Purpose
目的
This procedure covers the application of all concrete coating systems applied by CELEB. 本施工工艺规程规范所有北京九州华清防腐混凝土涂装系统的施工
Scope 范围
This procedure will be followed in all applications. 本规程应贯彻于所有施工过程中。
Responsibilities
责任
The Project Manager 项目经理
- Operation and management of grinding and painting works. Plan work
schedules. Maintained strict conformance to clients required specifications. 负责研
磨和涂装作业的管理及运作工作。准备工作进度表。严格遵照客户要求的涂装系统及规范施
工。
- Liaise with Engineers, Production, . Personnel and other contractors on work
schedules, job performance and implementation on quality control requirements.
Exercised quality control surveillance on conformance to required specifications.
协调施工各方,确保按质量按进度施工作业,控制质量以符合业主的涂装系统规范。
The Supervisor
监理
- To ensure that all tests are undertaken and, in the case of witness tests the client representative is present.
保证执行各项检测工作,检测时应有客户代表在场。
The Forman -
领班
- To ensure that all work conforms to specifications and is done
in a workman like manner.
保证按标准施工,施工人员工作态度端正。
References
标准
Where referred to in this specification, the latest edition of the following specifications, standards and other documents apply. 本规程参照以下标准及规范制定:
Standard Practice for the Qualification of Coating Applicators for Application of Coatings to Concrete Surfaces ” “Standard Practice for Surface Cleaning Concrete “Standard Practice for Abrading Concrete ” “Standard Practice for Surface C leaning Concrete
Unit Masonry for Coating ”
Documentation 文件
Daily Work Report / 每日工作报告
Daily Report / 质量日报表
Procedure 规程
6.1 Inspection of the Concrete Substrate 混凝土基层检测
It is to determine the concrete ' s general condition, soundness,
presence of contaminants, presence of moisture vapor emissions and the best methods to
use in preparation of the surface to meet the requirements of the client or the manufacturer ' s recommendation.
对混凝土通过现场堪察及基层检测,掌握混凝土的总体情况、表面坚实 度、污染情况及潮气含量,从而决定表面处理最佳方式,以达到客户和 材料生产商的要求。
Pre-clean all surfaces by brooming and if necessary accomplished by scrubbing with heavy
duty cleaner / degreaser or low pressure water cleaning (less than 5,000 psi) or chemical
washing to remove oils, grease, wax, fatty acids and other contaminations. 先用扫帚清洁地
表,必要时使用深度清洁剂去除地表污渍,或用低压水 冲洗(不超过 5,000 psi ),也可以使
用化学溶液去除油污,油脂,表 腊,脂肪酸或其它污染。
6.3 Removal of Surface Laitance and Creation of Surface Profile 去除水泥翻沫,提供粗糙度
Removal of surface laitance and /or curing compound and creation of surface profile can be
accomplished by a number of methods each utilizing a selection of tools, equipment and
materials to accomplish the intended purpose, (See table below). Selection is dependent
upon the type of surface to be prepared and the type of system to be installed. In addition,
floors, walls, ceilings, trenches, tanks and sumps each have their own particular
requirements. The type and thickness of the selected coating system also plays an important role in the selection process. Regardless of the method selected or tools employed, we must provide a surface that will accept the application of polymer-based products and allow the
mechanical bond of the polymer securely to the concrete.
去除水泥翻沫及养护剂、脱模剂需使用手动工具或设备来完成。根据待 涂装地坪的表面以及不同的涂装系统,选择不同的作业工具和作业方法 (见下表)。此外,地坪、墙壁、天花板、地沟、水槽和水罐对工具使用 会有不同的要求。而且工具选择与所选用的涂装厚度和类型也有关系。 无论选择哪种类型的工具,我们必需提供一个适合聚合树脂材料涂装的 表面,且保证涂装材料与地坪有良好的机械附着力。
The follow ing table provides a guide for the degree of surface profile required for the coating or overlay to be applied and the preparati on methods used to gen erate each profile to the specified sta ndard.
以下表格为各类涂装系统所需达到的粗糙度进行分类并对相应的表面处 理方法提供了指南。 ASTM D4227-99
ASTM D4258-83 for Coating ASTM D4259-88 ASTM D4261