水泥搅拌桩止水帷幕监理细则修订稿
止水帷幕监理细则改范本
止水帷幕监理细则改汉拿香邑花园三期工程止水帷幕施工监理细则监理工程师(编制)总监理工程师(批准)北京建工京精大房工程建设监理公司汉拿香邑花园项目监理部8月目录一、工程概况: ................................................... 错误!未定义书签。
二、止水帷幕工程设计 ....................................... 错误!未定义书签。
三、监理细则编写依据 ....................................... 错误!未定义书签。
四、水泥搅拌桩止水帷幕 ................................... 错误!未定义书签。
4.1监理内容......................................................... 错误!未定义书签。
4.2搅拌桩质量控制 ............................................. 错误!未定义书签。
4.2.1监理工作流程 .............................................. 错误!未定义书签。
4.2.2质量控制点的设置 ...................................... 错误!未定义书签。
4.2.3施工质量预控制 .......................................... 错误!未定义书签。
4.2.4搅拌桩施工过程质量监理........................... 错误!未定义书签。
4.2.5竣工后质量控制 .......................................... 错误!未定义书签。
五、高压旋喷桩 ................................................... 错误!未定义书签。
水泥搅拌桩施工监理实施细则范本
水泥搅拌桩施工监理实施细则范本1. 前言本文档旨在制定水泥搅拌桩施工监理的实施细则,以确保施工过程的质量和安全。
该范本适用于水泥搅拌桩施工监理工作的规范执行。
2. 施工监理责任2.1 监理单位应根据施工图纸和相关技术规范,对水泥搅拌桩施工进行全程监理,确保施工符合设计要求。
2.2 监理单位应组织监理人员对施工现场进行巡查和检查,及时发现问题并提出整改意见。
2.3 监理单位应与施工单位保持密切沟通,及时协调解决施工中的问题。
2.4 监理单位应定期向建设单位提供施工进展报告,包括工程质量、安全状况和材料使用情况等。
3. 施工准备3.1 施工前,监理单位应对施工图纸进行审核,确保设计符合相关标准和规范。
3.2 施工前,监理单位应检查施工场地的平整度和排水情况,确保施工条件符合要求。
3.3 施工前,监理单位应对施工设备和材料进行检查,确保其符合质量要求和安全标准。
4. 施工过程监管4.1 监理单位应对水泥搅拌桩的施工过程进行全程监督,包括桩孔的准确定位、钢筋的布置、混凝土浇筑等环节。
4.2 监理单位应检查施工现场的安全措施是否到位,防止事故的发生。
4.3 监理单位应抽查桩孔和钢筋的质量,确保施工质量符合要求。
5. 施工质量验收5.1 施工完成后,监理单位应对水泥搅拌桩的质量进行验收,包括桩孔的直径、混凝土的强度等指标的检测。
5.2 监理单位应制定质量验收报告,包括施工质量的评价和存在的问题。
5.3 如发现施工质量不合格或存在安全隐患的情况,监理单位应立即提出整改要求,并监督整改过程。
6. 后续工作6.1 完成施工监理任务后,监理单位应对监理工作进行总结和评估,并提出改进建议。
6.2 监理单位应向建设单位提交施工监理报告,详细记录施工过程、质量验收结果和存在的问题。
7. 其他事项本范本可根据实际情况进行调整和修改,以适应具体的水泥搅拌桩施工监理工作需求。
以上为水泥搅拌桩施工监理实施细则范本,供参考使用。
2024年水泥搅拌桩监理细则(三篇)
2024年水泥搅拌桩监理细则1、业主与承包人之间的《工程承包合同》2、《公路工程质量检验评定标准》(JTGF80/1-____)3、本工程的《招标文件》有关章节4、《公路路基施工技术规范》(JTGF10-____)5、本工程设计文件及有关设计技术联系单6、被批准的开工报告(含施工组织设计)监理工作控制目标及控制要点(一)监理工作控制目标水泥搅拌桩施工无质量事故,无安全事故,单桩或复合地基承载力满足设计要求。
(二)监理控制要点1、施工前的准备检查(1)施工场地搅拌桩施工场地应事先平整,清除桩位处地上的一切障碍物(包括石块、树跟和垃圾等),清表至桩顶施工工作面标高,如遇明、暗浜部分,采用满足规范要求的粘性土或粉性土等细粒土分层填浜,不可采用改良土(石灰土或二灰)或粒料等粗粒土,压实度应不小于____%(重型)。
(2)测量放线①测量的基准线、轴线、水准基点经总包复测无误后妥善保护,监理在施工前进行复核。
②桩位根据桩的定位控制线定位,该线施工单位测放完毕后,总包先复测,监理后复核。
③测量报验手续:先由总包填写“定位测量报验申请表”报监理,然后监理进行复核,并签字认可。
④规划红线必须由区(市)规划局签字认可。
(3)绘制水泥搅拌桩施工平面图施工单位应根据搅拌桩软基处理设计图、桩位布置图绘制水泥土搅拌桩施工平面图,并进行桩位编号,使施工图的桩号与实地桩号相符。
(4)开挖水泥土搅拌桩的施工沟槽,设桩的定位控制线及定位标志。
①施工单位根据设计修改通知单、桩位布置图及复核无误的轴线,在施工实地放测水泥土搅拌桩的施工轮廓线,作为开挖沟槽的界线。
②为了防止水泥土搅拌桩施工时水泥土隆起,影响施工,应根据实地的水泥土搅拌桩轮廓线开挖施工沟槽,沟槽的深度按桩的幅数及桩长确定。
开挖沟槽的过程中,要求施工单位有专人负责进行现场指导,应把障碍物清除干净,以减少施工中处理障碍物的时间。
③根据水泥土搅拌桩施工平面图,在沟槽边设桩的定位控制线。
世代家园止水帷幕监理细则
黄骅市世代家园止水帷幕工程监理实施细则(水泥土搅拌桩工程)编制人:_______________审核人:_______________黄骅市工程建设监理有限公司二0一一年二月目录一、工程况 (1)二、监理控制据 (1)三、监理工作控制标 (1)四、监理控制点 (2)五、水泥土搅拌桩监理控制流图 (2)六、水泥土搅拌桩质量控制施 (2)七、水泥土搅拌桩成桩质量检验与测 (4)八、施工技术资料的监督理 (5)九、旁站监理案 (5)十、安全监理控制措施 (7)为了止水帷幕工程施工阶段监理工作的顺利实施,根据《建设工程委托监理合同》和《监理规划(大纲)》的规定和要求,特制定本工程施工阶段监理工作实施细则。
一、工程概况:本工程为黄骅市沈庄片区回迁安置楼(世代家园)止水帷幕工程,该工程位于黄骅东区,交通便利,基础条件良好。
为保证周边已有建筑的安全和本小区的降水效果而进行的一项工程。
本工程由沧州市金龙桩基工程公司与黄骅市华中地基基础处理公司施工,黄骅市建筑设计院设计,黄骅市工程建设监理有限公司负责施工阶段的监理。
本工程止水帷幕采用水泥土搅拌桩,处理范围约1300米计3300 多根,设计桩径为600,有效桩长为14m设计水泥掺入比为15%水泥采用32.5 级复合硅酸盐水泥。
二、监理控制依据:建设单位与施工单位签定的《建设工程施工合同》、建设单位与监理单位签定的《建设工程委托监理合同》、《岩土工程勘察报告》、设计图纸及说明、国家现行建筑施工及验收规范、质量检验评定标准等,如:《建筑地基基础工程施工质量验收规范》GB50202-2002《建筑桩基技术规范》JGJ94-94、《混凝土结构工程施工质量验收规范》GB50204-2002《建筑工程施工质量验收统一标准》GB50300-2001《建筑基桩检测技术规范》JGJ106-2003建设部有关工程建设的政策、法规、文件、规定等(包括《建设工程监理规范》),如:《建设工程质量管理条例》(国务院令279 号)、《工程建设监理规定》(建设部、国家计委1995 年发布)、《房屋建筑工程和市政基础设施工程竣工验收备案管理暂行规定》(建设部2002 年发布)、建设部关于印发《房屋建筑工程施工旁站监理管理办法(试行)的通知》(建市[ 2002]189 号)等。
水环境治理项目水泥搅拌桩工程监理细则安全监理细则范本模板
监理细则审批表水环境综合治理PPP项目监理实施细则(扬尘污染防治)内容提要:专业工程特点监理工作流程监理工作控制目标及控制要点监理工作方法及措施项目监理机构(章)专业监理工程师总监理工程师日期建设工程咨询有限公司年月目录一、工程概况 (02)二、工程特点 (03)三、监理工作依据 (03)四、监理工作流程 (04)五、监理工作控制要点及目标值 (09)六、监理工作方法及措施 (09)七、安全文明施工监理要点 (12)一、工程概况本工程本工程包括16条水系79处水体综合治理,其中新建及改扩建排涝泵站28座工程,河道总长约122.33km,治理水域总面积约632.1ha,而水系水体提升治理包括截污、湿地生态修复、清淤、驳岸等工作。
工程场地地貌极大部分属于长江冲洪淤积平原,地势较平坦。
地下水、土对混凝土结构一般具有弱腐蚀性,对钢筋混凝土结构中的钢筋,在干湿交替条件下具有腐蚀性,在长期浸水条件下具有微腐蚀性。
本工程实行施工总承包,主要内容有:中心城区16条水系79处水体综合治理,其中,63处水体(黑臭水体33处,水质较差水体30处)需进行黑臭治理,54处水体需进行提标改造(既需要进行黑臭治理,又需要进行提标改造的水体共38处),同步提标新建及改扩建排涝泵站28座。
工程施工合同造价约为约315090.50万元,合同工期分五期实施,2020年前完成。
二、工程特点本工程场地地貌极大部分属于长江冲洪淤积平原,地势较平坦。
经勘察,地基土层按其成因类型和工程地质性质共分为9个工程地质层:①-1杂填土,①素填土,②淤泥质粉质粘土,③粉质粘土,④粉质粘土,⑤粉质粘土,⑥粉质粘土,⑦残积土,⑧强风化花岗岩闪长岩,⑨中风化花岗闪长斑岩。
淤泥或淤泥质粘土分布较广且层厚较大,其含水量大,天然孔隙比大,饱和度高,成流塑状,承载力较低,变形较大,压缩性高,抗剪强度低,极易产生土方滑动破坏及沉降破坏。
根据本工程的岩土特性和工程特点,河道护岸翼墙基础、进水闸、箱涵、防洪闸和消力池软基处理均采用水泥搅拌桩加固处理,布置形式有梅花形和矩形。
2023年水泥搅拌桩监理细则
2023年水泥搅拌桩监理细则第一章总则第一条监理细则的目的是为了规范和指导2023年水泥搅拌桩的监理工作,确保工程质量和工期的安全顺利完成。
第二条监理人员应具备相关专业知识和资格,熟悉水泥搅拌桩的施工工艺和规范要求。
第三条监理人员应按照国家和地方相关法律法规、标准和规范进行监督和检查,并及时发现和纠正施工中存在的问题。
第四条监理人员应与施工单位保持良好的沟通和协调,确保施工按照合同和设计要求进行。
第二章施工前准备第五条施工前,监理人员应对水泥搅拌桩施工进行审查,包括施工方案、施工设备和材料等。
第六条施工前,监理人员应检查施工现场的平整度和排水情况,确保施工条件符合要求。
第七条监理人员应检查施工方案的合理性和可行性,包括桩的数量、尺寸和布置等。
第八条监理人员应核实施工单位的施工设备和材料是否符合规定,并对其进行检测和验收。
第九条监理人员应核查施工单位是否制定了作业指导书和施工组织方案,并对其进行审核和批准。
第十条施工前,监理人员应与施工单位共同制定施工进度计划,并监督其按照计划进行施工。
第三章施工过程监督第十一条监理人员应在施工现场全程监督,确保施工按照设计要求和规范进行。
第十二条监理人员应检查施工设备的安全性和稳定性,并要求施工单位做好维护工作。
第十三条监理人员应检查水泥搅拌桩施工中的质量控制措施,包括材料的配比和搅拌过程的参数等。
第十四条监理人员应对水泥搅拌桩的施工质量进行抽样检测,并及时处理不合格的情况。
第十五条监理人员应对施工现场的环境保护进行监督,确保施工不对周边环境造成污染。
第十六条监理人员应及时记录施工过程中的问题和处理情况,并向相关人员进行报告。
第四章施工验收与结算第十七条施工完成后,监理人员应按照相关规定对水泥搅拌桩的施工进行验收。
第十八条监理人员应核查施工单位是否按照合同要求提供施工图纸、材料清单和质量检测报告等资料。
第十九条监理人员应对水泥搅拌桩的验收结果进行评价,并及时向施工单位和建设单位提出意见和建议。
混凝土搅拌桩监理实施细则范本
混凝土搅拌桩监理实施细则范本1. 范围本细则适用于混凝土搅拌桩监理工作的实施和管理。
2. 监理人员2.1 监理人员应具备相关的工程监理资质。
2.2 监理人员应熟悉混凝土搅拌桩施工工艺和要求。
2.3 监理人员应具备良好的沟通和协调能力。
3. 监理工作内容3.1 混凝土搅拌桩施工前,监理人员应仔细检查施工现场的平整度、排水情况和临时设施。
3.2 监理人员应参与混凝土搅拌桩施工方案的审查和确认。
3.3 混凝土搅拌桩施工期间,监理人员应对施工过程进行全程监督和检查。
3.4 监理人员应对混凝土搅拌桩的质量进行抽查和检验。
3.5 监理人员应及时发现和处理施工过程中的问题和隐患。
3.6 混凝土搅拌桩施工完成后,监理人员应进行验收并出具监理报告。
4. 质量控制要求4.1 混凝土搅拌桩施工应遵循相关的技术规范和标准。
4.2 施工过程中应加强质量控制,确保混凝土搅拌桩的质量符合要求。
4.3 混凝土搅拌桩的试块应按照规定的频率进行取样和试验。
4.4 施工结束后,应对混凝土搅拌桩进行质量检查和测试。
5. 安全防护要求5.1 混凝土搅拌桩施工前,应制定详细的安全施工方案。
5.2 施工现场应设置明显的安全警示标识,并配备必要的安全设施。
5.3 施工过程中,应加强现场安全监督和管理,防止事故的发生。
6. 文件管理6.1 监理人员应对混凝土搅拌桩施工相关文件进行管理和归档。
6.2 监理人员应定期向相关单位和部门报告工作进展和问题解决情况。
以上为混凝土搅拌桩监理实施细则范本,具体实施时应根据实际情况进行调整和补充。
水泥搅拌桩监理实施细则
二. 水泥搅拌桩(止水帷幕)监理实施细则
水泥搅拌桩施工质量监理细则
一、水泥搅拌桩施工的预控内容
1.施工单位应对设计图纸及总说明认真查看,如发现问题应及时与
有关方面联系。
2.核对本图的布置尺寸实际场地及上部结构是否相符,工程放线应
严格要求。
3.控制水泥进场后的报审报验;工程所用水泥应按设计要求,并按
规范要求进行复试,待复试合格后方可使用。
4.场地应先平整,清除桩位处地上、地下一切障碍物,场地低洼处
用粘性土料回填夯实,不得用杂土回填;
5.标定搅拌机械的灰浆泵输送量、灰浆输送管到达搅拌机喷浆口的
时间和起吊设备提升速度等施工工艺参数。
二、水泥搅拌桩施工的监理要点
1. 施工中固化剂应严格按预定的配合比拌制。
起吊应保证起吊设备的平整度和导向架的垂直度。
成桩要控制搅拌机的提升速度(0.2-0.5m/Min)和次数应符合设计要求,使连续均匀,以控制注浆量,保证搅拌均匀,同时泵送必须连续。
2.桩机就位后必须垂直,偏差不得大于0.5%,经确认后方可开钻。
3.搅拌机喷浆提升的速度次数必须满足施工工艺的要求,并应由专人记录。
4.搅拌机预拌下沉时,不宜冲水;当遇到较硬土层下沉太慢时,方可适量冲水,但应考虑冲水成桩对桩身强度的影响;
3.检查机头提升速度,水泥浆或水泥注入量,搅拌桩的长度及标高;
6.进行强度检验时,对水泥土搅拌桩应取28天的试件,试件可钻孔
取芯,或其他规定方法取样;
7.对不合格桩,应根据其位置和数量等具体情况,分别采取补桩或
加强邻桩等措施。
三诚里项目监理部。
三轴水泥搅拌桩止水帷幕的施工及监理控制要点
三轴水泥搅拌桩止水帷幕的施工及监理控制要点随着城市建设的不断发展壮大,水利工程和市政工程对于采用水泥搅拌桩进行支护和检修的需求逐步增加,而在水泥搅拌桩的支护和检修过程中,如何保证施工过程中的质量和安全问题,成为了工程建设中需要重点解决的难题之一。
三轴水泥搅拌桩止水帷幕技术作为一种较为常用的处理方法之一,具有施工方便,成本低、效果显着等优势,得到广泛应用。
接下来,本文将从施工和监理的角度,详细阐述三轴水泥搅拌桩止水帷幕的相关要点。
一、施工要点1. 准备工作在施工之前,必须对现场进行全面的勘察和分析,包括工程地质情况、地下水位、建筑物周围的环境等相关因素,根据实际情况选择合适的施工方案,避免在施工过程中发生意外。
2. 施工条件三轴水泥搅拌桩止水帷幕的施工条件主要包括水位控制、灌浆量控制以及拍打时间和力度控制等,确保过程中各项控制参数在标准范围内,以保证施工质量。
3. 设备选型在施工过程中应选择合适的设备,以确保施工过程的质量和效率。
同时,设备操作人员应具备专业的技能和经验,以确保施工安全。
二、监理控制要点1. 施工过程监理对于三轴水泥搅拌桩止水帷幕施工过程中的关键环节,如土壤桩的深度、桩径、灌浆度、拍打时间和拍打力度等进行全程监理控制,以确保施工过程的规范和质量。
2. 施工质量监理在施工过程中要对施工现场进行质量把控,确保三轴水泥搅拌桩止水帷幕的灌浆均匀、强度符合标准要求、桩身直径规范等要求。
3. 现场安全监理在施工过程中需要严格遵守安全操作规程,对现场进行安全监控,确保施工现场的安全,对于发生的安全事故,要及时报告并采取应对措施。
综上所述,三轴水泥搅拌桩止水帷幕的施工和监理控制要点包括准备工作、施工条件、设备选型等施工要点,以及施工过程监理、施工质量监理和现场安全监理等监理要点。
只有在严格按照要求进行施工和监理时,才能确保三轴水泥搅拌桩止水帷幕的施工质量和安全。
水泥搅拌桩工程监理实施细则模版(3篇)
水泥搅拌桩工程监理实施细则模版1.依据标准应符合国家标准GB50202-____《地基与基础工程施工质量验收规范》1.主控项目和一般项目项序检查项目允许偏差或允许值检查方法单位数值主控项目1水泥及外掺剂质量设计要求查产品合格证书或抽样送检2水泥用量参数指标查看流量计3桩体强度设计要求按规定办法4地基承载力设计要求按规定办法一般项目1机头提升速度m/min≤0.5量机头上升距离及时间2桩底标高mm+200测机头深度3桩顶标高mm+100-50水准仪(最上部500mm不计入) 4桩位偏差mm<50用钢尺量5桩径<0.04D用钢尺量,D为桩径6垂直度≤1.5经纬仪7搭接mm>200用钢尺量注:主控项目全面检查,一般项目可按____%抽查。
质量标准1.依据标准应符合国家标准GB50202-____《地基与基础工程施工质量验收规范》1.主控项目和一般项目项序检查项目允许偏差或允许值检查方法单位数值主控项目1水泥及外掺剂质量设计要求查产品合格证书或抽样送检2水泥用量参数指标查看流量计3桩体强度设计要求按规定办法4地基承载力设计要求按规定办法一般项目1机头提升速度≤0.5量机头上升距离及时间2桩底标高mm+200测机头深度3桩顶标高mm+100-50水准仪(最上部500mm不计入) 4桩位偏差mm<50用钢尺量5桩径<0.04D用钢尺量,D为桩径6垂直度经纬仪7搭接mm>200用钢尺量注:主控项目全面检查,一般项目可按____%抽查。
控制点1.防止搅拌不均匀⑴施工前对整套设备进行检修,检查搅拌机及各种计量设备使之处于正常工作状态⑵保证搅拌时间,增加拌和次数,提高搅拌转数,调整钻进速度⑶保证单位时间注浆相等,不得中断注浆⑷拌制固化剂(水泥或水泥砂浆以及减水剂)不得任意加水,保证水灰比及拌合程度2.防止喷浆不正常⑴设备经试运转,保证正常工作⑵喷浆口采用逆止阀(单向球阀)防止泥土倒灌⑶泵与输浆管应清洗干净,在集浆池上方细筛过滤防止杂物倒入⑷保证水灰比合适3.防止抱钻,冒浆⑴硬土层下沉太慢时适量冲水⑵提高桩顶处水泥掺量,一般为____%左右。
三轴水泥搅拌桩支护桩止水帷幕监理细则
XXX基坑工程三轴水泥搅拌桩监理实施细则编制审核建研凯勃建设工程询问有限公司目录一.工程概况 (2)二.监理依据 (2)三.监理主要工作内容 (2)四.监理限制措施 (2)一.工程概况:工程名称:建设地点:建设单位:设计单位:施工单位:监理单位:XXX基坑支护工程,基坑普遍开挖深度11.45m,基坑周长862m,基坑面积约47600m2。
本基坑主要采纳灌注桩排桩+一道钢筋砼支撑的支护方式。
基坑围护墙体采纳φ1000@1500钻孔灌注桩,桩长17.6~22.6m(有效桩长),桩顶落低地面约3m。
坑外止水帷幕采纳3φ850@650三轴搅拌桩,止水帷幕采纳单排三轴3φ850@650搅拌桩,桩长14.5~17.0m,水泥掺量20%;部分搅拌桩内插H500×200×9×14型钢,长度6.0m。
二.监理依据1、《建筑地基基础工程施工质量验收规范》;2、《建筑工程施工质量验收统一标准》(GB50300—2001);3、《建筑基坑支护技术规程》(JGJ120—99);4、《建筑机械运用平安技术规程》(JGJ33—2001);5、《施工现场临时用电平安技术规程》(JGJ46—2005);6、有关施工规范、质量标准和文明施工规定。
三.监理主要工作内容:依据国家规范、规程,依据本项目监理部所监理工程的特点,结合监理合同、施工合同的特别要求,对水泥搅拌桩施工中影响质量和平安的关键部位、关键工序编制监理细则;四.监理限制措施湿喷桩施工的场地,事先要回填平整,消退杂物,查明上空和低下有无管线。
假如有问题应要求施工单位提前向项目监理部和业主汇报,以便刚好妥当解决。
(一)机械设备及施工要求1.三轴搅拌桩机机组由深层搅拌机、步履式机架、流量计、灰浆拌制及泵送机组、限制柜、输浆管、电缆等组成。
水泥土搅拌桩采纳“两喷两搅”。
施工中正确运用搅拌机械,确保桩机对中及机架的垂直度和灰浆管路畅通以及灰浆泵的正常压力。
水泥搅拌桩工程监理实施细则范文(二篇)
水泥搅拌桩工程监理实施细则范文一、引言水泥搅拌桩工程监理实施细则的目的是规范水泥搅拌桩工程监理工作,确保工程质量和安全,促进工程顺利进行。
本细则包括水泥搅拌桩工程监理工作的组织与管理、质量控制、安全保障等方面的要求,以便监理人员在实施工程监理过程中的工作能够有序、高效进行。
二、水泥搅拌桩工程监理组织与管理(一)监理组织架构1. 设立项目监理部门,配备专业监理人员,包括工程监理师、监理工程师等。
2. 监理人员需具备相应的资质证书,并参加相关培训,熟悉水泥搅拌桩工程监理技术和法规要求。
3. 设立监理工作会议制度,在工程各阶段召开监理会议,讨论解决工程中存在的问题。
(二)监理任务分工1. 制定监理工作计划和监理方案,明确每个监理人员的任务分工。
2. 监理人员根据任务分工,进行工程质量检查、施工现场监督、工程文件审查等工作。
(三)监理合同管理1. 检查监理合同的签订情况及履行情况,确保监理权益。
2. 监控施工方与监理方的合作进展,及时处理纠纷和问题。
三、水泥搅拌桩工程施工质量控制(一)前期准备1. 监理人员需参与施工前的工程勘测、设计审查和施工方案的制定,确保施工前的准备充分。
2. 检查勘察设计文件的完整性和合法性,提出合理化建议和意见。
(二)施工现场管理1. 监理人员需对施工现场进行巡查和监督,确保施工进度和质量符合设计要求。
2. 检查施工机械设备的合理配置和使用情况,确保施工能够顺利进行。
(三)质量检查与验收1. 监理人员需按照规定对水泥搅拌桩施工过程中的质量进行检查和验收,发现问题及时整改。
2. 参与施工方的工程质量验收,确保水泥搅拌桩工程达到设计要求。
四、水泥搅拌桩工程安全保障(一)安全管理制度1. 监理人员需参与制定水泥搅拌桩工程的安全管理制度,保障施工过程中的安全。
2. 监督施工方严格执行安全管理制度,保障施工人员的人身安全。
(二)施工安全措施1. 监理人员需检查施工方的安全措施是否到位,包括工地围挡、安全标志标牌的设置等。
三轴水泥搅拌桩止水帷幕的施工及监理控制要点见解
Construction & Decoration建筑与装饰2023年1月下 89三轴水泥搅拌桩止水帷幕的施工及监理控制要点见解林晶中晟宏宇工程咨询有限公司 湖北 武汉 430040摘 要 止水帷幕是深基坑施工过程中比较常用的支撑、止水以及挡土结构,对深基坑施工的顺利开展具有重要的作用。
目前已经发展出了多项止水帷幕施工技术,其中的三轴水泥搅拌桩技术由于成桩时间较短,且止水效果较好,能够有效提高施工效率和施工质量。
因此在深基坑工程施工实践中得到了广泛的应用。
本文将对三轴水泥搅拌桩的各项施工技术要点进行分析,并探讨三轴水泥搅拌桩施工监理工作中应重点控制的技术环节,以保证止水帷幕施工的质量安全。
关键词 三轴水泥搅拌桩;止水帷幕;施工技术要点;监理控制要点Insights on Construction and Supervision Control Points of Three-Shaft Cement Mixing Pile Water-Stop CurtainLin JingZhongsheng Hongyu Engineering Consulting Co., Ltd., Wuhan 430040, Hubei Province, ChinaAbstract The water-stop curtain is a commonly used support, water-stopping and retaining structure in the construction of deep foundation pit, which plays an important role in the smooth development of deep foundation pit construction. At present, a number of water-stopping curtain construction technologies have been developed, among which the three-shaft cement mixing pile technology can effectively improve construction efficiency and construction quality due to the short pile forming time and good water-stopping effect. Therefore, it has been widely used in the construction practice of deep foundation pit engineering. This paper analyzes the key points of various construction technologies of three-shaft cement mixing pile, and discusses the technical links that should be controlled in the construction supervision of three-shaft cement mixing pile to ensure the construction quality safety of the water-stop curtain.Key words three-shaft cement mixing pile; water-stop curtain; key points of construction technology; supervision control points引言近年来我国建筑行业发展较快,施工技术水平取得了明显的提高,工程项目的规模和数量不断增加,深基坑工程已经成为很多工程项目中的重点施工内容。
水泥搅拌桩监理细则范本(2篇)
水泥搅拌桩监理细则范本水泥搅拌桩是一种常用的地基处理和加固技术,用于在建筑工程中增强土壤的承载能力。
为了确保水泥搅拌桩施工质量,监理工作非常重要。
下面是水泥搅拌桩监理的细则范本,详细介绍了监理工作的内容和要求。
一、监理人员要求1. 水泥搅拌桩监理人员应持有相关工程监理资格证书,并有相关工程监理经验。
2. 监理人员应具备较强的工程技术能力和协调能力,能够独立完成监理任务。
3. 监理人员应熟悉水泥搅拌桩施工的相关规范和技术要求,能够全面了解施工进度和质量控制。
4. 监理人员应具备良好的沟通和协调能力,能够与施工单位、设计单位等各方进行有效的沟通。
二、监理前期准备工作1. 监理人员要与设计单位充分沟通,了解设计要求和施工方案。
2. 监理人员要熟悉施工方案和施工图纸,对施工过程及各项指标进行全面的了解。
3. 监理人员要对施工现场进行勘察,熟悉地质情况和周边环境。
4. 监理人员要审核施工单位的施工组织设计和质量控制方案,并提出合理的修改意见。
5. 监理人员要与施工单位一起编制施工进度计划和质量检查计划。
三、监理过程中的工作1. 监理人员要根据施工单位提供的施工日志和施工记录,及时进行现场检查和监督。
2. 监理人员要密切关注施工过程中的关键节点和重要工序,确保施工进度和质量。
3. 监理人员要检查施工现场的安全措施是否到位,并及时提出整改意见。
4. 监理人员要对水泥搅拌桩的材料和配合比进行抽样检验,确保满足设计要求。
5. 监理人员要对水泥搅拌桩的施工过程进行全面监督,确保施工工艺规范和施工质量。
6. 监理人员要对水泥搅拌桩的成型情况进行检查,确保其形状和尺寸符合要求。
7. 监理人员要对水泥搅拌桩的坍落度和强度进行抽样检测,确保达到设计要求。
8. 监理人员要检查水泥搅拌桩周围的土壤情况,确保其承载能力满足设计要求。
9. 监理人员要与设计、施工单位及时进行沟通,协调解决工程质量和技术问题。
四、监理报告和总结1. 监理人员要及时编写监理记录,详细记录施工现场的情况和监理过程中发现的问题。
三轴水泥土搅拌桩 监理实施细则标准化示范文本(定稿)水利工程
三轴水泥土搅拌桩监理实施细则示范文本注:本细则为三轴水泥土搅拌桩施工监理的通用版本,各项目监理机构应参照本格式并结合各自的工程实际情况编制。
HB-SC-02-D上海××××××监理公司监理实施细则工程名称专业名称三轴水泥土搅拌桩编制人总监月日.年地址:××××××邮编:×××××电话:×××××传真:×××××目录第一章专业工程概况及特点 ..................................... - 3 -1. 专业工程概况............................................ - 3 -2. 专业工程特点............................................ - 3 -3. 编制依据................................................ - 3 -第二章监理工作流程及监控要点 ................................. - 4 -1. ×××施工监理工作流程.................................. - 4 -2. 监理工作的控制要点及目标值.............................. - 4 -2.1 ×××施工质量控制目标值............................... - 4 -2.2 施工准备阶段监理控制要点............................... - 5 -2.3 施工过程监理控制要点................................... - 9 -2.4验收阶段监理控制要点 .................................. - 15 -第三章监理工作方法及措施 .................................... - 17 -1. 监理工作方法........................................... - 17 -1.1 技术文件、报告和报表.................................. - 17 -1.2 指令文件与一般管理文件................................ - 17 -1.3 现场监督和检查........................................ - 18 -1.6.4 规定质量监控工作程序................................ - 18 -1.5 专题会议.............................................. - 18 -1.6 工程款支付............................................ - 18 -2. 监理工作措施........................................... - 18 -2.1组织措施 .............................................. - 18 -2.2 技术措施.............................................. - 18 -2.3 经济措施.............................................. - 18 -2.4 合同措施.............................................. - 18 -第四章安全监理措施.......................................... - 19 -第五章附表.................................................. - 20 -注:该目录参考《建设工程监理规范》(GB50319-)编制,其他行业或专业(如水利工程、水运工程、公路工程等)的监理细则目录应参考相应的监理规范。
2023年水泥搅拌桩监理细则
2023年水泥搅拌桩监理细则第一章总则第一条为了规范水泥搅拌桩施工监理工作,提高工程质量,保障工程安全,制定本细则。
第二条本细则适用于2023年进行的水泥搅拌桩工程的监理管理工作。
第三条监理单位应具备相应的资质要求和技术能力,并按照相关法规和标准进行监理工作。
第二章施工前准备第四条水泥搅拌桩施工前,监理单位应对项目资料进行审查,并与施工单位进行协调和沟通,确保施工方案和工艺符合规范和设计要求。
第五条监理单位应对现场进行勘察和堆场验收,确保场地平整、无积水、无障碍物,堆场应满足施工需要。
第六条监理单位应对施工设备进行检查和验收,确保设备齐全、完好,并按照相关规定进行安装和调试。
第三章施工过程监督第七条监理单位应对施工现场进行巡视和检查,确保施工过程符合技术标准和安全要求。
第八条监理单位应对材料和配合比进行抽查和检验,确保水泥搅拌桩的质量符合要求。
第九条监理单位应加强施工工序的监督,包括桩基钻孔、桩基清洗、注浆灌注等,确保施工无误。
第四章施工质量控制第十条监理单位应对桩基进行质量检查和验收,包括桩深、桩径、桩位偏离等,确保符合设计要求。
第十一条监理单位应对水泥搅拌桶进行检查和验收,确保设备和工艺符合标准和规范要求。
第十二条监理单位应对施工过程中的质量问题进行处理和记录,包括现场整改和整改报告。
第五章安全环保监管第十三条监理单位应对施工现场的安全措施进行检查和评估,确保施工安全无事故。
第十四条监理单位应对施工过程中的环境污染进行监督,确保施工符合环保要求。
第十五条监理单位应对施工现场进行消防检查和评估,确保消防设施完善,应急措施到位。
第六章工程验收和评估第十六条水泥搅拌桩施工结束后,监理单位应对工程进行全面验收,确保符合设计要求和规范和标准。
第十七条监理单位应对工程进行质量评估和验收报告的编制,报送相关部门。
第七章监理日志和报告第十八条监理单位应做好监理日志的记录,详细记录施工过程、质量问题、安全情况等,并及时报告给相关方。
水泥搅拌桩监理细则模版
水泥搅拌桩监理细则模版一、搅拌桩施工前的准备工作1. 施工前的准备施工前,监理人员应对施工现场进行全面检查,并与施工单位协商沟通,确保施工所需的人力、机械、材料等准备工作已完成,并按照设计要求进行组织研究和安排。
2. 搅拌桩设备与材料的检查监理人员应对搅拌桩设备和材料进行检查,包括设备的完好性、设备的调试情况、材料的质量等方面,确保搅拌桩施工能够顺利进行。
3. 施工现场的准备监理人员应对施工现场进行准备,包括现场的清理、场地的平整等工作,确保施工现场满足施工要求,并保证施工安全。
二、搅拌桩施工过程的监督1. 施工方案的确认监理人员应参与施工方案的制定与确认,确保施工方案符合设计要求,并具备合理性和可行性。
2. 施工人员的监督监理人员应对施工人员进行监督,包括施工人员的专业知识、施工技能等方面,确保施工人员具备相应的资质和能力。
3. 设备的监督与检查监理人员应对搅拌桩设备进行监督与检查,包括设备的使用情况、设备的维护保养等方面,确保设备能够正常运行。
4. 施工过程的监督监理人员应对搅拌桩施工过程进行全程监督,包括搅拌桩的混合均匀性、搅拌桩的灌注情况等方面,确保施工过程符合设计要求。
5. 质量验收监理人员应参与搅拌桩的质量验收工作,包括对搅拌桩的质量检查、质量测试等方面,确保搅拌桩的质量符合规范要求。
三、施工后的监理工作1. 施工记录的整理监理人员应对搅拌桩施工过程中的记录进行整理,包括施工日志、施工资料等方面,确保施工记录完整、准确。
2. 报告的编写与提交监理人员应及时编写施工监理报告,并向业主提交,报告内容应包括搅拌桩施工的进展情况、施工中出现的问题及解决方案等方面,以及对施工质量的评估。
3. 施工行为的监督监理人员应对施工单位的行为进行监督,包括施工单位的操作规范、施工单位的安全意识等方面,确保施工单位遵守相关规定。
四、安全管理与质量控制1. 安全管理监理人员应对搅拌桩施工的安全管理进行监督,包括施工现场的安全巡查、施工人员的安全培训等方面,确保施工过程安全可靠。
2023年水泥搅拌桩工程监理实施细则
2023年水泥搅拌桩工程监理实施细则第一章总则第一条为规范2023年水泥搅拌桩工程的监理工作,提高工程质量,确保工程安全,制定本实施细则。
第二条本实施细则适用于2023年水泥搅拌桩工程的监理工作。
第三条监理人应具备相应的资质,熟悉相关法规、规范和标准,具备一定的工程经验和技术能力。
第四条监理机构应具备相应的资质,能够独立、公正、客观地完成监理任务。
第五条监理人应秉持诚实、公正、勤勉、严谨的原则,坚守职业道德,保守工程商业秘密。
第六条监理机构应保持独立性,不与其他项目参与方发生利益冲突,不接受与项目相关的礼品、回扣等。
第七条监理机构应确保监理人员合理轮换,避免人员长期驻场,以免因熟悉程度的不同对工程质量造成影响。
第二章监理前准备工作第八条监理机构接到委托时,应派遣监理人员到工程现场进行勘察,熟悉工程地形、地质情况等。
第九条监理机构应制定监理计划和实施方案,明确监理工作的重点和难点,确保监理工作有序进行。
第十条监理机构应与施工单位、设计单位等相关参与方进行沟通,明确各方责任,确保监理工作得到充分合作。
第十一条监理机构应编制监理手册和监理表格,明确监测内容、频次和方法,确保监理数据的准确性和可比性。
第十二条监理机构应与委托方协商确定监理费用,并按照相关规定进行结算。
第三章监理施工阶段工作第十三条监理人员应全程驻场,对施工过程进行全程监理。
第十四条监理人员应对施工人员的资质进行核查,确保施工人员合格。
第十五条监理人员应对施工材料进行检查,确保施工材料符合相关标准和规范要求。
第十六条监理人员应对施工方案进行审核,并及时提出修改意见,确保施工方案的合理性和可行性。
第十七条监理人员应对施工现场进行巡查,及时发现并纠正施工中存在的问题,确保施工质量。
第十八条监理人员应记录施工过程中的关键节点,进行监理日志记录,以备后期复查和总结。
第十九条监理人员应按照合同约定及时提交监理报告,包括施工质量、安全、进度等方面的情况。
- 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
- 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
- 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。
水泥搅拌桩止水帷幕监理细则WEIHUA system office room 【WEIHUA 16H-WEIHUA WEIHUA8Q8-上海新高桥开发有限公司高桥新城B-3地块商品房项目水泥搅拌桩止水帷幕监理实施细则监理单位(章):上海三凯建设监理有限公司高桥新城B-3地块商品房项目监理机构专业监理工程师:总监理工程师:日期:水泥搅拌桩止水幕监理实施细则一、工程概况1、工程名称:上海高桥新城B-3地块商品房项目;2、设计单位:中建国际(深圳)设计顾问有限公司;3、建设单位:上海新高桥开发有限公司;4、施工单位:上海住总集团建设发展有限公司5、监理单位:上海三凯建设监理有限公司;6、工程建设地点:东至张杨北路、南至夏碧路、西至莱阳路、北至春晖路二、工程建设规模用地面积:27227平方米居住户数:314户;地上计容积率建筑面积:平方米;地上不计容积率建筑面积:平方米;住宅建筑面积:平方米;多层住宅建筑面积:平方米;高层住宅建筑面积:平方米;配套商业建筑面积:平方米;配套公建建筑面积:平方米;地下建筑面积:平方米;地下机动车库:平方米;1#-8#楼(住宅),9#楼(工建配套),南门卫,西门卫,人防地下车库及室外总体。
二、水泥搅拌止水帷幕工程设计要求:1.由于施工场地的限制,靠北面近高宝路设计采用双轴水泥土搅拌桩。
双轴水泥搅拌桩Φ700@950双轴水泥土搅拌桩,桩深。
水泥搅拌桩的水泥掺量为13%,在暗浜区域,水泥搅拌桩水泥掺量应增加至16%,并设计轻型井点降水。
三、监理依据:1、基坑围护设计方案,以及有关图纸会审纪要、设计变更、技术核定单等。
2、工程招标文件、合同及补充协议。
3、上级及国家政府机关颁发的施工规范、规定。
4、国家及上海市施工验收规范。
主要包括:《地基与基础工程及验收规范》GBJ202-83上海市标准《地基处理技术规范》DBJ08-40-94《建筑工程施工质量验收统一标准》(GB50300-2001)《软土地基深层搅拌桩加固技术规程》YBJ225-915、经审批的施工组织设计、施工方案等。
四、监理目标1.质量目标:一次验收合格。
2.进度目标:力争在业主计划工期内竣工。
3.安全监理目标:无重大安全事故和管线事故,争创市级文明工地。
五、监理准备工作围护结构施工前,监理组向公司办公室提供资源配备申请,包括与本工程相配套人员、检测设备、规范、标准图集等。
监理组熟悉施工图纸、地质勘察资料及国家、上海市相应的规范标准等。
编写水泥搅拌桩止水帷幕监理细则并进行交底。
总监组织监理组进行搅拌桩监理专业知识学习。
审核水泥搅拌桩止水帷幕施工方案。
检查施工单位设备、材料、人员准备情况,是否按既定的施工方案准备。
检查现场作业条件。
六、监理工作流程1施工组织设计(方案)审批程序3. 施工图纸设计交底程序4.材料审批程序5.七、施工操作程序 前期工作:1. 施工图、有关技术规范和验收标准。
2. 地质勘察资料。
3. 施工组织设计(施工方案)。
分项工程施工过程检查监理工作流程工序施工检查内容: *开工前检查 *工序交接检查 *隐蔽工程检查 *停工后复工前检查 *随班或跟踪检查检查方法 *目测法 *实测法 *试验检查整改措施 *口头通知 *发备忘录 *发监理通知4.材料:原材料合格证和试验报告。
5.作业条件:1)测量设置标准桩与水准点、标高和轴线标志;2)施工机具及设备的准备、完好率,保证正常作业;3)施工作业区域场地平整和排水措施的落实;4)邻近地下管线和建筑物的监测与保护措施的落实。
●施工阶段:深层搅拌施工可按下列步骤进行:1.深层搅拌机械就位;2.预搅下沉;3.喷浆搅拌提升;4.重复搅拌下沉;5.重复搅拌提升直至孔口;6.关闭搅拌机械。
●验收阶段:1.原材料合格证及试验报告;2.每根桩的施工记录及质量评定;3.成桩7天内用轻便触探观察搅拌均匀程度、判断桩身强度;4.如有必要,尚应进行取样做抗压强度试验、单桩或复合地基载荷试验检验其承载力、开挖检验桩顶部分外观质量。
八、控制程序及控制要点●前期工作:1.查看工程地质勘察报告。
要点:应查明填土层的厚度和组成,软土层的分布范围、含水量和有机质含量,地下水的侵蚀性质等。
2.审查承包商各项施工前作业条件是否具备。
要点:1)测量设置标准桩与水准点、标高和轴线标志;2)施工机具及设备的准备、完好率,保证正常作业;3)邻近地下管线和建筑物的监测与保护措施的落实。
4)地上和地下的一切障碍物是否已清除。
5)场地平整标高是否比设计确定的基底标高再高出~米。
3.参加设计交底及图纸会审,明确设计意图。
要点:水泥的品种、标号、掺量13%;设计停浆面的高度应不低于现场场地标高~;桩位平面布置图;成桩质量的检测手段和标准等。
4.审查承包商提交的施工组织设计、施工技术方案等。
重点审查:桩位平面布置图;打桩顺序;成桩工序;施工质量保证体系;成桩质量控制与检测措施;邻近地下管线和建筑物的监测与保护措施等。
5.督促承包商在正式施工前,按施工组织设计确定的搅拌施工工艺制作数根试桩,并对试桩结果组织各方评审,以确定:1)根据灰浆泵输浆量,灰浆经输浆管到达喷浆口的时间,以确定开始喷浆的座浆时间。
2)确定喷浆时的提升速度(以保证水泥均匀分布在桩身)。
3)确定浆液的水灰比。
4)确定是否添加外掺剂及其掺量。
5)复搅深度。
6)确定成桩的工艺流程。
6.在上述各项准备工作就绪后,协助业主下达开工通知。
施工阶段:1.原材料控制:要点:检查水泥的品种、标号是否符合设计要求,检查其出厂合格证及试验报告。
督促承包商对水泥按规定进行抽样复试。
检查外掺剂的出厂合格证及质保书。
抽查已制备的水泥浆是否沉淀、离析。
2.检查钻头直径,保证桩径偏差<4%设计桩径。
检查桩机定位偏差(<50mm)。
检查桩架水平度及垂直度,保证成桩垂直偏差<%。
3.预搅下沉时不宜冲水,当遇到较硬土层或糊钻须冲水下沉时,要征得监理工程师同意。
4.为了保证桩端施工质量,当浆液到达出浆口后,应喷浆座底30S,使浆液完全到达桩端。
5.为使水泥土桩体搅拌均匀,一般要求搅拌次数必须比喷浆次数多,为保证桩顶质量,当喷浆达到桩顶标高时,宜采用慢速提升搅拌或停止搅拌数秒,使桩头均匀密实。
6.抽查水泥浆的水灰比及外掺剂的掺量。
随机检查承包商的水泥浆设备记录(如拌制浆液罐数、浆液制备时间、泵送浆液的时间等)。
要点:严格控制喷浆提升时间。
应要求施工单位有专人负责制桩记录。
监理随机抽查,同时,监理应有自己的实测记录。
7.施工时,如因故停浆,其复喷应征得监理工程师同意,宜将搅拌机下沉至停浆点以下处,待恢复供浆时再喷浆提升。
8.桩与桩间的搭接时间超过24小时,应对最后一根桩先进行空钻,留出榫头,以待下一批桩搭接,接桩施工应征得监理工程师同意。
成桩后的质量检验:1.施工过程中必须随时检查施工记录,检查重点是:水泥用量、桩长、制桩过程中有否断桩现象、搅拌提升时间和复搅次数。
2.水泥土桩应在成桩后七天内进行质量跟踪检验。
可用轻便触探器中附带的勺钻钻取桩身加固土样,观察搅拌均匀程度和判断桩身强度,或用静力触探测试桩身强度沿深度的变化。
检验桩的总数量应不小于总桩数的2%。
对N10贯入100mm 击数少于10击的不合要求的桩体要进行桩头补强。
轻便触探贯入桩体的深度不小于,当每贯入100mm,N10≥30击时可停止贯入。
3.若因工程需要,可在桩头截取试块或钻芯取样作抗压强度试验,必要时可取基础下500mm长的桩段进行现场抗压强度试验。
4.水泥土搅拌桩的质量检验可用单桩或复合地基载荷试验检验其承载力。
载荷试验宜在龄期28天后进行,检验点数每个场地不得少于三点。
督促承包商按要求对桩身质量进行检测(如轻便触探、钻芯取样、静载或动载试验等),并审查检测结果。
5.基槽开挖后,督促承包商检验桩位、桩数与桩顶质量,绘制桩位竣工图。
6.对深层搅拌桩竣工后的质量进行检验评定。
九、监理手段主要采用施工前控制,确定主要参数及施工工艺。
在施工过程中,应随机抽查施工单位制桩记录的真实性、可靠性,以及水泥浆的水灰比。
同时根据需要,实测制桩过程中泵送时间、搅拌机提升速度和复搅深度等参数,加以记录。
十、质量目标风险分析水泥搅拌桩止水帷幕,在基坑开工程中使用频率相当高,施工工艺日趋成熟。
搅拌桩施工过程中应注意桩位准确,保证垂直度偏差在允许偏差范围内,以保证基坑开挖工程顺利施工。
作为防水设施,水泥搅拌桩之间搭接对工程最终质量影响甚大,施工过程中经常对施工机械进行检查,保证其正常运行,另外,加强浆液管理,保证前后台协调一致。
由于搅拌桩送浆时需要一定压力,应对周围敏感建筑物、管线进行监测,做到信息化施工。
施工过程中如发生意外事故,如停浆、冒浆、抱钻等,应会同有关人员妥善处理,并应对处理措施可行性进行周密研究,确保工程质量。
十一、资料管理工作要点1施工组织设计2水泥质保书,复验单、准产证、准用证3水泥土试块报告4搅拌桩施工汇总表,原始记录5施工竣工图6技术核定单7工程量变更签证8事故处理报告十二、本分部工程监理管理用表1 监A-01 施工组织设计(方案)报审表2监A-02 工程开工报审表3 监A-03 分包单位资格报审表4 监A-05 成品半成品供应单位资质报审表5 监A-06 建筑材料报审表6 监A-07 主要工程设备选型报审表7 监A-08 复工申请表8 监A-12 整改复查报审表9 监A-13 技术核定报审表10 监A-14 工程报验单11 监A-15 施工测量放线报验单12 监A-16 工程质量问题(事故)报告单13 监A-17 工程质量事故处理方案报审表14 监A-19 施工备忘录上海三凯建设监理有限公司高桥新城B-3地块商品房项目监理机构2011年月。