主变冲击试验流程
英文:
The main transformer impulse test process begins with preparation, including ensuring that all relevant equipment is in good condition and safety measures are in place. The test team then conducts a pre-test inspection and sets up the testing equipment. During the test, the main transformer is subjected to a series of high-voltage impulses while being monitored closely for any abnormalities. The test continues until the specified number of impulses has been applied, typically five times. After each impulse, the team records the transformer's response and checks for any damage or changes in performance. Once the test is complete, the team analyzes the data collected and prepares a detailed report on the transformer's performance during the impulse test.
中文:
主变冲击试验流程首先开始于准备工作,包括确保所有相关设备处于良好状态并采取安全措施。
然后,测试团队进行预测试检查并设置测试设备。
在测试期间,主变压器将受到一系列高压冲击,同时密切监视任何异常情况。
测试将一直持续到施加规定数量的冲击,通常为五次。
每次冲击后,团队都会记录变压器的响应并检查是否有任何损坏或性能变化。
测试完成后,团队将分析收集的数据,并就冲击试验期间变压器的性能准备一份详细的报告。