施工组织设计副斜井井口房及灯房

合集下载

副斜井井筒施工组织设计

副斜井井筒施工组织设计

国投哈密能源开发有限责任公司副斜井井筒及配套巷道、硐室施工组织设计河南煤炭建设集团有限责任公司二O一一年八月九日施工组织设计会审表施工组织设计、方案、措施会审表表号:GC-002/A 编号:GTHMNY/GC/HS/ /2021目录前言··································································1、工程概况·····························································································································································································································································································2、施工准备···········································································································································································································································································································································3、施工方案及施工顺序····················································································································································································································4、施工关键技术······································································································································································4.3冬、雨季施工措施···················································5、施工辅助系统·························································································································································································································································································5.5通风、降尘系统····················································································································5.7通讯、信号、照明系统·····························································································5.9测量······························································6、劳动组织····························································································································································································································7、施工排队和工期···················································································································································································································································································8、质量保证体系与质量保证措施········································································································································································································9、平安保证体系和平安技术保证措施·······································································································································································································10、文明施工及环境保护措施························································································································································11、提高工程质量、保证工期及降低造价的合理化建议······················12、副斜井井筒工程施工机械设备配备一览表······························前言国投哈密能源开发有限责任公司为国家开发投资公司下属国投煤炭公司的全资子公司,于2021年4月在哈密注册成立。

副斜井施工组织设计5171

副斜井施工组织设计5171

副斜井施工组织设计一、工程概况(一)项目概述:温家庄矿位于山西省寿阳县城西北侧,工业广场设在温家庄乡盘沟底村北侧300米处,地理位置优越,回风井距工业广场约1公里,有临时土路通往温家庄乡盘沟村公路。

矿井设计年生产能力120万吨,计划建设工期27个月,矿井采用斜井开拓方式。

本招标井筒为副斜井工程。

副斜井工程量895.601米,工程量见综合单价报价表。

(二)地形地貌:本井田位于沁水煤田北部边缘,寿阳(东)详查勘探区的北部,为低山丘陵地貌,地表多被第四系黄土覆盖,土梁现冲沟发育,地形山峦起伏,沟壑纵横,地势东高西低,地面最低处在井田的西北角盘沟底村内,标高为1122米,最高在井田的中北部,标高为1345.7米,相对高差约220米。

(三)水文:井田内地表水系不发育,只发育一些冲沟,由于降雨量少,基本上无积水,在井田西北边界外有温家庄河,在上游温家庄村东北约2.5公里处建有郑家庄水库,水库坝高16米,坝长350米,最大库容量240万平方米,库内现存水很少,温家庄河基本干枯无水。

(四)气象:地处山西黄土高原东南部,气候干燥,气温昼夜变化较大,四季分明,为半干旱大陆性气候,年平均降水量476.7毫米,多集中在6-9月,冬春多风,霜期从9月中旬至次年4月中旬,长达7个月左右,年平均气温7.4℃,最低气温-26.2℃,全年平均无霜期151天,平均冻土厚度0.904米。

(五)地质特征:本井田暂未打地质钻孔,地质情况不详,估计元流砂层,无瓦斯积存区。

(六)地震:本井田地震烈度七度。

(七)工程内容及特征根据招标文件及工程图纸,本工程(副斜井)井筒长度约915.119m,井筒的主要工程特征如下表:(八)井筒涌水量:井筒涌水量小于5立方米/小时。

二、施工准备(一)技术准备1.组织技术与管理人员认真审阅图纸,学习技术规范,组织图纸会审,并在此基础上编制可行性施工组织设计、安全技术措施、项目质量计划、填报项目开工报告,准备好各种技术资料和表格,开工前对技术人员、管理人员及施工人员做好技术交底。

施工组织设计副斜井井口房及灯房

施工组织设计副斜井井口房及灯房

郑煤集团朝阳沟煤矿副斜井井口房及灯房施工组织设计永煤开发公司第一分公司二00七年十二月十二日目录第一章编制说明 (5)1编制说明 (5)2编制依据 (5)3自然条件及环境条件 (7)4工程概况 (7)第二章施工说明 (8)1总体目标 (8)2施工说明 (8)3施工部署及总进度主要节点控制 (9)3.1总体施工原则 (9)3.2总体施工程序及施工流水段划分 (9)3.3施工工期安排 (10)第三章主要施工办法 (10)1施工准备 (10)1.1技术准备 (10)1.2现场准备 (11)1.3季节性施工准备 (11)1.4其它准备 (12)2各施工过程的施工顺序 (12)3分部、分项工程主要施工过程的施工方法 (13)4冬季施工措施 .......................... 错误!未定义书签。

第四章项目经理部及劳动力配置计划 (14)1项目经理部组成情况 (14)2分部分项工程所需工种类别和级别 (17)3分阶段施工计划投入劳动力人数 (17)第五章主要施工机械、材料供应计划 (19)1满足工程施工所需的机械数量及供应计划 (19)2测量、实验、检测仪器设备数量及供应计划 (19)3主要材料供应计划 (20)第六章创优技术组织措施 (21)6.1确保工程质量的技术组织措施 (21)6.1.1质量管理体系、制度及质量保证体系 (213)6.1.2关键部位及特殊工程的质量控制 (26)6.1.3工种岗位技术培训 (28)6.1.5送样检测、见证取样保证措施 (30)6.1.6分部分项工程分阶段验收步骤及办法 (30)6.1.7成品保护措施 (31)6.2确保安全文明施工的技术组织措施 (33)6.2.1安全管理组织 (33)6.2.2专职安全管理人员 (36)6.2.3特殊作业人员上岗 (37)6.2.4已具备的安全设施或准备配置的安全设施 (37)6.2.5安全防护措施 (38)6.2.6大、中型施工机械管理 (39)6.2.7文明施工技术组织措施 (40)6.2.8安全、文明施工责任目标奖惩办法 (43)6.3确保工期的技术组织措施 (44)6.3.1编制各施工节点月旬作业计划并定期落实 (44)6.3.2交叉、流水施工作业 (44)6.3.3合理调配机械、材料、劳动力 (45)6.3.4设计、建设、施工、监理配合措施 (46)6.3.5工期目标 (48)6.3.6节假日保证措施 (48)6.3.7其他措施 (49)※施工机械设备保证 (49)※专业施工保证 (49)※选择信誉好、素质高的劳务队伍 (49)※施工管理组织保证 (49)※作好材料准备 (49)第七章工期进度计划 (50)1施工过程项目划分 (50)2编排合理的施工顺序 (50)3工序合理搭接 (50)4工期进度计划 (53)第八章施工总平面布置图 (53)第九章环境保护及防污染措施 (53)1管理目标 (53)2组织管理 (54)3工作制度 (54)4管理规定 (55)第十章服务计划 (58)1宗旨 (58)2供货方面的协调服务 (59)3与甲方工地代表的配合 (60)4工程保修服务 (60)第一章编制说明1编制说明✧本施工组织设计严格按照工程招标范围和招标文件对施工组织设计的要求进行编制。

井口房房施工组织设计

井口房房施工组织设计

1.工程概况1、结构设计本工程是由大同煤矿集团设计研究有限责任公司设计的副立井井口房土建工程,建筑面积为552.96平方米,建筑层数为整体一层,建筑高度为13.5m,结构类型为钢筋混凝土框架结构,液控室部分为砖混结构。

基础采用毛石混凝土换填,框架结构部分基础为钢筋混凝土独立基础,基础、梁、板、柱均采用C30混凝土,垫层为C15混凝土,填充墙体采用M7.5水泥砂浆砌筑A3.5级加气混凝土砌块;液控室部分为毛石条形基础,采用MU30毛石,M7.5水泥砂浆砌筑,地上部分采用M7.5水泥砂浆砌MU15蒸压粉煤灰砖。

屋面工程:4mm厚SBS 改性沥青防水卷材、20厚1:3水泥砂浆找平层、1:10水泥膨胀珍珠岩保温层,最薄处100厚,找2%坡、1:3水泥砂浆找平层20厚。

2、钢材设计:a、钢筋:HPB300,HRB400钢。

b、焊条:HPB235钢筋焊接采用E43型,HRB335钢筋焊接采用E50型。

2.编制依据规范、规程:1、《施工现场临时用电安全技术规程》 JGJ46-20122、《建筑使用机械安全技术规程》 JGJ33-20123、《建筑施工现场环境与卫生标准》 JGJ146-20134、《建筑工程资料管理规程》 JGJ/T185-20095、《建筑施工安全检查标准》 JGJ59-20116、《混凝土结构工程施工质量验收规范》 GB50204-20157、《建筑给水排水及采暖工程施工质量验收规范》 GB50242-20138、《给水排水管道工程施工及验收规范》 GB50268-20089、《现场设备、工业管道焊接工程施工及验收规范》 GB50236-201110、《工程测量规范》 GB50026-201211、《建筑地基基础工程施工质量验收规范》 GB50202-201312、《砌体工程施工质量验收规范》 GB50203-201213、《建筑地面工程施工质量验收规范》 GB50209-201014、《建筑装饰装修工程施工质量验收规范》 GB50210-201115、《建筑电气工程施工质量验收规范》 GB50245-201516、《建筑工程施工质量验收统一标准》 GB50300-201317、《建筑电气安装工程质量检验评定标准》 GB50303-2013 3.目标策划1、工期目标;本工程开工日期为年月日开工,全部工程计划年月日竣工。

副井井口房施工组织设计

副井井口房施工组织设计

副井井口房施工组织设计内蒙古蒙西矿业有限公司库里火沙兔煤矿副井井口房施工组织设计施工单位:内蒙古恒安建筑有限公司编制日期:目录第一章编制依据 (2)第二章工程概况 (3)第三章施工部署 (3)第五章主要分部分项工程施工方法 (5)第六章质量保证措施 (17)第七章工期保证措施 (18)第八章施工安全管理及保证措施 (19)施工组织设计第一章编制依据1.1本工程施工组织设计根据国家法律、法规及以下相关的技术标准、规范、规程编。

建筑工程施工质量验收统一标准 GB50300-2001建筑地基基础工程施工质量验收规范 GB50202-2002砌体工程施工质量验收规范 GB50203-2002混凝土工程施工质量验收规范 GB50204-2002建筑地面工程施工质量验收规范 GB50209-2002建筑电气工程施工质量验收规范 GB50303-2001建筑施工安全检查标准 JGJ59-99建筑施工高处作业安全技术规范 JGJ80-91煤矿安装工程质量检验评定标准 MT5010-95;建筑机械使用安全技术操作规程 JGJ33-86建筑施工临时用电安全技术规范 JGJ46-88建筑施工手册第四版《钢结构设计规范》(GB50017—2003)《建筑钢结构焊接规程》(GB50018—2002)《钢结构工程施工及验收规范》(JGJ81-2002)1.2建设单位有关文件1.3施工图纸、招标文件、招标答疑等资料。

1.4施工现场条件。

1.5 ISO9001-2000《标准质量管理体系要求》1.6 ISO14001-1996《标准环境管理体系要求》1.7 GB/T28001-2001《标准职业健康安全管理体系要求》1.8相关建筑类规范及标准。

第二章工程概况副井井口房,位于内蒙古蒙西矿业有限公司矿区。

本工程轴线尺寸为24×6.6m,共一层,建筑高度为6.6m;建筑面积为158.4m2。

基础为混凝土独立基础。

柱基础混凝土强度等级均为C35,主体为砖混结构,墙后分别为300、200,门窗为塑钢门窗。

副斜井施工组织设计

副斜井施工组织设计

XX煤矿集团泽州天安圣鑫煤业有限公司副斜井井筒施工工程施工组织设计施工单位:编制时间:2012年1月圣鑫煤业副斜井井筒施工组织设计圣鑫煤业副斜井井筒施工组织设计会审签字表贯彻记录目录前言 (1)第一章简况 (2)第一节概述 (2)第二节编制原则 (2)第三节编写依据 (2)第二章工程简况 (3)第一节井田地理位置及交通情况 (3)第二节地层及地质构造 (4)第三节水文地质情况 (8)第四节工程简况 (9)第三章施工准备 (10)第四章施工方案及方法 (16)第五章劳动组织及主要经济技术指标 (26)第一节劳动组织 (26)第二节循环作业 (27)第三节技术经济指标 (28)第四节工程排队 (29)第六章施工设备及辅助作业系统 (30)第七章质量保证体系及文明施工措施 (39)第一节质量方针及目标 (39)第二节质量保证体系 (39)第三节质量保证措施 (44)第四节执行标准及技术规范 (47)第五节文明施工措施 (47)第八章安全管理体系及安全技术措施 (48)第一节组织与管理 (48)第二节安全保证体系 (50)第三节主要安全技术措施 (52)第四节井筒施工应急预案 (71)第九章冬雨季施工措施 (75)第十章环境管理 (76)第十一章其他 (77)附图、表前言山西晋煤集团泽州天安圣鑫煤业有限公司是由原山西泽州巴公圣鑫煤业有限公司整合而成,根据晋煤重组办发【2009】39号文《关于晋城市泽州县煤矿企业兼并重组整合方案(部分)地批复,原山西泽州巴公圣鑫煤业有限公司被山西晋煤集团泽州天安有限公司兼并重组,更名为山西晋煤集团泽州天安圣鑫煤业有限公司,2009年11月18日山西省国土资源厅以证号为C1400002009111220043893号换发了新地采矿许可证,属单独保留矿井,高瓦斯矿井,批准开采3号、9号、15号煤层,生产能力为900kt/a.圣鑫煤业2006年资源整合之后,2007年3月成立了泽州巴公圣鑫煤业有限公司,利用了原南连氏西头煤矿部分井筒设施和工业场地进行了扩建,整合之后被批准生产能力为300kt/a,批准开采3号煤层.2008年6月2日进行了基建开工建设.2009年8月兼并重组后,矿井一直处于停工状态.2011年4月15日,山西省煤炭工业厅基本建设局以晋煤办基发字〔2011〕631号文对该矿进行了开工批复.编制本施工组织设计大纲地指导思想是:贯彻执行国家及本行业部门有关建设方针和技术政策,采用先进地科学技术,充分利用本单位地施工能力和技术经验,提高矿井建设地综合效益,在确保安全和工程质量地前提下,合理安排施工顺序及工程进度.本着工期短、效率高、质量优、效益好地原则,建设本矿井.第一章概况第一节概述一、工程名称工程名称:副斜井井筒.二、掘进目地及巷道用途掘进目地是为了担负矿井辅助提升任务,兼做进风井和矿井安全出口.三、巷道设计长度及服务年限副斜井设计长度为640m,2006年资源整合时已掘80m,本次施工主要是延伸副斜井,新施工井筒工程560m.服务年限:同矿井服务年限.第二节编制原则1、认真贯彻执行国家地各项建设方针和技术政策.在确保安全施工和工程质量以及合同所规定其它指标地前提下,科学合理组织施工.2、积极推广国内外先进技术和先进经验,合理安排施工顺序,优选施工方案,组织平行交叉作业,加快施工进度.3、提高施工机械化程度,改善工作环境和劳动条件,提高劳动生产率,缩短建井工期.4、合理安排资源和劳动组织,有计划、有重点地组织人力和物力,确保各项技术经济指标地全面实现.第三节编写依据一、掘进巷道设计图纸圣鑫煤业副斜井井筒施工图.二、其余编制依据1、山西晋煤集团泽州天安圣鑫煤业有限公司副斜井井筒工程施工合同.2、山西晋煤集团泽州天安圣鑫煤业有限公司兼并重组整合工程初步设计说明书.3、《煤矿安全规程》(2011年版).4、《煤矿井巷工程质量验收规范》(GB50213-2010).5、《煤矿井巷工程质量检验评定标准》(MT5009-94);6、《钢筋混凝土工程施工质量验收规范》(GB50204-2002);7、《建设工程监理规范》(GB50319-2000);8、国家、省市和行业相关法律、法规、规范等要求.第二章工程简况第一节井田地理位置及交通情况井田地理位置:山西晋煤集团泽州天安圣鑫煤业有限公司位于泽州县巴公镇西南北连氏西头村口,井田外东部为凤凰山矿和古书院煤矿,北部与山西晋煤集团泽州天安靖丰煤业有限公司相接,四临关系相对简单.副斜井井筒位置:位置副斜井井筒位置位于井田北部,在矿工业广场西侧,回风立井西北,副立井西南.交通情况:该矿距巴公镇约8km处,东距长晋高速5km,距泽州北高速入口约3 km,距207国道约7km,北东距太焦铁路北板桥站约9km,距井田内东部陈大(陈沟-大阳)公路线1.5 km,交通运输十分便利.第二节地层及地质构造(一)、区域地质本井田位于沁水煤盆地东南缘,居新华夏系第三隆起带(太行山隆起),受不同时期、不同方向应力地叠加作用,形成了现存地构造形迹.新华夏系构造控制本区地构造格局,井田构造形态与其密切相关.区域地层为古生界奥陶系、石炭系、二叠系、中生界三叠系、新生界上第三系、第四系.(二)、井田地层井田位于山西省沁水煤田晋城国家规划井田东南部,白马寺Ⅰ区精查勘探区西部外约1km,井田内第四系中更新统(Q2)黄土大面积覆盖,井田东北部有奥陶系中统峰峰组(O1f)地层带状出露,井田外东部大面积出露二叠系上统上石盒子组(P2s)地层.根据矿井井筒实际揭露及钻孔资料,井田内赋存地层由老到新依次有:奥陶系中统峰峰组(02f),石炭系中统本溪组(C2b),石炭系上统太原组(C3t),二叠系下统山西组(P1s),二叠系下统下石盒子组(P1x),二叠系上统上石盒子组(P2s),第四系中更新统(Q2),现依次叙述如下:1、奥陶系中统峰峰组(02f)为含煤地层之基底,埋藏于井田深部;岩性为深灰、青灰色厚层状石灰岩,夹灰黄色、黑灰色泥灰岩,含次生石膏及侵染状黄铁矿,下部裂隙岩溶发育,并为方解石脉充填,局部为角砾状石灰岩,平均厚度约100m.2、石炭系中统本溪组(C2b)平行不整合于下伏奥陶中统峰峰组地层之上,岩性、岩相及厚度变化较大,一般有灰色鲕状铝土岩、铝土质泥岩、灰黑色泥岩组成,偶有灰黑色粉砂岩、夹菱铁矿及硫铁矿等组成,底部局部见“山西式”铁矿.全组厚度2~12.0m,平均5.0m.3、石炭系上统太原组(C3t)连续沉积于下伏本溪组之上,为本区主要含煤地层之一.主要由灰黑色、黑色泥岩,灰黑色、灰色中细粒砂岩,粉砂岩夹石灰岩及煤层组成,灰岩中常含燧石结核及少量生物碎屑,灰岩下常有煤层或煤线,为一套海陆交互相含煤沉积建造.沉积厚度较稳定,本组厚度55.35~111.65m,平均86.51m.根据其岩性组合特征自下而上可分为三段:下段(C3t1)自K1石英砂岩底至 K2石灰岩底,厚 6.6~15.39m,平均12.5m.由K1石英砂岩、粉砂岩、泥岩、铝土质泥岩和15号煤层组成,局部发育一层石灰岩,不稳定.15号煤层位于该段顶部,本区厚度0.60~2.49m,平均厚1.70m,煤层顶部有0.10~0.20m地黑色泥岩伪顶,为全区大部可采煤层之一.中段(C3t2)自K2石灰岩底至K4石灰岩顶,厚20.25~41.4m,平均31.1m.本段主要由K2、K3、K4石灰岩与泥岩、粉砂岩、中细粒砂岩及11号、12号、13号煤层组成.K2 石灰岩厚8~12.0m 平均10.2m,为全区最稳定之石灰岩,含生物碎屑、方解石条带及隧石结核,底部见炭质泥岩.K3石灰岩厚0~8.3m,平均3.20m,K3石灰岩为13号煤层直接顶板,为灰色生物灰岩,含丰富地生物化石碎屑及细脉状小团块状黄铁矿.K2~K3石灰岩之间厚度一般7.80m,由细粒砂岩、粉砂岩和泥岩组成.13号煤层层位稳定,为不可采煤层.K4石灰岩厚2.15~3.60m,平均3.00m,为11号煤层直接顶板,该石灰岩层位稳定,为黑灰色燧石灰岩,含有较多黄铁矿.K3~K4石灰岩层之间厚一般为6.9m,以中细粒砂岩、粉砂岩、泥岩及11号、12号煤层组成.11号、12号煤层为不稳定地不可采煤层.上段(C3t3)自K4石灰岩顶至K7砂岩底,厚28.5~54.86m,平均42.91m.由中细粒砂岩、粉砂岩、泥岩、K5石灰岩及5号、7号、8号、9号煤层组成,常以方解石条带充填.K4~K5石灰岩之间主要以粉砂岩和7号、8号、9号煤层组成.7号、8号煤层为不稳定地不可采煤层,9号煤层为局部稳定可采地薄煤层,厚0.50~1.56m,平均厚1.11m.K5灰岩为含团块状燧石灰岩,底部含泥质成分较多,一般厚3.50m.K6灰岩常相变为砂质泥岩或褐色燧石层,一般厚 4.90m.K5石灰岩~K7砂岩之间主要以泥岩、粉砂岩、细粒砂岩及5号煤层组成,顶部厚层状泥岩中含菱铁矿结核,5号煤层为不可采地稳定煤层.4、二叠系下统山西组(P1s)K7砂岩底至K8砂岩底,连续沉积于太原组之上,为区内主要含煤地层之一.主要由灰色、深灰色中~细粒砂岩夹黑色泥岩、粉砂岩及煤层组成,沉积厚度稳定,其中3号煤层位于本组地层底部.本组厚度39.7~56.62m,平均48.0m.3号煤层厚 1.70~6.02m,平均厚4.40m,含煤系数9.17%.5、二叠系下统下石盒子组(P1x)K8砂岩底至K10砂岩底,连续沉积于山西组地层之上,井田内本组地层遭受剥蚀,据邻区资料,本组地层厚度50.0~98.2m,平均厚75.1 m主要由黄绿色中细粒砂岩、粉砂岩、砂质泥岩、铝土质泥岩组成.底部砂岩中斜层理发育,含岩屑成分高,该砂岩在地表铁质晕圈发育,球形风化明显,为良好地标志层.下部泥岩颜色为灰黑色,向上渐变为黄绿色,到顶部为紫红色含锰铁质结核或鲕粒地铝土质泥岩,其层位俗称“桃花泥岩”,稳定而特征明显,为本区上、下石盒子组地层分界地辅助标志,与下伏山西组地层呈整合接触.6、二叠系中统上石盒子组(P2s)K10砂岩底至K14砂岩底,与下伏下石盒子组整合接触,按岩性特征分为上、中、下三段,在井田内仅出露下段地层.底部K10砂岩为浅色、灰色厚层状含砾砂岩,其上以浅灰绿色泥岩为主夹细粒砂岩及粉砂岩薄层,该层在区内保留厚度约120m,分布于井田外山梁.7、第四系中更新统(Q2)中更新统离石组黄土,厚0~40m,平均厚20.0m,多为耕植土,其上部为黄色粉质粘土、砂土等组成,含钙质结核与砂砾石,与下伏地层呈角度不整合接触.(三)、井田构造井田位于沁水复式向斜(沁水块坳)地东翼南段,晋获褶断带中.受区域构造晋(城)—获(鹿)褶断带地控制,井田内总体表现为一单斜构造,局部发育褶曲,地层总体走向NW,倾向NE,倾角一般7°~10°,在断层附近倾角变陡,约10°~20°,主要发育有三条区域大断层,未见陷落柱构造.1、上寺河逆冲断层(F1):据凤凰山井田精查勘探报告资料,该断层属白马寺逆冲断层地一部分,穿越井田东部,是晋(城)—获(鹿)断裂带地组成部分.位于下寺河村东—上寺河村—二仙掌村一线.走向NE 12°~15°,倾向NW,倾角65°~70°,落差约200m,井田内延展长度约500m.2、正断层(F2):据野外地质填图,北部陈沟乡村西,南部位于与南连氏村东与壁落寺之间东头间,走向NE 6°~10°,倾向NW,倾角70°,落差250~350m,井田内延展长度约2800m.3、逆冲断层(F3):位于井田西部边界外100m左右,走向NE 7~10°,倾向NW,倾角约70°,落差约350 m.断层构造特征一览表综上所述,本次勘查工作经过野外地质填图,井田内地层稳定、走向变化不大,对照DZ/T0215-2002《煤、泥炭地质勘查规范》,井田构造属简单类型.第三节水文地质情况井田位于沁水煤田东南边缘,地貌类型属侵蚀低山区,以丘陵为主,井田内地形总体西北高东南低,冲沟发育.井田内为白水河上游冲沟,井田内无水库等大地地表水体,主要水源为大气降水.雨季时节,沟谷有短暂洪流出现,流径不长,向南汇集注入西河,西河向东南注入白水河.井田内地形总体西北高东南低,冲沟发育,井口标高约899m,工业广场标高约895~900m,工业广场附近沟谷标高约887m,低于工业广场标高近10m,据访问当地人员,井口及工业广场周边标高均高于历史最高洪水水位,不存在洪水危险.副斜井井筒施工穿过地层依次为:第四系表土层,上石盒组,下石盒子组,山西组.地层岩性特征如下:(1)第四系:砂质粘土,有少量砂硕石层.(2)上石盒子组:由泥岩、粉砂岩组成.(3)下石盒子组:由灰色灰绿色细、中粒砂岩组成.(4)山西组:由灰色、深灰色细砂岩、粉砂岩、泥岩及3#煤层组成.水文情况:矿井充水方式一般为沿顶板岩石裂隙渗透或滴水,雨季局部可见短时淋水现象,井筒涌水自岩石裂隙流出沿井壁进入井下.井筒涌水量≤5m3/h, 在井筒施工实际作业中应密切注意涌水量变化,做好防水排水准备工作.第四节工程简况一、矿井简况山西晋煤集团泽州天安圣鑫煤业有限公司是由原山西泽州巴公圣鑫煤业有限公司整合而成,根据晋煤重组办发【2009】39号文《关于晋城市泽州县煤矿企业兼并重组整合方案(部分)地批复,原山西泽州巴公圣鑫煤业有限公司被山西晋煤集团泽州天安有限公司兼并重组,更名为山西晋煤集团泽州天安圣鑫煤业有限公司,2009年11月18日山西省国土资源厅以证号为C1400002009111220043893号换发了新地采矿许可证,属单独保留矿井,高瓦斯矿井,批准开采3号、9号、15号煤层,生产能力为900kt/a.圣鑫煤业2006年资源整合之后,2007年3月成立了泽州巴公圣鑫煤业有限公司,利用了原南连氏西头煤矿部分井筒设施和工业场地进行了扩建,整合之后被批准生产能力为300kt/a,批准开采3号煤层.2008年6月2日进行了基建开工建设.2009年8月兼并重组后,矿井一直处于停工状态.二、井筒技术特征山西晋煤集团泽州天安圣鑫煤业有限公司副斜井井口坐标为:X= 3940243.711、Y=19663446.217(80坐标系),Z=+899.377.副斜井设计总长640m,其中表土段57m,基岩段583m,半圆拱断面,净宽3800mm,净高3500mm,净断面积11.75 m2,倾角23°,水平标高+648m;表土段支护方式为双层钢筋混凝土砌碹,钢筋间排距300×300mm,支护厚度为400mm,砼强度等级为C30;基岩段支护方式为锚网喷,喷厚150mm,喷射砼强度等级为C25,锚索加强;锚杆间、排距为800mm×800mm,三花布置,锚杆为∮20mm×2200mmⅡ级无纵肋螺纹钢(HRB335),托板规格为200mm×200mm×10mm,金属网用Ⅰ级普通钢筋(HPB235)焊接而成,规格为2m×1m,网孔尺寸为100mm×100mm,网片各边搭接长度不小于100mm;锚索采用直径15.24mm地钢绞线制成,锚深6m,托板采用300mm×300mm,根据围岩情况锚索至少锚入坚硬岩层2m,三花布置,间排距为1600mm×1600mm.巷道技术特征表第三章施工准备一、技术准备1、组织技术与管理人员认真审阅图纸,学习技术规范,组织图纸会审,并在此基础上编制实施性施工组织设计、施工技术措施、工程质量计划、填报工程开工报告,准备好各种技术资料和表格,开工前对技术人员、管理人员及施工人员做好技术交底.2、组织测量人员做好接点复测工作,按业主提供地导线、水准点进行全面复核校验,进行井口基桩地布设..3、实验人员尽早进行实验、检验和各种强度混凝土配合比地实验.二、施工队伍准备1、为确保本工程施工速度和工程质量,特在本单位内精选素质好、经验丰富、从事过三次以上类似工程施工地施工队伍进场施工.2、根据施工进度情况,按总体施工计划,陆续组织各作业队、各岗位、各工种人员进场,所有人员在上岗前10天到岗,组织学习培训.3、施工单位成立了施工现场工程组织机构,明确了职责分工.图3-1:施工组织机构图三、施工现场准备遵循“方便实用、文明施工、节约用地、安全可靠、兼顾环保、CI达标、尽可能避开永久建筑物”地原则,现场准备基本到位,工队入场即可开工建设.场地:2006年资源整合时已施工80m,井口工业场地已平整,已具备开工条件,满足施工要求.道路:井口工业场地进场公路已修通.供水:施工生活用水来自原矿井工业场地水源.供电:引至原矿井变电所电源供电.通讯:电话已安装到位,可满足施工要求.四、施工总平面地布置(1)各临时建筑地相互位置要符合施工工艺要求,动力设施要靠近负荷中心.(2)尽量避免人流、物流地交叉干扰,避免器材、设备地长距离搬运.(3)尽量避免占用永久建筑位置.根据以上原则,施工总平面布置如下:生产性临时建筑围绕井口布置.浴室、锅炉房、职工宿舍食堂按现场实际情况布置,砂、石场地、水泥库搅拌站设在井口附近.(4)各临时建筑地平面布置,依据地形而建,不设统一地室内标高,但室内标高均应比室外标高高200-300㎜.图3-2:副斜井施工总平面布置图五、加快施工准备工作地技术及组织管理措施准备期准备工作内容繁多,准备工程量大,设备调运及安装工程多;因此,合理安排,精心组织施工准备期地各项工作,并抓住准备工作地主要矛盾线,展开平行交叉作业,是保证井筒按期开工地重要基础.为此,我处拟采取如下技术及组织管理措施.(1)合同签订后,立即组织施工队伍及设备进场,并迅速成立以凿井工程部为主地现场筹备领导小组,保证准备工作地顺利进行.(2)施工队伍进场后,立即施工井架、稳绞车及压风机基础,以保证砼有足够地凝固期,为设备地尽快安装创造条件.(3)在做好施工准备期各项准备工作平行交叉作业地基础上,抓住井筒提升绞车基础、机房、安装、调试这条主要矛盾线,确保各项准备工作总体推进,按期完成.(4)保证足够地强有力地施工力量,投入施工准备工作.(5)尽快按批复地施工组织设计编制实施性施工作业规程,确保各项临时工程地按时完成.六、设备材料准备由本单位机电、实验、材料供应部门组织设备、仪器、周转材料等调运工作.确保部门组织设备、实验、检验设备、测量设备等迅速进场.其余设备和周转材料根据工作进度工程进展情况,按计划陆续进场.组织物资供应人员进行市场调查,按本单位通过地质量、环境、职业健康安全三体系即ISO9001、ISO14001、GB/T28001标准,以及本单位《物质采购控制程序》,选择合适地供应商,落实货源,安排订货计划,设立堆放场地,搭设库房等.副斜井拟投入主要施工机械设备表见表3-1.图3-1:施工现场组织机构图3-2 副斜井井筒施工工广平面布置图表3-1 拟投入本工程地主要施工机械设备表第四章施工方案及方法一、表土段和风化基岩段施工方案及方法1、施工方案选择根据副斜井表土段地工程特征、地质状况、支护形式、施工设备和操作技术等因素,确定施工方案为:采用副斜井快速施工机械化配套施工工艺,即激光指向、局部震动爆破、挖掘装载机装渣、箕斗提升、翻矸台汽车排矸、潜水泵排水地成熟施工经验.采用YT-28型凿岩机打眼,激光指向仪定向、局部震动爆破、三八交叉作业制,多工序平行交叉作业.附图4-1:斜井机械化施工及斜井断面布置图2、施工工艺工艺流程如下:交接班、文明施工→安全检查→挂中腰线→人工挖掘(打眼、装药、放炮通风)→排矸→临时支护→挖基础、浇筑基础→铺设钢筋→立拱架支模→浇筑混凝土→拆除拱架支模.3、施工方法1)、掘进表土段和风化基岩段采用挖掘装载机挖掘,局部夹石坚硬地段采用局部震动爆破,掘进施工和局部震动爆破必须符合煤矿安全规程地有关规定.2)、钻爆施工⑴、首先由质检员根据中腰线将巷道轮廓线画出,并按爆破设计点出炮眼位置.⑵、打眼工和把钎工严格按质检员所点位置打眼,打出地炮眼要符合平直齐地要求.⑶质检员要对打好地炮眼地深度角度检查和验收,对不符合要求地炮眼必须重打.⑷、按爆破设计要求地数目和方式装药,质检员要现场监督检查.⑸、装完药,经检查无误后,即可进行联线工作,脚线地连接工作可由经过专门训练地班组长协助爆破工进行,爆破母线连接脚线、检查线路和通电工作,只准爆破工一人操作.3)、装矸、提升、排矸:采用ZWY-160型挖掘装载机装矸,JK-3×2.2型绞车提升 3.5m3箕斗出矸,矸石直接落地,用ZL-50F型装载机装矸,自卸汽车拉至排矸场地.井上下地轨道采用30kg/m钢轨,600mm轨距.4)、支护(1)临时支护a、支护形式:采用钢套管前探梁支护.b、支护材料:采用1.5M×Φ3寸钢管和1.5M×Φ2.5寸钢管,将1.5M×Φ3寸钢管套入1.5M×Φ2.5寸钢管内,在预定位置打孔两组;使用时,将1.5M×Φ2.5寸钢管从1.5M×Φ3寸钢管内抽出,在指定位置孔内穿销固定.c、支护参数:共使用钢管套7跟,间距600mm,钢管之间用板梁连接勾顶.边部钢管距离巷道帮内壁100mm.支护前最大空顶距顶距为1600mm,支护后最大空顶距400mm.d、临时支护平、剖、断面示意图e、质量要求临时支护应找准钢管架设位置,板梁必须贴紧岩帮.f、保证措施①、顶部挖开后及时进行敲帮问顶.把危矸、活矸及时处理掉,找顶人员必须站在支护完好地地点进行.②、架设临时支护必须及时有效,用长钎找净顶帮危岩活矸后及时打设,尽量减少空顶时间.③、钢管必须与井筒设计坡度相同.④、打临时支护时必须停止其它作业,专人观顶.断面图钢套管板梁平面图(2)永久支护A、支护材料:a、钢筋规格:环筋采用∮18mm地HRB335Ⅱ级无纵肋螺纹钢加工而成,内环筋每根长度11520mm,间距300mm,外环筋每根长度11500mm,间距300mm;纵筋采用∮16mm地HRB335Ⅱ级无纵肋螺纹钢加工而成,每根长度1500mm,间距300mm;联系筋采用∮8mm地HRB335Ⅱ级无纵肋螺纹钢加工而成,每根长度430—640mm,间距500mm;钢筋捆绑采用12#铁丝,每处必须捆绑扎实,铁丝环绕不得少于3圈.b、混凝土等级强度为C30,原材料采用P.O42.5型普通水泥、黄沙粗砂、20—40mm石子和中性水按1:1.82:3.38:0.48配比.c、基础:规格为深×宽=800mm×1000mm,其中下面540mm用片石混凝土砌筑而成,540mm向上与拱体支护相同.B、混凝土支护①检查钢筋铺设是否符合设计要求,发现问题及时处理.②清理支护现场地矸石杂物,准备好振捣棒.③检查搅拌机是否完好,并送电空载试运转,紧固好磨擦板,不得出现漏风现象.二、基岩段施工方案及方法1、施工方案选择根据副斜井基岩段地工程特征、地质状况、支护形式、施工设备和操作技术等因素,确定施工方案为:采用副斜井快速施工机械化配套施工工艺,即激光指向、光面爆破、挖掘装载机装岩、矿车提升、翻矸台汽车排矸、潜水泵排水地成熟施工经验.附图4-1:斜井机械化施工及斜井断面布置图2、施工工艺炮掘工艺流程如下:打眼→放炮→通风排烟→检查瞎炮处理、敲帮问顶清除浮矸→临时支护→排矸→打顶部锚杆孔、清孔→安装顶部锚杆→打两帮锚杆孔、清孔→安装帮部锚杆→初喷混凝土→复喷混凝土.3、施工方法1)、钻眼爆破工作面架设多功能简易凿岩台架,架上安设风、水管路,钻眼采用YT-28型气腿式风动凿岩机,分上、下部同时作业.操作人员执行七定(人、钻、位、眼、时、质、量)、两专(安锚杆、修钻)负责制,使用多炮杆导向,严格掌握炮眼角度.炮眼布置根据岩性变化及时调整数量、深度、角度等有关参数.炮眼深度为2.0m,掏槽方式为直眼菱形另加中心眼,爆破选用岩石水胶炸药,毫秒延期电雷管,全断面一次爆破.放炮器选用MFB-200型放炮器.基岩段炮眼布置图4-2,基岩段光面爆破参数表4-2-1,基岩段预期爆破效果表4-2-2.采取多组同时装药,约30-50min完成.放炮后通风30min左右吹散炮烟.采用YHJ-800型激光指向仪定向,激光前30-50设一组中线,互相校正,利用激光点准确以划定眼位,控制中腰线,便于巷道掘砌.附图4-2:副斜井基岩段炮眼布置图附表4-2-1:副斜井基岩段爆破参数表附表4-2-2:副斜井基岩段预期爆破效果表2)、钻爆施工⑴、首先由质检员根据中腰线将巷道轮廓线画出,并按爆破设计点出炮眼位置.⑵、打眼工和把钎工严格按质检员所点位置打眼,打出地炮眼要符合平直齐地要求.⑶质检员要对打好地炮眼地深度角度检查和验收,对不符合要求地炮眼必须重打.⑷、按爆破设计要求地数目和方式装药,质检员要现场监督检查.⑸、装完药,经检查无误后,即可进行联线工作,脚线地连接工作可由经过专门训练地班组长协助爆破工进行,爆破母线连接脚线、检查线路和通电工作,只准爆破工一人操作.3)、装矸、提升、排矸:采用P-60B型耙岩机装矸,JK-3×2.2型绞车提升3.5m3出矸,矸石直接落地,用ZL-50F型装载机装矸,自卸汽车拉至排矸场地.井上下地轨道采用30kg/m钢轨,600mm轨距.4)、支护(1)临时支护。

(建筑工程管理)施工组织设计(副斜井)

(建筑工程管理)施工组织设计(副斜井)

能源掘120101施工组织设计工作面名称:帽帽山煤业副斜井编制人:张锦如施工负责人:李连文总工程师:张锦如批准日期:2013 年4 月3 日执行日期:2013 年4 月3 日内蒙古神华建安有限X公司会审意见1. 进壹步完善帽帽山工程项目部领导机构,重要部门管理人员不得兼任。

2. 地测人员必须由有多年测量经验的人员担任。

3. 补充“放炮警戒图”。

4•排矸运输车辆必须有完善的安全技术措施。

5.明确倒车硐室的规格尺寸、支护方式及间距。

会审意见:1、在确定长距离通风方案后,另行编制专项安全技术措施。

2、为加强施工进程,缩短工期,可采用从措施巷和目前工作面相向施工,贯通措施另编。

目录第壹章工程概况 (5)第二章施工准备及场地布置 (14)第三章工程施工方案 (15)第四章施工组织及施工进度计划 (21)第五章工程质量保证系及质量措施 (22)第六章工程保证措施 (28)第七章文明施工措施 (29)第八章施工安全技术措施 (31)第九章井下灾害预防 (37)山西煤销集团帽帽山煤业有限X公司副斜井施工组织设计第壹章:工程概况第壹节:概述壹、井田概况山西煤炭运销集团帽帽山煤业有限责任X 公司井田位于大同市西南部40km 处的左云县水窑乡杨家窑村东部,西北距左云县城约24km ,行政隶属大同市左云县水窑乡,其地理坐标为:东经112 ° 51 ' 02 〃~112 ° 53 ' 55 〃。

北纬39 ° 50 ' 21 〃~39 ° 52 ' 01 〃。

井田面积,按山西省国地资源厅2009 年12 月9 日换发的C1400002009121220047226 号采矿许可证批准井田面积为17.4279km 2,开采石炭系2、5、8号煤层以(2009 年7 月15 日山西省煤矿企业兼且重组整合工作领导组办公室《晋煤重组办发[2009]9 号》文件批准面积为17.4304km 2,矿区范围拐点坐标如下:西安1980 坐标系北京1954 坐标系1X Y1X Y24419032.5019661614.67244190791966168634416492.4919661677.673441653919661749 44415489.4819661691.67444155361966176354414805.4819662433.68544148521966250564414770.4819660405.67644148171966047774413884.4719660418.677441393119660490 84413884.4719660173.678441393119660245 94413376.4719660149.679441342319660221104413348.4719658329.6610 441339519658401114416435.4819658277.6611 44164821965834 9124418975.4919658234.6512 44190221965830 6批准生产规模180 万吨/年,经济类型为有限X 公司,采矿许可证有效期限自2009 年12 月9 日至2011 年12 月9 日。

副斜井井筒施工组织设计

副斜井井筒施工组织设计

计划投入的主要施工机械设备表序号机械或设备名称规格型号数量国别产地制造年份额定功率KW生产能力备注1 提升绞车XTK1×2.5×2B-201 洛阳2007 3952 耙斗机P-90B 1 徐州2008 453 局扇2BKJ№6.3/60 2 湘潭2007 30×24 空压机4L-20/4 3 江苏2005 1305 喷射机PZ-5 1 河南2009 5.5×56 搅拌机JS-350 1 兴平2007 15×27 配料机HPB-1600 1 兴平2006 5.58 矿车1T 1 铜川20039 变压器KSGZY-500KVA 2 河南200410 自卸车康明斯8T 6 湖北200511 箕斗3M3 3 铜川2006 812 水泵100D45×4 2 西安2009 4513 潜水泵 2 西安2009 414 锚杆拉力计T52 1 湘潭200515 小绞车JD-4 3 常州2003 55kW山西山阴宝山腰寨煤业有限公司副斜井施工组织设计编制单位:山西宏图建设工程有限公司编制时间:2011年7月8日编制人:李学奎批准时间:2011年7月23日执行日期:2011年7月30日目录第一章概况 (5)第一节地理位置与交通情况 (5)第三节地质及水文地质 (6)第四节井筒技术特征 (6)第二章施工现场组织机构 (7)第三章施工方案 (8)第一节施工准备 (8)第二节施工工序安排 (12)第三节施工方案 (12)第四节施工方法 (13)第五节砼搅拌和运输 (18)第六节提升运输管理 (18)第七节地质测量工作 (19)第八节井筒通过破碎带的措施 (20)第九节防治水 (21)第十节防汛 (22)第十一节冬、雨季施工措施 (22)第四章辅助生产系统 (23)第一节提升系统 (23)第二节运输系统 (24)第三节压风系统 (24)第四节通风系统 (24)第五节排水系统 (24)第六节供电系统 (24)第七节信号、通讯、照明系统 (25)第五章施工进度、工期及保证措施 (27)第二节作业方式 (27)第三节进度及工期 (30)第四节工期保证措施 (30)第六章质量标准及施工保证措施 (31)第一节质量标准 (31)第二节施工验收 (33)第三节保证工程质量的技术措施 (35)第七章施工安全技术措施 (37)第一节安全目标 (37)第二节安全保证体系 (37)第三节施工安全技术措施 (38)第八章环境保护及文明施工 (42)第一节减少扰民噪音、降低环境污染措施 (42)第二节文明施工措施 (42)第九章计划、统计与信息管理 (45)第一节计划、统计 (45)第二节信息管理 (45)第一章概况宝山腰寨煤业有限公司是一座正在技改的、年规划生产能力120万吨的煤炭企业。

副斜井施工组织设计(自编)

副斜井施工组织设计(自编)

第一章工程概况1.1井田位臵山西煤炭运销集团盛泰煤业有限公司井田位于高平市陈区镇建宁乡,南西距高平市15Km,其地理座标为东经113º03´35"~113º05´49",北纬35º50´07"~35º53´22"。

井田南北长6.0Km,东西宽3.35Km,面积14.56Km²。

1.2井田交通井田北部和长治县相临,北距长治市直线距离38Km,西南距高平市直线距离15Km。

井田及周边交通发达,长(治)-晋(城)二级公路,长(治)-晋(城)高速公路从井田西侧约9Km通过,西距太(原)-焦(作)铁路线高平站约15Km。

曲(沃)-辉(县)公路从井田南侧通过,交通极为方便。

1.3自然地理1.3.1地形及地貌特征井田地处太行山中南段的高平山间盆地北东缘,属中低山区。

总体地势表现为北缘及中部高,东、西部低。

井田内最高标高为1239.55m(井田北缘山梁最高点),最低标高为973.5m(东窑头村西本井田西缘冲沟内),相对高差266.05m。

区内及周边无大的地表水体和地表径流,大气降水沿沟自然排泄。

1.3.2水系井田内较大沟谷近几十年来的最高洪水位一般高出沟底河床1.5-2.5m。

11.3.3气候本区属暧温性大陆性季风气候,四季分明。

春季干燥多风,夏季炎热多雨,秋季天高气爽,冬季寒冷少雪。

据井田周边区域气象资料,年均气温9.8ºC,一月最冷,平均-5.5 ºC,七月最热平均23.2 ºC,极端高温38.6 ºC。

无霜期180天,年均冻结天数100天,最大冻结深度56cm,全年平均日照时数2482.34小时,年均降水量617.1mm,年蒸发量为1631.6mm,年均风速2-3m/s,以东北风为主。

自1971年以来,晋城市地区最大积雪厚度达到28.2cm。

1.4地层及构造井田位于山西省沁水煤田东南部,晋城煤炭国家规划矿区高平西区的北东部。

副斜井井筒施工组织设计

副斜井井筒施工组织设计

副斜井井筒施工组织设计一、前期工作1.项目技术准备工作(1)进行项目立项,明确项目目标和需求。

(2)开展地质勘查和现场勘察,确定地质条件和目标井筒位置。

(3)进行工程设计,包括各种施工方案、施工工艺和施工方法的确定。

2.组织准备工作(1)成立项目管理团队,明确各个岗位的职责和任务。

(2)编制施工组织设计方案,确定施工过程中的各项指标和安全要求。

(3)制定施工计划,包括施工时间、资源配置和工作任务等。

二、施工方案的确定施工方案是副斜井井筒施工的核心内容,其合理性和科学性直接影响到施工效果和质量。

根据地质条件和工程要求,选择最合适的施工方案。

1.方案设计(1)确定井筒开挖的方式,可以采用机械开挖还是人工开挖。

(2)选择开挖的方法,可以采用顺垂、逆垂或者平行开挖等方式。

(3)确定支护措施,包括井壁衬砌、钢筋混凝土灌注桩等。

(4)确定排水和通风的方法,保证施工现场的安全和顺利进行。

2.施工工艺(1)制定施工工序和作业流程,明确各个作业环节的顺序和时间。

(2)确定施工的关键技术,包括土方开挖、支护施工、灌浆充填等。

(3)建立施工质量控制体系,包括施工过程中的检测和验收。

三、施工组织的安排施工组织的安排是确保施工过程中各项工作有条不紊进行的关键环节。

1.人员安排(1)组织施工人员的培训和技术交流,提高施工队伍的整体水平。

(2)明确施工人员的职责和任务,确保施工过程中各项工作的顺利进行。

(3)落实施工人员的安全教育和培训,提高他们的安全意识和应急能力。

2.设备安排(1)选择合适的机械设备,包括挖掘机、钻机和灌浆设备等。

(2)对设备进行检修和保养,确保设备的正常运行。

(3)合理安排设备的使用顺序和时间,避免重复使用或者闲置。

3.材料安排(1)确定施工所需的材料种类和数量,保证材料供应充足。

(2)对材料进行检验和验收,确保材料符合施工要求。

(3)合理安排材料的运输和储存,避免材料的浪费和损失。

四、施工安全及质量控制措施施工安全和质量控制是副斜井井筒施工的重要环节,必须严格按照标准进行操作。

副斜井井筒施工组织设计

副斜井井筒施工组织设计

计划投入的主要施工机械设备表序号机械或设备名称规格型号数量国别产地制造年份额定功率KW生产能力备注1 提升绞车XTK1×2.5×2B-201 洛阳2007 3952 耙斗机P-90B 1 徐州2008 453 局扇2BKJ№6.3/60 2 湘潭2007 30×24 空压机4L-20/4 3 江苏2005 1305 喷射机PZ-5 1 河南2009 5.5×56 搅拌机JS-350 1 兴平2007 15×27 配料机HPB-1600 1 兴平2006 5.58 矿车1T 1 铜川20039 变压器KSGZY-500KVA 2 河南200410 自卸车康明斯8T 6 湖北200511 箕斗3M3 3 铜川2006 812 水泵100D45×4 2 西安2009 4513 潜水泵 2 西安2009 414 锚杆拉力计T52 1 湘潭200515 小绞车JD-4 3 常州2003 55kW山西山阴宝山腰寨煤业有限公司副斜井施工组织设计编制单位:山西宏图建设工程有限公司编制时间:2011年7月8日编制人:李学奎批准时间:2011年7月23日执行日期:2011年7月30日目录第一章概况 (5)第一节地理位置与交通情况 (5)第二节自然环境 (5)第三节地质及水文地质 (6)第四节井筒技术特征 (6)第二章施工现场组织机构 (7)第三章施工方案 (8)第一节施工准备 (8)第二节施工工序安排 (12)第三节施工方案 (12)第四节施工方法 (13)第五节砼搅拌和运输 (18)第六节提升运输管理 (18)第七节地质测量工作 (19)第八节井筒通过破碎带的措施 (20)第九节防治水 (21)第十节防汛 (22)第十一节冬、雨季施工措施 (22)第四章辅助生产系统 (23)第一节提升系统 (23)第二节运输系统 (24)第三节压风系统 (24)第四节通风系统 (24)第五节排水系统 (24)第六节供电系统 (24)第七节信号、通讯、照明系统 (25)第五章施工进度、工期及保证措施 (27)第一节进度安排原则 (27)第二节作业方式 (27)第三节进度及工期 (30)第四节工期保证措施 (30)第六章质量标准及施工保证措施 (31)第一节质量标准 (31)第二节施工验收 (33)第三节保证工程质量的技术措施 (35)第七章施工安全技术措施 (37)第一节安全目标 (37)第二节安全保证体系 (37)第三节施工安全技术措施 (38)第八章环境保护及文明施工 (42)第一节减少扰民噪音、降低环境污染措施 (42)第二节文明施工措施 (42)第九章计划、统计与信息管理 (45)第一节计划、统计 (45)第二节信息管理 (45)第一章概况宝山腰寨煤业有限公司是一座正在技改的、年规划生产能力120万吨的煤炭企业。

副斜井施工组织设计

副斜井施工组织设计

贺兰山焦煤公司一矿副斜井井筒工程施工组织设计山东枣庄矿业集团中兴建安有限公司二○一○年六月十日第一章编制依据、原则和范围第一节编制依据1、焦煤公司一矿设计说明书;焦煤公司一矿采掘工程平面图及井上下对照图;矿方提供的井筒断面图2、《爆破安全规程》GB6722;《矿山井巷工程施工及验收规范》GBJ213-90;《煤矿井巷工程质量检验评定标准》MT5009—94;《煤矿安全规程》(2010);《煤矿建设安全规定》(试行)1997。

《工程测量规范》GB50026—93;《混凝土结构工程施工质量验收规范》GB50204—2002;《地下防水工程质量验收规范》GB50208-2002。

3、本公司现有施工力量、技术水平、技术装备和机械化程度。

4、现场实际情况。

第二节编制原则精心组织、科学管理、合理安排施工工序,正确选择经济合理、技术可行、安全可靠的施工方案和方法,贯彻执行国家的各项基本建设法规、经济及施工政策,狠抓主链锁工程及关键工程的施工,有计划、有重点地组织人力、物力,确保各项经济技术指标和建设工期的实现。

使用行之有效的先进经验,选用成熟配套的施工设备,提高机械化程度,减轻劳动强度,加快施工进度,提高施工效率,降低工程成本,确保施工安全.坚持严格的质量标准,确保实现创优质工程的目标。

第三节编制范围本设计编制范围为焦煤公司一矿副斜井井筒掘进及支护工程.第二章地质及工程概况第一节井田概况内蒙古太西煤集团贺兰山焦煤公司蚕特拉一矿位于贺兰山煤田呼鲁斯太矿区蚕特拉井田VI~辅VII勘探线之间,行政区划隶属内蒙古自治区阿拉善左旗宗别立镇,其地理坐标为:东经106°05′10″~106°07′28″、北纬39°07′51″~39°08′45″。

井田走向长2.77km,倾斜宽0.57km,面积1.58km2。

上部以+1750m 标高为界,深部以+1200m标高水平为界,技术改造设计规模0.30Mt/a。

副斜井施工组织设计

副斜井施工组织设计

山西美锦能源集团有限公司锦源矿副斜井井筒掘砌施工组织设计温州井巷工程有限公司锦源项目部二0一三年三月编制:审核:批准:项目部经理:总工程师:总经理:施工组织设计(方案、措施)审核表项目名称山西美锦能源集团公司锦源煤矿方案名称副斜井施工组织设计项目部温州井巷锦源项目部编制人报送日期审核人审核日期审批意见:目录一工程概况 (1)二、施工准备 (3)三、施工工艺及施工方法 (4)四、生产系统 (7)五、劳动组织和施工进度 (12)六、工程质量保证措施 (14)七、工期保证措施 (18)八、安全保证措施 (19)九、有关图表 (25)一、工程概况1、地理概况(1)矿井地理位置、范围与交通锦源矿井位于山西晋中煤炭基地离柳矿区,行政区划属临县管辖,矿井隶属于山西临县锦源煤矿有限公司,该公司为山西美锦能源集团有限公司全控子公司,井田地里坐标北纬37。

38'10"~37。

44'01",东经110。

45'58"~110。

54'23"。

井田走向长9.0~13.0km,倾斜宽13.65km,面积129.6km2.井田内交通便利,三交镇~碛口镇公路沿湫水河从井田中部蜿蜒穿过,在三交镇与太原~离石~临县公路相交。

建设中的太原~中卫~银川铁路线经过离石,距该矿60km.中阳县鑫隆煤源有限公司一期改扩建工程位于中阳县城东北3km。

(2)、地形地貌及河流、气候条件井田属于吕梁山系,为典型的黄土高原地貌。

晋西黄土高原,地表大部为黄土覆盖,经长期侵蚀切割,沟谷纵横,地形主要发育在秋水河谷,为冲击、洪积地形,秋水河谷宽阔、平坦,宽200米左右。

纵观井田走势,大致北高南西低。

井田内最高点位于北部的高家焉村西600米处,标高1080.4米,最低点位于南部秋水河床上,标高664.8米。

最大相对高差415.6米,一般相对高差100~150米。

(3)、水文及主要河流秋水河为井田内最大河流,流经本井田西北部在碛口镇注入黄河,全长107公里,井田内流长11.5公里。

矿井_副斜井井口房

矿井_副斜井井口房

第1章 编制依据一、 设计与施工应遵循的规范、规程1、《建筑结构荷载规范》(2006年版)(GB50009-2001)2、《建筑抗震设计规范》(GB50011-2010)3、《钢结构设计规范》(GB50017-2003)4、《冷弯薄壁型钢结构技术规范》(GB50018-2002)5、《门式刚架轻型房屋钢结构技术规程》(CECS102:2002)6、《钢结构工程施工质量验收规范》(GB50205-2001)7、《混凝土结构设计规范》(GB50010-2010)8、《建筑钢结构焊接技术规程》(JGJ81-2002)9、《建筑地基基础设计规范》(GB50007-2002)第二章 工程概况及特点1、 工程概况(1)建设单位:山西保利金庄煤业有限公司(2)工程名称:副斜井井口房(3)工程地点: 山西省灵石县交口乡温家沟村(4)设计单位: 煤炭工业太原设计研究院(5)建筑面积:231.4m2厂房简况1 结构形式:采用门式刚架钢结构厂房,双坡屋顶,坡度8%。

②材料选用:本工程钢结构部分屋架梁、柱等均采用国标热轧H型钢及Q235B钢板焊接而成,其中檩条、墙檀、窗樘柱均采用Q235B冷弯薄壁卷边槽钢;屋面板为80mm厚岩棉夹芯板。

二、工程特点:1、工期紧:本工程根据计划,从施工到交工验收共计37日历天,所以必须合理安排各阶段的工作时间及相互交接时间,且明确各工序的最迟交接时间,以保证工程如期竣工。

2、施工范围大:各种构件布置必须分类就近堆放,尽量减少材料的二次搬运,同进须合理安排起重机行走路线,以提高工效。

3、构件品种多:本工程各种钢构件均需工厂加工制作,然后装箱运输至工地,各种构配件必须有组织、有计划按图纸要求分类编号,小构件须分类打包做到有条不紊。

第三章 施工部署1、 实施目标为充分发挥企业优势,科学组织安装作业,我们将选派高素质的项目经理及工程技术管理人员。

按项目法施工管理,严格执行ISO9001质量保证体系,积极推广新技术、新工艺、新材料,精心组织,科学管理,优质高效地完成施工任务,严格履行合同,确保实现如下目标:(1)质量等级:优良。

副斜井延深施工组织设计.

副斜井延深施工组织设计.

达拉特旗苏家沟煤矿副斜井二水平延深施工组织设计施工单位:综掘队队长:编制:日期:2012年7月审批意见栏副斜井二水平延深施工组织设计一、工程概况:1、概述该工程为达拉特旗苏家沟煤矿二水平接续副斜井延深,井筒倾角-6°,斜长460m,(其中穿过一水平主运巷段:∠-8°6′,30m;∠-9°17′,22m;∠-10°14′,10m)。

该巷行驶防爆无轨胶轮车,敷设消防洒水管路,担负全矿井的矸石、材料、设备、人员运输任务,也是矿井的主要入风井及安全出口。

井筒断面形状为半圆拱,净宽4.5m,净高3.8m,净断面14.9 m2;煤岩结合段掘进宽度5.5m,高度4.55m,采用混凝土砌碹支护,支护厚度500mm,掘进断面积为21.8 m2;基岩段掘进宽度4.8m,高度4.2m,采用锚网喷支护,支护厚度150mm,掘进断面积为17.7 m2,底板浇筑250mm厚混凝土。

该工程延原副斜井方位、坡度、断面向下延伸至5-1上煤层底板,预计延伸460m左右。

地表无建筑物,地面标高+1329.8m~+1352.6m,5-1上煤层底板标高+1270m~+1261m,埋藏深度59.8m~91.6m。

2、设计依据《内蒙古达拉特旗苏家沟煤炭有限公司苏家沟股份制井水平接续初步设计》、《苏家沟煤矿水平接续初步设计地质说明书》、《副斜井延深掘进地质说明书》。

3、开口施工位置在副斜井二水平井筒预留段,直接延深掘进施工。

4、掘进方法及施工工艺采用EBZ-160型掘进机掘进,防爆胶轮车运输,防爆装载机装碴;采用二班工作制,煤岩结合段掘进锚网20m时进行喷浆支护,喷浆厚度50mm,掘进锚网、喷浆40m时进行砌碹支护;基岩段掘进锚网20m时进行喷浆支护。

副斜井延深工程主要内容包括井筒掘进、支护、底板硬化、水沟等。

斜井砌碹混凝土强度等级为C25、喷射混凝土强度等级为C20、铺底混凝土强度等级为C25,水泥标号为P.O-42.5;锚杆均为树脂锚杆。

  1. 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
  2. 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
  3. 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。

郑煤集团朝阳沟煤矿副斜井井口房及灯房施工组织设计永煤开发公司第一分公司二00七年十二月十二日目录第一章编制说明 (5)1编制说明 (5)2编制依据 (5)3自然条件及环境条件 (7)4工程概况 (7)第二章施工说明 (8)1总体目标 (8)2施工说明 (8)3施工部署及总进度主要节点控制 (9)3.1总体施工原则 (9)3.2总体施工程序及施工流水段划分 (9)3.3施工工期安排 (10)第三章主要施工办法 (10)1施工准备 (10)1.1技术准备 (10)1.2现场准备 (11)1.3季节性施工准备 (11)1.4其它准备 (12)2各施工过程的施工顺序 (12)3分部、分项工程主要施工过程的施工方法 (13)4冬季施工措施 .......................... 错误!未定义书签。

第四章项目经理部及劳动力配置计划 (14)1项目经理部组成情况 (14)2分部分项工程所需工种类别和级别 (17)3分阶段施工计划投入劳动力人数 (17)第五章主要施工机械、材料供应计划 (19)1满足工程施工所需的机械数量及供应计划 (19)2测量、实验、检测仪器设备数量及供应计划 (19)3主要材料供应计划 (20)第六章创优技术组织措施 (21)6.1确保工程质量的技术组织措施 (21)6.1.1质量管理体系、制度及质量保证体系 (213)6.1.2关键部位及特殊工程的质量控制 (26)6.1.3工种岗位技术培训 (28)6.1.5送样检测、见证取样保证措施 (30)6.1.6分部分项工程分阶段验收步骤及办法 (30)6.1.7成品保护措施 (31)6.2确保安全文明施工的技术组织措施 (33)6.2.1安全管理组织 (33)6.2.2专职安全管理人员 (36)6.2.3特殊作业人员上岗 (37)6.2.4已具备的安全设施或准备配置的安全设施 (37)6.2.5安全防护措施 (38)6.2.6大、中型施工机械管理 (39)6.2.7文明施工技术组织措施 (40)6.2.8安全、文明施工责任目标奖惩办法 (43)6.3确保工期的技术组织措施 (44)6.3.1编制各施工节点月旬作业计划并定期落实 (44)6.3.2交叉、流水施工作业 (44)6.3.3合理调配机械、材料、劳动力 (45)6.3.4设计、建设、施工、监理配合措施 (46)6.3.5工期目标 (48)6.3.6节假日保证措施 (48)6.3.7其他措施 (49)※施工机械设备保证 (49)※专业施工保证 (49)※选择信誉好、素质高的劳务队伍 (49)※施工管理组织保证 (49)※作好材料准备 (49)第七章工期进度计划 (50)1施工过程项目划分 (50)2编排合理的施工顺序 (50)3工序合理搭接 (50)4工期进度计划 (53)第八章施工总平面布置图 (53)第九章环境保护及防污染措施 (53)1管理目标 (53)2组织管理 (54)3工作制度 (54)4管理规定 (55)第十章服务计划 (58)1宗旨 (58)2供货方面的协调服务 (59)3与甲方工地代表的配合 (60)4工程保修服务 (60)第一章编制说明1编制说明✧本施工组织设计严格按照工程招标范围和招标文件对施工组织设计的要求进行编制。

在人员、机械、材料调配、质量要求、进度安排等方面统一部署的原则下,由土建、安装、装饰三大专业组成。

✧根据本工程设计特点、功能要求,本着对业主资金合理利用,对工程质量的终身负责,以“科学、经济、优质、高效”为编制原则。

✧我公司对此次施工组织设计的编制高度重视,召集了参加过类似工程施工、有丰富管理及施工经验的人员,在仔细研究图纸,明确工程特点、充分了解施工环境、准确把握业主要求的前提下,成立编制专题小组,集思广议、博采众长,力求方案切合工程实际,思路先进,可操作性强。

2编制依据✧根据建设单位提供的工程情况总说明、招标文件、答疑资料、施工图纸以及现场考察结果、市建公司施工工艺标准、现行施工规范。

✧我公司的技术、机械设备装备情况及管理制度。

✧国家和行业现行的建筑工程施工质量验收规范。

见下表主要法规3自然条件及环境条件✧环境特点:施工用各种材料运输采购已有保障,在组织施工时应按照有关市区施工管理规定进行施工。

✧工程特点:主体结构施工,对模板安装质量要求高,在施工中需加强对模板的制作、安装以及混凝土的浇筑、养护的管理,使结构混凝土外观质量达到清水混凝土的效果。

✧本工程施工期间将经过冬、雨季,现场需根据季节制定各项措施。

4工程概况该工程为郑煤集团朝阳沟煤矿副斜井井口房及灯房工程建设项目,其基础部分为钢筋砼条型基础、主体部分为砖混结构。

本工程建筑层数为一层,建筑高度为3.5米,长为26.64米,宽为8.24米,建筑面积219.51平方米。

内墙为混合砂浆抹灰,888仿瓷涂料批白。

结构材料情况:该副井口房基础采用天然地基,基础垫层砼强度等级为C10,现浇砼强度等级为C30。

基础以下M7.5水泥砂浆砌MU15蒸压粉煤灰砖,±0.000以上砌体为M10蒸压粉煤灰砖M10混合砂浆。

门窗:屋面:第二章施工说明1总体目标“诚信经营、塑造精品、顾客满意、保护环境、健康安全、持续改进”是我公司的管理方针。

为充分发挥我公司的综合优势和科学施工管理水平,以严密的管理,周密的计划,确保本工程以下目标实现:✧质量目标:达到“市优质结构”工程标准。

✧工期目标:根据我公司施工实力以及机械设备状况,有能力在44天内完成本工程的全部工作量。

✧安全施工目标:杜绝一切安全事故的发生及火灾发生。

✧文明施工目标:市级文明工地。

✧环保目标:采取有效措施,控制现场的种粉尘、废水、废气、固体废弃物以及噪声、振动等对环境的污染和危害。

确保施工期间不扰民、不影响城市道路及环境卫生。

✧科技进步目标:为实现上述工程质量、工期、安全文明施工、环保等目标,充分发挥科技是第一生产力的作用,在工程施工中,积极采用成熟的科技成果和现代化管理技术。

✧服务目标:接受业主、监理公司和省(市)质检部门对工程质量、工程进度、计划协调、现场管理的监督,信守合同,满足用户。

2施工说明✧根据施工平面布置进行临时设施的搭建,详见平面布置图。

✧模板制作、钢筋加工成型在施工现场内搭设作业工棚。

✧砼采用现场集中搅拌混凝土。

✧根据施工进程组建专业施工队。

在结构施工时,组建模板施工作业队、钢筋施工作业队、混凝土施工作业队、脚手架施工作业队、砌体施工作业队、安装作业队(配合管线予埋);在进入装修施工阶段时,组建粉刷作业队、防水作业队、安装工程专业施工作业队等。

3施工部署及总进度主要节点控制3.1总体施工原则为确保质量目标的工期目标的实现,针对本工程的特点,首先我们选用有同类工程施工经验的劳务队伍和管理人员:由我公司机关各专业工程师组成专家组,对方案进行研讨,制定切实可行的施工方案,确保工程顺利进行。

在装修材料选用上,实行货比三家,选用环保产品,同时在装修施工先做样板,经甲方监理认可后方可展开施工。

3.2总体施工程序及施工流水段划分本工程施工组织主导思想是:施工时采取“平面分段流水,立体穿插作业”的原则,结构施工中水、电等随土建施工做好预埋预留,装修施工中电气等设备安装随土建施工穿插作业。

外装修从上到下推进。

根据结构特点及施工任务量,分为一个施工段(检验批);具体分基础施工阶段、主体施工阶段,屋面施工阶段,装饰装修施工阶段,楼地面施工阶段。

3.3施工工期安排该工程总工期33天。

施工工期较短,多工种交叉配合复杂,是施工管理较为困难的阶段,因此必须要合理而科学地组织好交叉流水作业,以土建施工流水作业为主导时,装修做好配合工作。

当土建作业完成后,以装修为主导时,土建做好配合工作,按照施工先后顺序将工程分为四个阶段施工:第Ⅰ阶段:基坑开挖,工期5天。

第Ⅱ阶段:主体施工阶段,工期20天。

第Ⅲ阶段:装修配合阶段,工期8天。

因雨、大风、高热天气、事件、事故等人力不可抗拒因素,及设计变更、专业(特殊)工序插入配合、分包(装饰)工程、资金、材料、停水、停电等因素,工期顺延。

第三章主要施工办法1施工准备1.1技术准备✧熟悉和审查施工图纸。

组织各部门人员学科和审查施工图纸,领会设计意图,掌握工程建筑和结构的形式和特点,复核各主要尺寸及需要采用的新技术,同时审查建筑设备及加工定货有何特殊要求,对于设计中的不详之处及疑难点,积极与建设、监理、设计单位沟通、并提前作出解决。

✧提前编制施工组织设计、施工方案和技术交底。

针对特殊部位、施工难点部位专门成立QC小组,对特殊过程编制作业指导书,逐级进行技术交底,指导实际施工。

✧组织所有技术人员认真学习规范、新规程,积极推广应用建设部推广的新技术、积极学习、吸收国内外的先进施工经验,充分利用已有先进的技术,提高工程施工的科技含量。

✧组织相关人员认真学习监理规程,积极配合好监理单位的工作,保证各项工作的有序进行。

✧现场试验室在开工前做好原材料资源调查,对于所选用的材料作好复试和试验工作,同时做好各项见证取样试验。

✧钢筋、模板的预加工及半成品、构件的订购工作。

1.2现场准备1.2.1拆除现场障碍物进行场地平整,保证“三通一平”,并对现场周边毗邻的厂区道路、厂区设施和建筑物状况时行检查,做好有关情况记录,制定保护措施,对于甲方提供的各种地下管线,作好布置图并予以标识。

1.2.2立平面控制网根据给定永久性坐标和高程,按照总平面图的要求,进行控制测量,设立场区控制桩位,并做好保护措施。

1.2.3临设准备(详见施工现场平面布置图)1.3季节性施工准备冬季及高温天气施工提前做好现场场地及临时设施的施工准备工作,提前按有关方案认真落实各项设施和技术组织措施。

(详见冬、雨季施工措施)1.4其它准备1.4.1建立周边环境关系的联系渠道,确保施工现场运转。

1.4.2加强现场安全保卫系统,建立并完善进出门制度,设置安全生产标牌。

1.4.3加强现场通讯联络,以随时掌握工程现状,便于生产组织。

2各施工过程的施工顺序(1)基础工程施工工艺:场地平整→定位放线→基坑开挖→灰土垫层→混凝土垫层→条型基础(独立基础)→回填土。

(2)主体工程放线→柱钢筋→砖砌体→柱模板→梁模板→梁钢筋绑扎(水电配合)→浇筑砼→养护、拆模;(3)装饰工程✧内粉刷:浇水湿润基层→找规矩、做灰饼→设置标筋→阳角做护角→结合层→抹底层、中层灰→抹窗台板、踢脚板(或墙裙)→抹面层灰→清理。

✧楼地面:抄水平线→贴灰饼冲筋→扫浆→抹找平层→弹线排砖→铺贴→擦缝。

(4)屋面防水工程基层处理→做灰饼→找坡层→找平层→保温层→卷材防水层→保护层施工。

3分部、分项工程主要施工过程的施工方法4.1冬季施工措施详见各分部、分项工程施工方案。

✧在冬季施工时要有专人收听天气预报,合理调整顺序,现场水管、现场水箱等进行保温防冻,现场道路、脚手、钢平台等应及时清除积水、冰雪、采取防滑措施,冬季施工工地上要备齐防寒保温材料。

相关文档
最新文档