水利水电英文翻译
- 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
- 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
- 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。
英文
Placing and protecting fill
Fill shall be placed so that mo part of the final foundation surface remains exposed for more than 72 hours.
Fill shall be placed in such methods as will prevent segregation of the material.
Where the Contract requires the placing of different types of fill in separate zones,the Contractor shall carry out the work so as to prebent mixing of different types of fill.Shoud there be ,in the opinion of the Engineer, any excessive mixing of different types of fill , such mixed materials shall be removed to a spoil tip and replaced with fresh fill.
Any undesirable material accumulated on the fill surface shall be removed before placeing the next layer of fill.No fill material shall be placed on a previous layer of that has dried out,become saturated or in any way deteriorated by exposure or by spilling of other material or disterbance by mechanical transport or by deposition of wind blown particles or by any other means. Before fresh fill material is placed aoo such deteriorated fill or foreign material shall be removed to a depth at which material of an acceptable standard is exposed. The surface of each layer is to be approved by the Engineer before the next layer is placed.
Any fill shall be placed in uniform layers not greater than the approved thickness as specified hereafter and in an orderly sequence approximately horizontal along the centreline of the embankments.Except where specified of directed otherwise, no portion of any embankment shall be stepped more than 3 feet higher than any immediately adjacent portion except where permitted by the Engineer and the slope formed by such steps shall not exceed 1V:3H and not less than 1V:4H from one level to another.Except as shown on the Drawings or as otherwise directed, all fill placement surfaces shall be sloped at right angles to the centerline of the embankment in both the upstream and downstream direction from the downstream edge of the core so as to allow run-off and prevent the accumulation of water. The drainage slope on the temporary surface of anny zone shall not exceed 1 on 30 and the highest point shall be de downstream edge of the core.
Where,due to the specified geometry of the excavation into the top of the existing embankments, the surface slope is towards the downstream edge of the core, the Contractor shall take such measures an necessary to prevent erosion of fine material being washed into the filter zones downstream of the core. Any surface layer of filter material contaminated by such drainage or other cause shall be removed and replaced with fresh filter material before placing the next layer above.
Construction of any one embankment shall be carried out over the maximum possible length,mo less than 1500 feet,of that embankment in such a manner that mo temporary construction slope crosses the axis of the embankment except as approved by the Engineer. Where a temporary constrction slope crossing the axis of the embankment is permitted by the Engineer it shall be formed at a gradient of 1V:5H. When subsequently placeing material against this slope it shall be cut back in steps equal to the layer thickness to avoid feather edges. The Contractor shall complete each layer of fill fully up to the abutment contacts and structures and against sloping foundations and ensure that the fill is compacted an specified throughout. The Contractor shall not allow the fill in those areas to lag behind or to get ahead of the normal fill placing operations and form feather edges, except where fill has been placed in advance to cover grouted surface.
Where the Contractor is allowed to use either grvel fill and /or sandstone no intermixing of the two materials in a layer shall be allowed. The Constractor may place either of the materials in adjacent layers or sections of the embankment.
The Constractor shall be responsible for protecting temporary fill surfaces against damage of erosion. At the end of each working day,or if it start to rain ,the surface of the fill shall be made smooth and compacted with a smooth drum roller with a drainage slope to induce runoff from the filled areas and leave no areas that can retain water. Where necessary, grips,drainage ditches and the like shall be formed to assist drainage and to prevent runoff from damaging placed material.Runoff from heavy rain shall be controlled to prevent gully erosion of the placed fill. Any gully erosion shall be repaired with material compacted in accordance with the Specification, and eroded surfaces shall be restored and graded to ensure a proper bond with new fill placed on them.Any eroded material other than gravel and any