土耳其FK2水电站
FEKE-II DAM AND HYDRO-ELECTRICAL POWER PLANT
启动试运行大纲
Outlint of Start-up Test for Hydraulic-Turbine and Generator Units
EAST CHINA INVESTIGATION AND DESIGN INSTITUTE
2010-9
OUTLINE OF START-UP TEST FOR TURBINE-GENERATOR-3×36MW
------------------------------------------------------------------------------------------------------------------------------------------
目 录 Contents
1.组织措施 Organization (2)
2.安全措施 Safety measures (3)
3.机组启动试运行前应具备的条件conditions before start-up operation (6)
4.机组启动试运行前的检查Inspecti on before start-up operation (7)
5.机组充水试验Water-filling test (15)
6.水轮发电机组空转试验 Turbine generator no load test (18)
7.水轮发电机组过速试验Turbine generator over-speed test (25)
8.无励磁自动开停机试验Non-excitation auto start and shut down test (28)
9.水轮发电机、变压器、154KV升压站短路升流试验Turbine generator ,transformer and 154KV switchyard short circuit raise current test (30)
10.发电机空载特性试验Generator no-load characteristic test (36)
11.水轮发电机组并列试验 Turbine-generator parallel in test(此部份试验需要系统已经送电)(this test need system put into operate) (41)
12.水轮发电机组带负荷试验Turbine generator on-load test (44)
13.水轮发电机组甩负荷试验Generator group load rejection test (46)
14.调速器事故低油压关机试验Shutdown test of low oil pressure of governor (48)
15.事故配压阀动作关闭导水叶及重锤蝶阀联动关闭试验When accident distribution valve act, the linkage of closing vane and hammer butterfly (50)
16.机组72小时试运行Generator Unit 72h continuous test run with load 52
17.附件:Accessory (52)
1.组织措施 Organization
机组启动验收小组和试运行联合调试小组及各参试厂家代表具体人员名单如下:
Inspection of starts-up operation team, the joint commissioning team and manufacturer representative as following:
1.1试运行联合调试小组:Joint commissioning team
组 长(group leader): 陈志 Chen Zhi
副 组 长(vice-group leader):章启国 Zhang Qiguo 唐国方Tang Guofang 袁建伟 Yuan Jianwei
协 调(ordination): 海比布Haibibu 卢皖娇 Lu Wanjiao 指 挥 (conductor): 章启国 Zhang Qiguo
试 验 (tester): 毛华匡Mao Huakuang 张会忠 Zhang
Huizhong叶世武 Ye Shiwu
电气操作(electric operator):邝华昌 Kuang Huachang 彭玉军
Peng Yujun 管长周Guan Zhangzhou 机械操作(machine operator ):张常启 Zhang Changqi 张品寿
Zhang Pinshou 曲春峰 Qu Chunfeng 本启动试运行大纲由施工单位编制、校核,并报土方业主及相关部门备案、批准。
Start-up operation of the outline prepared by the construction unit, check and report to relevant departments and owners for approval.
1.2参试厂家人员:Manufacturer representative
主机厂家:Turbine-Generator
=================================================================================
监控厂家:CSCS
调试器厂家:Governor system
励磁厂家:Excitation system
蝶阀厂家:Butterfly valve
1.3试运行联合调试小组职责Joint commissioning team responsibilities
负责按本启动试运行大纲安全、技术措施对启动试运行的安全、技
术等方面全面部署、安排和现场指挥,是现场总负责人。对启动试运行
的安全、技术全面负责。
Joint commissioning team is responsible for the security framework, technical measures, security, technology, and full deployment, command arrangements and the scene is the overall responsibility for the scene.
2.安全措施 Safety measures
2.1总则 General principles
本措施适用于土耳其FEKE2水电站启动试运行全过程,本措施为通
用部分。
This measure applies to Turkey FEKE2 the whole process of
hydropower station starts-up operation, the measures for the
general. =================================================================================