轻型井点降水施工工艺标准
真空(轻型)井点降水
一、真空(轻型)井点降水本身就是一种地基处理方法,即所谓的“排水固结”。
比如我们通常所说的“井点降水联合强夯法”,它就是利用井点降水技术来加速强夯后超静孔压的消散和软土固结,主要加固的对象为饱和软粘土。
但真空(轻型)井点降水最广泛的应用还是为地基开挖服务的。
二、轻型井点降水和真空降水指的是一回事,“轻型”是从规模上进行命名的,“真空”则是从降水原理上来命名的,“真空-重力排水法”也决定了这种井点降水方式必定是轻型的。
三、真空(轻型)井点降水和深井井点降水分别对应不同的适用条件,后者可以替换前者,但前者一般不宜替换后者。
在同等条件下,前者具有使用灵活、装拆方便、可防止流砂现象发生、提高边坡稳定、费用较低等优势。
但“机具简单、降水效果好”的优势,那是书本上的说法,我看应该是相反1、轻型井点降水系统简介轻型井点降水为真空——重力排水法。
主要由井管(插入土体的立管)、卧管(铺设在地面上用于连接井管和真空泵的PVC管)及真空泵、排水设备组成。
通常情况下井管可为外径为2.0~5.0cm的钢管或尼龙管,下端打滤孔长度为1.0~2.0m的部分称作滤管,滤孔面积不少于滤管表面积的20~25%,外包滤膜以防降水过程中滤管堵塞。
卧管为PVC管,由三通与立管和相邻卧管连接,最后汇总与真空泵连接,整个系统密封,不能漏气。
2、轻型井点抽水原理及作用机理真空泵把井点管、卧管及贮水箱内的空气吸走,形成一定的真空度(即负压)。
由于管路系统外部地下水承受大气压力的作用,为了保持平衡状态,由高压区向低压区方向流动。
地下水被压入至井点管内,经卧管至贮水箱,然后用抽水泵抽走,从而水位下降,孔隙比减小,土体发生固结,地基承载力有所提高,[url =/jiangshui/qxjiangshui.htm]轻型井点降水设备[/url]经常作为强夯法加固地基、基坑开挖的辅助工艺。
轻型真空井点降水即可作为其他地基处理尤其是辅助于强夯施工、基坑开挖等的一种工艺,另一方面其本身对土体能起到加固作用,不但能通过饱和土体孔隙中水的排出与土的压缩同时作用,加速土的渗流固结过程,而且可以产生预压荷载△P=αγWZα—与土体中水饱和度有关的系数,取0.9~1.0γW——水的重度(kN/m3)Z—降水深度(m)3、工程常用降水方法①明沟排水在施工区域内设置排水网,主沟与支流沟均有一定坡度,用于排除地表水和部分地下水,对于含水量不大的地基处理采用明沟排水就可以了。
简述轻型井点降水的施工过程
简述轻型井点降水的施工过程
轻型井点降水是一种常用的降水技术,它适用于地下工程、基坑开挖等施工过程中的排水需要。
下面是轻型井点降水的施工过程简述:
1. 地面勘察:在开始施工之前,需要对施工区域进行地面勘察,确定降水井点的位置和数量。
同时还要考虑到地下障碍物的存在,避免对其造成破坏。
2. 井点打井:根据勘察结果确定的位置,在施工区域内打井。
井的深度根据地下水位和工程需要来确定,通常在数米到十几米之间。
3. 安装井管:井点打完之后,需要安装井管,确保井点的稳定性和安全性。
通常采用钢管或者塑料管。
4. 井管连通:将各个井管之间通过管道进行连通,形成一个井点系统。
确保井点之间的水能顺利流通,并且可以及时排出。
5. 电机安装:在井点系统中安装电机,用于抽水排水。
电机选型和安装要根据施工需要和地下水位来确定。
6. 排水系统调试:在井点系统安装完毕后,需要对排水系统进行调试。
包括检查井点系统的连通性、电机的正常运行等。
7. 井点降水开始:经过调试后,井点降水系统正式开始工作。
通过电机抽水,将地下水位降低,保持施工区域的干燥。
8. 定期维护:在施工过程中,需要定期对井点降水系统进行维护和保养。
包括清洁井点、检查井点管道是否有堵塞等。
以上是轻型井点降水的施工过程简述。
根据具体的施工需求和地下水位情况,还需要进行一些调整和适应性改变。
轻型井点降水施工方案(标准版)
第一节、编制依据 (1)第二节、工程概况 (2)第三节、施工部署 (2)第四节、施工方案 (6)1、施工准备 (6)2、井点安装 (7)3、抽水 (9)第五节、质量要求及保证措施 (10)第六节、安全保证措施 (11)第七节、文明施工保证措施 (12)第八节、施工应急措施 (12)第九节、附表材料及机械准备 (14)第十节、JHA (15)第一节、编制依据1。
青海大美聚丙烯装置水池图纸.2。
《青海大美聚丙烯装置岩土工程勘察报告》3.《建筑工程施工质量验收统一标准》(GB50300—2013)4.《建筑地基基础工程施工质量验收规范》(GB50202—2002)5.《建筑基坑支护技术规范》(JGJ120-2012)6。
《地下防水工程质量验收规范》(GB50208-2011)7.《建筑施工安全检查标准》(JGJ59—2011)第二节、工程概况项目名称:青海大美甘河工业园区尾气综合利用制烯烃项目聚丙烯装置项目地点:青海省西宁经济技术开发区甘河工业园区西区建设单位:青海大美煤业股份有限公司监理单位:上海青帝建设工程监理咨询有限公司EPC总承包单位:中石化上海工程有限公司施工总承包单位:上海市安装工程集团有限公司根据拟建场地地勘资料,根据本次勘察结果,本场地内地下水稳定水位埋深0.7~1.8m(对应标高2587。
24~2589。
78m)。
地下水属无压型孔隙潜水及基岩风化裂隙水,主要受大气降水补给,地下水流向为由南向北。
拟建场地范围内未发现塌陷、滑坡、泥石流、地面沉降等不良地质作用.建设规模:初期雨水池,正负零绝对标高为2589.00m,基础底标高1278。
55m,埋深为3.8m。
根据本工程特点,基础体型较大,较深,采用机械配合人工挖土,故采取边坡降坡方法,分层开挖,采用轻型井点降水。
根据本装置地质勘探报告与《建筑基坑支护技术规程》JGJ120-2012,决定放坡系数1:1。
25,确保边坡的稳定.按照现场文明施工需要,挖出的土方全部运至指定的堆土场。
井点降水施工工艺
井点降水施工工艺轻型井点的施工程序为:排放总管→埋设井点管→用弯联管将井点管与总管接通→安装抽水设备→试运行→正式抽水井点管的埋设一般用水冲法进行,并分为冲孔与埋管(图1-57)两个过程。
a) 冲孔;b)埋管图1-57井点管的埋设1—冲管;2—冲嘴;3—胶管;4—高压水泵;5—压力表;6—起重机吊钩;7—井点管;8—滤管;9—填砂;10—粘土封口冲孔时,先用起重机设备将冲管吊起并插在井点的位置上,然后开动高压水泵,将土冲松,冲管则边冲边沉。
冲孔直径一般为300mm,以保证井管四周有一定厚度的砂滤层,冲孔深度宜比滤管底深0.5m左右,以防冲管拔出时,部分土颗粒沉于底部而触及滤管底部。
井孔冲成后,立即拔出冲管,插入井点管,并在井点管与孔壁之间迅速填灌砂滤层,以防孔壁塌土。
砂滤层的填灌质量是保证轻型井点顺利抽水的关键。
一般宜选用干净粗砂,填灌均匀,并填至滤管顶上1~1.5m,以保证水流畅通。
井点填砂后,须用粘土封口,以防漏气。
井点系统全部安装完毕后,需进行试抽,以检查有无漏气现象。
开始抽水后不希望停抽。
时抽时停,滤网易堵塞,也容易抽出土粒,使水混浊,并引起附近建筑物由于土粒流失而沉降开裂。
正常的排水是细水长流,出水澄清。
试运转,如发现井管失效,应采取措施使其恢复正常,如无可能恢复则应报废,另行设置新的井管。
抽水时需要经常检查井点系统工作是否正常,以及检查观测井中水位下降情况,如果有较多井点管发生堵塞,影响降水效果时,应逐根用高压水反向冲洗或拔出重埋。
井点系统的拆除必须在地下室或地下结构物竣工后并将基坑进行回填土后进行,拔出井点管通常借助于倒链、起重机等。
拔管后所留的孔洞应用砂或土填塞,对有防渗要求的地基,地面以下2m范围可用粘土填塞密实。
另外,井点的拔除应在基础及已施工部分的自重大于浮力的情况下进行,且底板混凝土必须要有一定的强度,防止因水浮力引起地下结构浮动或破坏底板。
流沙成因:基坑挖土至地下水位以下,当土质为细砂土或粉砂土的情况下,往往会出现一种称为“流砂”的现象,即土颗粒不断地从基坑边或基坑底部冒出的现象。
真空(轻型)井点降水
基坑侧壁安全等级的划分原则
英文词条名:
基坑侧壁安全等级的划分原则:
根据基坑开挖深度、周边环境条件和支护结构破坏后果的严重程度,将基坑侧壁安全等级划分为三级。
基坑工程安全等级划分表
基坑工程安全等级环境、破坏后果、基坑深度、工程地质和地下水条件
一级:
周边环境条件很复杂;破坏后果很严重;基坑深度Hห้องสมุดไป่ตู้12M;
②连接抽气管道和真空泵的设置要根据地质情况、真空泵的功率及工程经验确定,抽气要连续。
③井点管的布置方式、插设深度要考虑地质情况及水力坡度,使水力坡度影响范围内的波峰低于降水深度要求,这样才能使降水达到实际要求。
④井点使用时,应保持连续不断抽水,并配用双电源以防断电。
5、典型工程实例上海芦潮港地基处理工程,苏州港太仓港区二期工程,青岛大炼油工程等工程,先是设计的专利法的高真空降水强夯法,有的已进行了部分施工,后经过我们和设计沟通均改为真空泵式轻型井点降水强夯,其处理效果一样,工程成本降低较大
一、真空(轻型)井点降水本身就是一种地基处理方法,即所谓的“排水固结”。
比如我们通常所说的“井点降水联合强夯法”,它就是利用井点降水技术来加速强夯后超静孔压的消散和软土固结,主要加固的对象为饱和软粘土。但真空(轻型)井点降水最广泛的应用还是为地基开挖服务的。
二、轻型井点降水和真空降水指的是一回事,“轻型”是从规模上进行命名的,“真空”则是从降水原理上来命名的,“真空-重力排水法”也决定了这种井点降水方式必定是轻型的。
xx井点:
当降水超过15m时,在管井井点采用一般的潜水泵和离心泵满足不了降水的要求,可加大管井深度,改采用深井泵即深井井点来解决。深井井点一般可降低水位30--40m,有的甚至可以达到100m以上。常见的深井泵有两种类型:
轻型井点降水施工方案
轻型井点降水施工方案降排水施工方案一、工程概况:本工程拟建管线位于石嘴山市大武口区,兴民村境内该管线分为两段,Ⅰ段西起井泵房,沿途经过井,东至井,总长约,支线由孔拐向西北至井,长约;Ⅱ段北起井,沿途经过井拐弯,东至井,总长,支线由孔拐向东北至井,长。
其中由我施工队承建的工程范围为:西起井,东至井,管材采用球墨铸铁管,设计管顶埋深左右。
本施工段沿途场地多为沼泽地,地表有积水,土质松软,并有小型人工湖、较深洼地地表积水水域,拟建管线穿越水利渠道、行车道路等,施工现场情况较为复杂。
根据现场踏勘情况我方就降排水方案拟采用如下施工方法:.无明显地下水及地表水积水较少地区拟建管线采用明挖浅埋;. 穿越水渠及车行路面采用钢筋混凝土套管顶管施工工艺;.穿越人工湖及较深水域地区采用施工场地围堰排水;.施工现场地下水位较深或地表水积水较多的地区采用轻型井点降水及明沟排水。
二、地质情况:.地形拟建管线相对较为平坦部分地段有沙丘,施工区最高处绝对标高,最低处绝对标高,相对高差.工程地质分层Ⅰ段(孔—孔):①表土():该层在()孔、孔一带分布。
层顶标高,层底埋深(标高),层厚,平均层厚。
风成砂为主,含有植物根系。
①杂填土():该层在孔一带分布。
层顶标高,层底埋深(标高),层厚。
风成砂为主,含有灰渣、砖块及植物根系。
①素填土():该层在、孔一带分布。
层顶标高,层底埋深(标高),层厚(孔一带较厚)。
细砂为主,含有植物根系。
该层进行标准贯入试验次,最大击,最小击,平均击,计算采用击。
②粉质粘土():分布连续。
层顶埋深(标高),层底埋深(标高),层厚,平均层厚。
灰褐、灰黄色,稍湿湿,可塑硬塑,切面有光泽,无摇震反应,干强度及韧性中等。
据室内原状土样分析,该层压缩系数,属于中压缩性土。
该层中夹有粉土及细砂透镜体。
原状土试验指标统计表②粉土():在、孔一带见到,层厚。
灰褐、灰黄色,湿,稍密,切面无光泽反应,摇震反应中等迅速,干强度及韧性低。
轻型井点降水施工工艺标准
轻型井点降水施工工艺标准一、施工前准备。
在进行轻型井点降水施工前,首先需要对施工现场进行全面的勘察和测量,确定井点位置和井筒尺寸,以及周围环境的情况。
同时,需要对施工所需的设备和材料进行清点和准备,确保施工所需的一切条件都已具备。
二、井点降水施工工艺。
1. 井点设置。
根据勘察和测量结果,确定井点位置,并进行标志和围栏设置,确保施工现场的安全。
同时,对井筒进行清理和修整,保证井筒的通畅。
2. 井点设备安装。
将井点降水所需的设备进行安装和调试,包括水泵、管道、阀门等设备的安装和连接,确保设备运转正常。
3. 降水施工。
根据实际情况确定降水的方案和方法,进行降水施工。
在施工过程中,需要密切关注井点的降水效果,及时调整和处理可能出现的问题,确保降水施工的顺利进行。
4. 安全监控。
在井点降水施工过程中,需要对施工现场进行全面的安全监控,确保施工人员和设备的安全。
同时,需要对降水效果进行实时监测,及时调整施工方案,确保降水效果达到预期要求。
5. 施工结束。
当井点降水施工完成后,需要对施工现场进行清理和整理,将施工所用的设备和材料进行清点和归库,确保施工现场的整洁和安全。
三、施工注意事项。
1. 施工现场的安全是首要考虑的问题,需要严格遵守相关的安全操作规程,确保施工人员和设备的安全。
2. 在进行井点降水施工时,需要根据实际情况进行合理的方案设计,确保降水效果达到预期要求。
3. 施工人员需要严格按照操作规程进行操作,确保施工的质量和效率。
4. 在施工过程中,需要密切关注施工现场的环境变化,及时调整施工方案,确保施工的顺利进行。
四、施工质量验收。
井点降水施工完成后,需要进行施工质量的验收,确保施工达到相关标准和要求。
同时,需要对施工现场进行清理和整理,恢复施工前的状态。
五、施工后维护。
完成井点降水施工后,需要对设备进行检查和维护,确保设备的正常运转。
同时,需要对施工现场进行定期的清理和维护,保持施工现场的整洁和安全。
轻型井点降水施工方案
轻型井点降水施工方案11(共5页)--本页仅作为文档封面,使用时请直接删除即可----内页可以根据需求调整合适字体及大小--轻型井点降水施工方案一、依据标准:本工程的基坑支护设计方案及岩土工程勘察报告。
《建筑工程施工质量验收统一标准》GB50300-2001。
《建筑地基基础工程施工质量验收规范》GB50202-2002。
二、概况工程菏泽市精神卫生中心病房楼位于菏泽市八一路3099号、市第三人民医院院内北部,现在病房楼南侧位置。
根据基坑支护设计方案及岩土工程勘察报告该工程采用轻型井点降水措施。
三、总体部署1、质量目标:保证土建正常施工,符合降水规范,达到降水合格标准。
2、工期目标:降水工期为90天,降水过程与基坑支护施工、土建施工、降水井施工做好配合。
四、施工方案(一)施工准备1、设备的选择:(1)井点管:用直径DN50的PVC管,长6m,下端为长的滤管。
(2)连接管:胶皮管与井点管和总管连接,塑料薄膜或胶泥裹住接头以防漏气。
(3)集水总管:用直径75mm的塑料管分节连接,每隔设一个连接井点管的接头。
(4)选用6台真空泵。
(5)冲孔设备:选用高压式离心泵。
2、技术准备(1)详细查阅工程地质勘察报告,了解工程地质情况,分析降水过程中可能出现的技术问题和采取的对策。
(2)凿孔设备与抽水设备检查。
(二)施工工艺1、井点施工工艺流程放线定位→铺设总管→冲孔→安装井点管、填砂砾滤料、上部填粘土密封→用弯联管将井点管与总管接通→安装抽水设备与总管连通→安装集水箱和排水管→开动真空泵排气、再开动离心水泵抽水、测量观测井中地下水位变化。
2、施工工艺(1)根据基坑支护设计方案及岩土工程勘察报告该工程降水将基坑内地下水降低米以下,采取二级降水。
施工时井点管位设在水泥土搅拌桩止水帷幕内侧及二级台阶上;有排桩位置设置在排桩内侧,待一级降水完成后再向下插管;轻型井点管长米,井点管间距~。
电梯井位置在以上二级降水的基础上采用轻型井点法进一步降水。
井点降水施工标准
轻型井点降水施工工艺标准依据标准《建筑工程施工质量验收统一标准》GB50300-2001《建筑地基基础工程施工质量验收规范》GB50202-20021、范围本工艺适用于轻型井点降水分项工程。
2、施工准备2.1施工机具(1)滤管:Φ38-55mm,壁厚3.0mm无缝钢管或镀锌管,长2.Om左右,一端用厚为4.0mm钢板焊死,在此端1.4m长范围内,在管壁上钻Φ15mm的小圆孔,孔距为25mm,外包两层滤网,滤网采用编织布,外再包一层网眼较大的尼龙丝网,每隔50-60mm用1O号铅丝绑扎一道,滤管另一端与井点管进行联结。
(2)井点管:Φ38-55mm,壁厚为3.0mm无缝钢管或镀锌管。
(3)连接管:透明管或胶皮管与井点管和总管连接,采用8号铅丝绑扎,应扎紧以防漏气。
(4)总管:Φ75-102mm钢管,壁厚为4mm,用法兰盘加橡胶垫圈连接,防止漏气、漏水。
(5)抽水设备:根据设计配备离心泵、真空泵或射流泵,以及机组配件和水箱。
(6)移动机具:自制移动式井架(采用振冲机架旧设备)、牵引力为6t的绞车。
(7)凿孔冲击管:Φ219×8mm的钢管,其长度为10m。
(8)水枪:Φ50×5mm无缝钢管,下端焊接一个Φ16mm的枪头喷嘴,上端弯成大约直角,且伸出冲击管外,与高压胶管连接。
(9)蛇形高压胶管:压力应达到1.50MPa以上。
(10)高压水泵:100TSW一7高压离心泵,配备一个压力表,作下井管之用。
2.2材料粗砂与豆石,不得采用中砂,严禁使用细砂,以防堵塞滤管网眼。
2.3技术准备(1)详细查阅工程地质勘察报告,了解工程地质情况,分析降水过程中可能出现的技术问题和采取的对策。
(2)凿孔设备与抽水设备检查。
2.4平整场地为了节省机械施工费用,不使用履带式吊车,采用碎石桩振冲设备的自制简易车架,因此场地平整度要高一些,设备进场前进行场地平整,以便于车架在场地内移动。
3、操作工艺3.1井点安装3.1.1安装程序井点放线定位——安装高位水泵——凿孔安装埋设井点管——布置安装总管——井点管与总管连接——安装抽水设备——试抽与检查——正式投入降水程序。
轻型井点降水、管井井点降水施工
第三十五章轻型井点降水、管井井点降水施工1.适用范围降水工程是指应用水文地质学原理,通过降水设计和降水施工,排除地表水体和降低地层中的上层滞水、潜水、承压水、基岩水、岩溶水等地下水位,满足工程的降水深度和降水时间的要求,并对工程环境无危害性的影响,它包括降水工作体系的建造与该体系的运转两部分。
其方法可分为轻型井点法、喷射井点法、电渗井点法、管井井点法及大口井、幅射井等方法、有时出于工程的特殊需要,还会建造减压井、回灌井等。
本标准仅涉及轻型井点降水与管井井点降水。
1.1轻型井点降水的适用范围轻型井点一般适用于渗透系数K=0.1~5m/d的土层,多为粘土、粉质粘土、粉土地层,地下水位埋深不超过6m。
降低水位的深度一层为3~6m,两层时为5~9m,适宜处理基坑边坡不稳,易流砂、管涌等现象。
1.2管井井点降水的适用范围管井降水一般适用于渗透系数大于1m/d的地层,降水深度大于5m;适合厚度大于5m 的第四系含水层,也适用于基岩裂隙水和岩溶含水层。
2.材料要求2.1针状过滤器:由直径38~55mm的钢管制成,长6~9m,下端配有1.5~2.0m的过滤管,管壁上钻有9=10mm的孔眼,呈梅花状分布,管壁外包两层过滤网,内层为30~60孔/cm2的细尼龙网,外层为5~10孔/cm2的粗尼龙网或棕皮。
2.2连接软管:一般为螺纹胶管或塑料管,其内径为38~55mm,管长1.2~2.0m,用于连接针状过滤器与集水总管。
2.3集水总管:直径为75~125mm的钢管,每根长4m左右,可用丝扣或法兰连接。
管壁每隔1~2m设一个接头,接头上设有开关严密的阀门。
2.4滤料:一般采用中、粗砂2.5粘土:当滤料填到设计深度后要立即用粘土封井,便于形成真空。
3.主要机具3.1轻型井点降水机具:3.1.1一般为小口径钻孔机或水力冲孔机具。
3.1.2抽水机具:一般为真空泵,可分为三种类型:干式真空泵,由一台真空泵(10KW),两台离心泵(7.5kw与2.2kw)和水气分离器组成,可带60~80根井点;射流真空泵,由离心泵(7.5kw)、射流器和水箱组成,可带动25-30根井点,往复式真空泵(3kw),流量为10m3/h。
降水施工工艺标准
3.6.1总则3.6.1.1降水作用与适用条件在地下水位较高的透水土层中进行基坑开挖施工时,由于基坑内外的水位差较大,较易产生流砂、管涌等渗透破坏现象,有时还会影响到边坡或坑壁的稳定。
因此,除了配合围护结构设置止水帷幕外,往往还需要在开挖之前,采用人工降水方法,将基坑内或基坑内外的水位降低至开挖面以下。
1.降水作用(1)防止地下水因渗流而产生流砂、管涌等渗透破坏作用。
(2)消除或减少作用在边坡或坑壁围护结构上的静水压力与渗透力,提高边坡或坑壁围护结构的稳定性。
(3)避免水下作业,使基坑施工能在水位以上进行,为施工提供方便,也有利于提高施工质量。
2.适用条件(1)地下水位较高的砂石类或粉土类土层。
对于弱透水性的黏性土层,可采取电渗井点、深井井点或降排结合的措施降低地下水位。
(2)周围环境容许地面有一定的沉降。
(3)止水帷幕密闭,坑内降水时坑外水位下降不大。
(4)采取有效措施,足以使邻近地面沉降控制在容许值以内。
(5)具有地区性的成熟经验,证明降水对周围环境不产生大的影响。
3.6.1.2编制参考标准及规范1.中华人民共和国国家标准《建筑工程施工质量验收统一标准》(GB50300—2001);2.中华人民共和国国家标准《建筑地基基础工程施工质量验收规范》(GB50202—2002);3•中华人民共和国行业标准《建筑基坑支护技术规程》(JGJ120—99);4•中华人民共和国国家标准《建筑边坡工程技术规范》(GB50330—2002)。
3.6.2术语1.降水:又称人工降水,即采用人工降低地下水位的方法将基坑内或基坑内外的水位降低至开挖面以下。
2.止水帷幕:用于阻止或减少基坑侧壁及基坑底地下水流入基坑而采用的连续止水体。
3.轻型井点降水:系在基坑外围或一侧、两侧埋设井点管深入含水层内,井点管的上端通过连接弯管与集水总管再与真空泵和离心泵相连,启动抽水设备,地下水便在真空泵吸力的作用下,经滤水管进入井点管和集水总管,排出空气后,由离心水泵的排水管排出,使地下水位降低到基坑底以下。
轻型井点降水
轻型井点降水轻型井点降水依据标准:《建筑工程施工质量验收统一标准》GB50300-2《建筑地基基础工程施工质量验收规范》GB50202-21、范围本工艺标准适用于工业及民用建筑轻型井点降水项目。
2、施工准备2.1、施工机具60kpa。
检查真空度表。
喷射井点>93kpa。
检查真空度表。
4.7、电渗井点阴阳极距离轻型井点80-100mm。
尺量检查。
喷射井点120-150mm。
尺量检查。
检查后形成施工记录,检查施工记录。
5、成品保护6、应注意的质量问题6.1、土方挖掘运输车道不设置井点,这并不影响整体降水效果。
6.2、在正式开工前,由电工及时办理用电手续,保证在抽水期间不停电。
因为抽水应连续进行,特别是开始抽水阶段,时停时抽,井点管的滤网易于阻塞,出水混浊。
同时由于中途长时间停止抽水,造成地下水位上升,会引起土方边坡塌方等事故。
6.3、轻型井点降水应经常进行检查,其出水规律应“先大后小,先混后清”。
若出现异常情况,应及时进行检查。
6.4、在抽水过程中,应经常检查和调节离心泵的出水阀门以控制流水量,当地下水位降到所要求的水位后,减少出水阀门的出水量,尽量使抽吸与排水保持均匀,达到细水长流。
6.5、真空度是轻型井点降水能否顺利进行降水的主要技术指数,现场设专人经常观测,若抽水过程中发现真空度不足,应立即检查整个抽水系统有无漏气环节,并应及时排除。
6.6、在抽水过程中,特别是开始抽水时,应检查有无井点管淤塞的死井,可通过管内水流声、管子表面是否潮湿等方法进行检查。
如“死井”数量超过10%,则严重影响降水效果,应及时采取措施,采用高压水反复冲洗处理。
6.7、在打井点之前应勘测现场,采用洛阳铲凿孔,若发现场内表层有旧基础、隐性墓地应及早处理。
6.8、如粘土层较厚,沉管速度会较慢,如超过常规沉管时间时,可采取增大水泵压力,大约在1.O~1.4MPa,但不要超过1.5MPa。
6.9、主干管应按本交底做好流水坡度,流向水泵方向。
轻型井点深井降水方案
启东市安置房城东村高层住宅小区轻型井点、深井降水施工方案江苏南通二建集团2021年4月25日目录一、工程概况···································································3二、编制依据····································································3三、降水方案选择及排水方案···············································41.轻型井点····································································42.深井降水····································································63.排水方案····································································9四、井点、深井降水施工机构及治理人员···························9五、降水时对周边边坡的阻碍和监测方式··························9六、质量保证方法·······························································10七、平安施工方法················································11八、危险点分析································································13九、平安生产及文明施工方法··············································14十、环保方法································································15附:现场排水布置图城东村安置房高层小区B标段井点、深井降水方案一、工程概况工程名称:城东村安置房小区B标段工程地址:城东村安置房小区A、B标段位于南苑路南侧,惠阳路东侧,纬一路北侧,秀水路西侧。
轻型井点降水施工工艺标准
轻型井点降水施工工艺标准Prepared on 22 November 2020A/0ZQN/JS-01-2012安徽中启能电力工程有限公司企业标准JZ-11轻型井点降水施工工艺标准2012-3-10发布2012-3-10实施安徽中启能电力工程有限公司发布目次轻型井点降水施工工艺标准1范围本标准规定了轻型井点降水施工的准备事项、工艺流程、施工工艺标准、质量标准、成品保护措施、职业健康安全和环境措施及质量记录。
本标准适用于渗透系数为~50m/d的土以及土层中含有大量的细砂和粉砂的土或明沟排水易引起流砂、坍方等情况的土方开挖降水;适合降低水位深度为3~12米(单层降低水位3~6米,多层为6~12米)。
2术语和定义下列术语和定义适用于本文件。
2.1降水工程engineeringdewatering降水工程系指应用水文地质学原理,通过降水设计和降水施工,排除地表水体和降低地层中滞水、潜水、承压水、基岩水、岩溶水等地下水的水位,满足建设工程的降水深度和时间要求,并对工程环境无危害性影响。
2.2降水地质条件dewateringprospecting是指同降水工程有关的水文地质、工程地质、环境地质等条件的总称。
2.3降水深度groundwaterlevelafterlowering自地面算起至基坑底面以下设计要求的动水位间的深度。
2.4降水出水量yieldwaterduringlowering指降水井从含水层中抽出的总水量。
2.5降水试验dewateringexperiment降水施工前进行抽水试验、引渗试验或注水试验,测定水文地质参数或其它参数;检查降水效果,确定工程参数,供分析调整降水方案的试验。
2.6轻型井点在基坑的四周或一侧埋设井点管深入含水层内,井点管的上端通过连接弯管与集水总管连接,启动抽水设备,地下水便在真空泵吸力的作用下,经滤水管进入井点管和集水总管,排除空气后,由离心水泵的排水管排出,使地下水位降至基坑底下。
真空(轻型)井点降水
一、真空(轻型)井点降水本身就是一种地基处理方法,即所谓的“排水固结”。
比如我们通常所说的“井点降水联合强夯法”,它就是利用井点降水技术来加速强夯后超静孔压的消散和软土固结,主要加固的对象为饱和软粘土。
但真空(轻型)井点降水最广泛的应用还是为地基开挖服务的。
二、轻型井点降水和真空降水指的是一回事,“轻型”是从规模上进行命名的,“真空”则是从降水原理上来命名的,“真空-重力排水法”也决定了这种井点降水方式必定是轻型的。
三、真空(轻型)井点降水和深井井点降水分别对应不同的适用条件,后者可以替换前者,但前者一般不宜替换后者。
在同等条件下,前者具有使用灵活、装拆方便、可防止流砂现象发生、提高边坡稳定、费用较低等优势。
但“机具简单、降水效果好”的优势,那是书本上的说法,我看应该是相反1、轻型井点降水系统简介轻型井点降水为真空——重力排水法。
主要由井管(插入土体的立管)、卧管(铺设在地面上用于连接井管和真空泵的PVC管)及真空泵、排水设备组成。
通常情况下井管可为外径为2.0~5.0cm的钢管或尼龙管,下端打滤孔长度为1.0~2.0m的部分称作滤管,滤孔面积不少于滤管表面积的20~25%,外包滤膜以防降水过程中滤管堵塞。
卧管为PVC管,由三通与立管和相邻卧管连接,最后汇总与真空泵连接,整个系统密封,不能漏气。
2、轻型井点抽水原理及作用机理真空泵把井点管、卧管及贮水箱内的空气吸走,形成一定的真空度(即负压)。
由于管路系统外部地下水承受大气压力的作用,为了保持平衡状态,由高压区向低压区方向流动。
地下水被压入至井点管内,经卧管至贮水箱,然后用抽水泵抽走,从而水位下降,孔隙比减小,土体发生固结,地基承载力有所提高,[url =/jiangshui/qxjiangshui.htm]轻型井点降水设备[/url]经常作为强夯法加固地基、基坑开挖的辅助工艺。
轻型真空井点降水即可作为其他地基处理尤其是辅助于强夯施工、基坑开挖等的一种工艺,另一方面其本身对土体能起到加固作用,不但能通过饱和土体孔隙中水的排出与土的压缩同时作用,加速土的渗流固结过程,而且可以产生预压荷载△P=αγWZα—与土体中水饱和度有关的系数,取0.9~1.0γW——水的重度(kN/m3)Z—降水深度(m)3、工程常用降水方法①明沟排水在施工区域内设置排水网,主沟与支流沟均有一定坡度,用于排除地表水和部分地下水,对于含水量不大的地基处理采用明沟排水就可以了。
轻型井点降水法施工工艺
轻型井点降水法施工工艺在基坑开挖深度较大,地下水位较高,而土质较差(如粉砂、细砂等)的情况下,用集水坑降水法施工往往容易出现坑内涌水、斜坡失稳塌方、坑底上冒(即管涌)、流砂等现象。
不但使基坑无法开挖,还会造成大量水土流失,影响邻近建筑物的安全,为此一般采用人工井点降水。
井点降水法就是在基坑开挖之前,在基坑四周埋设一定数量的滤水管,挖方前或挖方过程中利用抽水设备,通过井点管不断抽水,使地下水位逐渐降落至基坑底以下,形成较为稳定的水位曲线。
由于在基坑开挖过程中仍不断抽水,这样可使所挖土体始终保持干燥状态,从根本上防止了地下水涌入坑内,也防止了流砂的发生,既改善了工作环境,也利于提高工程质量。
若井点降水影响邻近建筑物的沉降与安全,应采取措施,用回灌法,旋喷加固土壤等法解决。
井点降水有两类:一类为真空抽水,有轻型井点(单级或多极)、电渗井点和喷射井点;另一类为非真空抽水,有管井井点和深井泵等。
施工时应根据含水层分布及类别、渗透系数、降水深度、工程特点及设备条件等,通过技术经济比较,选择适当的井点降水方法。
各类井点降水方法的参考适用范围可参照上表选择。
以轻型井点降水法采用较广。
轻型井点降水施工工艺:轻型井点法降水就是沿基坑的一侧、二侧或四周将多根较细的井点管埋入地下蓄水层内,井点管的下端装有滤管,井点管的上端通过弯管与总管连接形成管路系统,利用装在管路系统上的抽水设备将地下水通过井点管不断抽出,这样便可将原有地下水位降至坑底以下需要的高度。
轻型井点降水布置示意图1、井点管,直径与滤管相同,长度5~7m。
2、滤管,直径φ38~φ50mm,长度1.0~1.5m。
3、总管:直径φ100~φ127mm。
4、弯联管,一般为透明塑料管或橡皮管。
5、抽水设备,包括真空泵、离心水泵和水气分离器等组成。
一、轻型井点降水设备:轻型井点降水设备由管路系统与抽水设备两大部分组成。
甲、管路系统:包括滤管、井点管、弯联管及总管等。
1、滤管:滤管是进水渗透管,其构造是否合理对抽水效果影响很大。
轻型井点降水施工工艺标准
轻型井点降水施工工艺标准1 适用范围本标准适用于渗透系数为0.1~20m/d的砂土、粉土、含薄层粉砂的淤泥质(粉质)黏土等土层的基坑降水施工,适合降低水位深度为3~12米(单层降低水位3~6米,多层为6~12米)。
轻型井点降水系在基坑外围埋设井点管深入含水层内,井点管的上端通过连接弯管与集水总管连接,集水总管再与真空泵和离心水泵相连,启动抽水设备,地下水便在真空泵吸力的作用下,经滤水管进入井点管和集水总管,排出空气后,由离心水泵的排水管排出,使地下水位降到基坑底以下。
其优点是机具设备简单,使用灵活,装拆方便,降水效果好的特点。
图1.1 轻型井点降水示意图2 主要应用标准和规范2.0.1《建筑与市政降水工程技术规范》JGJ∕T111-982.0.2《建筑基坑支护技术规范》JGJ120-20123 施工准备3.1 技术准备3.1.1熟悉施工图纸、平面布置图、工程勘察资料、地质条件等,着重了解地下水位、土层渗透系数;根据建构筑物基坑形式、开挖支护设计、降水深度、降水范围、降水时间、工程环境(施工季节、江河水位、四周地表水等等)影响等进行井点降水设计。
3.1.2根据地基基础平面形状、技术要求和降水地质条件,通过对轻型井点的设计,预测计算降水水位和水量,并提出降水工程的辅助措施和补救措施。
3.1.3对工程环境问题应专门设计,对附近建构筑物是否沉降进行分析,必要时做好沉降观测记录;编制降水施工组织程序、施工安排和安全生产的要求。
3.1.4开工前,编制好降水工程量表、工期进度计划表,组织好人员和设备材料等。
并综合考虑安全文明施工和环境条件,合理布置泥浆池或泥浆坑,做好排污、防污措施。
3.1.5绘制井点平面布置图、降水设施结构图、降水水位预测曲线平面与剖面图,以备与降水日观测水位比较,并布置排水设施的数量、位置。
3.2 机具设备3.2.1 根据降水与排水工程施工实际情况制定施工工艺, 并相应选用适宜的施工机具。
2-1轻型井点降水
2—1轻型井点降水施工工艺标准(SEJ/BZ-0201-2002)1范围本工艺标准适用于工业及民用建筑、市政建筑的基坑轻型井点降水工程。
2施工准备2.1材料及主要机具:2.1.1材料:直径φ38—55mm井点钢管,直径φ50—70mm冲井钢管,直径φ100—127mm集水钢管,直径φ38—55mm塑料夹丝连接管,8—10孔/cm2,和30—50孔/cm2的滤网,规格及质量必须符合施工组织设计要求,并具有出厂合格证。
2.1.2主要机具:高压冲孔水泵、真空泵或水射泵、潜水泵、5 t 起重设备或2t的倒链。
2.2作业条件:2.2.1掌握正确的地质资料,制定合理的施工组织设计(内含井点降水计算书),做好技术交底工作。
2.2.2弄清临近建筑物或构筑物基础的技术资料,充分考虑由于井点降水引起土体产生不均匀沉降而影响临近建筑物或构筑物的结构安全,尽量减少土层沉降量,可采用降水和回灌相结合的方法。
2.2.3施工现场应具备二路电源供电或一路电源供电加备用发电机组。
3操作工艺3.1工艺流程:井管和滤管主装连接→冲井成孔﹑埋管﹑灌沙﹑密封→安装总集水管→井管和总集水管连接→安装抽水设备→检查、试运转→工作→工作结束,拆除3.2直径φ38—55mm钢滤管,管壁钻12—18mm孔,呈梅形分布,滤管外侧用8#铅丝呈螺旋型固定,外包双层滤网,内细滤网用30—50孔/cm2黄铜丝布或尼龙丝布,外粗滤网用8—10孔cm2铁丝或铜丝布,双层滤网外再固一层12#铅丝的保护网。
滤管和井管用螺纹、管箍连接,见滤管构造图1。
3.3水冲法进行井点冲孔。
根据施工组织设计的井点平面位置,用起重设备吊起冲井管,将冲井管插入井点位置,开动高压水泵将土冲松,冲井直径一般为300mm,冲井压力见表1。
井孔成型后,立即拔出冲管,插入井点管,并在井管壁外,迅速填灌粗砂滤层,填至井管上口距地面1—1.5m处再用粘土封堵。
见图2。
表1各种土层冲孔所需水流压力表①埋没井点冲孔水流压力,最可靠的数字是通过试冲,表列值可供施工预估配备高压泵及必要时的空气压缩机性能之用.②根据国产轻型井点的最小间距80cm(井点管中心至中心),要求冲孔位置不宜过近,以防两孔冲通(一般冲孔直径在30cm左右).轻型井点间距宜采用0.8—1.6m.②借助于冲管沉没井点过程中,当冲孔达额定深度(为井点管长加滤管长.再加约50cm)后,尽快减低水压,拔起冲管的同时.向孔内沉入井点管,并快速填入砂滤层填抖。
(完整版)SGBZ-0111轻型井点降水施工工艺标准
SGBZ-0111轻型井点降水施工工艺标准依据标准:《建筑工程施工质量验收统一标准》GB50300-2001《建筑地基基础工程施工质量验收规范》GB50202-20021、范围本工艺适用于轻型井点降水分项工程。
2、施工准备2.1、施工机具(1)滤管:Φ38~55mm,壁厚3.0mm无缝钢管或镀锌管,长2.Om左右,一端用厚为4.0mm钢板焊死,在此端1.4m长范围内,在管壁上钻Φ15m m的小圆孔,孔距为25mm,外包两层滤网,滤网采用编织布,外再包一层网眼较大的尼龙丝网,每隔50~60mm用1O号铅丝绑扎一道,滤管另一端与井点管进行联结。
(2)井点管:Φ38~55mm,壁厚为3.0mm无缝钢管或镀锌管。
(3)连接管:透明管或胶皮管与井点管和总管连接,采用8号铅丝绑扎,应扎紧以防漏气。
(4)总管:Φ75~102mm钢管,壁厚为4mm,用法兰盘加橡胶垫圈连接,防止漏气、漏水。
(5)抽水设备:根据设计配备离心泵、真空泵或射流泵,以及机组配件和水箱。
(6)移动机具:自制移动式井架(采用振冲机架旧设备)、牵引力为6t的绞车。
(7)凿孔冲击管:Φ219×8mm的钢管,其长度为10m。
(8)水枪:Φ50×5mm无缝钢管,下端焊接一个Φ16mm的枪头喷嘴,上端弯成大约直角,且伸出冲击管外,与高压胶管连接。
(9)蛇形高压胶管:压力应达到1.50MPa以上。
(10)高压水泵:100TSW一7高压离心泵,配备一个压力表,作下井管之用。
2.2、材料粗砂与豆石,不得采用中砂,严禁使用细砂,以防堵塞滤管网眼。
2.3、技术准备(1)详细查阅工程地质勘察报告,了解工程地质情况,分析降水过程中可能出现的技术问题和采取的对策。
(2)凿孔设备与抽水设备检查。
2.4、平整场地为了节省机械施工费用,不使用履带式吊车,采用碎石桩振冲设备的自制简易车架,因此场地平整度要高一些,设备进场前进行场地平整,以便于车架在场地内移动。
- 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
- 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
- 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。
3
3.1
电工、钻机班长、专业作业人员、普工。各工种具体人数由工程量大小、工期长短、施工环境确定。
3.2
3.2.1
3.2.2
3.2.3
3.2.4
3.2.5
3.2.6
3.3
材料采用直径38~55mm的钢管(或镀锌钢管),长度5~7m。连接管采用塑料透明管、胶皮管或钢管制成,直径38~55mm。集水总管用直径为75~100mm的钢管分节连接,每节长4m。
井点运转与监测:
a)井点运转管理:井点运行后要求连续工作,应准备双电源以保证连续抽水。射流泵井点与隔膜泵井点的运转管理比较简单,只要水泵不出事故,只需一人管理即可。真空度是判断井点系统是否良好的尺度,应通过真空表经常观测,一般真空度应不底于55.3~66.7Kpa。如真空度不够,通常是由于管路漏气,应及时修复。除测定真空度外,还可通过听、摸、看等方法来检查。听——有上水声是好井点,无声则可能井点已被堵塞。摸——手模管壁感到震动,另外冬天热、夏天凉为好井点,反之则为坏井点;看——夏天湿、冬天干的井点为好井点。如果通过检查发现淤塞的井点管太多,严重影响降水效果时,应逐个用高压水反冲洗或拔出重新埋设。
c)射水法:利用射水法进行井点管的埋设就是在井点管下安装射水或滤管,在地面挖小坑,将射水或井点管插入后,下有射水球阀,上接可旋动节管和高压胶管、水泵等。利用高压水在井管下端冲刷土体,使井点管下沉。下沉时,随时转动管子,以增加下沉速度,并保持垂直。射水压力为0.4~0.6Mpa,当为大颗粒砂粒土时,应为0.9~1.0Mpa。冲至设计深度后,取下软管,再与集水总管连接,抽水时球阀可自由关闭。冲孔直径一般为300mm,冲孔深度应比滤管底深0.5m左右,以利于沉泥。灌砂方法要求与水冲法相同。本法优点是一次冲成,直接埋管。
3.4
井点管、连接管、集水总管及抽水设备(分为真空泵轻型井点、射流泵轻型井点和隔膜泵轻型井点三种)
3.5
3.5.1
3.5.2
3.5.3
3.5.4
4
4.1
图1
4.2
准备工作:轻型井点的施工准备工作首先是需要根据工程的情况特点和地质条件等进行轻型井点的设计计算,根据计算结果准备所需的井点设备、动力装置、井点管、滤管、集水总管及必要的材料。另外还需搞好施工现场的准备工作,包括排水沟的开挖、临时施工道路的铺设、泵站处理等。对于周围在抽水影响半径范围内需要保护的建筑物及地下管线等建立好标高观测系统,并准备好防止沉降的措施及其实施等等。
另外,井点的拔除应在基础及已施工部分的自重大于浮力的情况下进行,且底板混凝土必须要有一定的强度。防止因水浮力引起地下结构浮动或破坏底板。
5
5.1
全部降水运行时,抽排水的含砂量应符合下列规定:
a)粗砂含量应小于1/5万。
b)中砂含量应小于1/2万。
c)细砂含量应小于1/1万。
5.2
井点施工允许偏差与检验方法见表1:
b)套管法:为保证施工时井点周围砂滤层的质量达到设计要求,可采用套管法施工。施工时先用吊车先将套管就位,然后开泵冲孔,当套管下沉时,逐渐加大高压水泵的压力,并须控制下沉速度。当冲孔深度达到设计标高时,需继续冲洗一段时间,视土质情况可以减少工作水压力或维持原来的压力。在井点未放入套管前,先倒入少量砂,其作用为带泥砂沉淀并防止井点插入粘土中,一般孔深比井点埋设标高深1m左右,然后再将井点放入套管内,砂分2~3次填完,最后拔出套管。如一次填到设计标高,井点易被挤在套管内,此时则可应用振动器助拔套管,否则在套管提升时会将井点一起带出,井点就会高于设计标高。为使井点处于中间位置,在滤管顶部可利用3根钢筋制成的定位导向器,放入时向外伸张,井点拔出时可收紧。
f)沉降观测:对于抽水影响范围以内的建筑物和地下管线,应进行建筑物的沉降和地下管线处地层沉降的观测。沉降观测的基准点应设置在井点影响范围之外。沉降观测可用水准仪和分层沉降仪进行。观测次数通常每天一次,在异常情况下须加密观测,每天不少于2次。
g)井点拆除:地下室或地下结构物竣工后并将基坑进行回填后,方可拆除井点系统。拔出井点管多借助于倒链,起重机等。所留孔洞用砂或土填塞,对地基有防渗要求时,地面下2m可用粘土填塞密实。
2.3
降水深度
自地面算起至基坑底面以下设计要求的动水位间的深度。
2.4
降水出水量
指降水井从含水层中抽出的总水量。
2.5
降水试验
降水施工前进行抽水试验、引渗试验或注水试验,测定水文地质参数或其它参数;检查降水效果,确定工程参数,供分析调整降水方案的试验。
2.6
轻型井点
在基坑的四周或一侧埋设井点管深入含水层内,井点管的上端通过连接弯管与集水总管连接,启动抽水设备,地下水便在真空泵吸力的作用下,经滤水管进入井点管和集水总管,排除空气后,由离心水泵的排水管排出,使地下水位降至基坑底下。
连接和试抽:
用连接管将井点管与集水总管和水泵连接,形成完整系统。井点系统全部安装完毕后,需进行试抽,以检查是否有漏气现象。抽水时,应先开直空泵抽取管路中的空气在真空吸力作用下被吸入集水箱,空气经真空泵排出,当集水箱存了相当多的水停抽。时抽时止,滤网易堵塞,也易抽出土颗粒,使水浑浊,并引起附近建筑物由于土颗粒流失而沉降开裂。正常的排水是细水长流、出水澄清。
2
下列术语和定义适用于本文件。
2.1
降水工程
降水工程系指应用水文地质学原理,通过降水设计和降水施工,排除地表水体和降低地层中滞水、潜水、承压水、基岩水、岩溶水等地下水的水位,满足建设工程的降水深度和时间要求,并对工程环境无危害性影响。
2.2
降水地质条件
是指同降水工程有关的水文地质、工程地质、环境地质等条件的总称。
d)地下水位观测:地下水位观测井的位置和间距可按设计需要布置,可用井点管作为观测井。在开始抽水时,每隔4~8h测一次,以观测整个系统的降水机能。3d或或降水达到预定标高前,每日观测1~2次。地下水位降到预期标高后,可数日或一周侧一次,但若遇下雨时,须加密观测。
e)孔隙水压力观测:通过降水期间观测地层中孔隙水压力的变化,可预计地基强度、变形以及边坡的稳定性。孔隙水压力的观测平常每天一次。在有异常情况时,如发现边坡裂缝、基坑周围发生较大沉陷等,须加密观测,每天不少于2次。
轻型井点降水施工工艺标准
1
本标准规定了轻型井点降水施工的准备事项、工艺流程、施工工艺标准、质量标准、成品保护措施、职业健康安全和环境措施及质量记录。
本标准适用于渗透系数为0.5~50m/d的土以及土层中含有大量的细砂和粉砂的土或明沟排水易引起流砂、坍方等情况的土方开挖降水;适合降低水位深度为3~12米(单层降低水位3~6米,多层为6~12米)。
b)井点监测:在重要的工程中,或者降水工地周围有较为重要的需要保护的建筑物或地下管线时,还需布置进行井点监测。
c)流量观测:流量观测很重要,一般可以用流量表或堰箱。若发现流量过大而水位降低缓慢甚至降不下去时,可考虑改用流量较大的离心水泵,若是流量较小而水位降低却较快则可改用小型水泵以免离心泵无水发热,并可节约电力。
井点系统的埋设:埋设井点管的程序是:先排水总管,再沉设井点管,用弯联管将井点管与总管接通,然后安装抽水设备。
井管沉设:
a)水冲法:井点管的沉设一般用水冲法进行,并分为冲孔与埋管填料两个过程。
水冲法时先用起重设备将直径50~70mm的冲管吊起并插在井点的位置上,然后开动高压水泵(一般压力为0.6~1.2Mpa),将土冲松。冲孔时冲管应垂直插入土中,并作上下左右摆动,以加速土体松动,边冲边沉。冲孔直径一般为300mm,以保证井管周围有一定厚度的砂滤层。冲孔深度宜比滤管底深0.5~1.0m,以房冲管拔出时,部分土颗粒沉淀于孔底而触及滤管底部。
表1
序号
检查项目
允许值或允许偏差
检查方法
单位
数值
1
井点管坡度
%
1
插管时目测
2
井管间距(与设计相比)%≤1Fra bibliotek0尺量
3
井管插入深度(与设计相比)
mm
≤200
水准仪
4
过滤砂砾填满(与计算值相比)
mm
≤5
检查回填料用量
5
井点真空度
kpa
≥60
真空度表
在基坑中心、最远边侧、井间分水岭处和基坑底任意部位,实际降水深度应等于或深于设计预测的降水深度,并应稳定24h。检验方法:查看降水记录及观察检查。
一套抽水设备的总管长度一般不大于100~120m。当主管过长时,可采用多套抽水设备;井点系统可以分段,各段长度应大致相等,宜在拐角处分段,以减少弯头数量,提高抽吸能力;分段宜设阀门,以免管内水流紊乱,影响降水效果。
真空泵由于考虑水头损失,一般降低地下水深度只有5.5~6m,当一级轻型井点不能满足降水深度要求时,可采用明沟排水与井点相结合的方法,将总管安装在原有地下水位线以下,或采用二级轻型井点排水(降水深度可达7~10m),既先挖去第一级井点排干的土,然后在坑内布置埋设第二级井点,以增加降水深度。抽水设备宜布置在地下水的上游,并设在总管的中部。