150吨履带吊
150吨履带吊安拆验收流程
150吨履带吊安拆验收流程The process of dismantling and inspecting a 150-ton crawler crane is a complex and critical task that requires careful planning and execution. 履带吊的安拆验收流程需要严谨的规划和执行。
First and foremost, before any work begins, it is essential to conduct a thorough risk assessment and safety inspection of the crane and the surrounding work area. 首先,在任何工作开始之前,必须对起重机和周围的工作区域进行全面的风险评估和安全检查。
The inspection should include checking for any structural damage, wear and tear on crucial components, as well as ensuring that all safety features and emergency systems are in proper working order. 检查应包括检查任何结构损伤,重要组件的磨损,以及确保所有安全功能和紧急系统处于正常工作状态。
Additionally, it is crucial to review the crane's service and maintenance records to ensure that it has been properly maintained and serviced according to manufacturer recommendations. 此外,重要的是要查看起重机的服务和维护记录,以确保它已按照制造商的建议进行了适当的维护和维修。
150T三一履带吊性能表
63.143m
2.01m
6.14m
SCC1500D
7
A SCC1500D 履带起重机 运输尺寸
运输尺寸
12m主臂 长 宽 高 重量 过渡臂
A长 宽 高 重量 固定副臂上节臂 长 宽 高 重量 固定副臂下节臂 长 宽 高 重量 3m固定副臂 长 宽 高 重量 6m固定副臂 长 宽 高 重量 加长臂 长 宽 高 重量
8
SCC1500D
×4 12.14m 2.30m 2.01m
1.8t ×1 6.13m 2.23m 2.55m 1.3t ×1 5.41m 1.01m 1.17m 0.32t ×1 5.11m 1.03m 0.83m 0.28t ×1 3.08m 1.01m 0.83m 0.13t ×3 6.08m 1.01m 0.83m 0.30t ×1 2.15m 1.04m 1.12m 0.32t
履带起重机系列
SCC1500D
A SCC1500D 履带起重机
A
SCC1500D履带起重机
03
整机基本尺寸
04
主要技术特点
05
主要性能参数表
ห้องสมุดไป่ตู้06
运输尺寸
07
安装示意图
11
B 设备简介
13
上车
14
A
下车
16
作业设备
17
安全装置
18
主要机构参数
20
C 工况组合
21
工况组合
22
轻型主臂HL工况
23
固定副臂FJ工况
28
SCC1500D
2
SCC1500D
A 04 整机基本尺寸 05 主要技术特点 06 主要性能参数表 07 运输尺寸 11 安装示意图
150t履带吊(LS248RH5-0145)
主臂单位:t工作半径(m)18.2921.3424.3827.4330.4833.5336.5839.6242.6745.7248.7751.8254.8657.9160.9664.0167.0670.173.1576.279.2582.35.5m 133.66.5m 104.37.5m 85.28.5m 70.19.5m 58.410.5m 11.0m 48.044.312.5m 13.0m 13.5m 38.036.733.714.5m 15.0m 15.5m 28.725.323.017.0m 34.525.0m 21.033.0m 13.541.0m 9.843.5m 8.749.0m 6.751.5m 5.957.0m 4.359.5m 3.72.42.23.22.82.6主 臂 长 度(m)额 定 起 重 量 表 (不 带 22t 行 走 配 重)5.0150.0121.7111.56.0140.0128.1116.8102.594.48.09.099.282.696.290.77.0123.610.012.014.016.070.654.744.637.628.030.032.034.020.022.024.026.036.040.098.982.470.454.444.337.232.118.044.137.131.927.998.882.370.354.324.524.32883.877.882.181.978.975.269.664.070.27066.562.370.169.331.427.454.14436.931.753.943.736.631.127.023.853.843.636.531.253.643.336.453.443.236.331.026.923.722.021.527.224.127.724.821.719.617.816.221.219.117.315.814.519.417.621.018.917.115.614.313.212.253.343.036.230.926.823.620.918.811.257.852.342.836.130.826.723.520.817.016.815.213.912.015.514.113.012.811.810.952.349.730.820.715.111.618.623.418.546.943.540.042.741.840.338.137.036.233.530.336.035.935.835.735.635.232.729.627.125.022.830.730.630.530.430.330.228.826.424.422.126.726.626.526.426.326.226.126.025.923.821.623.323.223.123.022.922.822.722.522.42120.620.520.420.320.120.020.019.818.418.318.217.618.118.017.917.817.517.416.716.616.516.416.316.216.116.015.715.615.515.014.914.814.714.614.514.413.613.513.414.113.313.213.113.012.712.512.712.412.312.212.112.011.911.813.711.511.411.211.411.311.211.111.010.910.810.510.210.1109.919.218.61810.410.114.013.919.719.612.620.319.716.915.413.812.59.59.39.142.010.211.2109.110.710.510.410.39.99.79.69.59.49.39.298.68.58.38.244.09.264.09.08.88.78.68.48.28.27.97.87.67.346.08.38.28.18.07.77.67.57.27.1 6.9 6.648.07.87.57.47.47.07 6.9 6.6 6.4 6.2650.07.0 6.8 6.8 6.4 6.4 6.36 5.8 5.6 5.352.0 6.3 6.2 5.9 5.9 5.7 5.4 5.35 4.854.0 5.8 5.4 5.45.45.054.5 4.5 5.2 4.9 4.7 4.5 4.356.0 4.7 4.4 4.24 3.858.0 4.34 3.8 3.5 3.460.0 4.1 3.9 3.6 3.4 3.1 2.962.0 2.7 2.53.5 3.23主臂单位:t工作半径(m)18.2921.3424.3827.4330.4833.5336.5839.6242.6745.7248.7751.8254.8657.9160.9664.0167.0670.173.1576.279.2582.35.5m 133.66.5m 104.37.5m 85.28.5m 70.19.5m 58.410.5m 11.0m 48.044.312.5m 13.0m 13.5m 38.036.733.714.5m 15.0m 15.5m 28.725.323.017.0m 38.825.0m 25.233.0m 16.541.0m 11.843.5m 10.849.0m 8.551.5m 7.957.0m 6.259.5m 5.55 4.7 4.55.5 5.2 4.564.04.3 4.160.0 4.75.4 5.1562.06.16 5.64.35.15.6 5.558.06.5 6.4 6.1 5.96.6 6.2 6.156.07 6.9 6.6 6.47.47.1 6.8 6.654.07.8 4.17.67.57.47.177.37.252.08.4 3.98.38.28.187.77.58.287.850.08.88.78.68.39.08.98.98.98.78.548.09.59.49.39.19.89.79.69.69.49.246.010.610.510.4 3.710.410.210.1109.79.610.410.210.144.011.010.910.810.511.411.311.211.211.542.011.511.411.21112.011.911.911.812.312.212.11212.413.812.811.813.413.313.11340.017.316.715.91512.512.412.220.319.719.218.61813.513.317.817.622.320.216.113.613.012.912.812.814.814.714.514.314.214.114.114.013.913.915.915.915.515.415.315.315.215.215.116.916.816.716.317.916.716.616.616.519.819.71918.618.518.418.418.218.218.221.719.620.520.420.320.220.220.120.120.024.122.522.422.422.022.422.322.322.324.822.42125.125.024.924.924.924.824.823.821.628.328.328.228.128.128.028.027.022.132.332.232.132.031.931.930.727.825.922.834.534.334.134.033.931.528.826.424.438.837.135.835.735.635.232.729.627.125.044.041.840.338.137.036.233.530.346.943.540.013.652.349.735.625.318.714.622.823.617.020.719.017.314.919.117.516.116.014.713.757.852.445.740.436.232.428.525.620.932.528.625.723.053.347.942.337.317.616.31525.923.221.119.226.023.421.219.317.823.621.519.426.323.821.532.628.826.526.233.129.233.429.65749.643.437.569.359.451.243.837.632.829.061.951.944.137.875.762.752.444.33833.263.452.744.438.278.672.866.562.387.282.878.975.269.664.083.877.829.529.432.098.889.979.263.552.744.538.333.536.038.098.990.579.463.652.944.738.418.020.022.024.026.028.030.032.034.079.563.853.144.810.012.014.016.0102.594.48.09.099.290.696.290.77.0123.6121.7111.56.0140.0128.1116.8主 臂 长 度(m)额 定 起 重 量 表 (带 22t 行 走 配 重)5.0150.0主臂单位:t工作半径(m)18.2921.3424.3827.4330.4833.5336.5839.6242.6745.7248.7751.8254.8657.9160.9664.0167.0670.173.1576.279.255.8m 13.56.4m 6.9m 13.513.57.4m 7.913.513.58.5m 13.59.5m 13.510.6m 11.1m 11.6m 13.513.513.512.1m 12.7m 13.2m 13.8m 13.513.513.513.514.2m 14.8m 15.3m 15.9m 13.513.513.513.516.4m 13.517.0m 13.525.0m 13.533.0m 13.541.0m 9.543.58.449.0m 6.451.5m 5.657.0m 4.159.5m 3.4主 臂 长 度(m)辅 助 伸 臂 额 定 起 重 量 表 (不 带 22t 行 走 配 重)5.060.0 3.2 2.9 2.7 2.413.513.56.013.58.09.013.513.513.513.57.013.513.510.012.014.016.013.513.513.513.528.030.032.034.020.022.024.026.036.038.013.513.513.513.513.513.513.518.013.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.512.911.913.513.513.513.513.513.513.513.510.913.513.513.513.513.513.513.513.513.513.513.511.713.513.512.712.511.510.613.513.513.513.511.313.513.513.413.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.512.413.513.012.912.812.713.513.513.512.412.112.011.911.211.111.111.010.910.810.710.610.511.89.89.79.613.311.711.611.513.213.113.513.513.510.113.513.512.313.513.513.513.513.513.513.512.29.29.99.69.440.010.99.88.810.410.210.110.09.010.29.99.39.29.19.08.98.78.38.28.042.08.98.78.58.48.38.17.97.97.67.57.344.08.07.97.87.77.47.37.2 6.9 6.8 6.646.07.57.27.17.1 6.7 6.7 6.6 6.3 6.1 5.948.0 6.7 6.5 6.5 6.1 6.1 6.0 5.7 5.5 5.350.06 5.9 5.6 5.6 5.4 5.15 4.752.0 5.5 5.1 5.1 4.9 4.6 4.4 4.254.0 5.14.7 4.7 4.4 4.1 3.9 3.756.0 4.2 4.2 4.0 3.7 3.5 3.258.0 3.8 3.6 3.3 3.1 2.862.02.32.12.92.5主臂单位:t工作半径(m)18.2921.3424.3827.4330.4833.5336.5839.6242.6745.7248.7751.8254.8657.9160.9664.0167.0670.173.1576.279.255.8m 13.56.4m 6.9m 13.513.57.4m 7.913.513.58.5m 13.59.5m 13.510.6m 11.1m 11.6m 13.513.513.512.1m 12.7m 13.2m 13.8m 13.513.513.513.514.2m 14.8m 15.3m 15.9m 13.513.513.513.516.4m 13.517.0m 13.525.0m 13.533.0m 13.541.0m 11.543.510.549.0m 8.251.5m 7.657.0m 5.959.5m 5.2462.0 4.84.4 4.23.83.6464.05.7 5.3 5.1 4.85.9 5.358.06.2 6.1 5.8 5.66.3 6.1 5.956.0 6.8 6.7 6.6 6.37.154.07.1 6.8 6.7 6.57.57.37.2752.07.97.77.47.28.18.07.950.08.387.97.78.68.68.58.48.78.448.09.198.88.69.49.39.39.29.59.146.09.89.79.49.310.210.110.19.910.344.010.510.210.19.910.910.910.710.611.211.111.010.942.011.611.511.211.111.811.711.711.613.513.011.913.113.012.812.712.113.312.740.012.112.011.913.513.513.513.513.512.213.513.513.513.213.513.513.513.513.513.512.612.512.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.313.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.513.536.038.013.513.513.513.513.513.513.518.020.022.024.026.028.030.032.034.013.513.513.513.510.012.014.016.013.513.57.013.513.56.013.58.09.013.513.5主 臂 长 度(m)辅 助 伸 臂 额 定 起 重 量 表 (带 22t 行 走 配 重)5.060.0 5.2 4.9 4.7 4.413.513.5主臂主杆长度(m )副杆长度(m )伸臂角度º工作半径(m )13.0m 15.017.0m13.019.0m 8.021.0m 21.0m 8.0 4.025.0m 6.010301030103010301030103010301030103010301030103042.6712.1918.2924.3830.4836.5839.6212.1918.2924.3830.4812.1918.2924.3830.48 伸 臂 额 定 起 重 量 表 (带 22t 行 走 配 重)12.013.012.015.015.013.015.013.012.015.012.015.08.016.015.05.015.015.014.015.018.020.015.015.032.034.036.038.012.530.013.013.013.013.022.024.026.028.012.012.012.012.012.011.811.513.012.814.512.08.07.58.08.08.08.015.013.012.08.012.015.012.08.08.0 4.015.013.012.08.08.08.0 4.015.013.015.013.012.08.08.0 4.08.08.015.08.08.08.0 4.04.06.06.06.06.0 4.04.04.0 3.03.03.06.08.013.013.012.215.015.015.015.014.313.212.011.512.012.08.013.012.911.812.512.011.712.012.08.08.0 6.08.08.04.015.013.013.04.08.08.07.36.06.08.08.08.07.97.715.08.0 6.015.04.08.08.0 6.012.04.0 3.015.013.08.08.0 6.0 4.0 3.015.013.012.04.0 3.014.112.811.88.012.08.07.7 6.013.08.07.4 6.0 4.0 3.012.012.511.811.58.07.26.04.03.08.08.010.911.211.03.03.03.03.03.013.012.08.015.012.08.012.012.08.0 6.06.06.07.5 4.06.0 4.04.04.0单位:t4.04.04.04.0 3.0主臂单位:t主杆长度(m )副杆长度(m )伸臂角度º工作半径(m )14.015.015.016.015.015.015.018.015.013.012.015.013.012.015.012.020.015.013.012.08.015.013.012.08.015.013.012.08.022.015.013.012.08.08.0 4.015.013.012.08.0 4.015.013.012.08.0 4.024.015.013.012.08.08.0 4.015.013.012.08.08.0 4.015.013.012.08.08.0 4.026.015.013.012.08.08.0 6.0 4.015.013.012.08.08.0 4.015.013.012.08.08.0 4.028.015.013.012.08.08.0 6.0 4.015.013.012.08.08.0 6.0 4.015.013.012.08.08.0 6.0 4.030.015.013.012.08.08.0 6.0 4.0 3.015.013.012.08.08.0 6.0 4.0 3.015.013.012.08.08.0 6.0 4.032.013.912.912.08.07.9 6.0 4.0 3.013.712.812.08.08.0 6.0 4.0 3.013.612.712.08.08.0 6.0 4.0 3.034.012.812.612.08.07.7 6.0 4.0 3.012.712.512.08.07.7 6.0 4.0 3.012.412.012.08.07.7 6.0 4.0 3.036.011.811.711.68.07.5 6.0 4.0 3.011.611.611.68.07.5 6.0 4.0 3.011.411.011.48.07.5 6.0 4.0 3.038.010.910.910.88.07.3 6.0 4.0 3.010.710.710.78.07.3 6.0 4.0 3.010.510.510.58.07.3 6.0 4.0 3.040.010.210.210.28.07.15.74.03.09.99.99.98.07.1 6.0 4.0 3.09.79.79.78.07.1 6.0 4.0 3.042.09.29.29.28.06.96.04.03.09.09.09.08.0 6.9 6.0 4.0 3.044.08.38.38.38.0 6.7 5.8 4.0 3.046.07.87.87.87.56.55.63.83.0伸 臂 额 定 起 重 量 表 (带 22t 行 走 配 重)45.7248.7712.1918.2924.3830.4812.1918.2924.3830.4851.8212.1918.2924.3830.48103010301030103010301030103010301030103010301030主臂主杆长度(m )副杆长度(m )伸臂角度º工作半径(m )16.015.015.018.015.012.015.015.020.015.013.012.015.013.012.015.013.012.022.015.013.012.08.0 4.015.013.012.08.015.013.012.08.024.015.013.012.08.08.0 4.015.013.012.08.08.0 4.015.013.012.08.0 4.026.015.013.012.08.08.0 4.015.013.012.08.08.0 4.015.013.012.08.08.0 4.028.015.013.012.08.08.0 6.0 4.015.013.012.08.08.0 6.0 4.015.013.012.08.08.0 4.030.014.913.012.08.08.0 6.0 4.014.813.012.08.08.0 6.0 4.014.713.012.08.08.0 6.0 4.032.013.513.012.08.08.0 6.0 4.0 3.013.413.012.08.08.0 6.0 4.0 3.013.313.012.08.08.0 6.0 4.0 3.034.012.312.312.08.08.0 6.0 4.0 3.012.212.212.08.08.0 6.0 4.0 3.012.112.012.08.08.0 6.0 4.0 3.036.011.311.311.38.07.9 6.0 4.0 3.011.211.211.28.07.9 6.0 4.0 3.011.111.111.18.07.9 6.0 4.0 3.038.010.410.410.48.07.7 6.0 4.0 3.010.310.310.38.07.7 6.0 4.0 3.010.210.210.28.07.7 6.0 4.0 3.040.09.69.69.68.07.5 6.0 4.0 3.09.59.59.58.07.5 6.0 4.0 3.09.49.49.48.07.5 6.0 4.0 3.042.08.88.88.88.07.4 6.0 4.0 3.08.78.78.78.07.4 5.9 4.0 3.08.68.68.68.07.4 5.9 4.0 3.044.08.28.28.28.07.3 5.8 4.0 3.08.18.18.18.17.3 5.8 4.0 3.08.08.08.08.07.3 5.8 4.0 3.046.07.57.57.57.47.0 5.7 3.9 3.07.47.47.47.47.0 5.7 3.9 3.07.47.47.47.4 6.9 5.7 3.9 3.048.07.07.07.07.06.55.63.83.06.8 6.8 6.8 6.8 6.5 5.5 3.8 3.0 6.8 6.8 6.8 6.8 6.5 5.5 3.8 3.050.0 6.36.36.36.36.15.23.63.06.2 6.2 6.2 6.2 6.2 5.3 3.6 3.052.0 5.8 5.8 5.8 5.8 5.8 5.2 3.5 2.954.05.45.45.45.45.15.13.42.810301030103010301030103010301030103010301030103012.1918.2924.3830.4812.1918.2924.3830.4812.1918.2924.3830.48单位:t伸 臂 额 定 起 重 量 表 (带 22t 行 走 配 重)54.8657.9160.96主臂主杆长度(m )副杆长度(m )伸臂角度º工作半径(m )18.015.015.015.0##20.015.012.015.012.015.0##22.015.013.012.08.015.013.012.015.013.012.0##12.024.015.013.012.08.0 4.015.013.012.08.0 4.015.013.012.08.0##12.0###26.015.013.012.08.08.0 4.015.013.012.08.08.0 4.015.013.012.08.08.0 4.0##12.0#####28.015.013.012.08.08.0 4.015.013.012.08.08.0 4.014.113.012.08.08.0 4.0##12.0#####30.014.613.012.08.08.0 6.0 4.014.513.012.08.08.0 6.0 4.014.413.012.08.08.0 4.0##12.0#####32.013.213.012.08.08.0 6.0 4.013.113.012.08.08.0 6.0 4.013.013.012.08.08.0 6.0 4.0##12.0#####34.012.012.012.08.08.0 6.0 4.0 3.011.911.911.98.07.9 6.0 4.0 3.011.811.811.88.07.9 6.0 4.0 3.0##11.8#####36.011.011.011.08.07.9 6.0 4.0 3.010.910.910.98.07.8 6.0 4.0 3.010.810.810.88.07.8 6.0 4.0 3.0##10.8#####38.010.110.110.18.07.7 6.0 4.0 3.010.010.010.08.07.6 6.0 4.0 3.09.99.99.98.07.6 6.0 4.0 3.0##9.9#####40.09.39.39.38.07.5 6.0 4.0 3.09.29.29.28.07.5 6.0 4.0 3.09.09.09.08.07.5 6.0 4.0 3.0##9.0#####42.08.48.48.48.07.4 6.0 4.0 3.08.28.28.28.07.4 6.0 4.0 3.08.28.28.28.07.4 6.0 4.0 3.0##8.2#####44.07.77.77.77.77.3 5.8 4.0 3.07.67.67.67.67.3 5.8 4.0 3.07.57.57.57.57.3 5.8 4.0 3.0##7.5#####46.07.07.07.07.0 6.9 5.6 4.0 3.07.07.07.07.0 6.9 5.6 4.0 3.0 6.9 6.9 6.9 6.9 6.9 5.6 4.0 3.0## 6.9#####48.0 6.4 6.4 6.4 6.4 6.4 5.4 3.9 3.0 6.4 6.4 6.4 6.4 6.4 5.4 3.9 3.0 6.3 6.3 6.3 6.3 6.3 5.4 3.9 3.0## 6.3#####50.0 5.9 5.9 5.9 5.9 5.9 5.3 3.8 3.0 5.9 5.9 5.9 5.9 5.9 5.3 3.8 3.0 5.7 5.7 5.7 5.7 5.7 5.2 3.7 3.0## 5.7#####52.0 5.4 5.4 5.4 5.4 5.4 5.1 3.6 3.0 5.4 5.4 5.4 5.4 5.4 5.1 3.6 2.9 5.2 5.2 5.2 5.2 5.2 5.0 3.6 2.9## 5.2#####54.0 5.0 5.0 5.0 5.0 5.0 5.0 3.5 2.9 5.0 5.0 5.0 5.0 5.0 5.0 3.5 2.8 4.7 4.7 4.7 4.7 4.7 4.7 3.5 2.8## 4.7#####56.0 4.54.54.54.54.54.53.42.84.5 4.5 4.5 4.5 4.5 4.5 3.4 2.8 4.3 4.3 4.3 4.3 4.3 4.3 3.4 2.8## 4.3#####58.0 4.14.14.14.14.14.13.22.73.9 3.9 3.9 3.9 3.9 3.9 3.2 2.7## 3.9#####60.0 3.5 3.5 3.5 3.5 3.5 3.5 3.1 2.6## 3.5#####62.03.23.23.23.23.23.23.02.5##3.2#####伸 臂 额 定 起 重 量 表 (带 22t 行 走 配 重)64.0167.0612.1918.2924.3830.4812.1918.2924.3830.4870.1012.1918.2924.3830.4810301030103010301030103010301030103010301030103070.101218.2924单位:t10101030主臂角度单位:t90º主杆长度(m )35.05~56.3935.05~56.3938.10~56.3941.15~56.3944.20~56.3947.24~56.3950.29~53.34塔杆长度(m )工作半径(m )10.020.0/10.9m 20.0/11.7m 12.020.020.019.4/12.5m 17.8/13.3m14.020.020.019.417.816.3/14.1m14.8/14.9m 15.020.0/15.8m20.0/15.8m19.4/15.8m 17.816.314.813.3/15.716.019.619.619.017.8/16.4m 16.3/17.5m14.813.318.017.817.817.817.216.114.8/18.6m 13.3/19.720.016.216.216.216.215.314.313.222.014.814.814.814.814.413.712.624.013.513.513.513.513.512.812.226.012.212.212.212.212.212.211.528.011.011.011.011.011.011.011.030.010.7/28.4m9.99.99.99.99.99.932.09.4/31.2m9.19.19.19.19.134.08.48.48.48.48.436.07.77.77.77.738.07.5/36.7m7.17.17.140.0 6.7/39.5m6.5 6.542.0 6.0 6.044.0 5.9/42.2m5.646.05.3/45.0m塔 式 臂 额 定 起 重 量 表45.7236.5839.6242.5727.3430.4833.53主臂角度单位:t80º主杆长度(m )塔杆长度(m )工作半径(m )15.221.4m 14.314.014.513.614.213.822.7m 23.2m 22.5m 23.8m 23.0m 23.5m 13.512.813.312.513.024.5m 25.1m 24.3m 25.6m 24.8m 12.011.712.211.426.4m 26.9m 26.1m 27.4m 10.910.728.2m 28.7m 10.710.710.710.710.728.4m 28.4m 28.4m 28.4m 28.4m 9.49.49.49.49.431.2m 31.2m 31.2m 31.2m 31.2m 7.57.47.57.27.57.536.6m37.1m36.7m 37.6m36.7m 36.7m 6.8 6.7 6.77.1 6.739.0m39.5m39.5m 38.1m39.5m 6.4 6.240.6m41.1m5.9 5.8 5.742.4m43.0m43.5m5.245.9m5.146.4m4.5 4.449.4m49.9m4.052.9m47.2427.4330.4833.534.14.44.94.95.15.15.15.65.65.6 5.66.0 6.06.0 6.06.5 6.5 6.56.57.17.17.17.17.17.77.77.77.77.77.78.48.48.48.48.48.49.19.19.19.19.19.99.99.99.99.911.011.011.011.012.212.213.542.6736.5839.624.95.15.1 5.65.66.0 6.06.07.17.17.16.5 6.5 6.57.77.77.77.77.78.48.48.48.48.49.19.19.19.19.99.99.99.911.011.011.011.012.212.212.213.544.2027.4330.4833.5339.6254.052.050.048.046.0 6.0 6.044.0 5.66.042.0 6.56.5 6.540.0 6.57.77.77.738.07.17.17.17.17.18.48.48.436.07.77.77.77.77.77.79.19.19.134.08.48.48.48.48.48.432.09.19.19.111.011.030.09.99.99.99.99.99.911.011.011.011.028.011.011.011.026.012.212.212.212.212.212.212.212.213.513.513.513.513.513.514.814.820.022.024.041.1530.4833.5336.58塔 式 臂 额 定 起 重 量 表30.4827.3430.4827.4333.5327.4335.0538.1036.58上海宝冶建设有限公司工程机械租赁中心LS248RH5-0145型150t 履带吊主臂角度单位:t80º主杆长度(m )塔杆长度(m )工作半径(m )13.512.713.112.212.824.1m 25.4m 24.6m25.9m 25.1m 11.911.011.612.011.226.7m 27.9m 27.2m 26.4m 27.7m 10.610.810.110.629.2m 28.5m 29.8m 29.0m 10.79.79.210.79.510.79.99.328.4m 30.5m 31.8m 28.4m 31.0m 28.4m 30.5m 31.6m 9.49.49.09.431.231.232.3m 31.27.57.07.57.536.7m 39.2m36.7m 36.7m 6.9 6.7 6.7 6.9 6.738.7m39.5m 39.5m 39.7m39.5m 6.141.6m5.96.0 5.9 5.9 5.942.2m 42.1m42.2m 42.7m42.2m 5.5 5.3 5.3 5.3 5.244.6m45.0m 45.1m45.0m 45.6m4.847.5m4.648.6m4.3 4.2 3.8 4.250.4m51.0m53.9m51.5m3.953.4m3.754.5m3.4 3.456.3m56.9m28.036.5827.3430.4812.233.5312.212.224.026.012.211.011.011.011.030.09.99.99.99.19.19.111.09.99.911.011.032.09.19.19.18.48.48.48.434.08.48.48.48.47.77.736.07.77.77.77.77.77.17.17.77.77.77.17.17.140.0 6.5 6.5 6.5 6.57.17.138.0 6.5 6.542.0 6.0 6.0 6.0 6.05.6 5.66.044.0 5.6 5.65.1 5.146.048.0 4.74.40.0 4.452.0 4.14.454.0 3.856.0 3.558.036.5839.6242.676.09.19.912.211.09.99.99.19.19.19.18.48.48.48.48.47.77.77.77.77.77.17.17.17.16.5 6.5 6.56.0 6.0 6.0 6.05.6 5.6 5.65.1 5.1 5.14.74.7 4.7 4.74.4 4.4 4.44.13.83.59.911.011.07.77.77.76.5 6.57.17.17.17.15.6 5.66.0 6.0 6.0 6.0 6.05.1 5.1 5.14.4 4.44.7 4.7 4.73.84.156.3945.7245.725.66.5 6.57.77.750.2953.3442.6736.5827.3430.4833.5339.6245.7227.3439.6242.679.19.19.130.4833.539.99.99.19.18.48.48.48.48.48.4塔 式 臂 额 定 起 重 量 表4.18.47.15.6 4.76.56.05.14.7第 11 页 共 11 页PDF 文件使用 "pdfFactory" 试用版本创建w 。
150吨履带吊参数
·
-u
均由--"机以
nm 叫回-川川一
… 出二 γ ll 川 川 川 川 爪 川
起-←凡 凡低吼扎
Ah
却
-1
U 川川川川口 川川 川
Mη
川们川川扒
阳 1/帧 /j\ 闹;悯白l j\ 监 坠金 (也 l 且i立 H 血 川|υ l 川 150 Uω 1 叫 6 门õl而 60 τ. 门盯
111\恻 (咱山,l[1.3 1 l~ l Ü5r o~lo ,~ I
1 , 叫2 邮蚓删单制帕(位 t为树略也f 以倒方日 M 虽时i 引 少咀:型叩 IJ\叫 盹 F 2载椭删删商削削 的1陌 M 川川 5% 灿 川圳革蛐胁川陆也川川,{E川在削州#机酬州咐州阳阳战阳阳阳处町 h 川丁于啤础.坚蚓阳坚盯实 U
--Hω.
一 -r------------------------------------------------------------
||
Hω 怕"阳"们 μ
叶 ""U
忖川刊 MHU
HHU 叫 "07OBo |||||||il--------------ll---
o
n-40
且 U
在寸||山川川川川川川川川尸|
J(-J7
一创
(ZHUYOU JAPAN LS-248RH-2)
川川一 -2
巾武
-d 「|||||川叫川川叫叫川川川叫川叫||||
川川
UMMUI
凡忱
巴
t
二川叫叫
vuttt
Hale Waihona Puke 孔且比U 川川川川川MUMMMMUM
MMMM 呻 MMMM 川札 MNhM 忖川hh 川川川
150t履带吊安装及负荷试验作业指导书讲解
5.3检查司机室内仪表、报警灯等监控仪器是否正常。
5.4检查离合器、制动器及各锁定装置是否正常。
5.5检查液压油箱的油量、检查燃油油箱油量及排水及排水情况、检查发动机油量、检查水箱水量及是否漏水。
5.6检查重要部位的螺栓、螺母是否有松动现象。
5.7检查各个销轴的销卡是否正确安装。
3.2组织参加本次施工的有关人员学习、全面了解该履带吊的相关技术参数、工作性能及各部分结构情况。
3.3技术人员应根据说明书和有关图纸及技术资料,结合现有起重设备和其它机具的条件,编制详细具体且安全可行的拆除施工方案及拆除施工安全技术措施,并向所有参加施工人员进行详细的技术交底和安全交底。
3.4准备好必要的起吊用钢丝绳、吊具以及其它工器具并检查其完好性,有缺陷的工器具严禁使用。
5.8臂架接头焊接状况;主杆、腹杆有无弯曲、裂纹、局部凹坑。
5,9拉绳的鸡心环和铝套有无缺陷、裂纹、喇叭口;拉绳有无压扁、断丝、硬弯、松散等。
6、起重臂的扳起作业
6.1 当进行完毕5中的全面检查后,开始准备进行扳起操作。
6.2起重臂做起臂、落臂操作时,一定要缓慢操作。
6.3起重臂30°之前吊钩不允许离地(起重臂提升钢丝绳有足够放出的长度)。
4.2.2利用50t汽车吊将组合好的起重臂和主机根部节相连接,在联接过程中一定要注意将销子的开口销安装到位;
4.3检查后起重臂的各节没有问题后,将大钩钢丝绳按照正确的位置进行穿绕;
4.4将各种液压接头安装完毕,并将电气线路进行正确的穿绕,确保正确无误。
5、全面检查
5.1检查起重机防过卷装置、起重臂78°限位装置是否正常。检查臂根部销轴是否注油。
2.1该履带吊主要有主机、配重、起重臂以及拉索等主要部件组成。
150吨履带吊安装工序签证单
臂架吊装
1、用辅助吊机吊装与机台连接,主臂头部以枕木支撑牢固
2、安装时要求正确选择吊点,严防臂架变形,组装时臂架下方节点处以枕木支垫平稳。
6
钢丝绳穿绕及固定
1、正确穿绕钢丝绳,钢丝绳死头固定夹头一定要夹牢,“U”端变形约1/3方可。
静负荷试验
先起吊较小载荷,然后以相应于各幅度的额定负荷和125%的超负荷进行静负荷试验,试验必须保证在静止状态下进行,即先由吊钩把额定负荷提升离地面100~300mm停止,在空中悬吊10分钟,然后缓慢无冲击地加上超载部分载荷悬吊10分钟,此时各机构不得作任何动作,并且在风力三级以下进行。在卸载后检查各部分结构不得有损伤和永久变形。
9
负荷试验
一般技术检查
按照图纸及说明书的技术要求,对吊机金属结构、机构、电气设备、吊钩、钢丝绳固定及联接、安全防护装置、等进行详细检查
空负荷试验
在空负荷状态下,试验各机构的操作系统:主起升机构在大、中、小三个幅度以额定速度动作起升、下降空钩各三次;变幅机构在全程范围内起落起重臂各三次;回转机构使臂架处于最大幅度状态,左右回转各两周;行走机构在行走范围内前后各行走三次,每次行走时间不超过十分钟;在不同时起动和制动的条件下作起升、回转、行走机构的联合动作十分钟。
动负荷试验
1、试验时以相应于各幅度下额定负荷的110%的试验负荷进行动负荷试验在三级风以下进行,使各机构单独轮流运转,此时不检验各机构速度。
2、起升机构升降各三次,起制动动作应平稳;回转机构带载左右回转360各三次,起制动动作应平稳,使臂架顺着轨道方向整机往返各行走三次;主钩起吊试验载荷仰升臂架三次(不得带载增幅),副钩起吊试验载荷仰俯臂架各三次,各机构均不准突然反向动作。
QUY150吨履带吊拆装方案
目录一、履带吊拆装前的准备工作及安全注意事项(一)拆装前的准备及安全注意事项 (2)二、履带吊拆卸程序及安全、质量要求(一)臂架放下 (2)(二)安放履带楔块 (3)(三)电气配线拆卸 (3)(四)钢丝绳吊钩拆卸 (3)(五)主臂(15.2m)的拆卸 (3)(六)臂架拆卸 (4)(七)配重拆卸 (5)(八)基础臂节拆卸 (5)(九)维护踏板拆卸 (5)(十)下车压重拆卸 (5)(十一)履带装置拆卸 (6)(十二)将主机装上拖车 (6)三、履带吊安装程序及安全、质量要求(一)组装前准备及安全注意事项 (7)(二)支撑油缸安装 (7)(三)履带装置安装 (7)(四)安装下车压重 (8)(五)安装A型架 (8)(六)安装下部臂架 (8)(七)安装配重 (9)(八)臂架组装四、主臂性能表(一)附表1(主臂工况臂节及悬挂钢绳的组合形式) (12)(二)附表2(主臂工况吊钩的穿绳法) (13)(三)附表3(主臂工况性能表) (14)五、负荷试验方案(一)施工方法步骤及作业程序 (15)(二)施工的质量要求 (16)(三)负荷试验用钢丝绳安全性 (16)六、交底记录150t履带吊拆装作业指导及负荷试验方案根据《QUY150C履带吊使用说明书》、《电力建设安全工作规程》、《电力建设安全健康环境管理工作规定》编制此施工作业指导书如下:一、履带吊车拆卸程序及安全、质量要求(一)拆装前的准备及安全注意事项选用的辅助吊车,起吊用的钢丝绳,钩环等要有足够的强度,人员配备,作业要求。
(1)工作前的准备a. 作业指挥者组织召开组装和拆卸前安全准备会。
b. 让现场作业者了解作业内容、步骤、指挥信号等。
c. 检查工具和材料的完备情况。
(2)场地的选择a. 拆装作业面积要足够大并且地面水平、坚硬。
b. 吊车的移动范围内不要有障碍物。
c. 场内保证辅助吊车可以移动。
d. 凸凹不平的地面要平整,软地面要铺设加固垫板或钢板等。
(3)准备用品:主要配合机械为50吨汽车吊a. 采用50吨汽车吊配合施工,使用前对50吨汽车吊进行安全检查,无安全隐患才能进行作业。
150吨履带式起重机安装拆卸方案
一、编制依据1.《履带式起重机使用说明书》2.《SCC8150C履带吊性能表》3.《起重机械安全规程》GB6067-854.《起重机械试验规范和程序》GB5905-865.《特种设备安全监察条例》国务院第549号令6.云鹃路综合管廊施工平面布置图二、工程概况1.本次拟建的南汇新城云鹃路(C港-临港北路)道路改建工程暨综合管廊实施工程位于上海市临港新城,工程起点位于黄日港南侧黄日港南路位置,延现状云鹃路向北延伸至临港南路南侧位置,期间横穿黄日港及绿丽港两条河道,工程总长度1912.8米。
本工程局部标准段采用预制拼装工艺,预制构件单环重量约为40吨,由于施工现场场地限制,特此项目选定吊装设备为三一重工牌SCC8150型履带起重机进行吊装,2.设备主要参数1)外形尺寸;10800mm*4300mm*3200mm2)主臂长度:30m;3)最大起重量:150T;4)整机总功率:320KW;5)整机总重量:140t。
6)根据产品说明书,履带吊拼装过程中需要起吊的最重配件为主臂下节臂,重量为2.5吨,其具体参数如下:三、施工前准备根据设备的特殊性,在设备组装前,前期准备工作必须完善就为后,方能进行设备组装工作,前期准备工作主要包括以下几个方面:1.人员准备根据履带式吊车组装需要配置人员数量,按照人员分组进行组装前相关事项的详细安全学习、交底工作。
施工人员必须熟悉施工现场,熟悉本安装、拆卸方案。
2.现场条件准备1)场地准备主要分为:a)吊车场地、主机场地、臂架场地、安装场地等准备工作。
b)组装整机场地要求宽敞、地面平整、坚实,场地开阔没有与安装施工相干涉的其他物体等障碍物,安装场地平整坚实,水平度≤5度,辅助吊车工作区域地基坚实可靠,满足吊车起吊要求。
c)必要时还要铺设钢板,杜绝倾翻危险。
2)环境条件准备:a)现场安装用吊车停放地点必须坚实。
b)天气晴朗,风力不大于6级,起重臂扳起时风力不大于5级。
遇大雨、大雾等恶劣天气应暂停施工。
神钢7150-150t履带吊性能表
30°
10°
30°
10°
30°
10°
30°
18
15
20
15
22
15
13
12
24
15
13
12
8
26
15
13
12
8
4
28
15
13
12
8
8
4
30
14
13
12
8
8
4
34
11.4
11.4
11.4
8
8
6
4
38
9.5
9.5
9.5
8
7.7
6
4
3
42
7.9
7.9
7.9
7.8
7.4
6
4
3
46
6.6
6.6
6.6
Байду номын сангаас
6.6
6.6
5.6
4
3
50
5.5
5.5
5.5
5.5
5.5
5.1
3.7
3
54
4.4
4.4
4.4
4.4
4.4
4.4
3.5
2.8
58
3.6
3.6
3.6
3.6
3.6
3.6
3.2
2.7
62
2.8
2.8
2.8
2.8
2.8
2.8
2.8
2.5
(单位:吨)
神户7150 150t履带式吊机性能表(标准吊杆加重式样 全周 平衡重53.7t (单位:吨)
150履带吊起重机拆装方案
150吨履带吊起重机拆装方案编制:审核:安全:批准:上海鼎重工程机械有限公司年月日目录1、概述2、安装步骤3、拆卸步骤4、拆装安全技术要求5、人力吊车使用6、安全责任制7、HSE风险预测与控制150履带吊起重机拆装方案一、概述:为确保起重机拆装作业安全稳妥的进行,特编制此方案。
二、安装步骤:(一)安装主机1、确定工作场地平整、结实,需要钢板2张,尺寸为:长9米,宽2.2米,厚30毫米。
两张钢板的间距为2.8米。
2、拖车运载主机到组装现场,调整好拖车位置。
起动履带起重机发动机,设为“装配作业”模式。
3、将支腿定位销拔下,旋转支腿到工作位置,插上定位销。
4、将车架支腿盘垫在支腿油缸正下方。
5、操作车架支腿油缸,缓慢使支腿油缸压紧在支脚盘上,注意使支腿盘不致翻落。
顶升整机主体部件,使主机部件油缸顶升,顶升到1.15米,静止3分钟,观察安全后,拖车缓慢驶出。
主体部分从平板车自行卸下,脱离平板车。
6、操作手柄,使支腿油缸处于全缩状态。
7、拔下操纵室定位销轴,操作操纵室旋转油缸,使操纵室处于工作位置,插上固定销。
(二)安装履带1、启动发动机,使主机处于待命状态;2、用100T辅助吊车吊起履带缓慢的靠近车架,让履带上的单耳插入车架上的双耳中去,缓慢操纵车架垂直油缸,使履带架和车架上的销轴孔对齐,操纵车架侧面的手柄,使销轴完全插入,用挡板固定好销轴。
3、同样方法安装另一履带。
4、连接好快速接头。
5、收起垂直油缸。
6、解体过程相反。
7、组装左、右走台板。
8、调整好驾车室,旋转900,板动A型架操作手柄,将A 型架弹起,当检查无误后,缓缓起升A型架至1200,将车体回转900。
(三)安装配重1、配重共5块,1号配重13T,2号配重10T,3号配重10.5T,4号配重10.5T,5号配重8T。
2、用辅助吊车先安装1号配重,然后2号、3号、4号、5号依次安装。
3、解体过程相反。
(四)装搬起架油缸1、装搬起架油缸直到桅杆接近树直,然后起配重油缸。
150t履带吊安装与负荷试验作业指导书
1、SCC1500履带式起重机概述2、SCC1500履带式起重机技术特点3、安装前的准备工作4、150t履带吊安装组合顺序5、全面检查6、起重臂的扳起作业7、试验和准备工作8、试验步骤及内容9、平安保护及环境限制举措10、施工组织及动力配备11、编制依据12、附表一150t履带式起重机主要部件重量表13、附表二150t履带式起重机负荷试验方案14、附表三施工作业流程图SCC1500型液压履带式起重机安装及负荷试验方案1.概述1.1本履带式起重机是上海三一科技采用国外最先进的技术、结合我国国情自行研制开发的全液压履带式起重机.该履带吊具有运输方便、便利,适用于现代化的电厂建设、港口、码头以及大中型企业的设备吊装等作业.1. 2该车的主要技术参数及规格尺寸2.整体结构简介2.1该履带吊主要有主机、配重、起重臂以及拉索等主要部件组成.2.2主机总重为45.316t,长为10809.5mm ,宽为6730mm ,高度为3534mm ,另外主机上还有配重八块,包括配重底盘5968Kg,中间配重为1580Kg,长为1860mm,宽为905mm , 高为800mm ,左侧配重共三块,每块重量为7900Kg ,长为1512mm ,宽为1235mm ,高为735mm ,右侧配重共三块,每块重量为7900Kg ,长为1512mm ,宽为1235mm ,高为735mm.2.3起重臂本机的根本臂长是18米〔顶部节10.5m,根底节7.5m〕,此外还有3m、6 m、9 m和12m 等臂杆,主臂的长度在根本臂18米和最大长度81米之间有多种组合方式,本次安装为45m 主臂工况.3、施工前的准备工作3.1对施工现场进行清理,保证施工机械的布置以及现场的履带吊组合有宽松环境,也保证履带吊临时运输过来的部件的现场存放和组合.3.2组织参加本次施工的有关人员学习、全面了解该履带吊的相关技术参数、工作性能及各局部结构情况.3.3技术人员应根据说明书和有关图纸及技术资料,结合现有起重设备和其它机具的条件,编制详细具体且平安可行的撤除施工方案及撤除施工平安技术举措,并向所有参加施工人员进行详细的技术交底和平安交底.3.4准备好必要的起吊用钢丝纯、吊具以及其它工器具并检查其完好性,有缺陷的工器具严禁使用.3.5对安装该履带吊所需的50t汽车吊及运输车辆进行全面检查,保证所有车辆工况良好.3.6准备好必要的起吊钢丝纯、卡环和吊具以及其它工器具,并检查各工器具的完好性,严禁使用有缺陷的工具或吊具.3.7当风力超过六级时,严禁进行履带吊的安装作业,特别是进行扳起和负荷试验.4、履带吊的组合安装3.1履带行走局部的安装3.1.1顶起四个支腿油缸,安装四个支腿,然后将运输车辆开走;3.1.2用50t汽车吊将左履带吊起,并对准位置将左履带对正后打入动力销子〔此时吊臂仰角约为83 0〕插入锁销;3.1.3根据4.1.2中的操作方法将右履带安装到位.3.2起重臂的组合3.2.1将需要组合的起重臂各段根据该吊车的使用说明书中的组合顺序进行连接,并在每节下面垫上道木;3.2.2利用50t汽车吊将组合好的起重臂和主机根部节相连接,在联接过程中一定要注意将销子的开口销安装到位;3.3检查后起重臂的各节没有问题后,将大钩钢丝绳根据正确的位置进行穿绕;3.4将各种液压接头安装完毕,并将电气线路进行正确的穿绕,保证正确无误.5、全面检查5. 1检查起重机防过卷装置、起重臂78°限位装置是否正常.检查臂根部销轴是否注油.5. 2主臂上不允许有杂物〔工具、木板、零件等〕5. 3检查司机室内仪表、报警灯等监控仪器是否正常.5. 4检查离合器、制动器及各锁定装置是否正常.5. 5检查液压油箱的油量、检查燃油油箱油量及排水及排水情况、检查发动机油量、检查水箱水量及是否漏水.5. 6检查重要部位的螺栓、螺母是否有松动现象.5. 7检查各个销轴的销卡是否正确安装.5. 8臂架接头焊接状况;主杆、腹杆有无弯曲、裂纹、局部凹坑.5.9拉绳的鸡心环和铝套有无缺陷、裂纹、喇叭口;拉绳有无压扁、断丝、硬弯、松散等.6、起重臂的扳起作业6.1当进行完毕5中的全面检查后,开始准备进行扳起操作.7.2起重臂做起臂、落臂操作时,一定要缓慢操作.6. 3起重臂300之前吊钩不允许离地〔起重臂提升钢丝绳有足够放出的长度〕.6. 4导向轮要压在排好的高50-80mm的道木上〔保证本体正角度〕.6. 5第一次起重臂离地即放下〔去除本体与主臂对位时可能产生的不对称〕.6. 6第二次起重臂至水平位置时停止,考核制动器、臂架稳定性及整机的稳定性.放下.6. 7第三次起臂时,要平稳、匀速,一次超过30 0,中间不允许停.6. 8落臂小于30°时吊钩要落地,中间不允许停.起落过程中限制接触开关要处于ON状态,起落臂结束后及时恢复限位接触开关到OFF位置.7、试验和准备工作7.1安装工作全部结束,并检查履带吊各部件合格后.7.2试验应在晴好的天气情况下进行,试验时的地面风速不得超过8.3m/s.7.3准备好试验重物,每一重物的重量应核实清楚,并按负荷试验的大小进行编号组合.7.4准备好所用的吊具、辅助吊车和测量工具.7.5办理平安工作票;对所有参试人员进行技术交底和平安交底.7.6试验前必须检查金属结构、各种动力设备、传动机构、电气设备、平安及限位装置、制动器、钢丝纯,吊具是否完好,确认无误前方可试验.8、试验步骤及内容8.1空负荷试验8.1.1试验目的分别试验各机构动作,以试验各电器设备和各机构动作的准确性、可靠性,并调整各平安限位装置.8.1.2试验内容及方法见附表8.2静负荷试验8.2.1试验条件在空负荷试验合格后及调整工作完成后进行.8.2.2试验目的检查起重机各部刚结构及各机构的强度、刚度和制动系统的可靠性和整机的静态稳定性.8.2.3试验内容及方法见附表8.2.4试验结果要求起重机刚结构不得有永久变形,回转局部与支撑滚子间不应有脱开现象,目测检查无裂纹、油漆剥落或其它损坏,连接处不得松动或损坏,制动应可靠,整机应稳定.8.3动负荷试验8.3.1试验条件必须在静负荷试验及调整工作完成后进行.8.3.2试验目的检验起重机各机构的运行情况,并验证起重机的稳定性.8.3.3试验内容及方法见附表8.4整理试验记录,填写试验报告8.5签字验收,移交使用.各项试验结果经有关部门及厂家代表和有关人员确认合格并验收后,方可投入使用.9、平安保护及环境限制举措9.1所有参加本次作业的施工人员必须熟悉本履带吊的相关资料和本作业指导书,必须严格执行本作业指导书.9.2参加施工人员必须服从统一指挥,并严格遵守各自的平安操作规程和有关平安施工的各项规程和标准.9.3施工时作业人员要劳逸结合,注意休息,施工要精力集中.9.4作业人员进入现场必须戴好平安防护用品,高空作业必须系好平安带,禁止违章作业.9.5道木支垫要牢固可靠.9.6所选钢丝绳及索具应可靠,作业中严禁以小代大.9.7作业前对工器具应仔细检查,严禁有缺陷的工器具在施工中使用.9.8起吊作业时,严禁起重臂下站人或任意通过.9.9严禁从上向下或从下向上抛扔工器具或其它物体.9.10起吊作业时,物件上严禁站人或有浮置物.9.11指挥人员信号应清楚,吊车操作人员要听从指挥.9.12施工区域周围应设立警戒标志,禁止非施工人员通过或入内逗留.9.13施工产生的废弃物应分类处理或销毁,或在治理部门指定的地点进行堆〔存〕放,以便统一处理.9.14施工应做到工完料净场地清,做好平安文明施工.10、施工组织及动力配备50t汽车吊1台乘龙汽车1台11、编制依据11.1?SCC1500液压履带式起重机使用说明书?上海三一科技11.2?电力建设平安工作规程?DL5009、1 —202211.3?起重设备安装工程施工及验收标准?GB50278-9811.4?起重机械平安规程?GB6067-8511.5?公司治理体系文件汇编?〔第三层〕有关机械治理方面的文件11.6«电力建设平安健康与环境治理工作规定?2022版11.7?五金手册?上海科技出版社附表一:SCC1500 (150t)履带式起重机主要部件重量表附表二SCC1500 〔150t〕履带式起重机负荷试验方案〔45m起重臂工况〕附表三:SCC1500 (150t)履带吊安装作业工艺流程。