环境,确保人民的生命财产安全。