【精品完整版】毕业设计(论文)220kv输电线路杆塔基础施工设计
220KV变电站电气部分设计毕业论文
设计课题:220KV变电站电气部分设计随着经济的发展和现代工业建设的迅速崛起,供电系统的设计越来越全面、系统,工厂用电量迅速增长,对电能质量、技术经济状况、供电的可靠性指标也日益提高,因此对供电设计也有了更高、更完善的要求。
设计是否合理, 不仅直接影响基建建投资、运行费用和有色金属的消耗量,也会反映在供电的可靠性和安全生产方面,它和企业的经济效益、设备人身安全密切相关。
本设计讨论的是220KV变电站电气部分的设计。
首先对原始资料进行分析,选择主变压器,在此基础上进行主接线设计,再进行电气总平面的布置及配电装置的设计,变压器的选择,然后进行短路计算,导体电气设备的选择,继电保护的设计和配备,最后进行防雷接地以及保护设计。
关键字:变电站;短路计算;设备选择;继电保护;防雷接地;ABSTRACTWith the development of economy and the rapid rise of the modern industrial construction, the design of the power supply system is more and more comprehensive, system, plant power consumption growing rapidly, the power quality, technical and economic conditions, the power supply reliability index also is increasing day by day, therefore also has a bigger, better for power supply design requirements. Design is reasonable, not only directly affect the capital construction investment, operation cost and the consumption of non-ferrous metal, also reflected in the power supply reliability and safety production, and it is closely related to the enterprise's economic benefits, equipment safety.The design is refer to the part of 220kV electrical substation design. First of all, analyze the original data ,based on it, design the main wiring and then the design of the electrical general layout of the arrangement and distribution equipment and choose the main transformer, then the short circuit calculation ,the choice of conductor electrical equipment, the design of relay protection and are equippedwith,at last, Lightning protection grounding and protection design .Key Words: Substation; Short Circuit Calculation; Equipment Selection; Relay protection; Lightning protection grounding;.IZ .A —刖日 ......1电气主接线的设计.・・・. 1. 1主接线概述 ........ 1.2主接线设计原则.・・・・ 1. 3主接线选择 ........2电气总平面布置及配电装置的选择 4 220KV 变电站电气部分短路计算・. 1.1 变压器的各绕组电抗标幺值计算..................................... 19 1.2 10KV 侧短路计算 .................................................. 90 1.3 3 220KV 侧短路计算 ............................................... 103 4.4 110KV 侧短路计算 ................................................. 114 5导体和电气设备的选择 .............................................. 136 5.1断路器和隔离开关的选择 ........................................... 137 5. 1. 1 220KV 出线、主变侧 ............................................ 27 5. 1.2 主变 110KV 侧 .................................................. 31 5.1.3 10KV 限流电抗器、断路器隔离开关的选择 .......................... 204 5. 2电流互感器的选择 ................................................. 39 5. 2. 1 220KV 侧电流互感器的选择 ..................................... 260 5. 2.2 110KV 侧的电流互感器的选择 .................................... 281 5. 2. 3 10KV 侧电流互感器的选择 ...................................... 292 5. 3电压互感器的选择 ................................................ 313 5. 3. 1 220KV 侧母线电压互感器的选择 ................................. 325 5. 3. 2 110KV 母线设备PT 的选择 (325)目录.8 10 102. 1概述 .................. 2. 1. 1配电装置特点 ....... 2. 1.2配电装置类型及应用..3. 2配电装置的确定 ........4. 3电气总平面布置 ........5. 3. 1电气总平面布置的要求6. 3. 2电气总平面布置 ..... 3主变压器的选择73. 1. 1 3. 1.2 3. 1.3 主变压器台数的选择 ..... 主变压器容量的选择 ..... 主变压器型式的选择 .....绕组数量和连接形式的选择 7. 2主变压器选择结果 .....错误!未定义书签。
220kV输电线路工程基础专项施工方案
(6)《地基与基础工程施工及验收规范》GB 50202-2002
(7)《架空送电线路施工手册》
(8)《混凝土结构工程施工质量验收规范》GB 50204-2002
(9)《混凝土质量控制标准》GB 50164-1992
(10)《普通混凝土用碎石或卵石质量及检验方法标准》J628-2006
TW3048+1.5
18
4#AC、6#BC、12#A、20#BD、24#C、34#BC、37#D、43#B、52#B、54#D、55#AD、71#D、73#B
TW3048+2.0
17
10#AB、12#B、16#B、22#B、24#D、37#C、41#D、43#CD、47#BC、54#C、69#D、72#AC、73#C
2.1.3、采用Z系列人工挖孔桩基础具体基础型式及桩号腿详见下表:
基础形式
塔腿个数
具体塔腿
Z1272系列
Z1272+1.0
2
7#AB
Z1272+1.5
2
23#A、31#C
Z1272+2.0
1
22#C
Z1272+2.5
2
#6A、23#D
Z1696系列
Z1696
5
47#D、50#B、52#CD、72#B
11
18#BC、21#AB、25#B、30#B、35#C、40#A、46#C、65#BC
TW2846+1.5
19
7#C、10#C、21#C、24#AB、30#AC、31#B、35#B、45#CD、51#B、61#ABCD、64#AB、69#B
TW2846+2.0
220kV输电线路工程设计论文
220kV输电线路工程设计论文一、线路的设计对于输电线路的架设工作我们在进行具体的操作过程中一定要进行比较科学的线路设计工作,考虑线路设计过程中出现的种种因素保证架设的输电线路能够科学顺利运行,将自然因素和人为因素可能对输电线路造成的危害降到最低。
通常线路在设计阶段都要利用科学技术例如卫星或是航拍获得线路架设设计线路的图片资料,利用遥感技术将该区域内具体地理数据进行整合将具体的地形地貌环境状况,交通状况进行汇总比较设计的方案后选择最科学最合理的方案进行施工。
输电线路的设计工作具体要考虑一下情况:一是输电线路在架设线路要避开军事工程,或是大型的机场,矿场,避免对架设区域造成较大的经济损失,对于地质条件不好的地区也要进行躲避。
二是输电线路在设计的阶段对于输电线路的长度也要进行一定的规划线路的长短要符合设计技术要求。
三是输电线路在架设过程中保证线杆之间的距离,和高差避免由于高差或是距离的原因导致输电线路出现线锤,下沉的现象。
二、基础工程的具体设计与施工对于220kV输电工程的线路施工中架设的线杆是整个施工工作的基础也是重点工程,只有保证输电线路线杆架设的顺利才能进行其他的施工作业。
线杆的架设工作需要我们给与足够的重视,线杆通常我们会利用混凝土将将其底部埋设到基坑中,使线杆在遇到外力的作用后不会出现倒塌现象。
通常线杆在埋设的过中一般会出现以下情况,例如混凝土出现裂缝,下沉,或是滑坡,或是由于积水的冲刷导致出现地盘不稳的现像出现。
1.岩石基础部分的设计输电线路的架设过程中由于多数是经过的山地地区因此对于地表的岩石或是土质的勘察就比较重要,一般在线路的架设前就要对整个线路的地表岩石情况进行详细的勘察,提取相应的的技术数据进行分析确定最终的设计方案。
一般情况下地表岩石的情况可以分成三种类型微风化、半风化、重度风化三种。
其中的微风化是架设线路的最佳选择但是由于,微风化地区的地表岩石还保留者着岩石的本质特性,通常情况是比较坚硬的不容易进行开挖的。
220kV输电线路工程施工设计完整版
(此文档为word格式,下载后您可任意编辑修改!)220kV萧牌2310线(牌头变侧)开口后接入诸西变输电线路工程项目管理实施规划绍兴市大兴电气承装有限公司2011年11月14日批准:年月日审核:年月日编写:年月日目录一、编制依据 (6)1编制依据 (6)二、工程概况与工程实施条件分析 (6)1工程概述 (6)2工程设计特点、工程量 (7)3施工实施条件及自然环境分析 (8)三、项目施工管理组织结构 (10)1项目管理组织结构 (10)2项目管理职责 (10)3工程主要负责人简介 (14)四、工期目标和施工进度计划 (15)1工期目标及分解 (15)2施工进度计划及编制说明 (16)3进度计划图表 (17)4进度计划风险分析及控制措施 (17)五、质量管理体系 (20)1质量目标及分解 (20)2质量管理组织机构 (21)3质量管理主要职责 (22)4质量控制措施 (22)5质量薄弱环节及预防措施 (25)六、安全管理体系 (25)1安全目标及分解 (25)2安全管理组织机构 (26)3安全管理主要职责 (27)4安全控制措施 (28)5危险点、薄弱环节分析预测及预防措施 (29)七、环境保护与文明施工体系 (30)1施工引起的环保问题及保护措施 (30)2文明施工的目标、组织结构和实施方案 (31)八、工地管理和施工平面布置 (32)1施工平面布置 (32)2工地管理方案与制度 (32)九、施工方法与资源需求计划 (35)1劳动力需求计划及计划投入的施工队伍 (35)2施工方法及主施工机具选择 (36)3施工机具需求计划 (39)4材料、消耗材料需求计划 (41)5资金需求计划 (42)十、施工管理与协调 (42)1技术管理及要求 (42)2物资管理及要求 (43)3资金管理及要求 (44)4作业队伍及管理人员管理及要求 (45)5协调工作(参建方、外部) (47)6分包计划与分包管理 (47)7计划、统计和信息管理 (48)8资料管理 (51)十一、施工科技创新 (53)十二、主要技术经济指标 (53)1项目技术经济指标 (53)2降低成本计划与措施 (54)十三、附录 (56)一、编制依据1 编制依据1.1《220kV萧牌2310线(牌头变侧)开口后接入诸西变输电线路工程施工合同》及相关设计文件1.2《110~500千伏架空送电线路施工及验收规范》(GB 50233-2005)及国家有关规定标准1.3公司本工程现场调查资料1.4公司历年积累的送电线路施工经验及统计数据1.5建设单位建设组织依据1.6《国家电网公司输变电工程达标投产考核办法》(国家电网基建〔2011〕146号)1.7《工程建设标准强制性条文-电力工程部分(2006版)》1.8《电力建设工程质量监督规定(暂行)》(2005版)二、工程概况与工程实施条件分析1 工程概述本工程线路从萧牌2310线28#开接后开始左转前进到金家山东侧,线路右转上至金家山往西北走线,沿黄泥尖北侧山坡走线至银河潭东侧后右转,往北从沙墩头东侧穿过上至麻圆岭东侧山头,线路在山上继续往北走线,至庙前南侧右转下山,从后山芝西侧穿过后上至翁家岭,左转下山走线至下蔚东南侧,右转跨过103省道后上山马上右转,在山上往东走线进入220kV进入诸西变。
220kV线路工程输电线路施工方案
220kV线路工程输电线路施工方案1. 引言本文档旨在提供一个针对220kV线路工程的输电线路施工方案。
在该方案中,将介绍施工前准备工作、线路塔杆的安装、导线的架设以及其他必要的施工步骤。
2. 施工前准备工作在开始施工之前,需要进行一系列准备工作,以确保施工顺利进行。
这些准备工作包括但不限于:- 确定工程的需求和目标- 分析施工环境和地形条件- 制定详细的施工计划- 获得必要的许可证和批准文件- 安排所需的人力资源和设备3. 线路塔杆的安装线路塔杆的安装是输电线路施工的重要步骤之一。
在安装过程中,需要注意以下几点:- 根据设计要求确定塔基位置- 按照设计图纸进行塔杆的组装和安装- 确保塔杆的垂直度和水平度符合要求- 使用适当的设备和工具进行安装,保证施工质量和安全性4. 导线的架设导线的架设是输电线路施工中的关键环节。
在架设导线过程中,需要注意以下几点:- 按照设计要求选择合适的导线类型和规格- 确保导线的正确张力和垂直度- 安装适当的绝缘子和振动减震器,提高线路的可靠性和稳定性- 进行必要的接地和防雷措施,保护线路设备和人身安全5. 其他施工步骤除了线路塔杆的安装和导线的架设,还有其他一些必要的施工步骤,包括但不限于:- 安装并连接变压器和开关设备- 进行线路的调试和试运行- 进行必要的检测和测试,确保线路符合标准和要求- 完成线路工程竣工验收,获得相应的证书和文件6. 结论通过执行本文档中提到的施工方案,可以有效地完成220kV线路工程的输电线路施工。
在施工过程中,应始终遵守相关法律法规和安全要求,确保施工质量和工程安全。
同时,根据实际情况适时调整施工方案,并与相关单位和部门进行密切合作,共同推动工程的顺利进行。
7. 参考资料- 相关法律法规和技术标准- 工程设计图纸和技术规范- 施工验收要求和程序。
220kV输电线路工程设计毕业设计
220kV输电线路工程设计毕业设计1.1课题研究目的输电线路工程设计是电力建设的重要组成部分,同时也对输电线路正常运行起着决定性作用。
本课题与输电线路工程专业联系比较紧密,通过这个输电线路工程的设计能够巩固和加深对本专业知识的理解,使我们的实际工程设计能力得到锻炼,培养及提高独立思考、分析和解决实际问题的能力。
为今后更好的从事线路相关工作提供了理论依据和专业基础,达到了培养工程实际运用能力的目的。
1.2本课题的工作任务本课题是在给定某平丘区段220kV输电线路工程设计的基本气象条件,污秽等级和平断面图的情况下,完成导、地线应力及弧垂计算,线路分段、杆塔定位和杆塔型式的确定,杆塔塔头荷载计算,防振,接地设计计算,铁塔的基础设计,以及后期数据整理和一些杆塔定位图,绝缘子串组装图,基础施工图等的绘制。
2 设计参数及已知条件本线路是某平丘区段220kV双分裂双回路线路,导线采用2 LGJ-300/40钢芯铝绞线,选配地线采用镀锌钢绞线GJ-50,线路经过地区污秽等级为Ⅲ级。
根据,本工程所处区域的泄漏比距要求不小于2.8cm/kV。
设计气象条件为典型气象VI区,最大设计风速为25m/s,覆冰厚度为10mm,最高气温为40℃,最低气温为-20℃。
金具、绝缘子型号选择及绝缘配合,导线换位,房屋拆迁,对弱电流线路的影响,均按220kV电压等级考虑,今后升压改造时,可根据当时情况进行处理;导线对地距离,交叉跨越以及防雷接地,均按相关规程确定。
3 导线应力弧垂计算及曲线绘制3.1导线应力弧垂曲线的绘制步骤3.1.1应力弧垂曲线的计算项目应力弧垂曲线的计算项目见下表3-1。
表3-1 应力弧垂曲线的计算项目注带Δ者为需要绘制的曲线,无Δ者为不需要绘制的曲线3.1.2应力弧垂曲线的计算步骤(1)确定工程所采用的气象条件;(2)依据选用的架空线规格,查取有关参数和机械物理性能;(3)计算各种气象条件下的比载;(4)选定架空线各种气象条件下的许用应力(包括年均运行应力的许用值);(5)计算临界档距值,并判定有效临界档距和控制气象条件;(6)判定最大弧垂出现的气象条件;(7)以控制条件为已知状态,利用状态方程式计算不同档距、各种气象条件下架空线的应力和弧垂值;(8)按一定比例绘制出应力弧垂曲线。
220kV输电线路保护方案的分析与设计+电力工程毕业论文
220kV输电线路保护方案的分析与设计电力工程毕业论文()题目 220kV输电线路保护方案的分析与设计系别电力工程系专业班级电气工程及其自动化专业电气05K5班学生姓名于腾指导教师李秀琴徐玉琴二??九年六月华北电力大学科技学院本科毕业设计(论文)220kV输电线路保护方案的分析与设计摘要在电力系统中保护装置是系统中的一个关键环节,它直接影响着整个输配电网的运行稳定及安全,任何的电力设备没有保护是不能进网运行的。
现在新投入使用的高中压等级继电保护设备几乎均为微机保护产品.对于220kV输电线路的微机保护方案,有多种配置选择,其中包括高频保护、电流差动保护、距离保护、零序电流保护等等,高频保护和电流差动保护常被用作输电线路的主保护,距离保护和零序电流保护则是后备保护.在220kV电压等级的输电线路上,一般要求装设全线速动的保护装置,对重要的220KV输电线路,一般应选择两套原理不同的保护作为主保护。
本文对微机保护的起动元件、选相元件以及采用闭锁信号和允许信号的高频保护、电流差动保护等主要保护类型的原理和分类做了介绍,并根据220kV输电线路保护配置的原则,初步选择了一套220kV输电线路的微机保护配置方案.关键词:微机保护;高频保护;电流差动保护; 距离保护I华北电力大学科技学院本科毕业设计(论文)THE ANALYSIS AND DESIGN OF 220KVTRANSMISSION LINES RELAYPROTECTION SCHEMEAbstractProtection devices is a key part of power system ,which directly impact on the operationstability and security of the entire transmission and distribution grid。
Any electrical equipment without protection can not run in the system。
220KV毕业设计
毕业设计(论文)任务书一、设计(论文)题目: 220kV变电站一次系统设计二、设计(论文)任务与要求1.根据电力系统规划需新建一座220kv降压变电所,该所建成后与110kv 和220kv电网相连,并供给近区用户,按规划该所装设两台容量为120MVA主变压器。
2.按规划要求,该所有220kv、110kv和10kv三个电压等级,220kv出线5回,110kv出线8回,10kv出线12回。
3.110kv侧有两回出线供给远方大型冶炼厂,其容量为60000kvA,其他作为一些地区变电所进线,10kv侧总负荷为30000kvA,І、Ⅱ类用户占60%,最大一回负荷为4500kvA。
4.各级电压侧功率因数和最大负荷利用小时数为:220kv侧 cosϕ=0.9 Tmax=3800小时/年110kv侧 cosϕ=0.85 Tmax=4200小时/年10kv侧 cosϕ=0.8 Tmax=4500小时/年5.系统阻抗:220kv侧电源近似为无穷大系统,归算至本所220kv母线侧为0.16(Sј=100MVA),110kv侧电源容量为1000MVA,归算至本所110kv母线侧阻抗为0.32(Sj=100MVA),10kv侧没有电源。
6.该区最热月平均温度为28℃,年平均气温16℃,绝对最高温度为40℃,土壤温度为18℃。
7.该变电所位于市郊荒土地上,地势平坦,交通便利,环境无污染。
8.负荷分类:110kv:最大负荷冶炼厂51000kvA,10kv最大负荷化肥厂4500kvA。
三、设计(论文)时间:年月日至年月日目录前言一、设计说明书第一章主变压器的选择第一节主变台数的选择 (1)第二节主变压器容量的选择 (2)第三节主变压器型式的选择 (2)第四节所变压器的选择 (4)第二章电气主接线的选择第一节概述 (5)第二节主接线接线方式选择 (6)第三节所接线方式 (9)第三章短路电流计算第一节短路电流计算 (10)第二节各回路最大持续工作电流 (13)第四章电气设备的选择第一节概述 (13)第二节断路器的选择 (14)第三节隔离开关的选择 (15)第四节互感器的选择 (16)第五节母线的选择 (20)第五章配电装置的选择第一节概述 (26)第二节高压配电装置的选择 (27)第六章继电保护的保护设计第一节线路保护的 (29)第二节母线保护 (29)第三节变压器保护 (30)二、设计计算书第一章所变压器计算 (32)第二章短路电流计算 (32)第三章断路器选择计算 (36)第四章隔离开关选择计算 (39)第五章电流互感器的选择 (41)第六章电压互感器的选择 (44)三、结束语 (53)四、参考文献 (54)1 引言1.根据电力系统规划需新建一座220kv降压变电所,该所建成后与110kv 和220kv电网相连,并供给近区用户,按规划该所装设两台容量为120MVA主变压器。
220kV线路工程杆塔组立工程施工组织设计方案
220kV线路工程杆塔组立施工方案目录一、编制依据 (1)二、适用围 (1)三、技术、质量、安全主要执行文件 (1)四、工程概况 (2)4.1 工程简介 (2)4.2 杆塔设计简介 (2)五、质量、工艺要求 (5)六、设计说明及相关技术参数 (6)6.1 脚钉安装 (6)6.2 螺栓级别 (6)6.3 螺栓安装 (6)七、塔材的检查验收 (7)八、铁塔的地面组装 (8)九、锚桩的选择 (9)十、施工方案及工艺流程 (11)10.1 铁塔组立方案 (11)10.2 施工工艺流程(见图一) (11)10.3 塔材运输 (11)10.4 抱杆的技术参数及使用条件 (12)10.5 抱杆安装组立步骤 (13)10.6 中心承托抱杆外落地拉线组立工艺 (14)十一、分解组立铁塔工艺流程 (16)11.1基本条件 (16)11.2 铁塔组立前的质量检查 (16)11.3 工艺流程 (16)11.4 施工要点 (16)11.5 铁塔组立 (17)11.6铁塔组立安全措施 (23)十二、劳动组织及施工进度计划 (25)12.1 劳动组织 (25)12.2 施工进度计划 (25)十三、施工质量保证措施 (26)13.1 塔腿编号 (26)13.2 安装要求 (26)13.3质量通病防治措施 (28)十四、施工安全保证措施 (30)十五、文明施工及环境保护 (31)15.1 文明施工 (31)15.2环境保护 (31)15.3 相关要求 (31)十六、铝合金抱杆起吊方案主要工具配套表(单基) (33)附:1、施工危险因素辨识、评价及控制对策表2、施工环境因素辨识、评价及控制对策表3、作业指导书交底记录表4、作业指导书实施小结表一、编制依据1.1、某变至南广变220kV线路工程施工组织设计、设计技术交底及杆塔组立施工图纸;1.2、监理、业主针对本工程相关技术要求;1.3《国家电网公司输变电工程施工工艺示手册》(输电线路工程分册)、《国家电网公司输变电工程标准化施工手册》(输电线路工程分册);1.4《国家电网公司输变电优质工程评选办法》(国家电网基建【2011】148号);1.5《国家电网公司电力建设工程施工技术管理导则》(国家电网工[2003]153号);1.6现行220kV及以上输电线路工程相关国家、国家电网及省电力公司要求下发的施工及验收规程、规、规定、导则和标准等文件;1.7、监理实施细则。
kv输电线路杆塔基础施工设计
目录一.概述 (2)1.1工程概况 (2)1.2编写依据 (3)二.施工准备 (5)2.1接桩 (5)2.2材料点(施工驻点)选择 (7)2.3施工测量(复测) (7)2.4工地运输 (7)三.基础施工 (10)3.1混凝土杆基础施工 (10)3.2铁塔基础施工 (12)3.3基础作业工艺流程图 (20)3.4混凝土配合比计算 (21)四.铁塔基础施工工艺及技术措施 (23)五.质量标准及检验要求 (36)六.安全措施及文明施工 (39)七.组织措施 (41)八.结束语 (42)一.概述1.1工程概况本工程为220kV架空输电线路全长61.5公里,全线路杆塔总共167基,其中混凝土杆82基,铁塔85基。
导线采用2×LGJQ-300分裂导线,地线采用两根GJ-50避雷线。
本工程根据地质水文资料,沿线主要地层为黄土状亚粘土,呈浅黄色、褐黄色,中密稍湿,地下水位均在8米以下。
本工程地势起伏变化较大,除电厂出口地形平坦外,其它地段地形变化大,台地多,冲沟多,部分冲沟宽而深,全线路越山河、河流、水库等较多,跨距大可供大车运输的道路很少,所以运输比较困难,大部分杆塔需人共搬运。
1.1.1工程技术特性:气象条件:最大设计风速30m/s;最大覆冰厚度10mm;电压等级:220千伏;建设性质:新建架空输电线路;导线:2×LGJ-300;地线:一根为GJ-50地线;根据岩土工程勘察报告,本线路沿线主要地层为黄土状亚粘土,呈浅黄色、褐黄色,中密稍湿,地下水位均在8米以下。
基坑开挖后若发现不良地质情况应及时通知项目部解决。
1.1.3交通状况本工程地势起伏变化较大,除电厂出口地形平坦外,其它地段地形变化大,台地多,冲沟多,部分冲沟宽而深,全线路越山河、河流、水库等较多,跨距大可供大车运输的道路很少,所以运输比较困难,大部分杆塔需人共搬运。
1.1.4线路方向1.2编写依据—2011)二.施工准备根据审定后的施工图纸及现场情况,在开工前应做好充分准备工作,其主要工作内容包括:现场调查,工程指挥部、材料站、施工驻点的选择,器材准备,施工机具准备、检修、障碍物处理及协议,占地赔偿,编制施工组织设计和施工计划及施工技术设计,进行技术培训、新技术科研试验,施工图技术交底等。
220kv输电线路毕业设计
220kv输电线路毕业设计220kV输电线路毕业设计随着电力需求的不断增长,输电线路的规模和重要性也日益凸显。
在电力系统中,220kV输电线路是一种重要的电力传输通道,承载着大量的电能输送任务。
为了满足电力系统的需求,我决定以220kV输电线路为主题进行毕业设计。
本文将从设计原理、材料选择、安装施工等方面进行探讨。
首先,设计原理是一个成功的输电线路设计的基础。
在220kV输电线路的设计中,需要考虑到电力传输的效率、稳定性和安全性。
为了提高输电效率,我们可以采用高导电率的导线材料,减小电阻损耗。
同时,为了保证线路的稳定性,需要考虑到电流的负载能力和电压的稳定性,可以通过合理的线路布置和电缆选择来实现。
此外,为了确保线路的安全性,还需要考虑到防雷、防震等因素,采取相应的措施来减小事故的发生概率。
其次,材料选择在输电线路设计中起着至关重要的作用。
导线是输电线路的核心组成部分,材料的选择直接影响着线路的性能。
在220kV输电线路的设计中,一般会选择铝合金导线,其具有导电性好、重量轻、抗腐蚀性强等优点。
此外,绝缘子、杆塔等材料的选择也需要考虑到其耐高温、耐电压等性能,以确保线路的正常运行。
在安装施工过程中,需要严格按照设计要求进行操作。
首先,需要进行线路的勘测和布线设计,确保线路的路径合理、安全。
然后,进行杆塔的安装和导线的悬挂,这一步骤需要注意施工人员的安全,同时保证线路的稳定性。
最后,进行绝缘子的安装和线路的接地工作,确保线路的安全可靠。
除了设计原理、材料选择和安装施工,还需要对线路的运行和维护进行全面考虑。
线路的运行监测是确保线路正常运行的重要手段,可以通过温度、电流、电压等参数的监测来判断线路的工作状态。
同时,定期的巡检和维护工作也是确保线路长期稳定运行的重要环节,可以及时发现并解决线路存在的问题,保障电力系统的正常运行。
综上所述,220kV输电线路的毕业设计是一个复杂而重要的任务。
通过对设计原理、材料选择、安装施工、运行维护等方面的探讨,可以全面了解和掌握输电线路设计的要点和技术。
输电线路毕业设计论文
61.163
30
44.317
47.684
50.859
53.418
55.394
56.905
58.063
58.959
59.659
60.213
表1-10 不同温度下安装曲线的弧垂
档距
温度
50
100
150
200
250
300
350
400
450
500
-10
0.104
0.426
1.001
1.870
3.071
62.560
63.133
65.375
73.579
450
70.271
69.645
62.560
63.162
65.518
74.162
500
69.064
68.413
62.560
63.184
65.630
74.626
1.4.5 计算安装曲线的应力和弧垂
架空线的安装是在不同的气温下进行的,紧线时按照安装曲线上相应与这一温度弧垂进行
62.56
83.330
4.100
300
52.996
6.608
76.200
4.596
62.56
82.191
5.986
350
54.670
8.719
73.400
6.494
62.56
81.285
8.238
400
55.975
11.123
71.264
8.737
62.56
80.575
10.855
450
57.005
推荐 220KV输电线路毕业设计 精品
220kV罗旺线Ⅵ标段输电线路工程设计摘要:本文主要介绍根据现有的技术规程及资料来设计线路为220kV输电线路,本设计按照工程设计要求,以及标准设计流程,并根据电压等级、导地线型号、气象条件、地形情况,完成如下设计内容:计算导地线应力弧垂,绘制成图;选择直线杆塔和转角杆塔,确定杆塔呼称高、金具和绝缘子型号数量;制作弧垂模板没在平断面上反复排杆定位,选择最佳方案;校检杆塔荷载和基础稳定;最后进行导地线的防振设计。
关键词:220Kv线路,应力计算,排杆定位,防振设计Abstract:According to existing technical regulations were introduced in this paper to design the circuit and the data of 500 kv transmission lines.Besides engineering design request and the standard design process,this paper mainly include following task in term of the voltage rank,the type of conductor and ground wire,the condition of weather and landform.Firstly,we calculate the stress of the wires,and draw out its chart.Secondly,we choose the type of straight line tower and the corner tower,ulteriorly confirm tower’s height,the type and amount of insulators and fittings.Thirdly,we repetitiously arrange the tower position on the plane cross section by the template of arc sag. Fourthly,we check the load of tower and the stability of tower foundation .Finally,we design the shockproof of conductor and ground were. Kye Words:220Kv overhead transmission,calculate the stress of the wires,arrange the tower position,Shockproof designing1前言电力能源在国家的发展中占有举足轻重的地位,电力的可靠供应是我国经济实现良好可持续发展的基础。
220KV输电线路工程施工设计三篇
220KV输电线路工程施工设计三篇篇一:220KV输电线路工程项目编号:施工组织设计批准:审查:安监:校核:编写:目录编制依据 (1)一、工程概况及特点 (2)1.1建设、设计、运行、监理、施工所属单位 (2)1.2开竣工日期 (2)1.3工程概况 (2)1.3.1线路概述 (2)1.3.2线路所经行政区域及地形地质 (3)1.3.3线路设计情况 (3)1.3.4交通运输 (3)1.3.5交叉跨越 (3)1.3.6全线杆塔型式统计表 (4)1.3.7主要工程量、材料: (4)1.4工程特点 (5)1.5施工现场总平面布置图 (5)二、施工组织 (7)2.1工程目标 (7)2.2项目经理部 (9)2.2.1工程管理组织机构关系图 (9)2.2.2项目经理简历表 (10)2.2.3项目经理部人员配备表 (10)2.2.4工程现场管理职责 (11)2.2.4.1项目经理和项目副经理的主要职责 (11)2.2.4.2工程部的主要职责 (11)2.2.4.3材料站及物质管理主要职责 (12)2.2.4.4计财部主要职责 (13)2.2.4.5办公室主要职责 (13)2.3施工、技术力量组织 (14)2.3.1组织依据 (14)2.3.2施工技术资料 (14)2.3.3建设场地的准备与清理 (14)2.3.4施工力量 (14)2.3.5技术力量 (15)2.4施工机具安排 (15)2.5器材供应 (18)2.6施工工序总体安排 (18)三、工期及施工进度计划 (19)3.1关键路径 (19)3.1.1影响工期的主要因素 (19)3.1.2解决问题的途径 (19)3.2计划实施 (19)3.3工期计划 (20)四、技术管理 (21)4.1技术资料的编写及交底 (21)4.2施工技术日志 (21)4.3各级技术负责人员的责任划分 (21)五、质量管理 (24)5.1质量目标 (24)5.2质量保证体系 (24)5.2.1思想体系 (24)5.2.2组织体系 (24)5.2.3检验体系 (25)5.3质量检验依据及检验分工 (26)5.3.1质量管理制度与检验评级依据: (26)5.3.2原材料、器材检验要求 (26)5.4工程质量管理规定 (27)5.4.1严格按设计图纸和说明书及技术措施施工 (27)5.4.2坚持“技术交底”、“站队三交”、“三级教育”制度 (28)5.4.3本工程设置质量管理点,加强质量控制 (28)5.4.4施工过程中的记录、检验及签证 (29)5.4.5施工工序检查及中间验收,由项目经理部统一要求按如下规定执行.29 5.4.6工程质量奖罚规定 (30)5.4.7工程资料归档及移交 (30)六、安全管理及文明施工 (31)6.1安全管理 (31)6.2文明施工 (32)6.3职业健康安全和环境整合体系管理 (33)6.3.1安全管理组织机构及主要职责 (34)6.3.2职业健康安全和环境管理整合体系的制度与措施 (36)6.3.3湖南省湘乡市电力建设有限公司危险源识别、评价、控制措施 (38)七、工程成本管理 (44)7.1工程承包合同管理及劳动力控制 (44)7.2降低工程成本的措施 (45)八、主要工序的施工方法及要求 (46)8.1基础施工 (46)8.2杆塔组立 (46)8.3架线施工 (46)九、施工难点及处理方法 (47)9.1基础施工 (47)9.2杆塔组立 (47)9.3放紧线施工 (47)编制依据1.湖南某输变电有限责任公司下发的有关招标文件。
220kV输电塔工程基础专项施工方案
220kV输电塔工程基础专项施工方案1. 简介本文档旨在提供220kV输电塔工程基础专项施工方案。
施工方案包括基础施工的方法和步骤,以确保工程质量和施工安全。
2. 基础施工方法和步骤以下是220kV输电塔工程基础施工的方法和步骤:2.1 地勘工作- 进行土质调查和地质勘察,确定地下情况和基础设计参数。
2.2 基础施工方案设计- 根据地质勘察结果和设计参数,制定基础施工方案设计。
- 确定混凝土配合比以及基础的尺寸和形状。
2.3 基础准备工程- 清理施工区域,确保施工区域无障碍。
- 进行基础开挖工作,确保基础尺寸和形状符合设计要求。
- 进行基础的处理和加固工作,确保基础的稳定性和承载力。
2.4 混凝土浇筑- 进行混凝土配制和搅拌工作,确保混凝土质量符合要求。
- 进行基础浇筑工作,根据设计要求进行浇筑过程控制和养护。
2.5 验收和监测- 进行基础施工的验收工作,确保基础质量符合设计要求。
- 进行基础的监测工作,及时发现和解决施工过程中的问题。
3. 项目安全管理为确保施工安全,以下措施需要被采取:- 严格遵守有关安全法规和标准。
- 提供必要的个人防护装备。
- 对施工人员进行安全培训和指导。
- 实施定期检查和安全巡逻。
4. 资源和时间计划根据施工方案的要求,制定详细的资源和时间计划,确保施工进度和质量。
5. 质量控制在施工过程中,需要进行质量控制,包括但不限于:- 混凝土质量监测- 基础尺寸和形状的测量- 基础稳定性和承载力的监测6. 总结本文档提供了220kV输电塔工程基础专项施工方案的概述和关键步骤。
通过严格按照施工方案进行施工,将确保工程质量和施工安全。
浅析220kV输电线路工程设计与施工
浅析220kV输电线路工程设计与施工【摘要】随着时代的发展,人们对电能的需求也日益增加。
国家开始建设和投入使用高压输电线路,这大大提高了电网的输送能力。
目前,500kV超高压输电线路已经基本建成,并在东部和中部地区逐渐取代220kV高压输电线路。
随着220kV输电线路的不断增多,同时也越来越接近城市,因此,对200kV输电线路的设计和施工进行深入的研究显得尤为重要。
本文将从基础部分、杆塔、架线等几个方面,详细探讨220kV输电线路的设计要点,以期为城市发展提供更好的保障。
【关键词】220kV输电线路;工程设计;施工1.220kV输电线路的设计要点和优缺点1.1设计要点(1)220kV输电线路拓扑设计一般来说,220kV输电线路的水平和垂直距离取决于导线与输电塔之间的最小间距。
然而,为了更好地控制摆动角度,以及减少相导线之间的垂直性,以及降低振动现象的发生,横担的位置应该比其他两个横档的距离更远。
通过改变导线的水平位置,可以显著提高输电线塔的安全性和稳定性。
在丘陵地带,由于障碍物的存在,导线的水平和垂直距离必须达到最小值,以确保覆冰和振动的安全性。
因此,铁塔外围的构件会产生较大的倾斜,这将导致导线的间距变得更远,增加了导线之间的水平距离。
当底部横担的构件与顶部连接处的倾斜角度变大时,任何两个横担之间的垂直距离也会随之增大,使得导线之间的间距得到有效的拉伸,提高了整体的性能。
(2)路径优化的选择为了确保线路的安全运行,应当尽量避开气候、水文和不利的地质环境,加强工程的抗自然灾害和突发事件的能力,减少对当地规划和其他设施的不利影响,尤其要尽量避免穿越采矿区,以提升线路的安全性。
如果条件允许,线路应尽量与现有和计划建造的电力线并行,这样可以降低建设成本,减少交叉干扰。
为了确保输电线路的安全运行,必须对其对环境的影响进行全面的评估,包括但不限于地震安全性、文物调查、地质灾害、压覆矿产、环境影响等,这些前期工作必须经过相关行政管理部门的审核和批准,方可正式开展。
220千伏线路直线杆塔基础施工技术
220千伏线路直线杆塔基础施工技术摘要:随着我国经济和科技的不断发展,工程建设对高压送电线路设计安装的要求也越来越高。
本文从高压送电线杆塔桩基础的受力特点、塔基设计、施工等方面阐述了我国高压送电线路杆塔基础的现状,本文主要论述了杆塔基础的主要分类和施工中几个常见问题的技术处理措施,希望能够对输电线路的杆塔基础施工方面起到部分参考作用。
关键词:220千伏线路;直线杆塔;基础;施工技术杆塔基础是输电线路系统的重要构成部分,是保障线路的安全运行的关键部件,以往输电线路设计时,为简化铁塔计算和制图工作量,方便施工基面开挖和铁塔组立,大多铁塔采用等长接腿,塔位需要较大的基面降,由此产生大量土方量,塔基内侧也产生了高边坡,由于以往工程一般经过简单处理,弃方堆放在塔基周围的沟洼、甚至沿波面自然滑落,当具有外部诱因,如强降水、地震等时,势必造成水土流失和泥石流、滑坡。
水土流失造成植被破坏,进而使铁塔塔基出现安全隐患。
地表径流产生的水土流失导致地表变化,使铁塔基础埋深减小甚至外露,基础有效埋深的减小,导致抗拔贮备的下降,当出现设计极限荷载组合条件时,将危及基础的稳定性,线路运行出现安全隐忌。
例如,山区输电线路基础基本上都是采用直柱平板基础,铁塔采用等高腿,基础施工中需大幅削减边坡形成基础平台,由此而引发下列问题。
1 杆塔基础1.1岩石基础是指在岩石地基中直接钻挖所需的基坑,然后将钢筋骨架和砼直接浇注到岩石基坑内,借助岩石本身的强度和岩石与水泥砂浆间以及砂浆与锚筋之间的粘结力,共同承担杆塔的上部外力,保证杆塔结构的稳固。
由于其充分利用了岩石本身的强度,减少了混凝土和钢筋的用量,也减少了基坑土石方量,使得施工费用得到了很大的降低。
该基础主要应用在覆盖层较浅或无覆盖层的高硬度岩石地基中,因此对岩石的构造要求比较高,不符合大规模应用的要求。
1.2把输电线路杆塔的作用力传递给地基土或者是岩石是架空输电线路的基础用途,经归纳总结,其在设计、施工和检测方面的行业特点有①输电线路跨越的区域广、线路距离长、所经过的地形地貌复杂,在设计和施工中需要综合进行考虑;②杆塔基础承受的荷载比较复杂,基础不但而且要承受拉压的荷载作用,还要承受较大的水平荷载作用。
220KV输电线路的工程设计与施工方法
220KV输电线路的工程设计与施工方法摘要:220kV的电路的设计难度并不高,但是,因为的其能够决定的电力的分配和传输,所以,在管理上必须要深入,以免影响正常的供电。
整体来看,在设计上需要考虑一些客观因素,例如环境因素、工艺因素、人力因素等,只有良好的保证工程实现,才能够在电路运行过程中实现安全,进而合理的帮助用户分配电能。
关键词:220KV;输电线路;工程设计;施工方法20世纪60年代以来直流输电有新发展,与交流输电相配合,组成交直流混合的电力系统。
更正一点,在电力系统中,35KV至220KV电压等级的电力线路成为输电线路;500KV至更高称为超高压输电线路,而10KV及以下的称为配电线路。
供电线路是要长距离输电,所以电压要高,就可以减少在输电过程中的损耗,而配电网是输电网的下级系统,已经过枢纽变电所的变电、降压,所以电压不高。
再经过地方变电所,就变成我们平常用的220v了。
本文所讲述的就是220kv输电线路。
众所周知,作为电路施工中最常用的输电线路之一,220kv输电线路需要确保安全无故障,才能保证人们的用电安全。
作者通过讲述自己的经验,系统地分析了施工中需要注意的地方,希望对读者有所帮助。
1设计工作的关键点1.1导线的设计由于220kV架空输电线路导线的质量要求十分的严格,我们在进行设计工作的时候,需要加大对影响因素的分析。
由于220kV的电压较高,大部分位于室外,我们需要做好的设计工作就是,加强其对防腐的要求,更需要跟根据工程的实际的需要进行处理。
我们需要采用导电性能强、重量轻的导线。
还有我们应该针对施工地点的环境选择最适合的配备方式。
架空电线通常是架设在电线杆上,我们在进行选择的时候,应该加大对影响因素的分析,做好导线的保护工作。
1.2220kV架空输电线路杆塔设计的要点电线路杆塔就是为了支撑电线的,我们在实际设计的时候,需要对电线路杆塔的高度和材质进行选择,当然最重要的工作就是进行安放地点的选择。
220kv铁塔组立施工--大学毕设论文
广西电力职技术学院电力工程系毕业论文题目 220kv铁塔组立施工专业班级学号姓名指导教师(签名)年月日教研室主任(签名)年月日摘要目前电力工业发展迅猛,电力体制改革不断深化,对电量需求越来越大,铁塔扩建的数量也越来越多。
电力架空线路的施工中,铁塔组立是重要部分之一。
铁塔组立能否顺利完成关系到整条线路的施工进度。
在铁塔组立过程中,若采取的措施不当,可能会导致铁塔不能正常组立,甚至造成安全隐患。
现阶段铁塔的组立方式主要有整体组立和分解组立,目前,分解组立铁塔是铁塔组立的常用方法。
其中包括:外拉线抱杆起吊;内拉线抱杆起吊和无抱杆倒装组塔。
各种方法都有各自的优缺点和适用场合。
它不受地形、内物限制,使施工现场紧凑;简化了组塔的工具,提高了施工的效率;起吊构件平稳方便,抱杆提升安全可靠;不会出现受力不均使局部塔材变形,避免了基础的不均匀沉降。
实践证明,内拉线抱杆分解组立铁塔是行之有效的铁塔组立新工艺。
内抱杆的优点有四条1. 施工现场紧凑,不受地形、地物限制。
轻易地解决了外拉线抱杆组塔法的外拉线不易或不能布置的困难。
2.简化组塔工具,提高施工效率。
取消了外拉线及地锚,缩短拉线长度,进一步使工器具简单轻便,运输、安装、撤除工具的工作量大为减少。
3.抱杆提升安全可靠,起吊构件平稳方便。
4.吊装塔材过程中,抱杆始终处于铁塔的结构中心,铁塔四角主材受力均匀,不会出现受力不均使局部塔材变形;同时,四个塔腿受力均匀,避免了基础的不均匀沉降,对底板较小的基础型式如金属基础尤其有利。
本文通过对内拉线抱杆分解组立铁塔的施工方案的设计和研究,以求达到对铁塔组立施工的施工方案、施工技术要求、安全要求等各个方面进一步的了解,优化和协调,以求达到更高效益不仅能加深对已学理论知识的理解,而且能学到更多新的知识,为今后的工作提供更多的理论与实践基础。
关键词:铁塔、组立、施工目录第一章工程概况------------------------------------------------------------ 1 1.1工程概述-------------------------------------------------------------- 1 1.2工程特点-------------------------------------------------------------- 1 1.3铁塔参数-------------------------------------------------------------- 2 1.4施工技术依据---------------------------------------------------------- 2第二章铁塔组立对混凝土浇筑基础的要求-------------------------------------- 3 2.1一般规定-------------------------------------------------------------- 3 2.2基础要求-------------------------------------------------------------- 3第三章内拉线悬浮抱杆组塔方法及说明----------------------------------------- 4 3.1 内拉线悬浮抱杆组塔工艺流程-------------------------------------------- 4 3.2内拉线悬浮抱杆组立---------------------------------------------------- 4 3.3内拉线悬浮拉线组立塔腿段---------------------------------------------- 6 3.4 内拉线方法铁塔组立工器具--------------------------------------------- 10第四章施工说明----------------------------------------------------------- 11 4.1线路方向------------------------------------------------------------- 11 4.2铁塔构件组装--------------------------------------------------------- 11 4.3铁塔脚钉安装--------------------------------------------------------- 11 4.4铁塔的连接螺栓------------------------------------------------------- 12第五章质量要求----------------------------------------------------------- 14 5.1组塔的技术交底------------------------------------------------------- 14第六章职业健康安全措施--------------------------------------------------- 16 6.1安全方针------------------------------------------------------------- 16 6.2职业健康安全目标----------------------------------------------------- 16 6.3安全规程------------------------------------------------------------- 16 6.4防止触电高空坠落的安全措施------------------------------------------- 16第七章环境保护文明施工--------------------------------------------------- 17 7.1环境保护及要求------------------------------------------------------- 17 7.2职业健康安全主要监控点与控制措施------------------------------------- 17 7.3杆塔组立工程文明施工关键点控制措施----------------------------------- 18参考文献------------------------------------------------------------------ 19致谢--------------------------------------------------------------------- 20第一章工程概况1.1工程概述本工程电压等级为220kv,分2条单回路架设,线路全长为21.867km,共104基杆塔。
- 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
- 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
- 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。
XXX电力高等专科学校毕业设计(论文)题目:220kv输电线路杆塔基础施工设计学号:姓名:指导教师:专业:高压输配电线路施工运行于维护班级:XXX电力高等专科学校毕业设计(论文)评审表XXX电力高等专科学校毕业设计(论文)答辩小组评价表答辩小组成员:年月日XXX电力高等专科学校毕业设计(论文)评阅教师评价表评阅教师:年月日XXX电力高等专科学校XXX电力高等专科学校XXX电力高等专科学校毕业设计(论文)中期检查登记表系部:班级:学号:14 学生姓名:毕业设计(论文)题目:220kv输电线路杆塔基础施工设计一、毕业设计(论文)进程情况(请在选择项上打“√”)1.文献查阅与资料总结:好;较好;一般;差;文献查阅数量:中文篇,外文篇。
2.是否按原定计划进程执行:是;基本是;否。
3.已完成总任务的百分数%。
4.指导教师对毕业设计(论文)开题阶段工作的评语:好;较好;一般;差。
二、学生前阶段工作态度和纪律情况1.每周平均工作时间;请假次数;主要原因。
2.对学生工作态度的评价:认真;一般;不认真。
三、中期检查综合评价1.综合评价2.存在问题及改进措施四、中期检查总体评价好;较好;一般;差。
检查教师:检查时间:年月日XXX电力高等专科学校毕业设计(论文)任务书目录摘要 (1)一.概述 (2)1.1工程概况 (2)1.2编写依据 (3)二.施工准备 (5)2.1接桩 (5)2.2材料点(施工驻点)选择 (7)2.3施工测量(复测) (7)2.4工地运输 (7)三.基础施工 (10)3.1混凝土杆基础施工 (10)3.2铁塔基础施工 (12)3.3基础作业工艺流程图 (20)3.4混凝土配合比计算 (21)四.铁塔基础施工工艺及技术措施 (23)五.质量标准及检验要求 (36)六.安全措施及文明施工 (39)七.组织措施 (41)八.结束语 (42)九.参考文献 (43)XXX电力高等专科学校毕业设计摘要随着国民经济快速增长,各地电网建设迅猛发展,从过去的“几年建一条线路”到现在的“一年建几条线路”实现了跨越式发展,供电可靠性进一步提高,电网输送能力大大增强,但输电线路建设的内部环境和外部空间却越来越小。
如何应对新形势,最大限度地满足电网建设需要已成为技术部门不断研究的课题。
本文从施工设计角度围绕杆塔基础的设计方面提出了意见和看法。
本文根据施工现场环境条件设计了施工方案,编写施工方法,确定施工现场布臵,选择了所需的工器具。
还通过施工地形,计算相关参数确定杆塔的基础。
还给出相关施工操作的施工工艺及技术标准。
最后还给出安全措施和组织结构图,保证送电线路稳定运行等条件,为提高线路安全运行的安全系数提供有利参数。
关键词 220kv输电线路杆塔基础设计混凝土配合比计算施工“三措”一.概述本作业指导书适用于某220kV架空输电线路工程基础施工的指导。
1.1工程概况本工程为220kV架空输电线路全长61.5公里,全线路杆塔总共167基,其中混凝土杆82基,铁塔85基。
导线采用2×LGJQ-300分裂导线,地线采用两根GJ-50避雷线。
本工程根据地质水文资料,沿线主要地层为黄土状亚粘土,呈浅黄色、褐黄色,中密稍湿,地下水位均在8米以下。
本工程地势起伏变化较大,除电厂出口地形平坦外,其它地段地形变化大,台地多,冲沟多,部分冲沟宽而深,全线路越山河、河流、水库等较多,跨距大可供大车运输的道路很少,所以运输比较困难,大部分杆塔需人共搬运。
1.1.1工程技术特性:气象条件:最大设计风速30m/s;最大覆冰厚度10mm;电压等级:220千伏;建设性质:新建架空输电线路;导线:2×LGJ-300;地线:一根为GJ-50地线;1.1.2地形、地貌及地质情况根据岩土工程勘察报告,本线路沿线主要地层为黄土状亚粘土,呈浅黄色、褐黄色,中密稍湿,地下水位均在8米以下。
基坑开挖后若发现不良地质情况应及时通知项目部解决。
1.1.3交通状况本工程地势起伏变化较大,除电厂出口地形平坦外,其它地段地形变化大,台地多,冲沟多,部分冲沟宽而深,全线路越山河、河流、水库等较多,跨距大可供大车运输的道路很少,所以运输比较困难,大部分杆塔需人共搬运。
1.1.4线路方向1.2编写依据1.2.1《110 - 500KV架空电力线施工及验收规范》(GB50233-2005)1.2.2《110-500KV架空电力线路工程施工质量及评定规程》(DL/T5168-2002)1.2.3《国家电网公司输变电工程质量通病防治工作要求及技术措施》(基建质量…2010‟19号)1.2.4《输变电工程建设标准强制性条文实施管理规程》(Q/GDW248-2008)1.2.5《钢筋焊接及验收规程》(JGJ 18-2003)1.2.6《混凝土拌合用水标准》(JGJ 63-2006)1.2.7《普通混凝土用砂、石质量及检验方法标准》(JGJ 52-2006)1.2.8《混凝土结构工程施工质量验收规范》(GB50204—2011)1.2.9《普通混凝土配合比设计规程》(JGJ 55-2011)1.2.10《混凝土强度检验评定标准》(GB50107-2010)二.施工准备根据审定后的施工图纸及现场情况,在开工前应做好充分准备工作,其主要工作内容包括:现场调查,工程指挥部、材料站、施工驻点的选择,器材准备,施工机具准备、检修、障碍物处理及协议,占地赔偿,编制施工组织设计和施工计划及施工技术设计,进行技术培训、新技术科研试验,施工图技术交底等。
现场调查主要包括:路径情况主要调查沿线的行政归属、地形、地质、劳力资源、地方材料及树木、经济作物分布情况;交通情况主要调查工地大运输、小运输的方式及距离,并计算大、小运输半径。
同时应调查大小运输的道路情况,特别是应调查修补或新修的道路的里程;交叉跨越情况主要调查线路施工要跨越的障碍物,如铁路、公路、电力线、弱电线路、河流、房屋等情况,同时应调查被拆迁的障碍物情况;住地及生活供应情况主要调查靠近线路的城镇、村庄、工厂等有无闲臵住地及其水、电资源和生活资源等;杆位情况调查主要调查杆位所在位臵的户主、归属单位、青苗归类。
每基杆塔具备的施工条件及材料、牵张设备等能否直达桩位;对于大跨越或重要的障碍物应作重点调查,为编写施工方案提供正确的依据。
2.1接桩设计单位按施工断面图进行现场定位,施工单位派人现场对线路所定的里程桩、杆位桩、方向桩和辅助桩进行现场交接。
现场接桩人员应进行现场调查,为的是了解现场情况以便顺利施工,现场调查的主要事项如下:⑴了解沿线地形、地貌以及各种地形(山地、丘陵、平原、沼泽等)的分布范围。
记录各杆塔所处地形能否满足组立杆塔的需要(如不能可要求设计单位移设杆塔位),以便考虑组立杆塔的吊装方法和紧线、放线区段及安放点。
⑵对山区的各个塔位应调查其能否满足杆塔堆放与所占场地的地形,以及需要开挖平整场地的工作量。
⑶了解沿线杆塔位臵的地质情况,以便考虑开挖基础的施工方法或采取爆破施工的可能性。
⑷调查了解浇制混凝土基础的水源分布情况、水质情况。
⑸调查了解沿线路交叉跨越情况,以便考虑搭设跨越架的型式和高度。
⑹跨越河流时,应调查水流速度、水深。
对季节性河流应了解涸水期、来水期等,以便考虑架线方法。
⑺调查线路附近地上、地下障碍物情况,以便考虑土石方开挖、爆破的主要措施和放线时应防止导线磨损的措施。
⑻调查电力线、通讯线的路径及交叉跨越电力线路停电的可能性、允许停电时间,以便与线路施工协调配合,安排施工有关工序的进度和应采取的措施。
⑼调查线路附近需要砍伐的树木种类、高度以及需要拆迁房屋的问题和沿线青苗分布面积及杆塔占地面积,以便进行障碍物的清理和赔偿。
2.2材料点(施工驻点)选择根据施工预算中给定的运输半径及便于施工减少二次运输的里程来选择材料点(施工驻点)。
材料点的选择应靠近公路、运输方便、通讯便利、地势较高的地方,应远离村屯(考虑防盗)的地方。
2.3施工测量(复测)对线路进行部分复测、杆塔基础分坑、基础操平,以及施工所需要的其它测量工作。
其主要内容如下:⑴复测设计勘定的杆塔中心桩的位臵,在进行基础分坑测量之前对设计勘定的杆塔中心桩进行复测。
如偏差超过以下规定时应查明原因予以纠正。
具体要求:①以设计勘测定的两相邻直线桩为基准,其垂直线路方向偏差不应大于50mm。
②测量使用的仪器和工具,在使用前应检查校正。
量距用的绳尺、钢尺应全面检查其差度是否符合计量标准,以免量距发生错误。
③废臵的桩位应拔掉以免误认为是杆塔中心桩造成施工错误。
④辅助桩应固定牢固。
对易碰损的桩应加以保护,以防松动或施工中改动、碰动。
⑤测量用的塔尺接口应牢固,以防塔尺下坠造成测距错误。
扶塔尺人员应注意附近高压线路以防塔尺接触带电体造成伤害。
⑥操作仪器人员不得离开仪器以免仪器被风吹倒损坏。
2.4工地运输根据施工图所编制的运输手册,将施工用的器材、机具及施工现场临时建筑材料、生活用品等运到指定的地点。
2.4.1负责运输工作的人员在施工准备阶段(指接桩时)应进行如下调查:①调查了解沿线交通运输道路的分布情况、路面的宽度、材质、转弯、坡度等情况,沿线桥梁、涵洞的宽度及承载能力以便考虑运输方式。
②沿村庄或路口标出通往杆塔方向的路标以便将所需材料运到杆塔位。
③如选择炸药存放仓库时要考虑容纳药量吨位和安全可靠程度,最好使用现有的炸药仓库。
2.4.2材料准备主要包括的内容:①根据施工图详细统计全线路各种材料规格、数量,并编制材料总表及各施工班组或施工队的材料分配表。
②统计各种杆段、底盘、卡盘、拉线盘等的规格和数量。
③联系杆塔、预制件、金具、绝缘子、导线、钢绞线的加工制造并签定加工定货合同,落实交货日期。
④验收各种器材是否符合质量标准和设计要求,开箱验货时应将原材料和器材出厂的质量合格证、试验记录保存好,竣工时移交。
2.4.3工地运输安全注意事项①机动车辆运输应按国家《道路交通管理条例》有关规定执行。
②冬季车辆通过河流时,必须根据当地气候情况和河水冻结程度决定是否行车,不得盲目通过。
③载货机动车除押运和装卸人员外,不得搭乘其他人员。
押运和装卸人员必须乘坐在安全位臵上。
载物高度超过车厢护栏时,货物上不得坐人。
④装运超宽、超高或重大物件时应遵守下列规定:a物体重心与车厢承重中心基本一致;b易滚动的物件顺其流动方向用楔掩牢并捆绑牢固。
c用超长架载运超长物件时,在其尾部设标志,超长架与车厢固定。
物件与超长架及车厢捆绑牢固。
d押运人员应加强途中检查,防止捆绑松动,通过山区或弯道时防止超长部分与山坡或树木刮碰。
e在施工车辆不足的情况下,允许用车携带少量炸药(10kg)和雷管(20个),但应采取防震、防火措施。
携带雷管的人员必须坐在驾驶室内。
⑤人力运输和装卸安全注意事项:a人力运输的道路应事先清除障碍物,山区抬运笨重物件或钢筋混凝土电杆的道路,其宽度不宜小于1.2m,坡度不宜大于1:4。