英文缩写:

PS (Program start)

项目开始

PSC (Program strategy confirmation)

项目策略确定

PTCC (Program Target Compatibility Check point)

项目目标分解

PTC (Program Target Confirmation)

项目目标确定

PA (Program Approval) 项目批准

LR (Launch Readiness) 投产准备就绪

LS (Launch Sign Off) 投产签收

J1 (Job1) 量产

Use for tooling kick off. 用于开模

Purchasing Related Process/ 采购相关的流程

RFQ

Request for quotation which include Commercial document and ESOW. Commercial document tells the commercial items and ESOW tells the product information and requirements. 询价书包括了商务文件和产品工程规范和要求( ESOW)

ESOW

ESOW1 based on first version drawing for quotation

ESOW2 based on 2nd version drawings for nomination

ESOW3 based on 3rd version drawing for CPA

ES0W1基于第一版图纸,用于询价

ES0W2基于第二版图纸,用于确定供应商

ES0W3基于第三版图纸,用于签订CPA

CPA

CPA is a commercial contract between Volvo and suppliers for the commodities. It is for the commodities price.

CPA是沃尔沃和供应商之间的关于零件价格的合同。

Tooling order / 模具订单

Tooling order is an order to kick off suppliers with commercial

tooling

and engineering perspectives. 模具订单是沃尔沃从工程和商务两

方面来启动供应商的模具工作。

PPAP Refer to STA training later 参考后面STA的培训Purchasing

Drawing related Process/ 图纸相关流程

V0

1st released version drawing. ESOW1 use it. Design supplier need release V0 drawing to Volvo

第一版图纸用于ESOW1 。设计供应商需要发布V0 数据到Volvo 系统V1

2nd released version drawing. ESOW2 use it. Design supplier need release V1 drawing to Volvo

第二版图纸用于ESOW2 。设计供应商需要发布V0 数据到Volvo 系统V2

3rd released version drawing. ESOW3 use it. Can be used for tooling design. Design supplier need release V3 drawing to Volvo 第三版图纸用于ESOW3 和模具设计。设计供应商需要发布V2 数据到Volvo 系统

FDJ

Last released version drawing. Used for tooling kick off. Design supplier need release FDJ drawing to Volvo 最终版图纸用于开模。设计供应商需要发布V0 数据到Volvo 系统Builds / 装车活动:

M1 build

M1 build is to verify under body. So under body related parts are affected.

M1装车是为了验证下车的设计,所以只有下车体的零件影响到。

E3/E4 build / E3/E4 装车

E3/E4 build is to verify electrical parts ' function (no

dimension requirement). All body electrical parts are affected. Chassis and PT electrical parts are not affected.

E3/E4 装车是为了验证车身电子零件的性能(对几何尺寸没有要求) ,车身电子相关零件需要支持该装车。底盘和动力系统的电气相关的零件不需要支持。

MTO Build (Machi ne Try Out Build)

MTO build is to verify BIW (body in white) and body shop process. All stamp ing parts are affected. No any trim parts are n eeded. Build will only in body shop.

Parts must be from job1 tooli ng. This build is before VP