电力建设工程装置性材料综合预算价格(2013年版)除税价格
电力建设工程预算定额(说明)第六册
电力建设工程预算定额国家能源局关于颁布2013版电力建设工程定额和费用计算规定的通知国能电力[2013]289号各有关单位:为适应电力工业发展的需要,规范电力工程建设投资,维护工程建设各方利益,我局委托中国电力企业联合会组织编制了《2013版电力建设工程定额和费用计算规定》,具体包括《电网工程建设预算编制与计算规定》、《火力发电工程建设预算编制与计算规定》、《电力建设工程概算定额——建筑工程、电气安装工程、热力设备安装工程、通讯工程、调试工程》,以及《电力建设工程预算定额——建筑工程、电气安装工程、热力设备安装工程、线路工程、通讯工程、调试工程、加工配制品》。
现印发你们,请遵照执行。
国家能源局(印)2013年8月1日电力建设工程预算定额第六册通信工程总说明一、《电力建设工程预算定额》(2013年版)共分七册,包括:第一册建筑工程(上册、下册)第二册热力设备安装工程第三册电气设备安装工程第四册输电线路工程第五册调试工程第六册通信工程第七册加工配制品二、本册为第六册《通信工程》(以下简称本定额),适用于电力专用通信网、信息网及视频监控、电子围栏、门禁系统、输电线路在线监测、光纤入户等相关工程建设。
三、本定额是编制施工图预算的依据,是编制概算定额的基础,也是编制标底、最高投标限价和投标报价的参考依据。
四、本定额主要编制依据有:1.GB/T7329-2008 电力线载波结合设备2.GB/T7946-2008 脉冲电子围栏及其安装和安全运行3.GB/T18018-2007 信息安全技术路由器安全技术要求4.GB/T50314-2006 智能建筑设计标准5.GB50374-2006 通信管道工程施工及验收规范6.GB50395-2007 视频安防监控系统工程设计规范7.GA/T367-2001 视频安防监控系统技术要求8.DL/T544-2012 电力通信运行管理规程9.DL/T545-2012 电力系统微波通信运行管理规程10.DL/T548-2012 电力系统通信站过电压防护规程11.DL/T598-2010 电力系统自动交换电话网技术规范12.DL/T788-2001 全介质自承式光缆13.DL/T795-2001 电力系统数字调度交换机14.DL/T798-2002 电力系统卫星通信运行管理规程15.DL/T832-2003 光纤复合架空地线16.DL/T860系列变电站通信网络和系统17.DL/T981-2005 电力系统控制及其通信数据和通信安全18.DL/T1146-2009 DL/T860实施技术规范19.DL5009 电力建设安全工作规程20.YD/T5032-2005 会议电视系统工程设计规范(附条文说明)21.DL/T5344-2006 电力光纤通信工程验收规范22.DL/T5391-2007 电力系统通信设计技术规定23.DL/T5392-2007 电力系统数字同步网工程设计规范24.电力建设工程工期定额(2012年版)五、本定额是在设备、装置性材料等施工主体完整无损,符合质量标准和设计要求,并附有制造厂出厂检验合格证和试验记录的前提下,在正常的气候、地理条件和施工环境条件下,按照施工图阶段合理的施工组织设计,选择常用的施工方法与施工工艺,考虑合理交叉作业条件下进行编制。
2013年版电力建筑定额介绍
单击此处编辑母版标题样式
3、 编制工作范围 本次定额编制范围包括:
——2006年版《电力建设工程概算定额》第一册: 建筑工程。 ——2006年版《电力建设工程预算定额》第一册: 建筑工程。
下列工程项目与技术不列入编制范围内: ——铁路; ——桥梁; ——码头; ——航道及港池; ——取排水隧洞。
架)已经综合在相应的定额子目中,其费用不再单独 计算。
Page 35
(3)混凝土施工费用调整 ——混凝土施工使用混凝土泵车浇注时,每浇制1m3 混凝土成品增加22元施工费用,其中:材料费增加22.7 元,机械费增加9.7元,人工费减少10.4元。泵送混凝 土工程量在初步设计阶段可以按照全厂(站)混凝土 量80%计算。混凝土量不包括临建工程中的混凝土量、 不包括购置成品混凝土构件混凝土量。如有施工组织 设计,泵送混凝土工程量按照施工组织设计确定。 ——混凝土施工采用现场制备(搅拌)时,每制备 1m3混凝土减少9.8元施工费用,其中:机械费减少 18.4元,人工费增加8.6元。
Page 15
单击此处编辑母版标题样式
(4)2013年国内人工、材料、机械台班单价。 (5)形成“四新”内容的技术标准、设计文件、施 工方案等资料。 (6)发电、电网企业定额标准。 (7)调研资料及有关资料。
Page 16
单击此处编辑母版标题样式
6、建筑工程概预算定额结构 (1)2013年版建筑工程概预算定额包括发电、变电、 换流站、通信站、串补站等建筑工程定额子目。 (2)2013年版《电力建设工程概算定额》第一册建 筑工程定额设置11章。包括建筑物与构筑物的一般 土建、给水、排水、采暖、通风空调、除尘、照明 与接地、特殊消防及烟塔接地工程定额子目。
P)2013年版《电力建设工程预算定额》第一 册建筑工程上册设置15章。包括建筑物与构筑 物的一般土建工程与措施工程定额子目。 (4)2013年版《电力建设工程预算定额》第一 册建筑工程下册设置7章。包括建筑物与构筑物 的给水与排水、照明与接地、消防、除尘、通 风与空调、采暖、防腐与绝热工程定额子目。
广东省电网工程建设预算编制与计算规定实施细则
粤电定〔2016〕3号附件1广东省电网工程建设预算编制与计算规定实施细则第一章总则第一条为加强我省电网工程建设预算管理,根据《电网工程建设预算编制与计算规定》(2013年版)的规定,结合我省具体情况,特制定本实施细则。
第二条本实施细则作为广东省电网工程基本建设的行业标准,适用于省内各种投资渠道建设上述范围的新建、扩建和改建工程。
第三条细则适用范围:适用于35千伏~1000千伏交流输变电(串联补偿)工程,±800千伏及以下直流输电工程、换流站工程,以及系统通信工程。
其他电压等级及类似工程可参照使用。
第四条本细则所称建设预算是指可行性研究投资估算、初步设计概算、施工图预算等工程造价文件。
第五条建设预算费用构成及计算规定按《电网工程建设预算编制与计算规定》(2013年版)执行。
电网工程建设费用由建筑工程费、安装工程费、设备购置费、其他费用、基本预备费和动态费用构成。
建筑工程费、安装工程费由直接费、间接费、利润、编制基准期价差、税金构成,计算标准详见附表一至附表三。
第六条建设预算编制基准期是指建设预算编制时的基准日历时点,在确定建设预算编制基准期时应将时间确认到编制基准月份。
第七条编制基准期价差是指建设预算编制基准期价格水平与电力行业定额(造价)管理部门规定的取费价格之间的差额。
编制基准期价差主要包括人工费价差、消耗性材料价差、施工机械使用费价差和装置性材料价差。
第八条当电力行业定额和取费不足时,涉及其他行业部分选用相应行业相应定额(指标)和取费标准,不足部分选用工程所在地的地方定额和取费标准。
第二章建筑安装工程第一节公用部分第九条直接工程费由人工费、材料费、施工机械使用费组成。
1、人工费(1)人工工日单价按照定额中规定的基准工日单价执行,工资性津贴暂不调整。
(2)人工费调差按相关文件调整,列入编制期基准价差。
2、材料费(1)送变电安装工程定额中未计价材料费按照2013年版《电力建设工程装置性材料预算价格》、《电力建设工程装置性材料综合预算价格》取定,与市场价(南方电网公司电网工程主要设备材料信息价)之间的价差,列入编制基准期价差。
关于发布2013版电力建设项目工程概预算定额价格水平调整的通知
电力工程造价与定额管理总站文件
定额〔2014〕1号
关于发布2013版电力建设工程概预算定额价格水平调整的通知
各有关单位:
按照新版电力建设工程概预算定额价格水平调整办法的有关规定,电力工程造价与定额管理总站根据各地区收集并上报的电力建设工程各种要素价格变化情况,完成了电力建设工程概预算定额人工费、材料和施工机械费价差调整测算工作,现予发布,请遵照执行。
附件:1.电力建设工程概预算定额人工费调整系数汇总表
2.电网安装工程概预算定额材机调整系数汇总表
3.发电安装工程概预算定额材机调整系数汇总表
4.电力建设建筑工程概预算定额材料价差调整汇总表
5.电力建设建筑工程概预算定额施工机械价差调整汇总表
附件1浏览
附件2浏览
附件3浏览
附件4浏览
附件5浏览
二〇一四年一月十五日
附件1。
电力工程计价依据适应营业税改征增值税调整过渡实施方案
电力工程计价依据适应营业税改征增值税调整过渡实施方案附件电力工程计价依据适应营业税改征增值税调整过渡实施方案一、为贯彻落实国务院有关营业税改征增值税(以下简称“营改增”)的战略部署,按照财政部、住房城乡建设部、国家税务总局有关要求,结合电力工程计价依据特点,制订本实施方案。
二、本实施方案的编制依据(一)《关于做好建筑业营改增建设工程计价依据调整准备工作的通知》(建办标[2016]4号)。
(二)《关于全面推开营业税改征增值税试点的通知》(财税[2016]36号)。
(三)《营业税改征增值税试点方案》(财税[2011]110号)。
(四)现行电力工程计价依据,包括概预算定额及费用计算规定、工程量清单计价规范、工程造价管理办法等。
三、本实施方案的适用范围是经国家能源局正式批准,并正在执行的各套现行电力工程计价依据,主要包括:(一)《20kV及以下配电网工程建设预算编制与计算标准》、《20kV及以下配电网工程预算定额-建筑工程、电气设备安装工程、架空线路工程、电缆工程、调试工程、通信及自动化工程》(国能电力[2009]123号);(二)《电网工程建设预算编制与计算规定》、《火力发电工程建设预算编制与计算规定》、《电力建设工程概算定额-建筑工程、热力设备安装工程、电气设备安装工程、调试工程、通信工程》以及《电力建设工程预算定额-建筑工程、热力设备安装工程、电气设备安装工程、输电线路工程、调试工程、通信工程、加工配置品》(国能电力[2013]289号);(三)《西藏地区电网工程建设预算编制与计算规定》、《西藏地区电网工程概算定额-变电站建筑工程、电气设备安装工程、通信工程》、《西藏地区电网工程预算定额-变电站建筑工程、电气设备安装工程、输电线路工程、调试工程、通信工程》(国能电力[2013]331号)。
(四)《电网技术改造工程预算编制与计算规定》、《电网技术改造工程概算定额-建筑修缮工程、电气工程、通信工程》、《电网技术改造工程预算定额-建筑修缮工程、电气工程、输电线路工程、调试工程、通信工程》、《电网拆除工程预算定额-电气工程、输电线路工程、通信工程》,《电网检修工程预算编制与计算规定》、《电网检修工程预算定额-电气工程、输电线路工程、调试工程、通信工程》(国能电力[2015]270号)。
火力发电工程取费标准及相关计算规定
火力发电工程建设预算编制与计算规定(2013年版)——建设预算取费参数中国电力出版社2016年07月1目录火力发电工程建设预算编制与计算规定(2013年版) (1)一、建筑安装工程费计算规定 (1)1、建筑安装工程费 (1)1.1 建筑安装工程计算 (1)1.2 钢结构、灰坝工程及大型土石方取费 (3)二、设备购置费计算规定 (3)2、设备购置费 (3)2.1 设备费 (3)2.1.1国产设备 (3)2.1.2 进口设备 (3)2.2 运杂费 (8)2.2.1 铁路、水路运杂费费率 (9)2.2.2 公路运杂费率 (10)2.2.3 其他说明(国产设备) (10)三、其他费用及基本预备费计算规定 (11)3、其他费用 (11)四、动态费用计算规定 (14)4.1 动态费用 (14)4.1.1 价差预备费 (14)五、项目计划总资金计算规定 (16)5、项目计划总资金 (16)5.1 项目建设总费用 (17)5.2 铺底流动资金 (17)附表: (18)一、建筑安装工程费计算规定1、建筑安装工程费建筑安装工程费=直接费+间接费+利润+编制基准期价差+税金1.1 建筑安装工程计算表1.1.1建筑安装工程计算取费表1注1:一般建筑工程费计算取费表适用于建筑工程的本体和与建筑相关的给排水、采暖、通风、空调、照明、电梯、消防等设施。
取费基数:直接工程费设备安装工程费计算取费表适用于电厂各工艺系统的各类设备、管道、线缆及其辅助装置的组合、装配,以及与建筑工程不直接相关的其他工艺管网和设施。
取费基数:人工费注2:缴费费率是指工程所在省(自治区、直辖市)社会保障机构颁布的以工资总额为基数计取的基本养老保险、失业保险和基本医疗保险、生育保险、工伤保险费率之和。
注3:住房公积金缴费费率按照工程所在地政府部门公布的费率执行。
注4:税率按照工程所在地税务部门的规定计算。
1.2 钢结构、灰坝工程及大型土石方取费发电工程的钢结构工程和灰坝工程的取费(含措施费、间接费、利润)实行综合费率。
广西电网工程建设预算编制与计算标准实施细则(2013年版)
XX电网工程建设预算编制与计算标准实xx 细则(2013年版)第一章总则第一条为加强广西电网工程建设预算管理,统一建设预算的编制和计算规则,合理确定工程造价,根据国家能源局发布的《电网工程建设预算编制与计算规定》(2013 年版)(以下简称《预规》),结合广西电网有限责任公司(以下简称公司)具体情况,制定本细则。
第二条本细则适用于各种投资渠道建设的35kV〜1000kV交流输变电(串联补偿)工程、士800k\及以下直流输电工程、换流站工程以及系统通信工程的新建、扩建和改建工程。
第三条变电站扩建和改建工程按变电站的高压侧电压等级执行相关费用标准。
第四条本细则与《预规》配套使用,本细则未提及部分费用计算标准按《预规》有关规定执行。
第五条《预规》及本实施细则作为电网工程投资估算、初步设计概算、施工图预算和工程量清单报价(以下简称预算)的编制和费用计算依据,应与电力建设工程投资估算指标、概算定额、预算定额和工程量清单计价规范配套使用。
第二章建筑安装工程费第六条人工费1、人工工日单价按照2013 年电力行业定额基准工日单价执行,各册定额基准工日单价标准为:普工34元/工日,建筑技工48元/工日,安装技工53元/工日,输电技工55 元/工日,调试技工75 元/ 工日。
2、人工费价格水平调整,根据电力工程造价与定额管理总站《关于颁布〈电力建设工程概预算定额价格水平调整办法〉的通知》(定额[2014]13号)规定执行,按照编制当期颁布的综合系数进行调整。
编制预算时,人工费调整金额汇入“编制基准期价差”,只计取税金,作为建筑安装工程费的组成内容。
第七条材料费电网工程建设预算中的材料费包括消耗性材料费和装置性材料费两部分。
1、消耗性材料费消耗性材料在建设预算定额中已经计价,消耗性材料价格水平调整,根据电力工程造价与定额管理总站文件《关于颁布〈电力建设工程概预算定额价格水平调整办法〉的通知》(定额[2014]13 号)规定执行。
电力建设工程装置性材料综合预算价格版除税价格
电力建设工程装置性材料综合预算价格版除税价格电力建设工程装置性材料是指在电力工程中,用于安装、调试和运行设备的各种材料,包括电缆、电线、开关、插座、灯具、变压器、断路器等。
这些材料的价格对于电力工程的成本控制非常重要,因此需要进行综合预算,确定除税价格。
首先,在进行电力建设工程装置性材料综合预算之前,需要明确工程的规模和种类。
例如,如果是输变电工程,需要考虑变压器、断路器、隔离开关等材料;如果是配电工程,需要考虑电缆、电线、开关、插座等材料。
其次,需要获取材料的价格信息。
可以通过询价或者查阅市场价格行情等途径,获取各种材料的市场价格。
在获取价格信息时,需要注意材料的规格、品牌、产地等因素的影响,不同规格、品牌、产地的材料价格可能不同。
然后,需要对材料进行综合预算。
综合预算是将各种材料的价格加总,得到一个总价。
在进行综合预算时,需要将相同种类的材料进行分类,然后对每种材料的价格进行加总。
加总时,需要考虑材料的使用数量和材料的价格,并计算出每种材料的总价。
综合预算的计算公式为:综合预算总价=Σ(材料使用数量×材料价格)。
其中,Σ表示求和运算,材料使用数量表示每种材料的使用数量,材料价格表示每种材料的价格。
最后,需要计算出装置性材料的除税价格。
除税价格是指在综合预算总价的基础上,减去相应的税费。
税费包括增值税、消费税等。
根据不同地区和政策,税费的具体计算方式可能有所不同,需要根据实际情况进行计算。
综上所述,电力建设工程装置性材料的综合预算价格版除税价格的计算需要明确工程规模和种类,获取材料的价格信息,进行综合预算,最后减去相应的税费。
通过这一过程,可以得到装置性材料的除税价格,为电力工程的成本控制提供参考依据。
2013版电力概预算定额价格调整办法
附件2013年版电力建设工程概预算定额价格水平调整办法第一章总则第一条为规电力建设工程概预算定额价格水平的测算、发布和实施工作,科学反映不同时间和不同地区价格水平差异,合理确定工程投资,特制订本办法。
第二条本办法适用于以《火力发电工程建设预算编制与计算规定(2013年版)》、《电网工程建设预算编制与计算规定(2013年版)》(以下简称“预规”)和《电力建设工程概算定额(2013年版)》、《电力建设工程预算定额(2013年版)》(以下简称“定额”)为计价依据,编制电力建设工程概预算时,对定额人工费、材料费和施工机械费价格水平的调整。
第三条本办法调整的主要容包括:工程所在地编制基准期价格与概预算定额价格之间的时间差及地区差水平调整。
第四条电力建设工程概预算编制基准期价格水平与定额编制价格水平之间的价差计算:发电和电网工程的人工费均以系数的形式进行调整;发电安装工程和电网安装工程的材料及机械费以系数的形式进行调整;发电建筑工程和电网建筑工程按照本办法中给定的典型材料及机械种类、品种及规格等直接进行价差调整。
第二章人工费调整第五条定额人工费每年调整一次,分别按照建筑工程和安装工程,采用综合系数法进行调整(见附件1)。
不分工种(普通工、技术工)、安装工程不分专业(热力设备安装工程、电气设备安装工程、输电线路安装工程和调试工程),计算时按照对应定额基价中人工费总额乘相应的调整系数。
第六条各地区定额人工费调整系数是参照住房与城乡建设部发布的各地区人工信息价格,或当地定额与造价管理部门公布的本地区定额人工价格,但其组成容要与电力建设工程预规和定额所规定的组成容相一致,进行转化后综合取定。
第七条定额人工费综合调整系数计算公式:建筑工程定额人工费调整系数=[(转化后当地建筑工程定额人工工日单价/定额普通人工工日单价)*0.79] *100%-1 安装工程定额人工费调整系数=[(转化后当地安装工程定额人工工日单价/定额普通人工工日单价)*0.72] *100%-1 第八条定额人工费调整金额计算公式:定额人工费调整金额合计=建筑工程定额人工费调整合计 + 安装工程定额人工费调整合计建筑工程定额人工费调整合计=建筑工程定额基价人工费总额*建筑工程定额人工费调整系数安装工程定额人工费调整合计=安装工程定额基价人工费总额*安装工程定额人工费调整系数此处安装工程包括热力设备安装工程、电气设备安装工程、输电线路安装工程和调试工程。
2013年版电力建设工程概预算定额价格水平调整办法
附件2013年版电力建设工程概预算定额价格水平调整办法第一章总则第一条为规范电力建设工程概预算定额价格水平的测算、发布和实施工作,科学反映不同时间和不同地区价格水平差异,合理确定工程投资,特制订本办法。
第二条本办法适用于以《火力发电工程建设预算编制与计算规定(2013年版)》、《电网工程建设预算编制与计算规定(2013年版)》(以下简称“预规”)和《电力建设工程概算定额(2013年版)》、《电力建设工程预算定额(2013年版)》(以下简称“定额”)为计价依据,编制电力建设工程概预算时,对定额内人工费、材料费和施工机械费价格水平的调整。
第三条本办法调整的主要内容包括:工程所在地编制基准期价格与概预算定额价格之间的时间差及地区差水平调整。
第四条电力建设工程概预算编制基准期价格水平与定额编制价格水平之间的价差计算:发电和电网工程的人工费均以系数的形式进行调整;发电安装工程和电网安装工程的材料及机械费以系数的形式进行调整;发电建筑工程和电网建筑工程按照本办法中给定的典型材料及机械种类、品种及规格等直接进行价差调整。
第二章人工费调整第五条定额人工费每年调整一次,分别按照建筑工程和安装工程,采用综合系数法进行调整(见附件1)。
不分工种(普通工、技术工)、安装工程不分专业(热力设备安装工程、电气设备安装工程、输电线路安装工程和调试工程),计算时按照对应定额基价中人工费总额乘相应的调整系数。
第六条各地区定额人工费调整系数是参照住房与城乡建设部发布的各地区人工信息价格,或当地定额与造价管理部门公布的本地区定额人工价格,但其组成内容要与电力建设工程预规和定额所规定的组成内容相一致,进行转化后综合取定。
第七条定额人工费综合调整系数计算公式:建筑工程定额人工费调整系数=[(转化后当地建筑工程定额人工工日单价/定额普通人工工日单价)*0.79] *100%-1 安装工程定额人工费调整系数=[(转化后当地安装工程定额人工工日单价/定额普通人工工日单价)*0.72] *100%-1 第八条定额人工费调整金额计算公式:定额人工费调整金额合计=建筑工程定额人工费调整合计+ 安装工程定额人工费调整合计建筑工程定额人工费调整合计=建筑工程定额基价人工费总额*建筑工程定额人工费调整系数安装工程定额人工费调整合计=安装工程定额基价人工费总额*安装工程定额人工费调整系数—2——3—此处安装工程包括热力设备安装工程、电气设备安装工程、输电线路安装工程和调试工程。
电力建设工程装置性材料综合预算价格(2013年版)(除税版)
电力建设工程装置性材料综合预算价格(2013年版)FZ01冷风道范围:从送风机、一次风机风口到预热器入口管道、磨煤机调温用的压力冷风道、磨煤机的密封风管道、安全监控系统冷却风道。
不包括消音器及暖风器。
内容:方圆形管道、孔门、补偿器、传动装置、支吊架、螺栓。
编码项目单位预算价(元)FZ011125MW冷风道t5589FZ012200MW冷风道t5613FZ013300MW冷风道t6951FZ014600MW冷风道t7005FZ0151000MW冷风道t7380FZ02热风道范围:从空气预热器出口分别到磨煤机入口、燃烧器(二次风)及煤粉混合器入口。
内容:方圆形管道、风门、孔门、补偿器、异形管件、传动装置、支吊架、螺栓。
编码项目单位预算价(元)FZ021125MW热风道t6576FZ022200MW热风道t6399FZ023300MW热风道t7440FZ024600MW热风道t7247FZ0251000MW热风道t7492FZ03烟道范围:从空气预热器出口到烟囱入口的所有钢管道,并包括高温炉烟道及烟气再循环管道。
内容:方圆形管道、孔门、补偿器、传动装置、支吊架、螺栓,不包括高温烟道的内衬材料。
编码项目单位预算价(元)FZ031125MW烟道t5337FZ032200MW烟道t5450FZ033300MW烟道t6820FZ034600MW烟道t6694FZ0351000MW烟道t6797FZ04原煤管道范围:从原煤斗出口到磨煤机入口,包括金属小煤斗。
内容:方圆形管道及管件、煤闸门、传动装置、接口法兰及支吊架。
编码项目单位预算价(元)FZ041125MW原煤管道t5369FZ042200MW原煤管道t5913FZ043300MW原煤管道t5597FZ044600MW原煤管道t5558FZ0451000MW原煤管道t5511FZ05制粉管道范围:从钢球磨煤机出口到煤粉仓和排粉机入口的全部煤粉空气管道,包括粗粉分离器至磨煤机入口的回粉管、细粉分离器至煤粉仓和螺旋输粉机粉仓的下粉管、煤粉仓的吸潮管和防爆门引出管、煤粉仓的粉位测量装置。
110千伏电网工程建设预算编制规定
某省地方电力(集团)有限公司35-110千伏电网工程建设预算编制规定第一章总则第一条为统一某省地方电力(集团)有限公司(以下简称“集团公司”)电网建设工程预算编制和计算规则,提高编制质量,加强电网建设工程造价管理,合理确定工程造价,提高投资效益,特制定本规定。
第二条本规定根据国家能源局发布的•电网工程建设预算编制与计算规定‣和•电力建设工程概、预算定额‣(国能电力…2013‟289号)及中国电力企业联合会发布的•电力建设工程装置性材料预算价格‣等有关文件为依据,结合某地区实际及造价水平制定,并作为工程项目投资控制的依据和标准。
第三条本规定所称的建设预算是指可行性研究投资估算、初步设计概算及施工图预算。
第四条本规定适用于集团公司35千伏及以上的电网建设工程。
第二章预算编制内容及程序第五条建设预算内容组成(一)、变电工程建设预算按费用性质分为建筑工程费、安装工程费、设备购置费和其他费用四个部分,送电线路工程建设预算按费用性质划分为线路本体工程、辅助设施工程和其他费用三部分。
(二)、建设预算由编制说明、工程概况及主要技术经济指标表、总预(概、估)算表、专业汇总预(概、估)算表、单位工程预算表、其它费用预(概、估)算表、建设场地征用及清理费用预(概、估)算表以及相应附表、附件等组成。
(三)、建设预算的编制说明要有针对性,要具体、确切、简练、规范。
其内容一般应包括:1.工程概况变电工程包括:设计依据,本期及规划建设规模、变压器台数及单台规划容量(分土建、安装);静态投资、静态单位投资,动态投资、动态单位投资;计划投产日期;资金来源;外委设计项目名称及分工界限;站址特点及交通运输状况;自然地理条件和对投资有较大影响的情况。
送电工程包括:线路经过地区的地形、地貌、地质、地下水位、风力、地震烈度、气象条件;线路长度;导、地线型号,杆塔类型;静态投资、静态单位投资,动态投资、动态单位投资;计划投产日期;资金来源;外委设计项目名称及分工界限等。
电力建设工程装置性材料综合预算价格(2013年版)除税价格
FZ33 厂区除灰管道·························································································································· 33 FZ34 厂外除灰管道·························································································································· 34 FZ35 脱水仓系统管道······················································································································· 35 FZ36 气力除灰系统管道···················································································································· 36 FZ37 煤矸石排渣系统管道················································································································· 37 FZ38 灰水回收泵房管道···················································································································· 38 FZ39 反渗透处理系统管道················································································································· 39 FZ40 凝聚澄清过滤系统管道·············································································································· 40 FZ41 除盐系统管道·························································································································· 41 FZ42 酸碱贮存及计量管道················································································································· 42 FZ43 酸碱废水处理管道···················································································································· 43 FZ44 树脂清洗及装卸管道················································································································· 44 FZ45 凝结水精处理管道···················································································································· 45 FZ46 循环水加药系统管道(加酸、加氯)··························································································· 46 FZ47 凝汽器铜管镀膜管道················································································································· 47 FZ48 化学加药系统管道(给水联胺、给水加氨、加氧、加磷、炉内水处理)············································· 48 FZ49 汽水取样管道·························································································································· 49
电力建设工程预算定额(2013版)结算范例
26.57 15.42
送电线路单位工程结算表
金额单位:元 合 价 安装费 其中机械 8.40 50.39
1025.52 2.04 8.28 51.79 1087.63 1139.00
地形系数 小计 附件安装 YX6-1 YX6-19 YX6-84 耐张杆塔 导线挂线及绝缘子串安装 直线杆塔 绝缘子串悬挂安装 防震锤安装 单导线 地形系数 小计 定额小计 35kv 35kv
0.2
组 单相 个 0.05
12.00 6.00 36.00
497.79 4.9 5.67
410.65 4.4 4.62
YX1-107 砂、石、水泥 YX1-108 砂、石、水泥
2 YX3-65 YX3-65 YX3-66 YX3-43
基础部分 每基混凝土量20m3以内 每基混凝土量20m3以内 (高低腿) 每基混凝土量40m3以内 基础钢筋加工及制作 一般钢筋 m3 m3 m3 t t 根 每基100m内 基 基 地形系数 0.1 24.9 57.39 28.03 2.44 0.42 28.00 7.00 7.00 158.7 175.31 148.83 427.57 219.79 8.79 39.34 21.8 98.37 113.13 95.52 282.52 123.7 7.94 32.49 9.1 12.34 14.19 11.73 135.43 89.46 0.85 3.39 12.7 3951.63 10061.04 4171.70 1042.04 92.31 246.12 275.38 152.60 2449.41 6492.27 2677.43 688.54 51.95 222.32 227.43 63.70 1287.31
பைடு நூலகம்
电力建设工程装置性材料综合预算价格(2013年版)教程
编码
项目
单位
Z071 125MW主蒸汽管道
t
28385
Z072 200MW主蒸汽管道
t
28709
Z073 300MW主蒸汽管道 P22
t
87426
Z074 300MW主蒸汽管道 P91
t
122045
Z075 600MW主蒸汽管道 P91
t
111864
Z076 600MW主蒸汽管道 P92
t
124093
Z022 200MW热风道
t
7423
Z023 300MW热风道
t
8630
Z024 600MW热风道
t
8407
Z025 1000MW热风道
t
8691
Z03 范围: 内容: 编码
烟道
从空气预热器出口到烟囱入口的所有钢管道,并包括高温炉烟道及烟气再循环管 道。 方圆形管道、孔门、补偿器、传动装置、支吊架、螺栓,不包括高温烟道的内衬 材料。
t
12821
t
12526
Z07 范围: 内容:
主蒸汽管道 300~1000MW机组从锅炉过热器集箱出口至汽机高压缸主汽门进口止,100~ 200MW机组至汽机本体定型设计界线接口止,包括高压旁路入口侧蒸汽管道、疏 放水管道、给水泵汽轮机高压进汽管道及主汽至轴封供汽管道(如采用主汽供) 。 管道、管件、疏放水闸门、接管座、蠕胀测点、位移指示器(含维护平台)、中 频弯管加工、支吊架,不包含主蒸汽阀门。
主给水管道 由主给水泵出口至锅炉入口的全部给水管道,包括给水再循环管道、过热器及旁 路减温水管道、上述管道的放水放气管道以及主给水杂项管道。母管制供水系统 还包括给水母管、冷供管。 管道、阀门、管件、节流装置、流量测量装置(不含维护平台)、中频弯管加工 、支吊架及接管座,不包括母管阀门、高加进出口三通阀、给水再循环阀、高压 旁路减温阀、汽泵和电泵出口逆止阀、电泵和汽泵最小流量阀前后的隔离阀。
电力建设工程装置性材料预算价格(2013年版)
60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90
S01020402 S01030101 S01030102 S01030103 S01030104 S01030105 S01030106 S01040101 S01040102 S01040103 S01040104 S01040105 S01040106 S01040107 S01040108 S01040109 S01040110 S01040111 S01040112 S01040113 S01040114 S01040115 S01040116 S01040117 S01040118 S01040119 S01040120 S01040121 S01040122 S01040123 S01040201
聚氯乙烯塑料板 聚氯乙烯塑料板 聚氯乙烯塑料板 聚四氟乙烯板 聚四氟乙烯板 橡胶板 橡胶板 橡胶板 橡胶板 橡胶板 高压石棉橡胶板 高压石棉橡胶板 高压石棉橡胶板 中压石棉橡胶板 中压石棉橡胶板 中压石棉橡胶板 低压石棉橡胶板 低压石棉橡胶板 低压石棉橡胶板 耐油石棉橡胶板 耐油石棉橡胶板 耐油石棉橡胶板 耐油石棉橡胶板 耐油石棉橡胶板 耐油石棉橡胶板 耐油石棉橡胶板 耐油石棉橡胶板 耐油石棉橡胶板
序号 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
材料编码 S01010101 S01010102 S01010103 S01010201 S01010202 S01010301 S01010302 S01010303 S01010304 S01010305 S01010401 S01010402 S01010403 S01010501 S01010502 S01010503 S01010601 S01010602 S01010603 S01010701 S01010702 S01010703 S01010704 S01010705 S01010706 S01010707 S01010708 S01010709
火力发电建设预算费用构成及费率(2013年版)
3 建设预算费用构成及计算规定3.1 一般规定3.1.1本章规定了建设预算各项费用的构成、计算方法、费率。
3.1.2在本预规之外确有必要增列的费用项目,必须以国家行政主管部门、各省(自治区、直辖市)人民政府的规定为依据,经电力行业定额(造价)管理部门核定后计列。
3.1.3凡注明“××及以下”的,其下限截止至低一档“××及以下”的上限之上。
凡注明“××以下”的,包括××在。
凡注明“××及以上”的,包括××在。
凡注明“××以上”的,不包括××在。
3.2建设预算费用构成3.2.1项目计划总资金项目计划总资金由项目建设总费用和铺底流动资金构成。
项目建设总费用由建筑工程费、安装工程费、设备购置费、其他费用、基本预备费和动态费用构成。
其中建筑工程费、安装工程费、设备购置费、其他费用、基本预备费之和称为静态投资。
3.2.2建筑工程费、安装工程费3.2.2.1直接费1 直接工程费(1)人工费。
(2)材料费。
(3)施工机械使用费。
2 措施费(1)冬雨季施工增加费。
(2)夜间施工增加费。
(3)施工工具用具使用费。
(4)特殊工程技术培训费。
(5)大型施工机械安拆与轨道铺拆费。
(6)特殊地区施工增加费。
(7)临时设施费。
(8)施工机构转移费。
(9)安全文明施工费。
3.2.2.2间接费1 规费(1)社会保险费。
(2)住房公积金。
(3)危险作业意外伤害保险费。
2 企业管理费3 施工企业配合调试费3.2.2.3利润3.2.2.4编制基准期价差3.2.2.5税金3.2.3设备购置费3.2.3.1设备费3.2.3.2设备运杂费3.2.4其他费用3.2.4.1建设场地征用及清理费1土地征用费2施工场地租用费3迁移补偿费4余物清理费3.2.4.2项目建设管理费1项目法人管理费2招标费3工程监理费4设备材料监造费5工程结算审核费6工程保险费3.2.4.3项目建设技术服务费1项目前期工作费。
电力建设工程预算定额(2013年版)
19.75 25.26 44.38 73.16 23.36 29.86 27.57 46.67 73.75 23.34 29.60 49.12 77.36 9.01 2.16 6.74 12.84 4.33 5.54 11.68 22.45 0.17 0.17 0.17 0.16 0.16 0.16 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.70 0.97 9.56 0.28 0.24 0.03 0.03 0.18
2.85 3.89 4.58 5.84 6.98 10.15 12.00 15.30 7.52 13.06 15.97 23.01 0.24 0.24 0.24 0.24 0.24 0.24 0.23 0.22 43.35 43.35 42.52 10.12 114.60 186.37 67.53 201.70 241.66 85.99 201.70 297.94 127.27 201.70 575.00 146.57 13.16 52.63 47.80 31.08 35.66 24.07 16.27
m³ m³ m³ m³ m³ m³ m³ m³ m³ m³ m³ m³ m³ m³ m³ m³ m³ m² m² m² m² m³ m³ m³ m³ m³ m³ m³ m³ m³ m³ m³ m³ m³ m³ m³ m³ m³ m³ m³ m³ m³ m² m² m³
19.75 25.26 44.38 73.16 23.36 29.86 36.89 58.51 88.28 33.49 45.04 69.8 103.92 9.01 2.16 6.74 12.84 4.33 5.54 11.68 22.45 2.02 2.79 4.34 2.5 3.31 6 3.37 4.28 0.91 2.03 2.56 7.49 7.71 6.31 1.28 5.06 15.23 1.32 14.16 9.93 15.73 0.4 0.06.00 0.00 0.00 9.32 11.84 14.53 10.15 15.44 20.68 26.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.73 0.00 0.00 0.00 0.00 0.03
关于发布2013版电力建设工程概预算定额价格水平调整的通知解析
附件2013年版电力建设工程概预算定额价格水平调整办法第一章总则第一条为规范电力建设工程概预算定额价格水平的测算、发布和实施工作,科学反映不同时间和不同地区价格水平差异,合理确定工程投资,特制订本办法。
第二条本办法适用于以《火力发电工程建设预算编制与计算规定(2013年版)》、《电网工程建设预算编制与计算规定(2013年版)》(以下简称“预规”)和《电力建设工程概算定额(2013年版)》、《电力建设工程预算定额(2013年版)》(以下简称“定额”)为计价依据,编制电力建设工程概预算时,对定额内人工费、材料费和施工机械费价格水平的调整。
第三条本办法调整的主要内容包括:工程所在地编制基准期价格与概预算定额价格之间的时间差及地区差水平调整。
第四条电力建设工程概预算编制基准期价格水平与定额编制价格水平之间的价差计算:发电和电网工程的人工费均以系数的形式进行调整;发电安装工程和电网安装工程的材料及机械费以系数的形式进行调整;发电建筑工程和电网建筑工程按照本办法中给定的典型材料及机械种类、品种及规格等直接进行价差调整。
第二章人工费调整第五条定额人工费每年调整一次,分别按照建筑工程和安装工程,采用综合系数法进行调整(见附件1)。
不分工种(普通工、技术工)、安装工程不分专业(热力设备安装工程、电气设备安装工程、输电线路安装工程和调试工程),计算时按照对应定额基价中人工费总额乘相应的调整系数。
第六条各地区定额人工费调整系数是参照住房与城乡建设部发布的各地区人工信息价格,或当地定额与造价管理部门公布的本地区定额人工价格,但其组成内容要与电力建设工程预规和定额所规定的组成内容相一致,进行转化后综合取定。
第七条定额人工费综合调整系数计算公式:建筑工程定额人工费调整系数=[(转化后当地建筑工程定额人工工日单价/定额普通人工工日单价)*0.79] *100%-1 安装工程定额人工费调整系数=[(转化后当地安装工程定额人工工日单价/定额普通人工工日单价)*0.72] *100%-1 第八条定额人工费调整金额计算公式:定额人工费调整金额合计=建筑工程定额人工费调整合计+ 安装工程定额人工费调整合计建筑工程定额人工费调整合计=建筑工程定额基价人工费总额*建筑工程定额人工费调整系数安装工程定额人工费调整合计=安装工程定额基价人工费总额*安装工程定额人工费调整系数此处安装工程包括热力设备安装工程、电气设备安装工程、输电线路安装工程和调试工程。
- 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
- 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
- 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。
电力建设工程装置性材料综合预算价格(2013年版)目录FZ01冷风道 (1)FZ02热风道 (2)FZ03烟道 (3)FZ04原煤管道 (4)FZ05制粉管道 (5)FZ06送粉管道 (6)FZ07主蒸汽管道 (7)FZ08再热热段管道 (8)FZ09再热冷段管道 (9)FZ10主给水管道 (10)FZ11锅炉排污、疏放水管道 (11)FZ12汽轮机抽汽管道 (12)FZ13辅助蒸汽管道 (13)FZ14中、低压给水管道 (14)FZ15加热器疏水、排气、除氧器溢放水管道 (15)FZ16凝汽器抽真空管道 (16)FZ17汽轮机本体轴封蒸汽及疏水系统 (17)FZ18汽轮发电机组油、氮气、二氧化碳、外部冷却水系统管道 (18)FZ19给水泵汽轮机本体系统管道 (19)FZ20主厂房循环水、冷却水管道 (20)FZ21主厂房内空气管道 (21)FZ22厂区中低压管道 (22)FZ23热网管道 (23)FZ24临时吹管管道 (24)FZ25输煤冲洗水管道 (25)FZ26卸油管道 (26)FZ27燃油泵房管道 (27)FZ28油罐区管道 (28)FZ29厂区燃油管道 (29)FZ30锅炉房燃油管道 (30)FZ31冲洗除尘水管道 (31)FZ32灰渣泵房管道 (32)FZ33厂区除灰管道 (33)FZ34厂外除灰管道 (34)FZ35脱水仓系统管道 (35)FZ36气力除灰系统管道 (36)FZ37煤矸石排渣系统管道 (37)FZ38灰水回收泵房管道 (38)FZ39反渗透处理系统管道 (39)FZ40凝聚澄清过滤系统管道 (40)FZ41除盐系统管道 (41)FZ42酸碱贮存及计量管道 (42)FZ43酸碱废水处理管道 (43)FZ44树脂清洗及装卸管道 (44)FZ45凝结水精处理管道 (45)FZ46循环水加药系统管道(加酸、加氯) (46)FZ47凝汽器铜管镀膜管道 (47)FZ48化学加药系统管道(给水联胺、给水加氨、加氧、加磷、炉内水处理) (48)FZ49汽水取样管道 (49)FZ50除盐水厂区衬胶管道 (50)FZ51除盐水厂区非衬胶管道 (51)FZ52补给水泵房管道 (52)FZ53深井泵房管道 (53)FZ54循环水泵房管道 (54)FZ55循环水管道 (55)FZ56厂区补水管道 (56)FZ57厂外补水管道 (57)FZ58启动锅炉房汽水管道 (58)FZ59启动锅炉烟、风、煤、油管道 (59)FZ60启动锅炉加药及汽水取样管道 (60)FZ61压缩空气(氢气)管道 (61)FZ62综合水泵房管道 (62)FZ63净化水站管道 (63)FZ64化学工业废水集中处理系统管道 (64)FZ65电力电缆6kV及以上 (65)FZ66电力电缆6KV以下 (66)FZ67电气控制电缆 (67)FZ68热控补偿电缆 (68)FZ69热控电缆 (69)FZ70热控系统脉动管路 (70)FZ71通信电缆 (71)FZ72计算机电缆 (72)FZ73消防电缆 (73)FZ74电缆防火材料 (74)FZ75封闭母线 (75)FZ76共箱母线 (76)FZ77安全滑线 (77)FZ78全厂(站)接地 (78)FZ79电缆托架 (79)FZ80电缆保护管 (80)FZ81保温制品 (81)FZ82抹面 (82)FZ83砌筑 (83)FZ84石灰石浆液制备管道 (84)FZ85石膏处理及浆液回收系统管道 (85)FZ86烟道防腐衬鳞 (86)FZ87褐煤高温炉烟管道 (87)FZ88空冷排汽管道 (88)FZ89落煤管 (89)FZ90平台扶梯 (90)FZ91间接空冷系统冷却塔内管道 (91)FZ92铁构件和网门制作安装中的钢材 (92)FZ93基础槽钢 (93)BZ01软导线引下线 (94)BZ02软导线设备连线 (95)BZ03硬母线 (96)BZ04组合导线 (97)BZ05软母线 (98)BZ06管型母线 (100)BZ07绝缘子串 (101)BZ08基础槽钢 (102)BZ09电力电缆 (103)BZ10控制电缆 (104)FZ01冷风道范围:从送风机、一次风机风口到预热器入口管道、磨煤机调温用的压力冷风道、磨煤机的密封风管道、安全监控系统冷却风道。
不包括消音器及暖风器。
内容:方圆形管道、孔门、补偿器、传动装置、支吊架、螺栓。
编码项目单位预算价(元)FZ011125MW冷风道t5589FZ012200MW冷风道t5613FZ013300MW冷风道t6951FZ014600MW冷风道t7005FZ0151000MW冷风道t73801FZ02热风道范围:从空气预热器出口分别到磨煤机入口、燃烧器(二次风)及煤粉混合器入口。
内容:方圆形管道、风门、孔门、补偿器、异形管件、传动装置、支吊架、螺栓。
编码项目单位预算价(元)FZ021125MW热风道t6576FZ022200MW热风道t6399FZ023300MW热风道t7440FZ024600MW热风道t7247FZ0251000MW热风道t74922FZ03烟道范围:从空气预热器出口到烟囱入口的所有钢管道,并包括高温炉烟道及烟气再循环管道。
内容:方圆形管道、孔门、补偿器、传动装置、支吊架、螺栓,不包括高温烟道的内衬材料。
编码项目单位预算价(元)FZ031125MW烟道t5337FZ032200MW烟道t5450FZ033300MW烟道t6820FZ034600MW烟道t6694FZ0351000MW烟道t67973FZ04原煤管道范围:从原煤斗出口到磨煤机入口,包括金属小煤斗。
内容:方圆形管道及管件、煤闸门、传动装置、接口法兰及支吊架。
编码项目单位预算价(元)FZ041125MW原煤管道t5369FZ042200MW原煤管道t5913FZ043300MW原煤管道t5597FZ044600MW原煤管道t5558FZ0451000MW原煤管道t55114FZ05制粉管道范围:从钢球磨煤机出口到煤粉仓和排粉机入口的全部煤粉空气管道,包括粗粉分离器至磨煤机入口的回粉管、细粉分离器至煤粉仓和螺旋输粉机粉仓的下粉管、煤粉仓的吸潮管和防爆门引出管、煤粉仓的粉位测量装置。
内容:管道、耐磨弯头、闸门、换向装置、补偿器、构件、支吊架。
注:包括铸石管及铸钢、铸铁管件,在统计工程量时,应将其重量统计在内。
编码项目单位预算价(元)FZ051125MW制粉管道t6553FZ052200MW制粉管道t6568FZ053300MW制粉管道t74475FZ06送粉管道范围:从煤粉混合器及排粉风机出口箱始,至喷燃器及三次风口的管道,包括排粉风机出口风箱至磨煤机入口的再循环风道。
内容:管道、耐磨弯头、闸门、换向装置、补偿器、构件、支吊架。
注:包括铸石管及铸钢、铸铁管件,在统计工程量时,应将其重量统计在内。
编码项目单位预算价(元)FZ061125MW送粉管道t7961FZ062200MW送粉管道t8100FZ063300MW送粉管道t8792FZ064600MW送粉管道t11053FZ0651000MW送粉管道t107986FZ07主蒸汽管道范围:300~1000MW机组从锅炉过热器集箱出口至汽机高压缸主汽门进口止,100~200MW机组至汽机本体定型设计界线接口止,包括高压旁路入口侧蒸汽管道、疏放水管道、给水泵汽轮机高压进汽管道及主汽至轴封供汽管道(如采用主汽供)。
内容:管道、管件、疏放水闸门、接管座、蠕胀测点、位移指示器(含维护平台)、中频弯管加工、支吊架,不包含主蒸汽阀门。
编码项目单位预算价(元)FZ071125MW主蒸汽管道t24470FZ072200MW主蒸汽管道t24749FZ073300MW主蒸汽管道P22t75367FZ074300MW主蒸汽管道P91t105211FZ075600MW主蒸汽管道P91t96434FZ076600MW主蒸汽管道P92t106977FZ0771000MW主蒸汽管道P92t1172797FZ08再热热段管道范围:300~1000MW机组从锅炉再热器集箱出口至汽机中压缸联合汽门进口止,100~200MW机组至汽机本体设计界线接口止,包含低压旁路入口侧蒸汽管道、上述管道的疏放水管道。
内容:管道、管件、疏放水管道阀门、蠕胀测点、位移指示器、中频弯管加工、支吊架,不包含维护平台和母管阀门。
编码项目单位预算价(元)FZ081125MW再热热段管道t23058FZ082200MW再热热段管道t22972FZ083300MW再热热段管道P22t89030FZ084600MW再热热段管道P91t103682FZ085600MW再热热段管道P92t119738FZ0861000MW再热热段管道P92t1199078FZ09再热冷段管道范围:从汽机高压缸两侧排汽口或汽机本体设计界线始至锅炉再热器两侧进口集箱止,包括上述管道的疏水放气管道;包含高低压旁路出口的管道。
内容:管道、管件、疏放水管道闸门、蠕胀测点、位移指示器、中频弯管加工、支吊架,包含维护平台,不包含母管阀门。
编码项目单位预算价(元)FZ091125MW再热冷段管道t19343FZ092200MW再热冷段管道t20882FZ093300MW再热冷段管道A672B70Cl3t30089FZ094600MW再热冷段管道A6911-1/4Cr CL22t49289FZ0951000MW再热冷段管道A6911-1/4Cr CL22t499239FZ10主给水管道范围:由主给水泵出口至锅炉入口的全部给水管道,包括给水再循环管道、过热器及旁路减温水管道、上述管道的放水放气管道以及主给水杂项管道。
母管制供水系统还包括给水母管、冷供管。
内容:管道、阀门、管件、节流装置、流量测量装置(不含维护平台)、中频弯管加工、支吊架及接管座,不包括母管阀门、高加进出口三通阀、给水再循环阀、高压旁路减温阀、汽泵和电泵出口逆止阀、电泵和汽泵最小流量阀前后的隔离阀。
编码项目单位预算价(元)FZ101125MW主给水管道t24603FZ102200MW主给水管道t29122FZ103300MW主给水管道WB36t44792FZ104600MW主给水管道15NiCuMoNb5t53293FZ1051000MW主给水管道15NiCuMoNb5t5824010FZ11锅炉排污、疏放水管道范围:锅炉定期排污管道、连续排污管道、锅炉疏水、放气、放水管道,直流锅炉启动系统有关管道;包括锅炉储水箱放水管道、空气预热器冲洗水管道、锅炉房放水管道。
内容:管道、联箱、阀门、管件、节流装置、流量测量装置及支吊架。
编码项目单位预算价(元)FZ111125MW锅炉排污、疏放水管道t10045FZ112200MW锅炉排污、疏放水管道t10982FZ113300MW锅炉排污、疏放水管道t10363FZ114600MW锅炉排污、疏放水管道t9613FZ1151000MW锅炉排污、疏放水管道t1203111FZ12汽轮机抽汽管道范围:300~1000MW机组包括包括汽机各级抽汽至加热器及除氧器的管道、给水泵汽轮机的低压进汽管道,100~200MW机组从汽机本体设计接口至各级加热器和除氧器进口的管道(包括给水箱再沸腾管),以及上述管道的放水放气管道。