更换补充水沟盖板作业指导书目次1.作业介绍 ....................................................... 1 1.1 作业地点 .....................................................1 1.2 适用范围 .....................................................1 1.3 上道作业 .....................................................1 1.4 人员要求 .....................................................1 1.5 作业要点 .....................................................1 2.作业流程 ....................................................... 2 3.作业程序、标准、示范 ........................................... 3 3.1 开工准备 .....................................................3 3.2 作业程序 .....................................................3 3.3 质量标准 .....................................................4 4.工装设备、检测器具及材料 ....................................... 5 5.安全风险 ....................................................... 6 5.1 违章施工作业风险 .............................................6 5.2 从业人员伤害风险 .............................................61.作业介绍1.1 作业地点 工务段管辖桥路设备。

厂房内排水沟盖板更换方案

厂房内排水沟盖板更换方案

斜沟煤矿选煤厂施工方案审批表厂房内排水沟盖板更换施工方案目录一、施工组织机构 (4)二、工程概况 (4)三、质量、安全及工期目标 (4)四、施工范围 (5)五、施工准备 (5)5.1、技术准备 (5)5.2、材料及施工用具准备 (5)5.3、劳动力准备 (5)六、施工方法 (7)6.1、排水沟盖板更换 (7)6.2、混凝土排水沟改造 (8)七、安全质量保证措施 (9)7.1、质量保证措施 (10)7.2、临时用电的施工组组织设计及防触电措施 (10)7.3、防火及防毒、防雷、防爆措施 (11)八、环境保护及文明施工措施 (11)厂房内排水沟盖板更换施工方案一、施工组织机构施工项目负责人:原杰施工技术负责人:张国庆施工安全负责人:秦元尧现场施工负责人:冯建军现场安全负责人:李本有施工地点:选煤厂厂房内二、工程概况由于厂房内部分排水沟沟壁及沟盖板坏损,造成厂房内地面排水系统混乱,现按要求将各厂房内坏损的排水沟壁及沟盖板进行拆换、更换改造。

三、质量、安全及工期目标质量目标:按照施工标准安全目标:杜绝一切安全事故发生工期目标:按甲方要求工期之内完工四、施工范围本工程更换的排水沟主要有主厂房,五号转载点、筛分楼、 703驱动站等厂房内。

五、施工准备5.1、技术准备施工技术人员施工前应弄清弄懂施工图纸,明确施工技术难点,做到有得放矢,施工前对施工班组进行技术交底,编制专项施工组织设计文件,做好资料准备工作。

5.2、材料及施工用具准备所有进场材料需有产品合格证,质量检验证明书、出厂合格证等,材料员对进场材料按照验收规范逐一检查,对于资料不全或者材料不合格,坚决不予接受,进场的盖板应对其材质、规格、色泽等检验批目,进行严格检查,材料员邀请甲方代表共同进行检查。

施工机械及用具施工前应进行检查,具体材料用量见下表5.3、劳动力准备因本工程全在车间厂房内部施工,施工人员应选择综合素质较高,遵守车间规章规定,有经验的施工队伍进场。

排水沟盖板施工方案

排水沟盖板施工方案

排水沟盖板施工方案排水沟盖板施工方案一、项目简介:排水沟盖板施工是指在排水沟或者地下管道上方安装盖板,目的是为了保护排水设施不受外界物体的侵入,同时能够承受人和车辆的压力。

二、施工准备:1. 了解施工现场的地形和环境条件,确定盖板的尺寸和材质。

2. 准备好所需的施工工具和材料,如切割机、砂浆、钢筋等。

3. 清理施工现场,确保工作区域整洁干净,便于施工。

三、施工工艺:1. 测量:根据实际情况,精确测量排水沟的尺寸,确定盖板的大小和位置。

2. 切割:使用切割机将盖板按照测量的尺寸进行切割,确保尺寸准确。

3. 螺丝安装:在排水沟的边缘或预留的孔上,用螺丝将盖板牢固地固定在地面上。

4. 砂浆填充:用砂浆将盖板与排水沟的空隙填满,确保盖板与地面之间没有空隙。

5. 钢筋加固:根据需要,可以在盖板中加入钢筋,增加盖板的强度和稳固性。

6. 检查:在施工完成后,对盖板进行检查,确保无松动或破损现象,确保施工质量。

四、安全措施:1. 在施工现场设置明显的警示标志,提醒路人和车辆注意施工。

2. 使用安全防护装备,如安全帽、手套等。

3. 施工过程中严禁乱扔杂物,保持施工现场整洁。

4. 确保施工工具和材料的质量和完好性,避免意外事故的发生。

5. 严格按照施工工艺操作,确保施工过程安全可靠。

五、施工注意事项:1. 盖板的尺寸应与排水沟的尺寸相匹配,且安装牢固,以确保排水系统正常运行。

2. 盖板的材质应具有防滑、耐腐蚀和耐压能力,适合施工现场的环境条件。

3. 盖板与排水沟的连接部位应牢固可靠,不得出现松动或者间隙。

4. 盖板施工完成后,应及时进行清理,保持施工现场的整洁。

5. 盖板施工完成后,应定期检查盖板的状况,如有损坏或松动应及时修复或更换。

六、施工成果:经过施工后,排水沟盖板安装牢固,与地面接缝紧密,能够有效防止外界物体进入,保护排水设施的正常运行,提高排水系统的安全性和可靠性。

以上就是排水沟盖板施工方案的基本内容,通过合理的施工流程和安全措施,能够确保施工过程顺利进行,达到预期的效果。

排水沟井盖铸铁井盖更换施工方案

排水沟井盖铸铁井盖更换施工方案

排水沟井盖更换施工方案编号:01排水沟井盖铸铁井盖更换施工方案编制人:审核人:批准人:广西联友建设工程有限公司2020年9月排水沟井盖更换施工方案目录一、编制依据及范围...................................................................................- 1 -二、工程概述...............................................................................................- 1 -三、主要技术指标.......................................................................................- 2 -四、施工现场情况:.................................................................................- 4 -五、材料、设备、人员准备.....................................................................- 4 -六、施工准备...............................................................................................- 6 -七、施工工艺和方法.................................................................................- 6 -八、质量检验标准................................................................................... - 11 -九、进度计划.......................................................................................... - 12 -十、安全保证措施.................................................................................. - 13 - 十一、附图.............................................................................................. - 15 -一、编制依据及范围1、施工现场情况2、排水沟渠流量及载物重量60T设计3、铸铁检查井盖CJ/T511-20174、按照要求尽量节约成本5、建设单位要求二、工程概述1、工程概况现场实际情况排水沟盖已经损坏,排水沟宽1.4m,长约200m。

排水沟及盖板施工方案

排水沟及盖板施工方案

排水沟及盖板施工方案排水沟及盖板施工方案一、施工前准备:1. 确定施工位置和尺寸,制定详细的施工方案。

2. 设计并准备好所需材料和工具。

3. 安排施工人员,并组织施工前的安全培训。

二、施工流程:1. 清理施工区域,将杂物、泥土等清除干净。

2. 按照设计要求,用标线工具划出管道的位置和尺寸。

3. 开挖排水沟,根据设计要求确定排水沟的深度和宽度,确保排水沟有足够的容量进行排水。

4. 进行排水沟的土工处理,使用合适的防水材料(如沥青涂料)涂刷排水沟内侧和底部,以增加排水效果和延长使用寿命。

5. 铺设排水管道,根据设计要求选择合适的材质和规格的排水管道,确保管道连接牢固,没有漏水现象。

6. 进行排水沟的德国砖铺设,首先将准备好的德国砖放置在合适位置,然后使用适量的水泥砂浆将德国砖一一粘贴固定。

7. 完成排水沟的砌筑后,进行排水沟的水平检查和排水试验,确保排水沟的坡度正确,并能够顺利排水。

三、盖板施工:1. 根据设计要求制作合适尺寸的盖板,可以选择耐久性好且防滑的材料(如混凝土、钢板等)。

2. 将盖板安装在排水沟上,确保盖板与排水沟紧密连接,没有松动和漏水现象。

3. 完成盖板安装后,进行质量检查,确认盖板的牢固程度和使用安全性。

四、施工安全:1. 施工过程中需要注意人员的安全,加强安全教育和培训,确保所有人员具备必要的安全知识和操作技能。

2. 严格遵守施工现场的安全规定,配备必要的安全保护设备和器材,如安全帽、手套、安全网等。

五、施工质量控制:1. 在施工过程中,随时进行质量检查,并及时进行必要的调整和修复。

2. 施工完成后,进行终验,确保排水沟和盖板的牢固性和使用性能符合设计和施工要求。

3. 根据验收结果进行整理和整治,确保施工现场的整洁和安全。

六、验收与交付:1. 完成施工后,进行终验和质量验收。

2. 完成验收后,整理施工资料和图纸,交付施工方或业主方。

排水沟井盖角钢混凝土盖板更换施工方案

排水沟井盖角钢混凝土盖板更换施工方案

排水沟井盖更换施工方案编号:02排水沟井盖更换施工方案(角钢混凝土盖板)编制人:审核人:批准人:2020年9月排水沟井盖更换施工方案目录一、编制依据及范围...................................................................................- 1 -二、工程概述...............................................................................................- 1 -三、主要技术指标.......................................................................................- 2 -四、施工现场情况:.................................................................................- 4 -五、材料、设备、人员准备.....................................................................- 4 -六、施工准备及投入主要管理人员...........................................................- 6 -七、施工工艺和方法.................................................................................- 7 -八、质量检验标准.................................................................................. - 17 -九、进度计划.......................................................................................... - 18 -十、安全保证措施.................................................................................. - 18 - 十一、附图.............................................................................................. - 20 -一、编制依据及范围1、施工现场情况2、排水沟渠流量及载物重量60T设计3、混凝土结构工程施工质量验收规范GB50204-20154、按照要求尽量节约成本5、混凝土结构施工图平面整体表示方法制图规则和构造详图16G101-1/2/36、钢筋焊接及验收规程JGJ18-20127、建筑工程施工质量验收统一标准GB50300-20138、钢筋混凝土用钢热轧带肋钢筋GB1499-20079、建设单位要求二、工程概述1、工程概况现场实际情况排水沟盖已经损坏,排水沟宽1.4m,长约200m。

厂房内排水沟盖板更换方案

厂房内排水沟盖板更换方案

厂房内排水沟盖板更换方案一想到厂房内排水沟盖板的更换,我的思绪就像打开了一扇窗,清新的空气扑面而来。

十年前的我,还是一个对工程方案写作一窍不通的小白,但如今,我已经可以轻松驾驭这样的任务。

下面,就让我以流畅的笔触,为你呈现一份详尽的更换方案。

一、项目背景我们要明确项目的背景。

厂房内的排水沟盖板已经使用了多年,由于长时间的风吹雨打,部分盖板已经出现破损、腐蚀、变形等问题。

这些问题不仅影响了厂房的美观,还可能对排水系统的正常运行造成影响。

因此,我们决定对这些盖板进行更换。

二、项目目标我们来看看项目目标。

我们的目标有三:1.确保排水沟盖板的质量,提高排水系统的稳定性。

2.提高厂房内环境的美观度。

3.降低后续维护成本。

三、项目实施步骤1.材料选择耐腐蚀性强:不锈钢材质可以有效抵抗酸碱盐等腐蚀性物质的侵蚀。

承重能力强:不锈钢盖板的承重能力远高于传统铸铁盖板。

2.施工准备清理排水沟:将排水沟内的杂物、淤泥等清理干净,确保施工顺利进行。

检查排水系统:检查排水系统是否正常运行,如有问题,及时进行修复。

3.施工过程拆除旧盖板:将原有的破损盖板拆除,注意不要破坏排水沟的结构。

安装新盖板:按照设计要求,将不锈钢盖板安装到排水沟内,确保盖板与排水沟的接口严密。

固定盖板:使用膨胀螺栓将盖板固定在排水沟两侧,确保盖板不会移动。

检查施工质量:在施工完成后,对排水沟盖板进行检查,确保安装牢固,无渗漏现象。

4.施工验收在施工完成后,我们需要对项目进行验收。

验收标准如下:排水沟盖板安装牢固,无松动现象。

排水系统正常运行,无渗漏现象。

施工现场干净整洁,无遗留垃圾。

四、项目后期维护为了确保排水沟盖板的使用效果,我们需要做好后期维护工作:1.定期检查:每隔一段时间,对排水沟盖板进行检查,发现破损、腐蚀等问题,及时进行修复或更换。

2.清理排水沟:定期清理排水沟内的杂物、淤泥等,确保排水系统的正常运行。

3.防止腐蚀:在排水沟内涂抹防腐涂料,防止腐蚀性物质对盖板造成损坏。

排水沟清淤更换钢玻璃盖板施工方案

排水沟清淤更换钢玻璃盖板施工方案

排水沟清淤更换钢玻璃盖板施工方案
排水沟清淤更换钢玻璃盖板是通过优化罩体结构设计,提高了产品载荷负重,满足了超大跨度池体的需要。

有效地对废气进行收集,然后进行处理。

排水沟清淤更换钢玻璃盖板根据客户排水沟大小进行定制,净化塔根据排水沟面积大小设计,处理换气量按6次/h以上进行计算。

具有强度好,耐腐蚀,抗老化,寿命长,冷热膨胀伸缩系数小等特点。

净化系统工艺采用氧化净化+加碱液吸收,工艺流程符合环保要求,使用寿命达到15年以上。

排水沟罩是处理污水须要使用的,它的作用就是将有害的气体密封在排水沟内使之不能散发到空气中影响空气质量和污染周围的环境。

那么,对于排水沟罩要选用的材质则须达到排水沟使用的条件。

而玻璃钢材质的排水沟罩板以其天生所具有的良好的耐腐蚀性能以及非常好的强度非常的适合为排水沟罩的材质,并且也是。

排水沟清淤更换钢玻璃盖板采用的防酸防碱耐腐蚀性能优异的不饱和聚酯树脂,作为基体材料,以中碱或无碱玻璃纤维布作为增强材料,采用优良的固化配方,先进的固化工艺,根据各排水沟的状况形状,确定特定模具作为成型外模固化成型。

排水沟清淤更换钢玻璃盖板表面采用抗老化、耐候、抗紫外线胶衣树脂,色泽鲜艳,美观大方。

经上述工艺形成的排水沟清淤更换钢玻璃盖板强度高、耐腐蚀、抗老化、安装维护方便、美观大方。

排水沟盖板更换拆除清运方案

排水沟盖板更换拆除清运方案

排水沟盖板更换拆除清运方案以下是 7 条关于排水沟盖板更换拆除清运方案:1. 嘿,朋友们!咱先来说说这排水沟盖板更换哦!就像给咱家里换个新地板一样重要。

你想想,那破破烂烂的盖板多碍事啊!咱得赶紧把它拆喽,换上新的,让排水都顺畅起来呀!比如那旧盖板就好像是个捣乱的家伙,老是给咱添麻烦,咱能不赶紧把它弄走嘛!所以说,换新的势在必行呀!2. 哇塞!拆除这排水沟盖板可不能马虎呀!这就好比拆一座小城堡,得小心翼翼的。

不能太粗暴啦,不然会搞出更多麻烦哟!清运的时候也是呀,得像护送宝贝一样把那些旧盖板运走。

就好像咱护送生病的小伙伴去医院一样认真呢!你们说是不是该这样好好对待呀!3. 哎呀呀!这排水沟盖板的更换可是个大工程呢!但咱不怕呀!咱们要像勇敢的战士去战斗一样对待。

把那该拆的果断拆掉,清运的工作也得干得漂亮。

就像比赛跑步一样,不能拖拖拉拉的!想想看,要是一直留着那破盖板,多影响心情啊,咱得赶紧行动起来呀!4. 嘿哟!更换排水沟盖板的时候,大家可得齐心协力呀!可别你干你的我干我的,那不就乱套啦!我们要像一个紧密的团队一样,有拆除的,有清运的,配合得天衣无缝呀!这就好像踢足球,每个人都有自己的位置和任务,不然怎么能赢呢!所以,大家一起加油干哟!5. 哇哦!这排水沟盖板不换不行啦!那老的简直没法看了。

咱得快马加鞭地把它换了,给排水沟也穿上新衣服呀!拆除的时候注意安全哦,可别伤着自己。

清运也得妥妥当当的,这就跟整理房间一样重要呀!难道你们不想看到排水沟焕然一新的样子吗?6. 嘿嘿!排水沟盖板更换真不是小事哦!想想如果不换,那得有多少麻烦呀!脏水漫出来咋办呀!所以呀,拆除要干脆,清运要及时。

这就好像我们每天要洗脸刷牙一样,保持干净整洁呢!这样我们走在路上也安心呀,对不对?7. 哎呀!排水沟盖板更换拆除清运,这可是一连串的工作呀!每一步都很关键呢!就好比建房子,少了哪一块砖头都不行。

我们得把这个工作做好,让排水沟重新焕发活力呀!这是必须要做的呀,不能偷懒哦!结论:排水沟盖板的更换拆除清运是非常有必要的,关系着我们的生活环境和使用体验,大家要认真对待,好好完成每一个环节!。

排水沟盖板更换安全生产保障措施计划

排水沟盖板更换安全生产保障措施计划

排水沟盖板更换安全生产保障措施计划嘿,朋友们!今天咱们来唠唠排水沟盖板更换这事儿的安全保障,可别小瞧了这活儿,就像走钢丝一样,得处处小心。

首先呢,咱得把那些参与更换的小伙伴们武装起来。

安全帽得戴着,这安全帽就像是超级英雄的头盔,能抵御各种“暗器”。

要是不小心有个小石子啥的从上面掉下来,安全帽就像忠诚的卫士,把危险挡在脑袋外面,保你脑袋像在金钟罩里一样安全。

再说说这工作服,那必须得是紧身又耐磨的。

这就好比给工人们穿上了一层坚韧的“铠甲”,不管是被旁边的杂物刮到,还是不小心蹭到粗糙的地面,这工作服都能像盾牌一样,把伤害降到最低。

工具的管理也不能马虎。

那些工具啊,就像是一群调皮的小怪兽,要是放得乱七八糟,随时可能给你来个突然袭击。

所以呢,得专门给它们找个“小窝”,就像幼儿园里的小床一样,每个工具都有自己的位置。

这样既方便找,又不会让它们到处乱跑伤人。

在施工现场,设置一些警示标志那是必须的。

这些警示标志就像是严肃的交通警察,大声喊着:“嘿,这里危险,离远点!”不管是路过的行人还是其他工作人员,看到这些标志就像看到红灯一样,乖乖听话。

对于那些旧的排水沟盖板,可不能随随便便就扔。

它们就像退役的老兵,虽然不能再坚守岗位,但也得妥善安置。

要是乱放,那就像在战场上到处扔炸弹一样危险,指不定谁就会被绊倒。

还有啊,在抬起新的盖板的时候,大家要像配合默契的篮球队员一样。

一起喊着口号,同步用力,可不能有人像个调皮的小猴子,突然用力不均,那盖板就可能像失控的火箭一样乱窜,那可就糟了。

天气也是个小捣蛋鬼。

如果是大太阳天,就像在火海里干活,得给工人们准备好防晒措施,不然就像烤红薯一样,皮肤很快就会受不了。

要是下雨天呢,场地就像溜冰场,那防滑措施就得像防滑链一样紧紧跟上。

在工作过程中,还得有个小队长随时监督。

这个小队长就像一个超级管家,眼睛像探照灯一样扫视着整个施工现场,一旦发现有人违规操作,就像抓小老鼠一样把他揪出来,及时纠正。

排水沟盖板更换安全生产保障措施计划

排水沟盖板更换安全生产保障措施计划

排水沟盖板更换安全生产保障措施计划Replacing Drainage Trench Covers: Safety Measures and Implementation PlanIntroduction:The replacement of drainage trench covers is an integral part of ensuring safety in any industrial setting. The temporary removal of these covers during maintenance or repair poses a potential hazard to workers and pedestrians. Therefore, implementing effective safety measures is essential to minimize the risk of accidents and injuries. In this article, we will discuss the importance of safety precautions when replacing drainage trench covers and provide a comprehensive plan for their implementation.Importance of Safety Measures:Ensuring the safety of workers and the general public should always be the top priority when replacing drainage trench covers. By implementing proper safety measures, organizations can reduce the likelihood of accidents,injuries, or even fatalities. This not only protects human lives but also helps avoid costly legal consequences, reputation damage, and productivity loss caused byworkplace accidents.Implementation Plan:1. Communication and Awareness:Effective communication is crucial for promoting awareness about the importance of safety during drainage trench cover replacement. All employees involved in the project should receive clear instructions regarding safety protocols, including supervisors, contractors, and maintenance personnel. Regular training sessions can be conducted to educate everyone on safe practices.2. Personal Protective Equipment (PPE):Ensuring that all workers have access to appropriate Personal Protective Equipment (PPE) is imperative to guarantee their safety during trench cover replacement. PPE might include hard hats, reflective vests, steel-toed boots, gloves, protective eyewear, and hearing protection devices.3. Trench Preparation:Before initiating any work on the drainage trench covers, it is essential to conduct a thorough inspection toidentify potential hazards such as loose soil or debris. Any obstructions found should be cleared away before continuing with the replacement process.4. Temporary Barriers:Installing temporary barriers around open trenches not only alerts individuals about hazardous areas but also prevents accidental falls. Clearly visible signs indicating "Caution" or "Danger" must be displayed at all entrance points as a reminder to exercise caution when approaching the work area.5. Proper Equipment and Tools:Using appropriate equipment and tools is vital for both successful replacement and worker safety. This includes ensuring that equipment used to lift or remove trench covers is in good condition, with proper maintenance records in place. Workers should be trained in the safeoperation of any machinery involved.6. Work Scheduling:Scheduling trench cover replacement during periods of minimal activity can help reduce the risk of injury to workers and pedestrians. This may involve conducting work outside peak hours or coordinating alternative pathways for pedestrian traffic during construction.翻译:引言:排水沟盖板更换是确保工业环境安全的重要组成部分。

厂房内排水沟盖板更换技术方案

厂房内排水沟盖板更换技术方案

厂房内排水沟盖板更换技术方案为了确保厂房内排水沟的疏通和运行,及保证生产安全的顺利进行,在使用一定时限后,需要对排水沟盖板进行更换。

本文将从技术方案的编制、施工前的准备工作、更换过程、验收等方面,为大家详细介绍厂房内排水沟盖板更换技术方案。

一、技术方案编制1.项目背景该项目是为了保证厂房内排水沟的疏通和运行,及保证生产安全的顺利进行,更换已使用一定时限的排水沟盖板。

2.工程范围工程涉及排水沟盖板的更换,具体范围和数量如下:(1)更换排水沟盖板,共计50个。

(2)更换排水沟盖板的固定螺栓,共计500个。

3.施工单位施工单位应具有相应的水利工程施工资质,施工单位的选定应根据相关评审文件进行评审。

4.主要工艺流程(1)拆除旧排水沟盖板。

(2)清理排水沟的沉淀检查排水沟底部。

(3)检查排水沟的固定螺栓,更换损坏的螺栓。

(4)安装新的排水沟盖板。

5.施工安全本次工程施工是在现有的厂房内进行,存在一些施工安全风险。

因此施工单位必须引起足够的重视和注意,采取一切必要的施工安全措施,确保施工安全。

6.施工管理施工单位应拥有严格的质量管理和安全生产管理体系,并安排专门的管理人员,做好工程的质量、安全管理。

二、施工前的准备工作1.现场勘察施工前,必须进行现场勘察,了解现场实际情况。

对已使用的排水沟盖板进行检查,了解需要更换的数量和大小。

在保证施工安全的情况下,制定详细的施工方案。

2.施工图纸和预算的编制根据现场实际情况及需求,制定施工图纸和预算,明确施工范围和内容,确保施工的透明和准确。

3.施工材料的准备根据施工范围和内容,将需要的施工材料准备好,确保施工的顺利进行。

4.施工设备的备齐按照施工图纸和施工方案的要求,将需要的施工设备备齐,确保施工的进行。

5.现场安保措施的制定在施工前,必须做好现场安保措施的制定工作,确保施工安全。

6.通知相关部门将施工工作通知相关部门,确保其他工作的顺利进行。

三、排水沟盖板更换过程1.拆除旧排水沟盖板首先要断电断气,切断排水沟口附近的电路和通风管道,破坏旧盖板上的固定螺栓,拆卸旧盖板。

排水沟井盖铸铁井盖更换施工方案

排水沟井盖铸铁井盖更换施工方案

排水沟井盖更换施工方案编号:01排水沟井盖铸铁井盖更换施工方案编制人:审核人:批准人:广西联友建设工程有限公司2020年9月排水沟井盖更换施工方案目录一、编制依据及范围...................................................................................- 1 -二、工程概述...............................................................................................- 1 -三、主要技术指标.......................................................................................- 2 -四、施工现场情况:.................................................................................- 4 -五、材料、设备、人员准备.....................................................................- 4 -六、施工准备...............................................................................................- 6 -七、施工工艺和方法.................................................................................- 6 -八、质量检验标准................................................................................... - 11 -九、进度计划.......................................................................................... - 12 -十、安全保证措施.................................................................................. - 13 - 十一、附图.............................................................................................. - 15 -一、编制依据及范围1、施工现场情况2、排水沟渠流量及载物重量60T设计3、铸铁检查井盖CJ/T511-20174、按照要求尽量节约成本5、建设单位要求二、工程概述1、工程概况现场实际情况排水沟盖已经损坏,排水沟宽1.4m,长约200m。

排水沟井盖角钢混凝土盖板更换施工方案.docx

排水沟井盖角钢混凝土盖板更换施工方案.docx

排水沟井盖角钢混凝土盖板更换施工方案.docx范本1:【正文】一、工程概述根据实际需要,本次施工工作是为了更换排水沟井盖角钢混凝土盖板。

具体工程范围包括沟井区域的旧井盖拆除、新井盖安装、施工现场清理等。

二、工程目标本次施工的目标是确保排水沟井盖角钢混凝土盖板的更换工作顺利进行,保证施工质量和安全。

三、施工方案1. 准备工作(1)确定施工现场根据施工需要,选定沟井区域作为施工现场,并确保场地平整、无障碍物。

(2)调集施工人员与机械设备根据工程需要,安排施工人员及机械设备在合适的时间到达施工现场。

2. 拆除旧井盖(1)保护周边设施在拆除旧井盖之前,需进行周边设施的保护工作,如围栏设置、临时交通措施等。

(2)拆除旧井盖使用专业工具逐个拆除旧井盖,保证施工过程中不损坏井身及其他设施。

3. 安装新井盖(1)准备新井盖对于新井盖,需要提前准备好,并进行检验合格。

(2)安装新井盖使用合适的设备将新井盖安装到沟井中,确保井盖与井身之间密封良好。

4. 施工现场清理施工完毕后,及时清理工地,保证周边环境干净整洁。

【附件】1. 工程图纸2. 施工计划表3. 相关材料清单【法律名词及注释】1. 沟井:地下用于排水的设施,一般由混凝土或塑料构成。

2. 井盖:覆盖在沟井顶部,起到封闭和保护作用的构件。

【参考文献】(1)《排水沟井盖安装规范》(2)《建筑施工安全管理条例》示例产品合格证明【正文】一、工程概述本文档是排水沟井盖角钢混凝土盖板更换施工方案,在施工过程中需要参考相关的法律和规范。

为了确保工程质量,特此编写施工方案,对工程范围、目标、施工方案等进行详细说明。

二、工程目标本次施工的目标是完成排水沟井盖角钢混凝土盖板更换工作,保证施工质量和安全,并满足相关法律和规范的要求。

三、施工方案1. 准备工作(1)确定施工范围和现场根据实际情况,确定施工范围和施工现场,并在施工现场设置必要的安全警示标志和临时措施。

(2)人员和设备调配根据施工需要,合理调配施工人员和设备,并确保施工人员具备相关证书和资质。

更换排水渠盖板施工方案

更换排水渠盖板施工方案

更换排水渠盖板施工方案1. 引言排水渠盖板是城市排水系统的重要组成部分,负责保护排水渠道不被阻塞并确保人行道的平整。

然而,由于长时间的使用以及自然磨损,排水渠盖板可能会损坏或变形,需要进行更换。

本文档将提供一种更换排水渠盖板的施工方案,以确保施工过程安全高效。

2. 施工前准备在进行排水渠盖板更换施工之前,需要进行以下准备工作:•获取施工许可:在进行任何市区道路和人行道施工之前,应向相关政府部门申请并获得施工许可。

•检查现有排水渠盖板:对现有排水渠盖板进行检查,确定是否需要更换。

如果只是表面磨损,可以选择修复而不是更换。

•选择材料和规格:根据实际需求选择适当的材料和规格的排水渠盖板。

其中,材料可以选择钢铁、铸铁、塑料等,规格应与现有的排水渠盖板相匹配。

3. 施工步骤步骤一:设置施工场地标识•在施工现场周围设立警示标识,提醒行人和车辆注意施工。

•在路面标示出施工区域的边界,以确保安全施工。

步骤二:拆除旧排水渠盖板•使用专业工具,如扳手或锤子,将旧排水渠盖板从渠道中取出。

•在拆除时,要小心防止对旁边的管道或结构物造成损坏。

步骤三:清理和准备施工区域•清理渠道中的杂物和垃圾,确保施工区域干净。

•清理渠道壁面,以确保新排水渠盖板可以正确安装并固定。

步骤四:安装新排水渠盖板•在渠道底部涂抹一层防水胶水或胶封料,以增加排水渠盖板的密封性。

•将新排水渠盖板放置在渠道上,确保与周围地面平齐。

•使用胶合剂或螺栓将排水渠盖板固定在地面上,以确保稳固和安全。

步骤五:清理和测试•清理新排水渠盖板的表面,确保其完整无损。

•进行测试,检查排水渠盖板是否能够正常排水,并且没有异响或松动现象。

4. 施工安全注意事项施工过程中,需要注意以下安全事项:•确保施工人员戴上适当的安全帽、手套和工作服。

•安排人员进行交通指挥,确保施工现场的安全通行。

•使用合适的工具和设备,并确保其正常工作状态。

•提醒行人和车辆注意施工现场,避免事故发生。

排水沟井盖角钢混凝土盖板更换施工方案

排水沟井盖角钢混凝土盖板更换施工方案

排水沟井盖更换施工方案编号:02排水沟井盖更换施工方案(角钢混凝土盖板)编制人:审核人:批准人:2020年9月排水沟井盖更换施工方案目录一、编制依据及范围...................................................................................- 1 -二、工程概述...............................................................................................- 1 -三、主要技术指标.......................................................................................- 2 -四、施工现场情况:.................................................................................- 4 -五、材料、设备、人员准备.....................................................................- 4 -六、施工准备及投入主要管理人员...........................................................- 6 -七、施工工艺和方法.................................................................................- 7 -八、质量检验标准.................................................................................. - 17 -九、进度计划.......................................................................................... - 18 -十、安全保证措施.................................................................................. - 18 - 十一、附图.............................................................................................. - 20 -一、编制依据及范围1、施工现场情况2、排水沟渠流量及载物重量60T设计3、混凝土结构工程施工质量验收规范GB50204-20154、按照要求尽量节约成本5、混凝土结构施工图平面整体表示方法制图规则和构造详图16G101-1/2/36、钢筋焊接及验收规程JGJ18-20127、建筑工程施工质量验收统一标准GB50300-20138、钢筋混凝土用钢热轧带肋钢筋GB1499-20079、建设单位要求二、工程概述1、工程概况现场实际情况排水沟盖已经损坏,排水沟宽1.4m,长约200m。

山西省沟盖板更换施工方案

山西省沟盖板更换施工方案

山西省沟盖板更换施工方案一、工程概况与目标本工程旨在更换山西省境内部分老旧、损坏的沟盖板,以提升道路安全,保障交通顺畅,维护市容市貌。

工程将针对特定路段的沟盖板进行更换,具体路段将在施工前详细勘查并确定。

二、施工前期准备现场勘查:对目标路段进行详细勘查,了解沟盖板的现状、尺寸、材质等信息。

制定施工方案:根据勘查结果,制定详细的施工方案,明确施工步骤、所需材料、人员配置等。

人员培训:对施工人员进行安全操作、质量标准和施工流程的培训,确保施工质量。

材料采购:按照施工方案要求,提前采购所需沟盖板及其他辅助材料。

三、沟盖板选择与采购材料选择:选择符合国家标准、质量稳定、耐用的沟盖板材料。

采购渠道:选择有良好信誉的供应商,确保材料质量可靠。

样品检验:在材料进场前,对样品进行检验,确保符合设计要求。

四、施工流程与步骤清理现场:清理施工区域,确保无杂物、积水等。

拆除旧盖板:使用专业工具拆除旧盖板,注意避免损坏周边设施。

安装新盖板:按照设计要求,安装新沟盖板,确保平整、牢固。

调整与固定:对新安装的盖板进行调整,确保与周边环境协调,并固定牢固。

清理现场:施工结束后,清理现场,保持环境整洁。

五、质量标准与检验质量标准:沟盖板安装应符合相关国家标准和行业规范,确保平整、牢固、美观。

质量检验:施工过程中,进行定期的质量检查,确保施工质量符合要求。

施工结束后,进行总体验收,确保工程质量达标。

六、安全文明施工要求施工现场应设置明显的安全警示标志,确保过往行人和车辆的安全。

施工人员应佩戴安全防护用品,遵守安全操作规程,确保施工安全。

施工现场应保持整洁,避免扬尘、噪声等污染。

施工结束后,应及时清理现场,恢复道路通行。

七、环境保护与措施施工过程中,应采取有效措施减少扬尘、噪声等污染,保护周边环境。

废弃材料应妥善处理,不得随意丢弃,避免对环境造成污染。

施工过程中,应保护周边植被,避免破坏生态环境。

八、工程验收与交接施工完成后,应组织相关部门进行验收,确保工程质量符合要求。

更换补充侧沟盖板作业指导书

更换补充侧沟盖板作业指导书

更换补充侧沟盖板作业指导书
一、作业内容和适用范围
1.作业内容
更换、补充破损、裂纹严重的侧沟盖板。

2.适用范围
⑴本作业指导书适用于桥路维修作业。

⑵本作业指导书适用于天窗点内或天窗点外作业,行车限界以内作业时必须纳入天窗点内。

二、劳力组织
作业负责人不低于班长,除设驻站联络员和现场防护员外,作业人员2人及以上。

三、机具材料及安全备品
人力小车、河砂、水泥、手锤、撬棍、抹子、水桶、水平尺、钢卷尺、铁锹、灰盘、手套、口罩、护目镜等。

四、作业程序
1.准备作业
准备对应规格水沟盖板、沙子、水泥、水及作业工具。

2.作业过程
⑴拆除旧有的水沟盖板,对圬工的支承表面进行整平处理。

⑵清除侧沟内杂物,铺设新更换的水沟盖板。

⑶找平找齐新换的盖板,缝大者用砂浆进行填补。

3.作业结束
清点材料机具,回收旧料,清理场地,工完料净。

五、技术质量标准
1.缺少、损坏的水沟盖板全部更换,盖板铺设整齐、平稳,大缝隙用水泥砂浆堵塞抹平。

2.盖板正反面安放正确,与相邻盖板衔接处,平面相错不大于10mm,高差不大于2 mm,板缝不大于10mm,板下铺砂浆,装后无空响。

六、作业安全要求
1.必须按规定申请施工命令票。

2.必须按规定设驻站联络员和现场防护员。

3.倒运盖板时要戴好手套,轻拿轻放,小心挤手。

4.隧道内作业时要设好照明。

5.在隧道内放置盖板,不许侵入限界。

6.凿除混凝土时戴好劳保用品。

  1. 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
  2. 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
  3. 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。

斜沟煤矿选煤厂施工方案审批表
厂房内排水沟盖板更换




目录
一、施工组织机构 (4)
二、工程概况 (4)
三、质量、安全及工期目标 (4)
四、施工范围 (5)
五、施工准备 (5)
、技术准备 (5)
、材料及施工用具准备 (5)
、劳动力准备 (5)
六、施工方法 (7)
、排水沟盖板更换 (7)
、混凝土排水沟改造 (8)
七、安全质量保证措施 (8)
、质量保证措施 (10)
、临时用电的施工组组织设计及防触电措施 (10)
、防火及防毒、防雷、防爆措施 (11)
八、环境保护及文明施工措施 (11)
厂房内排水沟盖板更换施工方案一、施工组织机构
施工项目负责人:原杰
施工技术负责人:张国庆
施工安全负责人:秦元尧
现场施工负责人:冯建军
现场安全负责人:李本有
施工地点:选煤厂厂房内
二、工程概况
由于厂房内部分排水沟沟壁及沟盖板坏损,造成厂房内地面排水系统混乱,现按要求将各厂房内坏损的排水沟壁及沟盖板进行拆换、更换改造。

三、质量、安全及工期目标
质量目标:按照施工标准
安全目标:杜绝一切安全事故发生
工期目标:按甲方要求工期之内完工
四、施工范围
本工程更换的排水沟主要有主厂房,五号转载点、筛分楼、 703驱动站等厂房内。

五、施工准备
、技术准备
施工技术人员施工前应弄清弄懂施工图纸,明确施工技术难点,做到有得放矢,施工前对施工班组进行技术交底,编制专项施工组织设计文件,做好资料准备工作。

、材料及施工用具准备
所有进场材料需有产品合格证,质量检验证明书、出厂合格证等,材料员对进场材料按照验收规范逐一检查,对于资料不全或者材料不合格,坚决不予接受,进场的盖板应对其材质、规格、色泽等检验批目,进行严格检查,材料员邀请甲方代表共同进行检查。

施工机械及用具施工前应进行检查,具体材料用量见下表
、劳动力准备
因本工程全在车间厂房内部施工,施工人员应选择综合素质较高,遵守车间规章规定,有经验的施工队伍进场。


体施工人员安排见施工人员表。

施工材料及施工用具表
劳动力计划表
具体施工劳动力安排依据施工具体情况
六、主要工程施工方法
、排水沟盖板更换
、本工程施工位置主要分布在各生产厂房内,施工时采取分段施工,保证厂房内正常生产,每个施工段设置施工围栏,保持厂房内整洁有序。

施工前,各施工班组首先要现场查明盖板破损情况,确定施工范围,在拆换盖板时,使水沟内有毒害气体排放干净,将无损的沟槽及沟壁上杂物、淤泥清理干净,保证沟边线形顺适,且沟边内侧平滑、光亮后方可施工作业。

拆除下来的盖板,统一放置在堆置点集中外运。

每一施工段作业完成后拉线检查盖板平整度,并清扫作业现场。

、混凝土排水沟改造
、拆除混凝土排水沟:混凝土排水沟拆除采用人工破除,施工废料及混凝土块采用手推车统一运至厂房外,自卸车外运至排矸山。

、沟槽开挖及放样:人工开挖排水沟沟槽,分段放样,每25米一段放出水沟边桩及中桩,中桩桩顶标记开挖深度,现场洒白灰线控制沟槽开挖宽度与顺直度,
、混凝土浇筑:沟槽检验合格后,先用木桩每10米一处钉好模板位置,挂好横断面线及纵断面线,即可按线立模,砼底板及侧壁采用C30抗渗混凝土,首先浇混筑凝土地板,在浇筑侧壁,浇注时由一端平行向另一端推进摊铺,采用平板振动器及振捣棒振捣,人工收浆抹平,浇筑砼时,进行跟踪测量,严格控制高程,用平整尺检查,底板及侧壁采用人工洒水进行养护。

、预埋铁件:在沟盖板槽口处均设置50×50角钢焊Ф8@400锚筋,预埋在混凝土沟壁上口处,角铁刷防锈漆一遍,调和漆两遍。

、养护:每浇筑好一段,待混凝土初凝后,用塑料薄膜覆盖定时洒水养护,覆盖养户7~14d。

养护期间避免外力碰撞、振动或承重。

七、安全质量保证措施
1、安全措施
①、项目部建立施工安全领导小组,项目经理任组长,划分领导机构、明确个人职责,健全安全防护制度。

②、作业时,设专人统一指挥,相互配合,由现场调度员统一指挥,配合机械作业人员。

各种施工、操作人员须经安全培训,不得无证上岗,各种作业人员应配带相应的安全防护用具和劳保用品。

严禁操作人员违章作业,管理人员违章指挥。

③、各施工段要设置施工围栏,施工道口设置明显标语牌,并设专人看守,疏导交通。

④、各种机械要有专人负责维修、保养,并经常对机械的关键部位进行检查,预防机械故障及机械伤害的发生。

运输车辆服从指挥,信号要齐全,不得超速,过岔口、遇障碍物时减速鸣笛,制动器齐全,功能良好。

⑤、施工现场设置专职安全员,对施工人员经常进行安全教育,提高安全意识,实行班前会制度。

⑥、厂房内施工用电,应申请办理用电手续,经甲方领导确认后,未经甲方同意,不得私拉电源线。

⑦、施工现场用电,应设置各级分配电箱,不准总配电线接电源。

⑧、各级分配电箱应设置漏电保护器,并安排电工日常进行施工检修维护。

⑨、施工场区内用电,电源线应密闭无损,电源线应拉
2、质量保证措施
①实行工程质量责任到人,实行奖惩制度,确保工程质量。

②严格执行自检制度,检测人员及时对已完工作面进行检测,避免出现重复施工现象。

③施工完成并经自检合格后方可向甲方报检、交接。

3、临时用电的施工组组织设计及防触电措施
1、临时用电必须按JGJ46-2005《施工现场临时用电安全技术规范》的要求进行设置,并由专业电气技术人员编制临时用电施工组织设计。

2、现场临时用电必须实行“三相五线制“将保护零线与工作零线分离,所有用电设备必须实现三级配电二级保护。

3、现场临时用电的所有线路均要按《规范》要求敷设,统一采用橡胶绝缘电缆,所有线路不准绑在脚手架上和围挡上,不准随地乱拖、乱拉。

4、现场临时用电应设专人管理维护,非电气人员不得随便拆装用电设备和线路。

5、现场所用钢筋机械、搅拌机及其他机具设备必须配备末端开关箱加漏电保护装置,开关箱加漏电保护装置,开关
箱内严谨用同一个开关电器直接控制两台以上的设备(含插座)。

6、现场各种机械及电气设备等必须摆放平稳、牢固。

设备各部件灵敏、齐全、可靠,并做好接地保护。

4、防火及防毒、防雷、防爆措施
1、要从实际出发,贯彻预防为主、防消结合的消防工作方针,项目部成立防火领导小组,制定防火制度,本着“谁主管谁负责“的原则,坚持与安全检查同步检查防火工作。

2、成立义务消防队,每个班组要有一名义务消防员,负责班组施工防火,根据现场实际情况设立防火点。

3、对易燃易爆物品要存放在专用仓库内,尤其是装饰装修阶段施工,要有专人负责巡逻监护。

4、建筑物内动火要经项目部批准,并有专人检查余火,现场不留火种。

5、施工现场的易燃、易爆物,如油漆、氧气乙炔瓶、苯板、挤塑板要远离生活区,要设置专用库房,生活用液化气罐要单独设房间,不得放置在宿舍内。

6、氧气乙炔瓶要注意遮阳,气瓶和油料要远离火源,库房内应采用防爆电器照明。

7、施工现场禁止吸烟,现场要设有吸烟室。

8、施工现场应配备足够灭火器材。

八、环境保护及文明施工措施
1、严格执行选煤厂关于“文明施工”的有关规定。

2、建立健全文明施工组织及责任制,对施工的全过程、全方位实行项目经理负责制,管理人员责任制,强化文明施工管理。

3、施工作业人员须统一着装,并配带上岗证上岗,服从厂房内各项安全规定。

4、运输车辆须符合环保要求并与之签订协议。

5、进入厂区内现场放慢车速,防止扬尘。

6、施工作业人员厂房内不得吸烟、酗酒、随意触碰厂房内机械设备。

7、正确佩戴安全帽,不符合文明规定的处以罚款。

8、禁止车辆带泥上路。

9、施工在人流量车流量较大的地段,需设安全警示标志、隔离设施必须设置到位。

10、运输淤泥车辆停放要整齐合理,不影响其他车辆及行人。