1.0 Purpose
目的
This procedure covers the application of all concrete coating systems applied by CELEB.
本施工工艺规程规所有九州华清防腐混凝土涂装系统的施工。
2.0 Scope
围
This procedure will be followed in all applications.
本规程应贯彻于所有施工过程中。
3.0 Responsibilities
责任
3.1 The Project Manager
项目经理
- Operation and management of grinding and painting works. Plan
work schedules. Maintained strict conformance to clients
required specifications.
负责研磨和涂装作业的管理及运作工作。准备工作进度表。严格
遵照客户要求的涂装系统及规施工。
- Liaise with Engineers, Production, Q.C. Personnel and other contractors on work schedules, job performance and implementation on quality control requirements. Exercised quality
control surveillance on conformance to required specifications.
协调施工各方,确保按质量按进度施工作业,控制质量以符合业
主的涂装系统规。
3.2 The Supervisor
监理
- To ensure that all tests are undertaken and, in the case of witness tests the client representative is present.
保证执行各项检测工作,检测时应有客户代表在场。
3.3 The Forman -
领班
- To ensure that all work conforms to specifications and is done in a
workman like manner.
保证按标准施工,施工人员工作态度端正。
4.0 References
标准
Where referred to in this specification, the latest edition of the following specifications, standards and other documents apply.
本规程参照以下标准及规制定:
ASTM D4227-99 “Standard Practice for the Qualification of Coating
Applicators for Application of Coatings to Concrete
Surfaces”
ASTM D4258-83 “Standard Practice for Surface Cleaning Concrete for Coating”
ASTM D4259-88 “Standard Practice for Abrading Concrete”
ASTM D4261 “Standard Practice for Surface Cleaning Concrete Unit
Masonry for Coating”
5.0 Documentation
文件
Daily Work Report / 每日工作报告
Daily Q.C Report / 质量日报表
6.0 Procedure
规程
6.1Inspection of the Concrete Substrate
混凝土基层检测
It is to determine the concrete’s general condition, soundness, presence of
contaminants, presence of moisture vapor emissions and the best methods to
use in preparation of the surface to meet the requirements of the client or the
manufacturer’s recommendation.
对混凝土通过现场堪察及基层检测,掌握混凝土的总体情况、表面坚实
度、污染情况及潮气含量,从而决定表面处理最佳方式,以达到客户和
材料生产商的要求。
6.2 Pre-clean all surfaces by brooming and if necessary accomplished by scrubbing
with heavy duty cleaner / degreaser or low pressure water cleaning (less than
5,000 psi) or chemical washing to remove oils, grease, wax, fatty acids and
other contaminations.
先用扫帚清洁地表,必要时使用深度清洁剂去除地表污渍,或用低压水
冲洗(不超过5,000 psi),也可以使用化学溶液去除油污,油脂,表
腊,脂肪酸或其它污染。
6.3Removal of Surface Laitance and Creation of Surface Profile
去除水泥翻沫,提供粗糙度
Removal of surface laitance and /or curing compound and creation of surface
profile can be accomplished by a number of methods each utilizing a selection
of tools, equipment and materials to accomplish the intended purpose, (See
table below). Selection is dependent upon the type of surface to be prepared
and the type of system to be installed. In addition, floors, walls, ceilings,
trenches, tanks and sumps each have their own particular requirements. The
type and thickness of the selected coating system also plays an important role in
the selection process. Regardless of the method selected or tools employed, we
must provide a surface that will accept the application of polymer-based