英文码率控制论文3

合集下载

关于PLC的英文文献Word版

关于PLC的英文文献Word版

1. PROGRAMMABLE LOGIC CONTROLLERS1.1 INTRODUCTIONControl engineering has evolved over time. In the past humans was the main method for controlling a system. More recently electricity has been used for control and early electrical control was based on relays. These relays allow power to be switched on and off without a mechanical switch. It is common to use relays to make simple logical control decisions. The development of low cost computer has brought the most recent revolution, the Programmable Logic Controller (PLC). The advent of the PLC began in the 1970s, and has become the most common choice for manufacturing controls. PLC have been gaining popularity on the factory floor and will probably remain predominant for some time to come. Most of this is because of the advantages they offer.. Cost effective for controlling complex systems.. Flexible and can be reapplied to control other systems quickly and easily.. Computational abilities allow more sophisticated control.. Trouble shooting aids make programming easier and reduce downtime. . Reliable components make these likely to operate for years before failure.1.2 Ladder LogicLadder logic is the main programming method used for PLC. As mentioned before, ladder logic has been developed to mimic relay logic. The decision to use the relay logic diagrams was a strategic one. By selecting ladder logic as the main programming method, the amount of retraining needed for engineers and trades people was greatly reduced. Modern control systems still include relays, but these are rarely used for logic.A relay is a simple device that uses a magnetic field to control a switch, as pictured in Figure 2.1. When a voltage is applied to the input coil, the resulting current creates a magnetic field. The magnetic field pullsa metal switch (or reed) towards it and the contacts touch, closing the switch. The contact that closes when the coil is energized is called normally open. The normally closed contacts touch when the input coil is not energized. Relays are normally drawn in schematic form using a circle to represent the input coil. The output contacts are shown with two parallel lines. Normally open contacts are shown as two lines, and will be open (non-conducting) when the input is not energized. Normally closed contacts are shown with two lines with a diagonal line through them. When the input coil is not energized the normally closed contactswill be closed (conducting).Relays are used to let one power source close a switch for another (often high current) power source, while keeping them isolated. An example of a relay in a simple control application is shown in Figure 2.2. In this system the first relay on the left is used as normally closed, and will allow current to flow until a voltage is applied to the input A. The second relay is normally open and will not allow current to flow until a voltage is applied to the input B. If current is flowing through the first two relays then current will flow through the coil in the third relay, and close the switch for output C. This circuit would normally be drawn in the ladder logic form. This can be read logically as C will be on if A is off and B is on.1.3 ProgrammingThe first PLC were programmed with a technique that was based on relay logic wiring schematics. This eliminated the need to teach the electricians, technicians and engineers how to program a computer - but, this method has stuck and it is the most common technique for programming PLC today. An example of ladder logic can be seen in Figure 2.5. To interpret this diagram imagines that the power is on the vertical line on the left hand side, we call this the hot rail. On the right hand side is the neutral rail. In the figure there are two rungs, and on each rung there are combinations of inputs (two vertical lines) and outputs (circles). If the inputs are opened or closed in the right combination the power can flow from the hot rail, through the inputs, to power the outputs, and finally to the neutral rail. An input can come from a sensor, switch, or any other type of sensor. An output will be some device outside the PLC that is switched on or off, such as lights or motors. In the toprung the contacts are normally open and normally closed, which means if input A is on and input B is off, then power will flow through the output and activate it. Any other combinationof input values will result in the output X being off.The second rung of Figure 2.5 is more complex, there are actually multiple combinations of inputs that will result in the output Y turning on. On the left most part of the rung, power could flow through the top if C is off and D is on. Power could also (and simultaneously) flow through the bottom if both E and F are true. This would get power half way across the rung, and then if G or H is true the power will be delivered to output Y. In later chapters we will examine how to interpret and construct these diagrams. There are other methods for programming PLC. One of the earliest techniques involved mnemonic instructions. These instructions can be derived directly from the ladder logic diagrams and entered into the PLC through a simple programming terminal. An example of mnemonics is shown in Figure 2.6. In this example the instructions are read one line at a time from top to bottom. The first line 00000 has the instruction LDN (input load and not) for input 00001. This will examine the inputto the PLC and if it is off it will remember a 1 (or true), if it is on it will remember a 0 (or false). The next line uses an LD (input load) statement to look at the input. If the input is off it remembers a 0, if the input is on it remembers a 1 (note: this is the reverse of the LD). TheAND statement recalls the last two numbers remembered and if they are both true the result is a 1; otherwise the result is a 0. This result now replaces the two numbers that were recalled, and there is only one number remembered. The process is repeated for lines 00003 and 00004, but when these are done there are now three numbers remembered. The oldest number is from the AND, the newer numbers are from the two LD instructions. The AND in line 00005 combines the results from the last LD instructions and now there are two numbers remembered. The OR instruction takes the two numbers now remaining and if either one is a 1 the result is a 1, otherwise the result is a 0. This result replaces the two numbers, and there is now a single number there. The last instruction is the ST (store output) that will look at the last value stored and if it is 1, the output will be turned on; if it is 0 the output will be turned off.The ladder logic program in Figure 2.6, is equivalent to the mnemonic program. Even if you have programmed a PLC with ladder logic, it will be converted to mnemonic form before being used by the PLC. In the past mnemonic programming was the most common, but now it is uncommon for users to even see mnemonic programs.Sequential Function Charts (SFC) have been developed to accommodate the programming of more advanced systems. These are similar to flowcharts, but much more powerful. The example seen in Figure 2.7 is doing two different things. To read the chart, start at the top where is says start. Below this there is the double horizontal line that says follow both paths. As a result the PLC will start to follow the branch on the left and right hand sides separately and simultaneously. On the left there are two functions the first one is the power up function. This function will run until it decides it is done, and the power down function will come after. On the right hand side is the flash function; this will run until it is done. These functions look unexplained, but each function, such as power up will be a small ladder logic program. This method is much different from flowcharts because it does not have to follow a single path through the flowchart.Structured Text programming has been developed as a more modern programming language. It is quite similar to languages such as BASIC.A simple example is shown in Figure 2.8. This example uses a PLC memory location N7:0. This memory location is for an integer, as will be explained later in the book. The first line of the program sets the value to 0. The next line begins a loop, and will be where the loop returns to. The next line recalls the value in location N7:0, adds 1 to it and returns it to the same location. The next line checks to see if the loop should quit. If N7:0 is greater than or equal to 10, then the loop will quit, otherwise the computer will go back up to the REPEAT statement continue from there. Each time the program goes through this loop N7:0 will increase by 1 until the value reaches 10.N7:0 := 0;REPEATN7:0 := N7:0 + 1;UNTIL N7:0 >= 10END_REPEAT;2. PLC ConnectionsWhen a process is controlled by a PLC it uses inputs from sensors to make decisions and update outputs to drive actuators, as shown in Figure 2.9. The process is a real process that will change over time. Actuators will drive the system to new states (or modes of operation). This means that the controller is limited by the sensors available, if an input is not available, the controller will have no way to detect a condition.The control loop is a continuous cycle of the PLC reading inputs, solving the ladder logic, and then changing the outputs. Like any computer this does not happen instantly. Figure 2.10 shows the basic operation cycle of a PLC. When power is turned on initially the PLC does a quick sanity check to ensure that the hardware is working properly. If there is a problem the PLC will halt and indicate there is an error. For example, if the PLC backup battery is low and power was lost, the memory will be corrupt and this will result in a fault. If the PLC passes the sanity checks it will then scan (read) all the inputs. After the inputs values are stored in memory the ladder logic will be scanned (solved) using the stored values - not the current values. This is done to prevent logic problems when inputs change during the ladder logic scan. When the ladder logic scan is complete the outputs will be scanned (the output values will be changed). After this the system goes back to do a sanity check, and the loop continues indefinitely. Unlike normal computers, the entire program will be run every scan. Typical times for each of the stages are in the order of milliseconds.3. SUMMARY. Normally open and closed contacts.. Relays and their relationship to ladder logic.. PLC outputs can be inputs, as shown by the seal in circuit.. Programming can be done with ladder logic, mnemonics, SFC, and structured text.. There are multiple ways to write a PLC program.(注:可编辑下载,若有不当之处,请指正,谢谢!)。

码率控制策略对视频剪辑效果的影响研究

码率控制策略对视频剪辑效果的影响研究

码率控制策略对视频剪辑效果的影响研究随着互联网的快速发展和带宽的提升,视频播放成为互联网上最受欢迎的媒体形式之一。

为了满足用户对高质量视频的需求,视频剪辑制作变得越来越重要。

然而,视频剪辑的过程涉及到码率控制策略,这对于最终生成的视频效果有着重要的影响。

本文将探讨不同码率控制策略对视频剪辑效果的影响,并提出相应的研究结果和建议。

1. 码率控制策略简介码率控制策略是指在视频编码过程中,通过控制单位时间内所需要的码率大小,来达到平衡视频质量和带宽消耗之间的关系。

常见的码率控制策略包括恒定码率(Constant Bit Rate,CBR)、可变码率(Variable Bit Rate,VBR)和恒定质量(Constant Quality,CQ)。

2. 码率控制策略与视频剪辑的关系视频剪辑通常涉及到对视频中的不同部分进行处理和编辑,这会导致码率需求的变化。

不同的码率控制策略会对视频剪辑效果产生不同的影响,影响体现在视频质量、播放流畅性和文件大小等方面。

2.1 视频质量恒定码率策略在剪辑过程中可能会导致某些部分质量较差,而其他部分质量较好,导致视频质量不均衡。

可变码率策略能够根据不同区域的复杂性和运动情况,灵活调整码率,从而保证整个视频质量相对均衡。

恒定质量策略则更加注重保持视频的一致质量,无论剪辑区域的复杂度。

2.2 播放流畅性恒定码率策略容易导致码率过高或过低的情况,过高可能导致播放卡顿,过低则可能导致视频质量下降。

可变码率策略能够根据剪辑区域的复杂度和运动情况,灵活调整码率,从而保证播放的流畅性。

恒定质量策略则会根据视频内容的复杂性和细节进行自适应调整,以确保流畅播放。

2.3 文件大小不同码率控制策略会对生成的视频文件大小产生影响。

恒定码率策略生成的视频文件大小相对稳定,但可能存在空间浪费或者码率不足导致质量损失的问题。

可变码率策略会根据剪辑区域的复杂度和动态性调整码率,从而使生成的视频文件大小更加紧凑。

HEVC码率控制浅析——HM代码阅读之一

HEVC码率控制浅析——HM代码阅读之一

HEVC码率控制浅析——HM代码阅读之一注:本篇博客大部分内容转载于下面的链接,转载过来之后,我根据原文对博客部分内容做了更改和批注。

博客原文地址如下:/hevc_cjl/article/details/10982699HM的码率控制提案主要参考如下三篇:K0103,M0036,M0257。

本文及后续文章将基于HM12.0进行讨论,且首先仅讨论K0103对应的代码,之后再陆续补充M0036,M0257对应的代码分析,这么做可能会使得剧情不会显得那么地跳跃,分析起来能够更好地被接受。

按照我的个人习惯,还是先分析HM中码率控制部分(以后简称RC)的总体框架吧。

跟RC有关的头文件和源文件为工程TLibEncoder中的TEncRateCtrl.h和TEncRateCtrl.cpp,其余的地方都是调用这两个文件中定义的函数或者变量。

在最顶层,TEncT op这个类定义了成员变量TEncRateCtrl m_cRateCtrl,类TEncGOP,TEncSlice以及TEncCu也分别定义了成员变量TEncRateCtrl *m_pcRateCtrl,但是请注意,这三个类的m_pcRateCtrl实际上都是指向TEncTop这个类的m_cRateCtrl,即它们本质上是同一个。

这个从这三个类的成员函数init中对各成员变量的初始化可以看出来。

在主函数中调用:1.int main(int argc, char* argv[])2.{3.TAppEncT op cTAppEncTop;4.cTAppEncTop.create();5.// call encoding function6.cTAppEncTop.encode();7.}1.Void TAppEncT op::encode()2.{3.xCreateLib();//也是TAppEncTop的成员函数4.m_cTEncTop.encode();//为TEncTop的成员函数5.6.}1.Void TAppEncT op::xCreateLib()2.{3.m_cTEncTop.create();//m_cTEncTop 为TEncTop类型的成员变量4.}到此,才开始正式调用HEVC中码率控制的函数(1)初始化:首先,在TEncTop::create()中,对整个序列都要用到的相关参数进行初始化1.#if RATE_CONTROL_LAMBDA_DOMAIN2.if ( m_RCEnableRateControl )3.{4.m_cRateCtrl.init( m_framesToBeEncoded, m_RCTargetBitrate, m_iFrameRate, m_iGOPSize, m_iSourceWidth, m_iSourceHeight,5.g_uiMaxCUWidth, g_uiMaxCUHeight, m_RCKeepHierarchicalBit, m_RCUseLCUSeparateModel, m_GOPList );6.}7.#else8.m_cRateCtrl.create(getIntraPeriod(), getGOPSize(), getFrameRate(), getTargetBitrate(), getQP(),getNumLCUInUnit(), getSourceWidth(), getSourceHeight(), g_uiMaxCUWidth, g_uiMaxCUHeight);9.#endif其次,在TEncTop::encode()中,对整个GOP需要用到的相关参数进行初始化1.#if RATE_CONTROL_LAMBDA_DOMAIN2.if ( m_RCEnableRateControl )3.{4.m_cRateCtrl.initRCGOP( m_iNumPicRcvd );5.}6.#endif接着,在TEncGOP::compressGOP()中,对每一幅picture需要用到的相关参数进行初始化1.#if RATE_CONTROL_LAMBDA_DOMAIN2.Double lambda = 0.0;3.Int actualHeadBits = 0;4.Int actualTotalBits = 0;5.Int estimatedBits = 0;6.Int tmpBitsBeforeWriting = 0;7.if ( m_pcCfg->getUseRateCtrl() )8.{9.Int frameLevel = m_pcRateCtrl->getRCSeq()->getGOPID2Level( iGOPid );10.if ( pcPic->getSlice(0)->getSliceType() == I_SLICE )11.{12.frameLevel = 0;13.}14.m_pcRateCtrl->initRCPic( frameLevel ); //!<picture level 初始化15.estimatedBits = m_pcRateCtrl->getRCPic()->getTargetBits();16.17.Int sliceQP = m_pcCfg->getInitialQP();18.if( ( pcSlice->getPOC() == 0&& m_pcCfg->getInitialQP() > 0) || ( frameLevel == 0&& m_pcCfg->getForceIntraQP() ) ) // QP is specified19.{20.Int NumberBFrames = ( m_pcCfg->getGOPSize() - 1 );21.Double dLambda_scale = 1.0- Clip3( 0.0, 0.5, 0.05*(Double)NumberBFrames );22.Double dQPFactor = 0.57*dLambda_scale;23.Int SHIFT_QP = 12;24.Int bitdepth_luma_qp_scale = 0;25.Double qp_temp = (Double) sliceQP + bitdepth_luma_qp_scale - SHIFT_QP;mbda = dQPFactor*pow( 2.0, qp_temp/3.0 );27.}28.else if ( frameLevel == 0 ) // intra case, but use the model29.{30.#if RATE_CONTROL_INTRA31.m_pcSliceEncoder->calCostSliceI(pcPic);32.#endif33.if( m_pcCfg->getIntraPeriod() != 1) // do not refine allocated bits for all intra case34.{35.Int bits =m_pcRateCtrl->getRCSeq()->getLeftAverageBits();36.#if RATE_CONTROL_INTRA37.bits = m_pcRateCtrl->getRCPic()->getRefineBitsForIntra( bits );38.#else39.bits = m_pcRateCtrl->getRCSeq()->getRefineBitsForIntra( bits );40.#endif41.if ( bits < 200 )42.{43.bits = 200;44.}45.m_pcRateCtrl->getRCPic()->setTargetBits( bits );46.}47.48.list<TEncRCPic*> listPreviousPicture = m_pcRateCtrl->getPicList();49.#if RATE_CONTROL_INTRA50.m_pcRateCtrl->getRCPic()->getLCUInitTargetBits( );mbda = m_pcRateCtrl->getRCPic()->estimatePicLambda( listPreviousPi cture, pcSlice->getSliceType());52.#elsembda = m_pcRateCtrl->getRCPic()->estimatePicLambda( listPreviousPi cture );54.#endif55.sliceQP = m_pcRateCtrl->getRCPic()->estimatePicQP( lambda,listPreviousPicture );56.}57.else// normal case58.{59.list<TEncRCPic*> listPreviousPicture = m_pcRateCtrl->getPicList();60.#if RATE_CONTROL_INTRAmbda = m_pcRateCtrl->getRCPic()->estimatePicLambda( listPreviousPi cture, pcSlice->getSliceType());62.#elsembda = m_pcRateCtrl->getRCPic()->estimatePicLambda( listPreviousPi cture );64.#endif65.sliceQP = m_pcRateCtrl->getRCPic()->estimatePicQP( lambda, listPreviousPicture );66.}67.68.sliceQP = Clip3( -pcSlice->getSPS()->getQpBDOffsetY(), MAX_QP, sliceQP );69.m_pcRateCtrl->getRCPic()->setPicEstQP( sliceQP );70.71.m_pcSliceEncoder->resetQP( pcPic, sliceQP, lambda );72.}73.#endif最后,在TEncSlice::compressSlice()中,对每一个LCU需要用到的相关参数进行初始化:1.#if RATE_CONTROL_LAMBDA_DOMAIN2.Double oldLambda = m_pcRdCost->getLambda();3.if ( m_pcCfg->getUseRateCtrl() )4.{5.Int estQP = pcSlice->getSliceQp();6.Double estLambda = -1.0;7.Double bpp = -1.0;8.9.#if M0036_RC_IMPROVEMENT10.if( ( rpcPic->getSlice( 0)->getSliceType() == I_SLICE && m_pcCfg->getForceIntraQP() ) || !m_pcCfg->getLCULevelRC() )11.#else12.if( rpcPic->getSlice( 0)->getSliceType() == I_SLICE || !m_pcCfg->getLCULevelRC() )13.#endif14.{15.estQP = pcSlice->getSliceQp();16.}17.else18.{19.#if RATE_CONTROL_INTRA20.bpp = m_pcRateCtrl->getRCPic()->getLCUT argetBpp(pcSlice->getSli ceType());21.if( rpcPic->getSlice( 0)->getSliceType() == I_SLICE)22.{23.estLambda =m_pcRateCtrl->getRCPic()->getLCUEstLambdaAndQP(bpp, pcSlice->getSliceQp(), &estQP);24.}25.else26.{27.estLambda = m_pcRateCtrl->getRCPic()->getLCUEstLambda( bpp );28.estQP = m_pcRateCtrl->getRCPic()->getLCUEstQP ( estLambda, pcSlice->getSliceQp() );29.}30.#else31.bpp = m_pcRateCtrl->getRCPic()->getLCUT argetBpp();32.estLambda = m_pcRateCtrl->getRCPic()->getLCUEstLambda( bpp );33.estQP = m_pcRateCtrl->getRCPic()->getLCUEstQP ( estLambda, pcSlice->getSliceQp() );34.#endif35.36.estQP = Clip3( -pcSlice->getSPS()->getQpBDOffsetY(), MAX_QP, estQP );37.38.m_pcRdCost->setLambda(estLambda);39.#if M0036_RC_IMPROVEMENT40.#if RDOQ_CHROMA_LAMBDA41.// set lambda for RDOQ42.Doubleweight=m_pcRdCost->getChromaWeight();43.m_pcTrQuant->setLambda( estLambda, estLambda / weight );44.#else45.m_pcTrQuant->setLambda( estLambda );46.#endif47.#endif48.}49.50.m_pcRateCtrl->setRCQP( estQP );51.pcCU->getSlice()->setSliceQpBase( estQP );52.}53.#endif(2)参数值更新:首先,在TEncSlice::compressSlice中,每编码完一个LCU,进行一次更新:1.#if TICKET_1090_FIX2.#if RATE_CONTROL_LAMBDA_DOMAIN3.if ( m_pcCfg->getUseRateCtrl() )4.{5.#if !M0036_RC_IMPROVEMENT6.UInt SAD = m_pcCuEncoder->getLCUPredictionSAD();7.Int height = min( pcSlice->getSPS()->getMaxCUHeight(),pcSlice->getSPS() ->getPicHeightInLumaSamples() - uiCUAddr / rpcPic->getFrameWidthInCU() * pcSlice->getSPS()->getMaxCUHeight() );8.Int width = min( pcSlice->getSPS()->getMaxCUWidth(),pcSlice->getSPS()->getPicWidthInLumaSamples() - uiCUAddr % rpcPic->getFrameWidthInCU() * pcSlice->getSPS()->getMaxCUWidth() );9.Double MAD = (Double)SAD / (Double)(height * width);10.MAD = MAD * MAD;11.( m_pcRateCtrl->getRCPic()->getLCU(uiCUAddr) ). m_MAD = MAD; //!< 注意:此处的MAD已经进行过K0103中公式的两个处理了。

基于场景切换的码率控制方法

基于场景切换的码率控制方法
MAD 只 有 在 RD O 后 才能 计 算 出。 因 此 H . 2 6 4 中 采 用的 码 率控 制 算法 采用 了 R- D 优 化模式判别,在控制的流程中依次根据之
前的参考帧来预测得到当前编码帧的复杂 度 MAD 值 。 而 发生 场 景 切 换的 帧 , 由 于 前 后帧的复杂度可能完全无关,仍采用原有
3 比特预分配 H. 2 6 4 编码 器采 用了 分层 编 码的 方式 ,
将 整 个 视频 序 列 分成 GO P 、 帧 及基 本 单 元 三层,并对每层采用了不同的比特分配策 略。帧 层比特分配如下 :
科技资讯 200 8 NO. 03 S CI ENCE & TECHNOLOGY I NF ORMATI ON 基于场景切换的码率控制方法
IT 技 术
王 红玉 1 管鑫 2 周洪敏 3 ( 1 南京邮电大学通达学 院 江苏南京 21 00 03; 2 中国人民武装 警察部队江苏省总队 通信站 江苏南京 21 00 03 ;
关键词:H. 26 4 码率 控制 MAD RDO 场景 切换
中图分类号:TN9 19 . 8 1
文献 标识码:A
文章 编号:16 72 - 3 79 1( 20 0 8) 01 ( c ) - 00 96 - 02
1 引言 在视频编码中,码率控制起了非常重
要的作用。一般来讲,码率控制算法的实 现主要分为两个部分:第一是合理地分配 比特 ,第二是实 现所分配的 比特。然而 ,
码率控制算法并未考虑发生场景切换时造 成 的 失 真 , 如 果 场 景 切 换 , 这 就 破坏 了 码 率 控制 的系 统流 ,导 致了 视 频质 量的 下
降 。 因 此 , 场 景 切 换 检 测 和 适 当 的码 率 控 制 是有 必要 的[ 1~6] 。

外文文献原稿及译文

外文文献原稿及译文

外文文献原稿和译文PLCs)About Programmable LogiccontrollersPLCs (programmable controller) is used in a variety of automatic control system and process control contain multiple input and output, input and output is used to transistors and other circuit, analog switch and relay to controlthe software interface, standard calculator interface, specialized language programming and network equipment.Programmable logic controller I/O channel rules including all input output contact and contact, to expand capacity and the largest number of number is the sumof input and output can specify any combination of these units can be stack or connected to each other to increase the total largest number of channels are in an extension system, the total number of maximum input and output system rules include scanning time, number of instructions, data storage and storage time is used to monitor input and output module of PLC need operationinstruction is used in PLC storage is the ability to store memory is theability to control software.Used for programmable controller input devices including DC, AC, intermediate relay, thermocouple, RTD, frequency or pulse, transistors and interrupt signal input;Output devices include DC, AC, intermediate relay, frequency or pulse, transistor, three-terminal two-way thyristor switch components;PLC programming equipment including control panel, handle and computer.Programmable control is used to control a variety of software programming languages including iec61131-3, sequential table (SFC), action block diagram (FBD), ladder diagram (LD), and the structure of the text (ST), instruction sequences (IL), relay ladder diagram (RIL), flow charts, C language and Basic programming environment can support five languages, with international standards to regulate, SFC, respectively,FBD, LD, ST and allows more vendor compatibility and a variety of is a kind of graph language, it provides the programming in order to cooperate, can support the order selection and tied for choice, to choose betweenFBD with a big, established the complicated process, in the form of mathematical and logical operation can be combined with user interaction and interface is suitable for discrete control and interlock logic diagram is fully compatible with FBD on discrete is a kind of text language, used for complex mathematical and computational process, language is not applicable to issimilar to the combination of coding low-level is used in relatively simple logical ladder diagram and ladder diagram is used for programmable controller is an important programming diagram programming is designed to relay logic diagram representation of the chart is a graphic language, for use in a controller or operations described in the order of application software, it is used to establish a standard component of recycled language is ahigh-level programming language, suitable for processing the most complicated calculation, a continuous data acquisition typicallyrun in PC language is used to handle the number of consecutive data acquisition and interface operation of high-level language.Programmable controller also specification of many computer interface equipment, network rules and energy equipment and running environment is also very important.The development history of programmable controllerIn 1968, general motors (GM), according to the needs of the development of the market situation and put forward the "many varieties, small batch, new car brand model" implement this strategy, relying on the original industrialcontrol device obviously not, and there must bea kind of new industrial control device, it can be with the change of the products, flexible and easily change control scheme to difficult to meet the different requirements of control.In 1969, the famous American digital equipment corporation (DEC) according to the function requirements of GM,developed the newindustrial control device, and the GMof a vehicle to run automated production line for the first time to to this new type of industrial control devices can be programmed to change control scheme this characteristic, and the situation of the specialized for Logic control, says the new industrial control device for the Programmable control (Programmable Logic Controller), hereinafter referred to as PLC.From 1968 to now, the PLC has experienced four generation: most of the first generation of PLC with a machine development, with the core memory storage, only the logic control the second generation of PLC products for 8-bit microprocessor and semiconductor memory, PLC product third generation of PLCproduct with high performance microprocessor and chip is used in greatquantities in the PLCCPU,PLCspeed greatly improved, thus enabling it to develop in the direction of multi-function communications and fourth generation of PLC products not only comprehensive use 16-bit and 32-bit high-performance microprocessors, high-performance slice microcontroller processor, RISC(Reduced instruction set computer) Reduced instruction system CPU and other advanced CPU, and more than one processor in a PLC configuration,multi-channel produced a large number of embeddedmicroprocessor only makesthe fourth generation of PLCproduct has the function of control, process control, motion control, data control, networked functionsreally worthy of the name of multi-functional the same time, the PLC network composed of PLC has also been rapid and industrial control ofPLCnetwork in factory enterprises becomethe preferred composedofPLCmulti-stage distributed PLCnetwork becomeindispensable fundamentalpart of CIMS spoke highly of the importance of PLC and its network, it is one of the three pillars of modern. Selecting machine modelMarket popular PLCproducts manufacturer in China with the followingcompanies:(1) schneider company, including the introduction of early fromModicon company by the tianjin instrument instrument and meter plant products, products are now Quantum, Premium and Momentum;(2) rockwell company (including AB company) PLC products, products are now SLC and Micro Logix Control Logix etc.(3) of Siemens PLCproducts, products are now 400/300 / S7-200 series;(4) ge PLC products;(5) the company's products such as omron, mitsubishi, Fuji, panasonic, one of the most popular is the mitsubishi FX series.module, logical control device,The basic principle of PLCselection is: in the input/output quantity meet the requirements under the premise of should choose the most reliable, maintenance, and use the most convenient and cost-effective optimal products.Selecting I/OPLCis an industrial control system, the control object is industrial production equipment or the production process of industrial products, working environment is the industrial production connects the industrial production process is achieved by I/O interface has a lot ofI/O interface module including switch input module, the switch output module, analog input module and analog output module and special module, we should use according to the characteristics of their implementation options.(1)determine the number of input/outputAccording to the requirements of the control system, determinethe number of input/output required, should increase the spare quantity of 10% 20%, in order to increase control function in any time.(2)the switch quantity input/outputSwitch input/output interface and can take the signals fromthesensors and switches and control typical 24-240 - v acinput/outputsignals, 5-240 - v dc input/outputsignals.(3) the analoginput/outputAnalog input/output inte rface can accept the signal generated by the interfaces can be used to measure turnover rate, temperature and pressure,and thus to control the voltage or current output for theseinterfaces- 10-10 v, + 0 to 10 v, 4-20 ma, or 10 to 50ma.Some manufacturers on the PLC design special dedicated analog interface, so it can receive low level general, this interfacemodulecan be used to receive different types of thermocouple and RTDmixedsignal.(4) special functioninput/outputWhen selecting a PLC, user may faced some special types ofinput/output and somebecause of the location of the limited input/outputand fast response and frequency problem caused by the non standard input/,the user should consider whether to accept by the market or manufacturersto provide a special module, through a dedicated part of the moduleanddispose data, so as to reduce the use of the CPU, improve theefficiencyof the task processing, to minimize failure caused by high limit control.PLCstatusIn a PLC, the lack of keyboard and other input and output devicesis avery worthy of PLC front usually have a certain amount ofstatusindicatesthat:The start-up - as long as the PLC charged, it will be started.Program is running - this will indicate whether running or if no program isrunning.Error display - when PLChas a large hardware or software errors, itwillbe displayed.These lights are usually used for certain number of button will also be provided to the PLC most common button is a run/programming selectionswitch, when in keeping the state, it will be transferred to theprogramming;When the production status, it will be transferred to thePLC system almost no start closing switch or reset switch at the needs to be designed into the system the rest.The state of the PLC can also be ladder logic whether the program implemented is very commonfor the first time.'first scan input in ladder diagram by scanningfor the first time, will is right, and in the rest of the time when the scanning is this case, the PLC - 5 'first scan' address is' S2:1/14 '.According to the example of the logical relationship, the first scan will seal the 'light' until the 'clear' is the light will be start brighter in the PLC, but after the "clear" is launched, it will shut down and remain in the closed position.'first scan module is mentioned in the "first pass" module.PLC application domainAt homeand abroad at present, the PLC has been widely used in steel, petroleum, chemical, electric power, building materials, machinery manufacturing, automobile, textile, transportation, environmental protection and cultural industries with happiness and usage can be roughly divided into the following categories:(1)the switch quantity logic controlThis is the most basic, the most widely PLCapplications, it replaces the traditional relay circuit, realize logic control, sequence control, can be used for control of single equipment, also can be used in many machines and automatic assembly as injection molding machine, printing machine, stapler machinery, combined machine tool, grinding machine, packaging production line, plating production line, etc.(2)analog controlIn the process of industrial production, there are a lot of continuouschange, such as temperature, pressure, flow, liquid level and speed and so onare all order to make the programmable controller to deal with analog, mustimplement the analog quantity and digital quantity betweenA/D and D/A conversion module, the programmable controller for analog control.(3)motion controlPLC can be used in circular motion and linear motion controlmechanism configuration, early applied directly to switch the I/O module connection position sensors and actuators, now in general use special motion control as driving a stepper motor or servo motor of uniaxial or multi-axis position control world's major products almost all have motion control function of PLC manufacturers, widely used in all kinds of machinery, machine tools, robots, elevators, etc.(4)process controlProcess control is to point to the analog quantities such as temperature, pressure, flow rate of the closed loop industrial control computer, PLCcan prepare the all kinds of control algorithm procedures, complete the closed-loop control is generally be applied closed loop control system of the control and medium-sized PLC has PID module, at present manysmall PLCalso has the function processing is generally run special PID process control in metallurgy, chemical industry, heat treatment, boiler control occasions has wide application, etc.(5)the data processingModern PLC with mathematical operation, data transmission, data conversion, sorting, look-up table, a function, such as the operation can complete data collection, analysis, and data can be compared with the reference value of memory, accomplish a certain number of control operation, also can send to other intelligent device, the use of communication function or printing them processing is generally used in a large control system, such as unmannedcontrol of flexible manufacturing systems;Can also be used to process control system, such as paper making, metallurgy, food industry, some of the large control system.(6)communications and networkingPLC communication with the communication between PLC and the communication between PLC and other smart the development of computer control, factoryautomation network is growing fast, the PLC manufacturers have attached great importance to PLC communications functions, have launched their own network newly production PLC has a communication interface, communication is very convenient.PLC application field is still in the extension, in Japan, the application of PLC has been from the traditional industrial automatic control equipment and machinery, extended to the following areas of application: small and medium-sized process control system, remote maintenance service system, the energy conservation monitoring control system, and of the relation of living machines, relationship with the environment, and all have rapidly rising is important to note that withPLC, DSCmutual penetration, both the boundaries of an increasingly fuzzy, PLC applied to discrete manufacturing industry from the traditional to the applied to the continuous process industries to expand.译文PLC 介绍PLC (可编程控制器)是用于各种自动控制系统和过程的可控网络集线器。

关于控制的英语论文

关于控制的英语论文

de(t ) dt
(1)
1 In1
-Kkpn
1 Out1
-KG-asr
1 s I-asr
Fig.3. The simulation model of the ordinary PID controller
4. Fuzzy Controller Fuzzy control is a kind of computer intelligent control based on the fuzzy set theory, the fuzzy language variables and the fuzzy logic. The basic concept is proposed by the famous professor of the university L.A.Zadeh. After over 20 years’ development, it makes a great success in the fuzzy control theory. Fuzzy controller is also called Fuzzy Logic Controller. Because the fuzzy control rules are described by the fuzzy conditional statement of the fuzzy theory, it’s a kind of language controller, so it’s also called Fuzzy Language Controller.[4] The composition of the fuzzy controller is showed in Fig. 4:
-Kkpn Saturation

2015immc优秀论文3

2015immc优秀论文3

2015 IM2C Problem Movie SchedulingTeam 2015004Team # 20150042 / 44SummaryArranging a movie’s shooting schedule can mean a lot of hard work. Different actors and actresses have their own schedules, various resources need to be booked, and special restrictions of some scenes must be considered. In order to offer a satisfactory solution, we have developed a model capable of finding possible schedules and selecting several better schedules based on our clients’ preferences. We have also provided solutions that help our clients adjust their plan if an accident happens, as well as helping them identify the most important constraints that would most greatly affect their schedule if varied.In the first part of our model, we search the possible shooting schedules according to the information that our clients provided, which may include the available time periods of each actor, specific sites and special resources. We sort out the various available dates by scenes, and using a 0-1 matrix to represent the availability of each scene on each of possible shooting dates. We then use the backtracking method, which is commonly used in solving constraint satisfaction problems and combinatorial search, to find arrangements that satisfy each scene’s availability dates. Moreover, in order to further shorten the running time of our program, we pre-arranged the order of scenes, so that the scenes with the strictest restrictions would be considered first, enabling the program using the backtracking method to find more results more quickly.In the second part of our model, we consider other special restrictions requested (for example, the required order of some scenes) and the general preference of our clients. We filter the solutions drawn from the previous part (which could be up to 10000 solutions), by first deleting the deficient solutions based on special restrictions, and then arraying the remaining solutions from the best to the worst. Our model can calculate the total shooting schedule length, the frequency of location changes, and required number of studios in a solution. And along with the average cost to rent a studio, the intended frequency of flexible day, the total budget, and traffic budget of our clients, we can assess the general appropriateness1and some characteristics of a schedule, based on which we array the solutions and provide 11 top schedules to our clients. The solutions include 5 overall best solutions, 2 solutions with least number of location changes, 2 solutions with least number of studios2, and 2 solutions with least number of shooting days.Extending our model, we provide ways to adjust an original schedule to various accidents. When our clients provide us with information of the original schedule they selected, accidents occurred and new restrictions, we can return a new schedule with feasible adjustments. These adjustments are achieved by running the program with the new data while leaving intact the scenes that have already happened or that are not expected to change. In this way, the computational complexity would be greatly reduced and the new schedule would involve as few changes as possible. Lastly, we can also evaluate the most important constraints for our clients by calculating the differences in average characteristic value of top solutions before and after a constraint is changed. Having access to such information, our clients would be able to pay more attention to those important constraints and prevent major delays of their original shooting schedule.1We use the characteristic value to evaluate the appropriateness of a solution. For further explanation, please see 2.2, where we explain in detail how we calculate the characteristic value of a solution.2 Different settings cannot be constructed or shooting simultaneously at the same studio, so more than one studio may be required.Content1. Problem interpretation (4)1.1 Problem restatement (4)1.2 Assumptions and Justifications (4)1.3 The goal of modeling (5)2 Model (5)2.1 Overview of the model (5)2.2 Definition of variables (5)2.3 Relations between variables (8)2.4 Algorithm of finding all possible schedules (9)2.5 Algorithm of finding the best schedule (10)2.6 Adjustment for accidents (11)3 Programming Approach (11)3.1 Overview of the program (11)3.2 Introduction of the program (12)3.2.1 Inputs (12)3.2.2 Algorithm of finding (12)3.2.3 Algorithm of filtering (12)3.2.4 Outputs (13)4. Case Analysis (13)4.1 Overview of the case (13)4.1.1 Roles and the available times of their actors (13)4.1.2 Scenes (14)4.1.3 Available time of sites (15)4.1.4 Preparation time of settings (15)4.1.5 Restriction of specific orders (15)4.1.6 Other constraints (16)4.1.7 Other settings (16)4.2 Case solving (16)4.2.1 The optimal schedule (16)4.2.2 Schedule analysis (17)4.3 Adjustment for accidents (17)4.3.1 Assumed accidents (17)4.3.2 Adjustment realization (17)4.3.3 Results (18)5 The way of finding the most important constraints (19)5.1 Overview of the algorithm (19)5.2 Description of the algorithm (19)6 Reviews and Prospect (20)7 Reference Material (21)8 Appendix (22)1. Problem interpretation1.1 Problem restatementAs one of the major types of popular entertainment, motion picture has become a fast-growing industry. The constant demand for new excellent films makes effective filmmaking an important job. Therefore, it is necessary for every producer to develop a good filming schedule within certain constraints, such as the availability dates of stars and specific resources. We hope to use mathematical models to come up with this optimal schedule.1.2 Assumptions and Justifications1) The filming schedule has a limited time span whose starting point and ending point are both reachable.2) The filming schedule must conform to the following restrictions, which are inflexible and cannot be violated:i.The availability dates of some stars.ii.The availability dates of specific sites.iii.The availability dates for specific resources.iv.The time required to construct and film on a list of sets.v.Some scenes cannot be shot until after certain computer generated content is defined and other physical items are constructed.vi.Some scenes cannot be shot until other scenes are finished. For example, if a set is finally destroyed, all other scenes related to this set are supposed to be shot beforeit happens.vii.Extra time is needed for redoing some shots if they turn out to be inadequate after editing and review.viii.Extra time is needed for making up some delay or changes.ix.During the filming process, the director might decide to add some new scenes, which will influence the schedule.3) The schedule breaks down time into days for further allocation.‐Filming schedules always choose “Day” as their unit, which is pretty reasonable.First, it is small enough, because most scenes require one or several days to be shot.Second, it is still flexible, because in every single day small delays can becompensated by working overtime, and night shoots can be compensated by morerests in the daytime.4) Several scenes cannot be shot at the same time.‐Every time a scene is shot, the director must be present.5) The construction of sets does not interfere with the filming process.‐Workers can build the sets themselves without being monitored by the director.6) If multiple schedules are available, the studio will consider the continuity of locations.‐ Since the crews do not wish to move frequently, a small number of changes infilming locations is preferred.7) Since we can rent several filming studios, it is possible to build different settings at the same time. However, renting more filming studios will increase the cost, so we hope that these constructions do not conflict with each other.8) Although the crew may not work every day, we should pay for them as long as the shoot is not finished. Therefore, the whole time span is not likely to be too long.9) To deal with problems of delays and reshoots, the filming crews usually have a “flexible day” for every two weeks. On this “flexible day”, they can shoot the scenes that were not completely finished before. Each day without a shooting plan can be seen as a flexible day.1.3 The goal of modelingAccording to the assumptions given above, the optimal schedule derived from our model is an arrangement that:‐ satisfies all the inflexible restrictions in 2nd assumption;‐ promises relatively less changes in locations;‐ has relatively less conflicts in construction of different settings;‐ has an appropriate time span;‐ has enough flexible day for problems of delays and reshoots.In this model, we attempt to find a schedule that can excel in all these criteria.2 Model2.1 Overview of the modelThe whole model consists of two parts: “finding” solutions and “filtering” solutions. For each specific situation, our model first figures out all possible schedules, and then picks up the best ones among them. The model can also adjust previous schedules to deal with new accidents, such as delays in some aspects or changes in the availability of some assets.2.2 Definition of variablesIn order to build a reasonable model, we first introduced some variables:max T : The maximum time length of filming schedule, which is the difference between the latestdate and the earliest date appearing in the input sheets. A movie cannot be finished if the span of shooting schedule is longer than max T .min T : The minimum time length of filming schedule, which is the actual shooting time. k A : The personal schedule of actor k , which is a 0-1 array within the spread of max T . A ‘0’ as the n th element means that the actor cannot work on the n th day. Similarly, ‘1’ means the actor can join shooting on that day.l B : The availability dates of site l . We can simply regard a site as an actor, because toaccomplish a shooting task, we need both the actors and the sites available at the same time. If one element is unavailable, the shooting cannot be accomplished. Thus we describel B in the same way as that of k A ; that is, a 0-1 array with the length of max T . Additionally, we define B as the number of sites.m C : The availability dates of setting m . Similar to sites, a setting can be treated just like an actor. We define C as the number of the settings.n D : The availability dates of special resource n , such as a helicopter or a tank, which is only available at certain time intervals. Since resources also can be treated as actors, we use k A to record n D to simplify the model. We define A as the total number of actors and specialresources. (The reason why we do not combinel B and m C with k A is that information about sites and settings are required for other calculations in the “filtering” process.)o N : A set that records the time required (a.k.a. time length) to film scene o and the elements (e.g. actors, special resources, and a site or a setting) involved. o N cannot be an empty set; it has to contain at least one actor and one site or setting. Generally, its time length cannot be changed, which already contains a little flexible time for preparation and transportation. Moreover, we consider a scene the smallest part of shooting, which means that a scene cannot be divided. When all scenes are finished, the shooting task is done. We defineo N as the time length of this scene,which is an element of the set. i Q : A sequence showing a specific arrangement of all o N s. i Q is a time plan for all scenes. o N t : The number of possible ways to arrange scene o , regardless of arrangements of all otherscenes.i x : The actual shooting time length of i Q .*k A : An “Invisible actor” that has the same character as a real actor. We can use this idea to fulfill the special requirements, such as a specific scene that can be shot in several particular time intervals. This variable depends on requirements of the clients.p E : A special restriction p that i Q must conform to. For example, the restriction that 1Nmust be shot before2N are accomplished. This variable depends on requirements of the clients. P : A value between 0 and 1 that measures the ability of a schedule to deal with delays and reshoots. We define that in every 1P days, one flexible day is used to compensate delays and reshoots. Small delays or quick reshoots, which need only a few hours, can be adjusted on the very day it occurs, so that the whole schedule will not be affected. If delays or reshoots cost a longer time, we can resort remaining scenes into a new schedule. So that only when delays and reshoots need one day or several days, the flexible day in the 1P days is needed. P is an average value, which satisfies 01P £<. This variable depends on requirements of the clients.i K : The number of changes in sites or settings (a.k.a. location changes) that occur in an arrangement i Q .0K : The least possible number of location changes.i L : The number of required filming studios.i y : The extra number of i Q ’s location changes. Since we want to avoid unnecessary location changes, the smaller i y is, the better i Q is.i z : The extra number of filming studios that are required. We say that the more filming studios are used, the more money is spent, and the less efficient the schedule is.budget M : Total budget of the movie, which is given by our client.totaltraffic M : Total traffic budget of the movie, which is also decided by our client.itrafficpertime M : The average cost of a location change, which is the money spent on travelling andtransportation.studio M : The average cost of one studio, including the construction cost and art design cost. It is decided by client. h : The budget per day. This variable builds a connection between time and money, so that we can find the equivalent of a certain amount of money in some measure of time. However, it is just an estimation variable, time is always invaluable.i q : Penalty coefficient of i y (illustrated below).a : Penalty coefficient of i z (illustrated below).2.3 Relations between variables According to the definitions of these variables, we can come up with some basic relationships:min =o T N å (2.3-1)min max i T x T ££ (2.3-2)0=1K B C +- (2.3-3)0i i y K K =- (2.3-4)when 0i L ¹,1i i z L =-; when 0i L =, 0i z = (2.3-5)=i totaltraffic trafficpertime i M M K (2.3-6) min budgetM T h = (2.3-7)We believe that a large number of changes in locations are “bad” for a shooting schedule; too many filming studios are “bad”, too. In order to describe the how bad they are, we can transform their financial cost into time of equal value. So we have=itrafficperday i M q h(2.3-8) =studio M a h (2.3-9)Moreover, when the constraints are too loose, most of possible solutions will be far from optimal. To prevent this condition, we add another limit:max min 21T T P êú£êúêú+ëû(2.3-10) This means that max T cannot be too long. max T should be longer than min T by a period of time no more than min 2PT , or there will be too much idle time. Since too much idle time causes the increase of possible solutions, if the case holds false to the formula, we know that there are too many i Q s.2.4 Algorithm of finding all possible schedulesFinding possible schedules is a process of trial and error, which is meant to include both successes and failures. However, in order to reduce the mass of calculation, we hope to obtain all solutions with the least number of failures. To achieve this, we can determine the relatively inflexible times first, and leave the flexible ones for permutations later.Since o N t , the number of possible ways to arrange scene o (regardless of all other scenes), is anindication of o N ’s flexibility in time, we can arrange all o N s by ascending order of o N t{}*****1231,,,......,,q q N N N N N -This arrangement enables us to settle these scenes in an efficient order.Then we use backtracking algorithm to find all of i Q .In fact, the finding process is like finding all**1q N N path -s in a directed graph:First, we choose one *o N . Then we pick oneof the available choices of *1o N +. If wecannot find a *1o N +, which means that thechosen *o N is unfeasible, we will go backto the last order and find another *o N . Wewill continual to repeat this procedure untilwe get a complete **1q N N path -. Everytime we obtain a path, we record it and go back to the last order.Even though the crotches of tree are numerous and unknown, we have promised the least number of crotches by arranging o N by o N t . After reducing a large amount of computations, the newlyderived *o N is suitable for finding i Q .2.5 Algorithm of finding the best scheduleAfter all possible schedules are found, we need to evaluate each of them to find the top solutions. First, we have to follow the restrictions in E . If i Q does not accord with p E , it should be eliminated from our consideration.Second, we need to assess how good i Q is. In an optimal situation, we can assume a numerical relationship among several variables:min min i i i i x T y z T P q a ---» (2.5-1)i x is the whole time span of i Q , while min T is the real shooting time, and i q and a are the time spent on transportations and constructions. Therefore, the left side of the equation stands for the actual flexible time ready to deal with delays and reshoots, which is expected to be min PT Based on formula (11), we introduce a new index ()i S Q :min min min ()()=ln i i i i i T P x T y z S Q T Pq a ----() (2.5-2) The function ()i S Q , a characteristic value, indicates the superiority of each i Q . The less ()i S Q is, the more orderly i Q is, and the better the schedule is.In the best solution whose free time is just appropriate, min min ()=0i i i i T P x T y z q a ----, and ()-i S Q ®¥.If free time is too little, and flexible days are just enough to cover the penalty time (time spent on transportations and constructions) but not enough to compensate for delays and reshoots, we will have min ()0i i i i x T y z q a ---=, and ()0i S Q =.If free time is too much, and the time for delays and reshoots are twice as much as needed, we will have min min ()2T i i i i x T y z P q a ---=, the characteristic value ()i S Q also equals to 0. Eventhough the two cases above are different, they are both considered as mediocre choices, and their()i S Q values are the same.2.6 Adjustment for accidentsIf the clients encounter an accident that cannot be solved by existing flexible days (for example, significant delays in one aspect or the availability of some asset changes) during the filming process, we can provide a model for them to rearrange the future plan. The rearrangement can be achieved through a similar program, so they could quickly obtain the new schedule after changing some basic information and running the program.This adjustment is based on information in several aspects:1) The change in constraints (if any). For example, if the delay is caused by change in availability of an actor, a site or a resource, the new available time must be known.2) The present achievements. Since some tasks are already finished, the schedule before the present day cannot change anymore.3) The future dates that are hard to change. Some appointments with actors and specific resources (such as a helicopter) cannot be cancelled or changed, so the related scenes have to stay at the same date.After these information are entered, the program will add new constraints {}****123,,,......,r A A A A and the unchangeable scenes {}''''123,,,......,r N N N N (unchangeable scenes will be considered as “Invisible actors”, and the detailed procedure is discussed in 2.2) and give solution based on the new circumstances. Therefore, if these information are known, the program can provide an optimal future schedule for the clients when an accident happens.3 Programming Approach3.1 Overview of the programBased on our model, we developed a computer program that is capable of generating possible schedules as well as determining the priority of each schedules according to their characteristic values and sorting them by the priority in descending order.3.2 Introduction of the program3.2.1 InputsOur program contains a function that can read an Excel file so that it is very convenient for clients to input data. The Excel has 6 sheets which contain the information of actors, places, sets, scenes and two kinds of restrictions.The input function named ‘Read’ works by transferring information in Excel into four variables (Data form: double) named Ifm_Actors, Ifm_Places, Ifm_Sets, Ifm_Scenes and Cmd_Time.3.2.2 Algorithm of finding3.2.2.1 Preliminary filteringFirst of all, the program will check whether a possible solution exists. If there’s obviously no possible solution3, it will display an error and terminates the program.3.2.2.2 Estimation and tipsUse the formula (10) to determine whether the restrictions are too loose so that the quantity of possible schedules might be too large. If the case holds false to the formula, the program would display a warning.3.2.2.3 Searching for possible schedulesThe program generates 0-1 matrixes Ifm_Actors, Ifm_Places, Ifm_Sets and Ifm_Scenes with 1 representing available days and 0 representing occupied days. In this way we can figure out the intersection of available time by multiplying the correspondent row.Then, by rearranging the 0-1 matrix in order of the method that was mentioned in 2.4, the computational complicity is significantly reduced.Finally, we use the backtracking method to search for all possible schedules within the 0-1 matrix. Solutions are saved in variable All_Solutions (data form: cell).During the searching, if the number of solutions is too large, the program simply stops searching when 1000 solutions are recorded.3.2.3 Algorithm of filteringAfter generating all solutions, our program will follow time restrictions to delete those solutions that don’t fit in. Then, the program determines the changing times of places and sets, and calculates the characteristic values with function (12) to judge whether a solution is practical enough. The solutions are rearranged according to their characteristic values.3 For example, if the schedules of two actors who cooperate in a specific scene do not have intersection, the scene obviously cannot be shot.3.2.4 OutputsFinally, the output function of the program creates an Excel file and writes 11 possible scheduleswith the top priority in four different criteria. They include 5 overall best schedules, 2 scheduleswith least number of location changes, 2 schedules with least number of studios, and 2 scheduleswith least number of shooting days. In each schedule, scenes are arranged chronologically.4. Case Analysis4.1 Overview of the caseFor most movies, the detailed information about the preparing process are not open to public,which makes it hard to find a realistic case to test our model. However, we gathered some basicfacts about film shooting from internet and libraries, and used them to create a mostly reliable caseto test our model.This movie tells the stories of a group of physicists. It contains 18 roles, 9 sites, 11 settings, and 29 scenes. The studio wants the whole filming to be finished within 60 days. They also give some constraints, which are all displayed as below.4.1.1 Roles and the available times of their actorsThe following chart displays all the roles included in the film and the available dates of theiractors:Role Available dates of actorRydberg 13-14 Thomson 26-2824-25,29-30 Rutherford 1-5,29-30 Chadwick 4-5,Planck 11-12, 16-17, 23, 29-30Bohr 1-3,7,9,26-28, 34-35, 51-54Landau 21 Fermi 41-50 Oppenheimer 22, 41-47, 51-52Feynman 44-4734-35 Schrödinger 18-20,34-35 Compton 24-25,De Broglie 34-35, 40-60Einstein 6, 8, 16, 17, 21, 34-40Heisenberg 7-9, 23, 31-36, 53-60Dirac 31-35,51-52 Pauli 10,34-35 Born 10,19-20,34-35 4.1.2 ScenesThe following chart displays all the scenes in the film, the locations of and roles in them, and thetime needed to shoot them. There are two types of locations, sites and settings, which will bespecifically discussed in following paragraphs.Scene Location Roles Time(day)Solvay Conference Brussels Einstein, Bohr, Planck, Dirac,Born, Pauli, Schrödinger,Compton, De Broglie, Heisenberg2Experiment 1 Lab 1 Rydberg, Bohr 2 Experiment 2 The University of Manchester Rutherford, Bohr 3 Experiment 3 The University of Cambridge Thomson, Chadwick 3 Story 1 The University of Manchester Rutherford, Chadwick 2 Story 2 The University of Cambridge Rutherford, Einstein 2 Story 3 Humboldt University of Berlin Planck, Einstein 2 Story 4 Auditorium 1 Landau 1 Story 5 The University of Chicago Fermi, Oppenheimer, Feynman 4 Story 6 The University of Cambridge Dirac, Heisenberg 2 Story 7 Humboldt University of Berlin Schrödinger 1 Story 8 House 1 Einstein, Heisenberg 1 Story 9 House 2 Planck, Heisenberg 1 Story 10 Auditorium 2 Einstein 1 Story 11 Meeting room 1 Einstein 1 Experiment 4 University of Copenhagen Dirac, Bohr, Oppenheimer 2 Experiment 5 Lab 2 Compton, Rutherford 2 Story 12 Auditorium 2 Heisenberg, Bohr 1 Story 13 University of Copenhagen Heisenberg, Bohr 2 Story 14 University of Göttingen Pauli, Born 1 Experiment 6 Lab 3 Planck 2 Story 15 Meeting room 2 Heisenberg, Bohr 1 Story 16 Princeton University Einstein 2 Story 17 House 1 Einstein 2 Story 18 Humboldt University of Berlin Schrödinger, Born 2 Story 19 House 3 Oppenheimer 1 Story 20 Lab 4 Oppenheimer, Fermi 2 Story 21 National Library Fermi 3 Story 22 University of Copenhagen Heisenberg 24.1.3 Available time of sitesFor some specific reasons, a few sites cannot be shot all the time. The following chart displays theavailable dates of each site:date Place Available University of Copenhagen 50-60Humboldt University of Berlin 15-20Brussels 1-60 The University of Manchester 1-7The University of Cambridge 25-33The University of Chicago 44-60University of Göttingen 1-57Princeton University 1-42National Library 48-604.1.4 Preparation time of settingsThe time of preparation for settings is a determinant of the number of filming studios. Thefollowing chart displays this preparation time:time(day) Set PreparationHouse 1 4House 2 3House 3 6Meeting room 1 0Meeting room 2 0Lab 1 0Lab 2 0Lab 3 0Lab 4 0Auditorium 1 0Auditorium 2 0We assume in this way because compared to filming in meeting rooms, labs and auditoriums, it isharder to film in a realistic house (For example, a high filming position cannot be reached).Therefore, we must build some “houses” in the filming studio, which requires several days toprepare.4.1.5 Restriction of specific ordersThe studio also requires some specific orders of scenes to be shot:“Story 20” must go after “Experiment 1”.“Story 13” must go after “Experiment 5”, and “Experiment 5” must go after “Experiment 2”.。

H.264AVC论文:H.264AVC码率控制柯西分布统计模型场景切换

H.264AVC论文:H.264AVC码率控制柯西分布统计模型场景切换

H.264/AVC论文:H.264/AVC 码率控制柯西分布统计模型场景切换【中文摘要】码率控制技术是视频压缩编码的一项重要技术,它的作用是控制压缩视频的质量,使视频输出码流满足一定的传输和存贮要求。

在ITU-T和ISO/IEC共同制定的最新视频编码标准H.264中,率失真优化(RDO)模块被引入,作为选择合适的运动估计和宏块模式的依据。

然而,RDO的引入导致在码率控制过程中出现“蛋鸡悖论”,很多经典码率控制算法在H.264中不再适用。

虽然JVT-H017能较好地解决“蛋鸡悖论”,但其采用了不够精确的R-D模型,而且没有考虑场景切换带来的影响,因此需要做进一步的研究和改进。

本文在对现有的JVT-H017码率控制算法分析的基础上,研究了基于DCT系数统计分布的码率控制技术。

论文首先对柯西分布模型进行了深入的分析和研究,把柯西分布模型应用到H.264中,并对其R-D模型进行简化,提出了基于柯西率失真模型的H.264码率控制算法,并且对算法进行了详细地描述。

其次,论文在基于柯西分布的率失真模型基础上,对图像复杂度的预测方法加以改进。

由于在场景切换或运动剧烈的情况下,单独使用MAD预测图像的复杂度就会失效,因此本文引入了将PSNR因子和MAD联合的方法来改进图像复杂度预测,并通过实验仿真对新算法以及参考文献中的MADr atio算法进行了比较分析,结果表明,改进算法不仅获得更精确的码率控制,而且获得更平稳的输出码率和PSNR;最后,针对现有H.264码率控制算法不能适应场景切换的问题,本文提出了基于柯西率失真模型的简单有效的场景切换检测算法,利用实验统计的方法得出检测所需的阈值,并对有场景切换的序列进行了仿真实验,通过新算法与JVT-H017算法的实验结果比较证明,新算法具有较高的视频质量和较平稳的输出码流,而且其附加计算复杂度并不高,具有一定的实用价值。

【英文摘要】Rate control is an important technique of video compression encoding. Its role is to control the quality of compressed video and the output stream to satisfy certain requirements of the transmission or storage. H.264 is the newest video coding standard developed jointly by ITU-T and ISO/IEC, and R-D optimization is introduced in H.264 for selecting the appropriate mode of motion estimation and macro-block. However, this could cause a well known chicken and egg dilemma. Therefore, a lot of conventional rate control algorithms are not applicable in H.264. Although the JVT-H017 algorithm can solve the dilemma, the R-D model is not precise enough and do not consider the impact of scene change, so it requires further research and improvement.Based on the analysis of the rate control algorithms of JVT-H017, as well as the statistical distribution of the DCT coefficients, this thesis has made deep study the rate control. At first, Cauchy model has in-depth analysis and research and simplified Cauchy R-D model in H.264 , and then the algorithm was described indetails. Secondly, the thesis has study on the complexity of the image prediction method for further improvement based on Cauchy distribution R-D model. As the scene changes or a severe case of motion, the use of MAD prediction complexity of the image will fail, this thesis introduces the PSNR factor and MAD jointly to predict the image complexity method, and also the algorithms are given by simulations. The experimental results show that the new algorithm obtains precise and stable rate control compared with the MADr atio algorithm. Finally, take into account the existing H.264 rate control algorithm can not adapt the scene change problem, a simple and effective scene change detection algorithm is proposed based on Cauchy R-D model. The detection threshold was obtained by using statistical method, and a lot of scene change video sequences were tested. And also the experimental results proved that the new algorithm has higher video quality and more stable output stream compared with JVT-H017, and its additional computational complexity is not high and has practical application values.【关键词】H.264/AVC 码率控制柯西分布统计模型场景切换【英文关键词】H.264/AVC Rate control Cauchy distribution Statistical Model Scene Change【目录】基于统计模型的H.264码率控制技术研究摘要4-5Abstract5第一章绪论8-12 1.1 研究背景8 1.2 码率控制研究意义与目的8-9 1.3 国内外研究现状的概述9-10 1.4 本文的主要工作及内容安排10-12第二章H.264/AVC 编码技术与码率控制技术研究12-27 2.1 H.264/AVC 的结构及其关键技术12-16 2.1.1 H.264/AVC 的结构12-13 2.1.2 帧内编码13-14 2.1.3 帧间预测14-15 2.1.4 去方块滤波15-16 2.1.5 自适应熵编码16 2.2 码率控制的基本原理及其关键技术16-19 2.2.1 码率控制的基本原理16-17 2.2.2 率失真理论17-18 2.2.3 编码参数对码率控制的影响18-19 2.3 H.264 JVT-H017 的码率控制算法19-24 2.3.1 GOP 层码率控制21 2.3.2 帧层码率控制21-23 2.3.3 基本单元层码率控制23-24 2.4 H.264 中的其他码率控制算法24-26 2.4.1 基于ρ域模型的码率控制24-25 2.4.2 基于MAD_(ratio)的H.264 码率控制25-26 2.5 本章小结26-27第三章 Cauchy 率失真模型的分析与研究27-35 3.1 常见信源率失真模型分析与比较27-28 3.2 DCT 系数分布模型与Cauchy 模型的引入28-31 3.3 基于Cauchy 分布率失真模型分析31-34 3.3.1 基于Cauchy 分布的码率模型32-34 3.3.2 基于Cauchy 分布的失真模型34 3.4 本章小结34-35第四章基于Cauchy 模型的图像复杂度预测算法35-44 4.1 H.264 码率控制的存在的问题35-36 4.2 基于 Cauchy 模型的H.264 码率控制算法36-40 4.2.1 基于Lagrange 率失真优化36 4.2.2 GOP 层比特分配36-38 4.2.3 帧层比特分配38-39 4.2.4 宏块层比特分配39-40 4.3 基于图像复杂度的H.264 码率控制算法40-43 4.3.1 基于PSNR 差值比率和MAD 比率联合预测图像复杂度40-41 4.3.2 改进的目标比特分配及量化参数的调整41-43 4.4 本章小结43-44第五章基于Cauchy 模型的场景切换检测改进算法44-50 5.1 场景切换的简介和检测方法44-46 5.2 H.264 中场景切换对编码的影响46-47 5.3 基于Cauchy 模型的H.264 场景切换的检测和处理47-49 5.3.1 场景切换检测改进算法47-48 5.3.2 比特分配算法的改进48-49 5.4 本章小结49-50第六章实验结果与分析50-69 6.1 基于Cauchy 模型的码率控制系统框架及实验平台50-51 6.2 图像复杂度预测改进算法仿真结果与分析51-63 6.3 场景切换检测改进算法仿真结果与分析63-68 6.4本章小结68-69第七章总结与展望69-717.1 本文研究总结697.2 研究展望69-71参考文献71-74致谢74-75攻读硕士学位期间发表的论文75【采买全文】1.3.9.9.38.8.4.8 1.3.8.1.13.7.2.1 同时提供论文写作一对一辅导和论文发表服务.保过包发.【说明】本文仅为中国学术文献总库合作提供,无涉版权。

媒体控制英语作文模板

媒体控制英语作文模板

媒体控制英语作文模板Title: The Influence of Media Control: An English Essay Template。

Introduction:In today's interconnected world, the media holds significant power in shaping public opinion and influencing societal norms. However, this power can sometimes be wielded in ways that raise concerns about media control and its implications. This essay will explore the concept of media control, its effects on society, and potential strategies to address it.Thesis Statement:Media control, whether exercised by governments, corporations, or other entities, poses a threat to freedom of expression, diversity of viewpoints, and the integrity of information dissemination.Body Paragraph 1: Definition and Forms of Media Control。

Media control encompasses various tactics used to manipulate or influence the content and distribution of information. This includes censorship, propaganda, monopolistic ownership of media outlets, and manipulationof algorithms on digital platforms.Body Paragraph 2: Impact on Freedom of Expression。

[原创]matlab英文论文

[原创]matlab英文论文

Transient Stability of a power system with SVC and PSS包含SVC及PSS的电力系统暂态稳定性IntroductionThe example described in this section illustrates modeling of a simple transmission system containing two hydraulic power plants(本例为包含两个水电厂的简单传输系统). A static var compensator (SVC) and power system stabilizers (PSS) are used to improve transient stability and power oscillation damping of the system(本系统使用静止无功补偿器和电力系统稳定器以提高暂态稳定性及振荡阻尼). The power system illustrated in this example is quite simple. However, the phasor simulation method allows you to simulate more complex power grids. (虽然本例所示的电力系统非常简单,但是这种相量仿真方法仍然适用于更复杂电力网络的仿真)The single line diagram shown below represents a simple 500 kV transmission system. (简单500KV传输系统的单线图如下所示)500 kV Transmission SystemA 1000 MW hydraulic generation plant (M1) is connected to a load center through a long 500 kV, 700 km transmission line(一个1000MW水电厂M1通过500KV,长700公里的传输线与负荷中心相连). The load center is modeled by a 5000 MW resistive load(负荷中心可采用5000MW电阻性负载模拟). The load is fed by the remote 1000 MV A plant and a local generation of 5000 MV A (plant M2)(负载通过远方1000 MV A电厂及当地5000MV A电厂供电).A load flow has been performed on this system with plant M1 generating 950 MW so that plant M2 produces 4046 MW(负载所需功率由电厂M1提供950MW,因而电厂M2需产生4046MW功率). The line carries 944 MW which is close to its surge impedance loading (SIL = 977 MW)(当线路传输944MW功率时很接近其自然功率(977MW)). To maintain system stability after faults, the transmission line is shunt compensated at its center by a 200 Mvar static var compensator (SVC). The SVC does not have a power oscillation damping (POD) unit(为了维持故障后系统稳定性,在线路中点处并联了200MV AR静止无功补偿器。

dsp英文作文

dsp英文作文

dsp英文作文Digital signal processing or DSP is a fundamental field of study in electrical engineering and computer science. It involves the analysis and manipulation of digital signals such as audio, video, sensor data, and other time-varying information. DSP plays a crucial role in modern technology, enabling a wide range of applications from digital communications and multimedia to industrial control systems and medical imaging.At the core of DSP is the concept of converting analog signals, which are continuous in nature, into digital form. This process, known as analog-to-digital conversion (ADC), involves sampling the analog signal at discrete time intervals and quantizing the amplitude of the signal into a finite number of discrete levels. The resulting digital signal can then be processed using various algorithms and techniques to achieve a desired outcome.One of the primary advantages of DSP is its ability to perform complex operations on digital signals with high precision and efficiency. Unlike analog signal processing, which can be susceptibleto noise, drift, and other environmental factors, digital signal processing is inherently more reliable and consistent. Additionally, digital signals can be easily stored, transmitted, and manipulated using digital computers and microprocessors.A wide range of DSP algorithms and techniques have been developed to address various signal processing tasks. These include filtering, spectral analysis, image and video processing, speech recognition, and digital communications. Filtering, for example, is a fundamental operation in DSP that involves removing unwanted frequency components from a signal, such as removing noise or enhancing specific frequency bands.Spectral analysis, on the other hand, is the process of decomposing a signal into its frequency components, which can reveal important information about the underlying signal characteristics. This is particularly useful in applications such as audio processing, where the frequency spectrum of a signal can provide insights into the timbre and quality of the sound.In the field of image and video processing, DSP techniques are employed to perform tasks such as image enhancement, object detection, and video compression. These techniques leverage the digital representation of images and video frames to apply various image processing algorithms, such as edge detection, colorcorrection, and image segmentation.Another important application of DSP is in digital communications, where it plays a crucial role in the encoding, modulation, and demodulation of digital signals. DSP-based techniques are used in the design and implementation of various communication systems, including wireless networks, satellite communications, and digital television.The development and implementation of DSP algorithms and systems often involve a combination of theoretical analysis, computer simulations, and hardware implementation. This process typically includes the following steps:1. Signal modeling and analysis: Developing a mathematical model of the input signal and understanding its characteristics.2. Algorithm design: Selecting or designing appropriate DSP algorithms to achieve the desired signal processing objectives.3. Simulation and verification: Implementing the algorithms in software and verifying their performance through computer simulations.4. Hardware implementation: Translating the algorithms into hardware designs, such as application-specific integrated circuits (ASICs) or field-programmable gate arrays (FPGAs), for real-time signal processing.The field of DSP has seen significant advancements in recent years, driven by the increasing computational power and storage capacity of modern digital devices. The widespread availability of powerful microprocessors, digital signal processors, and dedicated hardware accelerators has enabled the deployment of sophisticated DSP-based solutions in a wide range of applications.One of the key trends in DSP is the integration of machine learning and artificial intelligence techniques. By leveraging the power of data-driven algorithms, DSP systems can now perform tasks such as pattern recognition, image classification, and speech understanding with unprecedented accuracy and efficiency. This integration of DSP and machine learning has opened up new frontiers in areas like smart home automation, autonomous vehicles, and medical diagnosis.Furthermore, the emergence of Internet of Things (IoT) and edge computing has driven the need for efficient and low-power DSP solutions that can be deployed at the edge of the network, closer to the data sources. This has led to the development of specialized DSP hardware and software architectures that can perform real-time signal processing on resource-constrained devices, enabling a wide range of IoT applications, from industrial monitoring to wearable healthcare devices.Looking to the future, the field of DSP is poised to continue its rapid evolution, driven by advancements in hardware, software, and algorithmic techniques. As the demand for intelligent, data-driven solutions continues to grow, the role of DSP in shaping the technological landscape will become increasingly crucial. From enabling the next generation of communication networks to powering the smart cities and intelligent systems of the future, DSP will undoubtedly remain a cornerstone of modern technology.。

基于ROI的直播视频传输中码率控制策略

基于ROI的直播视频传输中码率控制策略

基于ROI的直播视频传输中码率控制策略基于ROI的直播视频传输中码率控制策略摘要:随着互联网的高速发展,直播视频成为了日常生活中广泛应用的一种形式。

针对直播视频传输过程中的码率控制问题,本文提出一种基于ROI(Region of Interest)的策略。

该策略通过利用ROI的优先级特性,动态调整视频传输的码率,以提高用户观看体验。

一、引言随着互联网的普及和网络带宽的增加,直播视频成为人们日常生活中常用的媒体形式。

然而,在直播视频传输过程中,由于网络带宽波动、数据丢失等原因,可能会导致视频质量的下降,给用户带来不好的观看体验。

因此,如何保证直播视频传输中的码率控制成为一个重要的研究方向。

二、直播视频传输中的码率控制问题直播视频传输中的码率控制问题主要包括两个方面的挑战:一是如何适应不同的网络环境和带宽波动,保证视频的稳定传输;二是如何提高用户的观看体验,尽可能地减少视频质量的下降。

针对这些挑战,传统的码率控制方法主要是基于帧间压缩和帧内压缩来实现的。

然而,由于直播视频传输具有实时性的特点,传统的方法往往在适应网络环境变化和提高用户观看体验方面存在一定的局限性。

三、基于ROI的码率控制策略在直播视频传输中,ROI是指视频画面中的关注区域,这些区域通常是用户感兴趣的内容,如人物的脸部特征等。

基于这一特点,本文提出一种基于ROI的码率控制策略。

该策略的核心思想是根据视频画面中ROI的大小和重要性,动态调整视频的码率。

具体而言,当网络带宽较小时,可以减小非ROI区域的码率,而保持ROI区域的高码率,以提高用户对ROI区域内容的观看质量。

当网络带宽较大时,可以适当增加非ROI区域的码率,以提高整体视频质量。

四、基于ROI的码率控制策略的实现在实际应用中,基于ROI的码率控制策略可以通过以下步骤来实现:1. 视频帧预处理:对每一帧的视频进行预处理,提取出ROI区域的位置和相关特征。

2. ROI区域划分:根据预处理得到的信息,将视频画面划分为ROI区域和非ROI区域。

H.264AVC的码率控制算法的研究的开题报告

H.264AVC的码率控制算法的研究的开题报告

H.264AVC的码率控制算法的研究的开题报告
一、选题意义
随着网络的不断发展和带宽的不断提升,视频成为网络上广泛传播
的主要媒体之一,而H.264/AVC编码已成为目前最流行的视频编码标准
之一。

H.264/AVC编码标准相比其他标准具有更好的视频质量和更低的
数据率,因此越来越受到了广大用户和开发者的青睐。

码率控制算法作
为H.264/AVC编码中最为重要的一个环节,其优化对于视频品质和编码
效率的提高有着至关重要的作用,因此这是一个非常有研究价值和现实
意义的问题。

二、研究目的
本论文旨在通过对现有H.264/AVC码率控制算法的综述和分析,提
出一种更为优化和高效的算法,以实现对视频品质和编码效率的再提高。

三、研究内容
1、H.264/AVC编码标准的概述
2、H.264/AVC码率控制算法的分类和研究现状
3、提出一种基于视频特征的新型H.264/AVC码率控制算法
4、利用对比实验验证新算法的有效性和可行性
四、预期结果
通过本次研究,我们希望能够提出一种更加优化和高效的
H.264/AVC码率控制算法,从而在提高视频品质和编码效率方面取得更
好的效果,对于H.264/AVC编码标准的进一步发展和应用都将具有重要
的意义。

AVC的码率控制算法的研究的开题报告

AVC的码率控制算法的研究的开题报告

H.264/AVC的码率控制算法的研究的开题报告题目:H.264/AVC的码率控制算法的研究一、研究背景随着高清视频的普及,码率控制算法成为了视频压缩中的重要领域。

H.264/AVC作为一种高效的视频压缩标准,其复杂度和压缩比都比以往的标准有了大幅提升。

其中,码率控制算法的优良程度直接影响到视频的视觉质量和压缩率。

目前已有许多关于H.264/AVC的码率控制算法的研究,但是这些算法在不同的场景下有着不同的表现。

因此,研究如何根据不同场景选取适当的算法,进一步提高视频的压缩质量和码率控制的效果,具有重要的研究意义和实际应用价值。

二、研究内容本研究将围绕H.264/AVC的码率控制算法展开研究,主要内容包括:1. 对当前常用的一些H.264/AVC码率控制算法进行深入研究,探讨其原理、特点、优缺点以及适用场景等。

2. 分析H.264/AVC码率控制算法影响压缩率和视觉质量之间的因素,并建立相应的理论模型。

3. 根据实际场景,结合实验数据,分析不同码率控制算法在不同场景下的表现,并比较其优劣。

4. 提出针对不同场景的自适应码率控制策略,从而提高视频的压缩质量和码率控制的效果。

三、研究方法本研究将采用以下几种方法:1. 文献调研方法:在对H.264/AVC码率控制算法进行研究的过程中,将参考并分析已有的相关文献,全面了解该领域的研究现状。

2. 理论分析方法:对于码率控制算法对压缩率和视觉质量之间的影响因素,建立相应的理论模型,分析其本质机理,为后续实验提供理论指导。

3. 实验证明方法:根据实际场景,采集并分析大量的视频数据,从而比较不同算法在不同场景下的效果,并根据实验结果提出相应的自适应码率控制策略。

四、预期成果1. 对当前常用的一些H.264/AVC码率控制算法进行深入研究,探讨其原理、特点、优缺点以及适用场景等。

2. 分析H.264/AVC码率控制算法影响压缩率和视觉质量之间的因素,并建立相应的理论模型。

码率控制算法参考文献

码率控制算法参考文献
25 000 20 000
(7)
比特率( / bit · s-1)
宏块 i 的方差为:
15 000 10 000 5 000
JM11.0 本文
其中 L 为宏块 i 的平均值。 基本单元的方差为:
Var = 1 åVari M i=1
M
(8)
0 10 20 帧数 30 40 50
其中 M 为每个基本单元中的宏块数。 设定阈值 T:
n=1 N
4
实验结果与分析
提出的算法采用仿真平台 JM11.0, 所有测试序列均为
QCIF 4 ∶ 2 ∶ 0 格式, 50 帧, 帧率为 30 frame/s, 帧类型为 IPPP, 采 用率失真优化。 表 1 给出了 JM 模型、 文献[7]以及本文算法目标码率的比 较, 可见, 改进算法能够有效地控制码率的波动, 尤其对于运 动比较剧烈的物体, 码率波动改进十分明显。
Vari = 1 å å ( x j k - L)2 256 k = 0 j = 0
15 15
由此可见, 改进后的算法在信噪比几乎没有影响的情况 下, 更有效地控制了码率的波动。 图 1 和图 2 分别给出了 JM 和改进后的算法的每一帧比特 数的分配情况。由此可以看出, 改进后的算法对于复杂度不 同的帧分配的比特数是不一样的, 实际编码所需比特数更接 近目标比特水平。
分配帧层的目标比特数, 在基本单元层通过计算当前基本单元的亮度像素方差, 来衡量该区域的纹理复杂程度, 通过纹理复杂度 优化比特分配。实验结果表明: 与原算法相比, 该算法在几乎不影响信噪比的情况下, 能将码率更精确地控制在目标码率附近。 关键词: 码率控制; 像素方差; 纹理复杂度 DOI: 10.3778/j.issn.1002-8331.2011.13.052 文章编号: 1002-8331 (2011) 13-0186-02 文献标识码: A 中图分类号: TN919.81

英语专业论文范文

英语专业论文范文

英语专业论文范文The advent of digital technology has revolutionized the way we communicate, and the English language has not been immune to these changes. The impact of digitalization on the English language is multifaceted, affecting everything from vocabulary to grammar, and even the way we interact with one another.Firstly, the digital age has seen an explosion in the creation of new words and phrases. Terms like "selfie," "hashtag," and "tweet" have become commonplace in everyday language, reflecting the influence of social media anddigital communication. This lexical expansion is not just limited to technical jargon; it also includes slang and abbreviations that have been popularized by online communities.Secondly, the structure of language has also been affected. The brevity required by platforms like Twitter has led to a trend of concise expression, often at the expense of traditional grammar rules. Sentence fragments and creative punctuation are now accepted forms of communication, as long as the intended meaning is clear.Moreover, the digital environment has facilitated the spread of language variations and dialects. English speakers from different regions can now easily share their linguistic nuances, leading to a greater appreciation for the diversitywithin the language.However, this digital influence is not without its critics. Some argue that the casual nature of online communication is eroding the standards of written English, leading to adecline in literacy and language skills. Others see it as a natural evolution, reflecting the dynamic and adaptive nature of language.In conclusion, the impact of digitalization on the English language is profound and ongoing. It has introduced new words, altered grammatical structures, and diversified linguistic expressions. As digital technology continues to evolve, sotoo will the English language, reflecting the ever-changing landscape of human communication.。

一种改进的基于柯西模型的H.264码率控制方法

一种改进的基于柯西模型的H.264码率控制方法

一种改进的基于柯西模型的H.264码率控制方法胡栋;孙前锋;谢光剑【期刊名称】《信号处理》【年(卷),期】2011(027)011【摘要】Rate control in H. 264 is a key technology which improves the quality of the compressed video via controlling the bit rate of output streaming. An improved algorithm is proposed on the basis of the JVT-H017 algorithm in this paper. According to the distribution of DCT coefficients in H. 264, Cauchy rate module which replaces traditional quadric rate distortion model is adopted into the rate control. Moreover, a prediction algorithm which is used to predict the image complexity via PSNR ratio and MAD ratio is also proposed in this paper, and then the frame bits and QP can be adjusted based on the predicted results. Thus, in the case of complex movement or scene change, this prediction method can overcome the inaccuracy of MAD prediction method in the JVT-H017 algorithm because of the reduced correlation in the adjacent video frames. Simulation results show that, compared with the algorithm in JVT-H017 and reference[5 ], the new algorithm not only achieves more accurate rate control, but also obtains more stable output bit rate and better PSNR value of reconstructed image.%H.264/AVC编码中的码率控制是通过有效控制输出码流的码率来提高其压缩视频质量的重要技术.本文基于H.264/AVC中的JVT-H017码率控制方案提出了一种改进算法.新算法根据H.264中DCT系数的分布特征,将柯西分布引入到码率控制模块,用更精确的柯西率失真模型取代了原先的二次率失真模型.在此基础上,进一步引入了一种联合PSNR比率和MAD比率进行图像复杂度预测的方法,并依此来调整帧级比特的分配和量化参数,克服了在出现复杂运动或场景切换时,因视频序列相邻帧之间相关性降低而导致的MAD预测失准的情况.实验结果表明,与JVT-H017方案及文献[5]中的算法比较,新的算法不仅具有更精确的码率控制,而且改善了输出码率的平稳性及重建图像的PSNR.【总页数】4页(P1671-1674)【作者】胡栋;孙前锋;谢光剑【作者单位】南京邮电大学江苏省图像处理与图像通信重点实验室,江苏南京210003;南京邮电大学江苏省图像处理与图像通信重点实验室,江苏南京210003;南京邮电大学江苏省图像处理与图像通信重点实验室,江苏南京210003【正文语种】中文【中图分类】TN【相关文献】1.一种基于H.264/AVC宏块级改进的码率控制算法 [J], 金建;李小红;李寅2.H.264中一种基于R-Q模型的自适应码率控制算法研究 [J], 郑新资;骆冰清;孙知信3.一种帧间稳定的H.264/AVC实时码率控制方法 [J], 曾嘉亮4.面向H.264标准的改进码率控制方法 [J], 钟伟成;曾青松;何书前5.一种基于TMN8模型的H.264码率控制方法 [J], 李娜;王中元;何政;傅佑铭;常军因版权原因,仅展示原文概要,查看原文内容请购买。

基于TFRC的H.264码率控制算法研究的开题报告

基于TFRC的H.264码率控制算法研究的开题报告

基于TFRC的H.264码率控制算法研究的开题报告一、研究背景及意义在视频通信中,码率控制是一项非常重要的技术,其目的是在保证视频质量的前提下,有效利用带宽资源,使视频传输更稳定,更流畅。

海量的视频数据和不断增长的网络数据流量使得研究和优化视频传输技术变得越来越重要。

H.264作为当前广泛应用的视频编解码标准之一,其码率控制算法也备受关注。

H.264码率控制算法需要根据网络带宽的变化进行灵活调节,同时也要对视频的内容特征进行分析和处理,以最大程度地保证视频质量的同时,尽可能利用网络带宽资源。

传统的基于TCP的码率控制算法主要依赖于TCP拥塞控制机制来调整码率,但TCP并不适用于视频传输。

因此,基于TCP的传统码率控制算法不能很好地适应视频传输的需求。

相反,TFRC作为新一代流控制协议,其码率控制机制和视频传输更为契合。

因此,基于TFRC的H.264码率控制算法具有很好的应用前景和研究价值。

本文将基于TFRC协议,研究H.264码率控制算法,探讨如何在保证视频质量的同时,尽可能地利用网络带宽资源,提高视频传输效率和稳定性。

二、研究内容及方法1.基本思路本文的基本思路是研究基于TFRC的H.264码率控制算法,并以此为基础,实现一种高效、稳定、适应性强的视频传输方案。

2.具体研究内容(1)TFRC协议的研究:研究TFRC协议的基本原理、机制,探讨其在视频传输中的应用。

(2)H.264编解码器和码率控制算法的研究:H.264编解码器是目前最为广泛应用的视频编解码标准之一,探讨其编解码原理以及码率控制算法的优劣。

(3)基于TFRC的H.264码率控制算法的研究:基于TFRC的H.264码率控制算法是本文的重点研究内容,需要深入探讨如何将TFRC协议与H.264码率控制算法相融合。

3.研究方法(1)文献资料法:深入了解TFRC协议、H.264编解码器和相关的视频传输技术,为研究提供理论基础。

(2)仿真实验法:利用Matlab等仿真工具进行实验验证和性能比较,为研究结论提供实验基础和支持。

  1. 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
  2. 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
  3. 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。
ቤተ መጻሕፍቲ ባይዱ
Efficiency Video Coding (HEVC) is the latest video coding standard developed by JCT-VC (Joint Collaborative Team on Video Coding) [1], which significantly improves the coding efficiency than the previous video coding standards. Due to the limited storage capacity or communication bandwidth, quantization is introduced to reduce the bit rate of the compressed video signal such that the capacity or bandwidth limitation can be met properly. To achieve a target bitrate, rate control, which dynamically adjusts the quantization parameters (QPs), is usually adopted in the video coding framework. Many rate control algorithms and rate quantization (R-Q) models have been developed for previous video coding standards. As far as HEVC is concerned, the rate control problems have been discussed in [2] [3] [4]. It’s flexible for designers to develop suitable schemes for specific applications of HEVC. Choi et al. [2] proposed a pixel-wise R-Q model with a quadratic form and a temporal linear model for predicting the mean absolute difference (MAD) value. Li et al. [3] developed a rate control algorithm based on the R-λ model for HEVC temporal scalability, considering that
H
I. INTRODUCTION
λ is the key factor to determine bitrate. Wang et al. [4] modified the ρ-domain rate control according to the new feature of quadtree coding structure in HEVC. It should be noted that all the above algorithms mainly take into account the coding efficiency and video quality, but are not designed for low delay applications of HEVC. For low delay video communication systems such as video conferencing, the buffer size has to be limited to meet a low delay constraint. Besides, to avoid buffer overflow and underflow, more accurate bit allocation and encoding parameter adjustment is desired in low delay applications. The state-of-the-art R-λ algorithm [3] in HM10.0 cannot be used for low delay cases directly because the number of frames to be coded is not available on the fly. There are two problems with the rate control algorithm in HM10.0. Buffer overflow and underflow: If the number of frames to be coded is set to a very large number, the buffer occupancy will increase or decrease at a constant speed, so the buffer may overflow or underflow. And if it is used in the low delay applications, the buffer size should be set a large size, which is not suitable for low delay requirement. Inaccurate CTU bit estimation: In HM10.0, the bit allocation for CTU is according to the MAD ratio of the same position of the previous frame. But inaccurate MAD estimation which causes an inaccurate CTU bit estimation will bring about an unstable buffer occupancy. So the simple CTU bit allocation will impair the final rate control result, especially in the low delay applications. In this paper, a low delay rate control scheme for HEVC is proposed. We improve the algorithm in HM10.0 for more accurate bit allocation. A new bit allocation method based on the buffer status is proposed to control the buffer better, and a weight ratio using a numerical method is adopted to get over the inaccurate MAD estimation. Experimental results show that the algorithm has a lower buffer occupancy and a smaller bit fluctuation, which enables a lower delay and adapts better to low delay applications of HEVC. The remainder of this paper is organized as follows. In Section II, we briefly describe three rate control models that have been used for HEVC. In Section III, the rate control scheme for low delay video communication of HEVC is proposed. The experimental results and discussions are presented in Section IV. The conclusion is drawn in Section V.
IGH This work was supported by National 863 project (2012AA011703), National Key Technology R&D Program of China (2013BAH53F04), NSFC (61221001, 61271221), the 111 Project (B07022) and the Shanghai Key Laboratory of Digital Media Processing and Transmissions. Z. Yang is with the Department of Electronic Engineering, Shanghai Jiao Tong University, 200240, China (e-mail: yangzhongzhu@). L. Song is with the Institute of Image Communication and Network Engineering, Shanghai Jiao Tong University, 200240, China (86 21 34204468; e-mail: song_li@). Z. Luo and X. Wang are with the Shanghai University of Electric Power, 200240, China (e-mail: lzy@, wxw21st@).
1
Low Delay Rate Control for HEVC
Zhongzhu Yang, Li Song, Zhengyi Luo and Xiangwen Wang
相关文档
最新文档