消防系统调试方案

合集下载
  1. 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
  2. 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
  3. 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。

消防调试方案

Commissioning Plan for Fire System

一、工程概况Brief Introduction

本工程为北京宝洁技术有限公司研发中心及中试线厂房等5项机电安装工程。该工程的消防系统调试内容主要有:火灾自动报警及联动系统、水喷淋自动喷水灭火系统、消火栓灭火系统、气体灭火系统、消防防排烟系统及其他消防系统的综合调试。

This project is mechanical and electrical installation one for R&D Center and PRL of P&G (Beijing). Fire system to be commissioned with this project covers fire auto alarming and linkage system, water sprinkling system, hydrant fire system, gas fire system, smoke exhausting system and other fire systems.

消防水系统包括:1、研发楼消防喷淋及消火栓系统。2、中试厂房消火栓及消防喷淋系统。

Fire water system includes: 1. fire sprinkling and hydrant system in R&D; 2. hydrant and fire sprinkling system in PRL.

消防自动报警系统包括:1、感烟探测器、感温探测器。2、声光报警器、手动报警按钮。3、输出模块、输入模块。4、报警主机、CRT系统。5、联动控制盘。6、电话主机、消防广播。消防控制室位于中试厂房一层。

Fire auto alarming system includes: 1. smoke detector, temperature detector; 2. audible and visual alarm, manual alarming button; 3. input/output module; 4. alarming main unit, CRT; 5. linkage control panel; 6. dispatching telephone control board, fire broadcasting system. Fire control room is located on the ground floor of PRL.

气体灭火系统包括:1、烟洛尽气体灭火系统,主要由储气钢瓶、低压二氧化碳灭火控制器、气路控制器、主控阀、溢流安全阀、选择阀、压力开关、灭火喷放管道、喷头等组成。共计对地下室核磁共振、一层电讯室、二层数据中心3个防护区进行灭火控制。

Gas fire system includes inergen system made up of gas cylinder, low pressure CO2 fire controller, gas circuit controller, main control valve, overflow release valve, selecting valve, pressure switch, fire gas sprinkling pipe and sprinkling nozzles. A total of 3 areas will be fire controlled. They are NMR room in the basement, telecom room on the ground floor and data room on the second floor respectively.

二、工程调试准备Preparation for Commissioning

2.1技术准备:项目负责人熟悉、审核图纸,确定图纸的编码表和联动逻辑关系的正确性。

Technical Preparation: Those in charge of the project shall get familiar with and review drawings to verify the logical relations between coding list and linkage.

2.2材料准备:依据设计探测器的特点要求,准备加烟材料和备品备件。

Material Preparation: According to design requirements for detector, prepare inergen and spare product and parts.

2.3施工工具:电气调试工具应有加烟器、加温器、兆欧表、万用表和各种手头工具;水系统调试准备流量计和压力计。

Tools: Inergen feeder, heater, megger, multimeter and various hand tools shall be

available for commissioning of electrical system. Flowmeter and pressure gauge shall be available for commissioning of water system.

2.4系统准备:System Preparation

1.电系统:系统调试前,现场所有涉及到的联动设备动力、照明、应急照明电源供应正常,系统自调完毕,设备运行良好,无故障,具备联动条件。应急照明系统自动投入功能正常。

Power System: Prior to commissioning, power for the related linking equipment and power supply for lighting and emergency lighting shall function well. After commissioning, equipment runs well without failure. Automatic function of emergency lighting system runs well.

2.水系统:首先消防水池要注满水,供水阀门打开,所有消火栓出水口关闭,室外管网保证畅通,室外消火栓使用正常。屋顶消防水箱具备稳压、补压功能,各种泄水口、排水沟到位,具备放水、排水条件。

Water System: Fill up the fire basin with water, open water inlet valve; close all water outlets of hydrants. Fire water tank on the roof deck shall be capable of stabilizing pressure. Various drain outlets, drain trenches are in place.

3.风系统:各种消防风机调试完毕,设备运行正常,各种阀类机械开启灵活,各种信号反馈正常。

Air System: After commissioning, various fire fans function well. Various valves function well and feedback of signals goes well.

4.其它:电梯自检自验迫降功能正常,卷帘门自检自验功能正常。

Others: Functions of self-examination and emergency landing of lift are normal. Function of self-examination of rolling shutter is normal.

三、系统调试步骤:Commissioning Procedures

1.自动报警系统Automatic Alarming System

(1)消防控制中心联动报警主机,主备电源自动切换正常,主机各项功能符合设计及消防施工验收规范要求。对于现场自动报警设备逐一进行通电试验,模拟报警试验;联动控制模块逐一模拟手动通电试验,模拟控制模块动作以后末端联动设备的启停信号的反馈情况是正常、及时。

The main standby power supply for the main alarming unit of linkage in fire control center shifts automatically well. Each function of the main unit meets design and acceptance requirements. Energizing and simulating tests are conducted with auto alarming equipment. Each linked module is energizing tested manually. Start/stop signal of the terminal linked equipment is fed back normally and timely once simulated linkage module reacts.

(2)所有联动控制模块功能实验合格后,进行终端设备的单点启动实验,即:有关消防联动设备的电源控制柜全部转换到自动状态(消防风机、消防泵、喷洒泵等),消防中心主机发出单点启动命令后,相应的联动设备应能启动,并且设备启动后消防中心主机应能接收到设备的启动状态信号。然后进行其他设备照明强切、各种风阀、预作用电磁阀、电梯迫降的启动试验。

After the function test of all linked control modules is acceptable, single point startup test for the terminal equipment can be done. That is, power control cabinets for the fire linked equipment are shifted into automatic mode (fire fan, fire pump, sprinkling pump etc.). When the main unit at the fire center gives out command, the

相关文档
最新文档