个人创业计划书样本

合集下载
  1. 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
  2. 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
  3. 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。

个人创业计划书样本

temporary construction organization design requires the implementation of the overall layout. 2 site near the high voltage line protection near power lines to have a reliable protective measures protective closely, to meet safety requirements. 3 branch set up distribution box into outlet sleeve and a cross arm to be used; Access to wires neatly, reasonable matching; Prohibited the use of insulation is poor, aging skin, broken wires, to prevent leakage; Should be fixed by insulators, and overhead laying; Line the hallway to have a reliable protection; Direct buried lines, laying depth of not less than 0.6m, leads to the ground from the 2m height to the ground at 0.2m, you must set up protective casing. 4 spot lights hand-held lamp 36V safe voltage should be used; 36V safety at hazardous voltages, particularly in hazardous areas using 12V; Lighting wires should be fixed on the insulators; Insulated rubber sheathed cable for field lights, lighting the use of sheathed wires; Lighting circuits and lighting from the ground not less than the prescribed distance, prohibited the use of electric arc furnace; To prevent the wire insulation is poor, aged, broken skin and leakage, with tungsten heating is strictly prohibited. 5 to set up low-voltage lines are not allowed to use bamboo poles, pole cross arm should be established and insulators; Fine wires can not be mounted on scaffolding or tree branch; Overhead lines required high enough off the ground. 6 electric ... Project name: 5-5-2 sequential

order of the subsidence observation observation point number support (supporting) and diagrams year month day year month day year month Day, the distance (m) deformation (mm) the relative distance (m) deformation (mm) the relative distance (m) deformation (mm) today this this this

this cumulation Engineering formwork supporting system self-test State observer records form template project name: construction site: construction: support materials: Ann 5-6 serial number check project check requirements behave records results 1 construction programme programme full, support system design calculation, and approval procedures complete, job Qian should for security low-down, low-down material full 2 support material support column material: wood Rod application pine or FIR, shall not used easy deformation, and decay, and split crack, and dry section of wood; as used pipe, pipe od shall not is less than φ 48x3.5 of pipe, no serious rust, and crack, and deformation 3 column stable column bottom of pad material, Shall conform to the construction design requirement, do not use bricks blocked up by construction organization design requirements, support height () when m, between columns of the level of support set () road horizontal support, vertical scissors spacing (), m, spacing for horizontal scissors () m. Column spacing in accordance with design requirements, portrait () mm, transverse () mm pole joints should be staggered, long bar 创业项目计划书样本

, 按国际惯例通用的标准文本格式形成的项目计划书~是全面介绍公司和项目运作情况~阐述产品市场及竞争、风险等未来发展前景和融资要求的书

相关文档
最新文档