卧加技术协议复习过程

合集下载
  1. 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
  2. 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
  3. 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。

审核编号:ATTACHMENT FOR CONTRACT (TECHNICAL AGREEMENT) 合同附件(技术协议):

TECHNICAL AGREEMENT

技术协议

甲方(买方):江苏九龙汽车制造有限公司

The Buyer : Jiagsu Joylong Automobile Co., Ltd.

乙方(卖方):

The Seller :

丙方(制造商):

The Maker :

2014年3月12日

CONTENT

目录

Technical Agreement

技术协议书

Attachment 1: Supply scope sheet

附件一:供货范围

Attachment 2: Machine Specifications

附件二:机械参数

Attachment 3: NC Unit specification

附件三:数控参数

Attachment 4: Pre-acceptance Test Record of machine accuracy 附件四:机床预验收精度检验书

Attachment 5:Technical Proposal

附件五:技术方案

TECHNICAL AGREEMENT

技术协议

Jiagsu Joylong Automobile Co., Ltd. (The End User) will purchase 17sets Horizontal Machining Centers from, the machine is made by . After full discussion by three sides, we work out the technical agreement as follow:

江苏九龙汽车制造有限公司(需方)设计、制造的卧式加工中心17台,经友好协商就有关技术问题达成如下协议:

I. Buyer duty 买方负责:

a)After receive the foundation drawing, should finish the foundation in advance.

在收到平面基础图后,提前做好基础

b)is responsible for foundation checking and punching and buyer should help maker to installation and

commissioning.

负责地基的核实以及地基打孔工作同时买方应配合制造方进行机床的安装与调试。

should provide all necessary foundation components for the machine installation, such as

anchor plate leveling plate and chemical bolts

提供设备安装所需的所有地脚零件如地脚垫块,水平调整,化学螺栓等。

c)Buyer shall be responsible for machine installation and commission. The buyer will supply the lifting

equipment for machine

机床安装就位由买方负责并无偿提供起重设备。

II. Maker duty 制造商负责:

Provide 17sets Horizontal Machining Center, the type are NHP5500(2 sets)& HC505(15 sets).

提供卧式加工中心NHP5500(2台),HC505 (15台)。

a)Supply scope供货范围:

Refer to Attachment Supply scope sheet 请查阅供货范围附件。

b)Standard accessories 标准附件:

Refer to Attachment Machine & NC specification 查阅附件机械&NC参数。

c)Manual with machine(three sets, English and Chinese language and three sets electrical copy.):

maintenance manual, using manual, operation manual, parts and assembly simple drawing, circuit diagram, ladder diagram, NC instruction, operating manual.

随机说明书(3套,中、英文各3套,电子版3套):维修说明书、使用说明书、操作说明书、零件及装配示意图、电器图、梯形图、NC说明书、操作手册。

d) should provide the energy (power, compressed air) connection interface data to buyer for install inlet

and outlet pipes hang down ceiling

须提供设备(动力电,压缩空气)的详细接口信息,买方将负责至设备端的电缆和气管的安装。

III.Installation安装:

1.设备到场后由买方负责卸货及安装就位,卖方派人员进行现场支持。

2.设备基础采用二次灌浆,二次灌浆水泥由买方提供;卖方提供地脚螺栓,买方按要求准备安装所需的垫块。

IV.Acceptance验收:

1.Standard标准:

a) Machine standard机床标准:DIC’s & DIY`s machine tool accuracy testing form, KSB4404

出厂标准。

b) Machine accuracy is according to Attachment 4; 机床的精度符合附件4。

2. Pre-acceptance 预验收:

Including items内容包括:

a) Equipment and accessories inspection 设备配套情况;

b) Accuracy inspection各项精度检测;

c) CNC control system function数控系统各控制功能;

d) Provide the report of the pre-acceptance include the above items.提供包括以上各项检测收报告。

e) Buyer will send persons to for pre-acceptance and also accept the initial technical training. The

period is 5 working days. The charge will be borne by the buyer

买方派人员到工厂预验收及接受卖方的初次技术培训,为期5天。该费用由买方承担。

f) machine 50 pieces of workpiece which were provided by Buyer for testing to meet the requirement

during pre-acceptance

预验收期间买方提供50个工件给用于试加工和预验收以满足所提图纸要求。

g) Buyer should send * pieces of workpiece to factory within * days after singing the commercial

contract, the expenses shall be borne by the buyer.

买方需在4月20日提供设计样件1件,6月25日提供试切件10台,8月10日提供验收件40件至工厂,该费用由买方承担。

3. Final acceptance and Training 终验收及培训:

1) Final acceptance will be carried out at end-user’s factory. shall dispatch electrical and mechanical

engineers to the end-user’s factory to supervise the unpacking,installation, commissioning, the final acceptance till the hand over. The end-user should arrange concerning personnel to co-work with maker’s engineer.

终验收在最终用户工厂进行。应派机电专家到最终用户工厂指导进行开箱、安装、调试及终验收直至交付使用。最终用户应安排有关人员配合工作。

The final acceptance include 终验收包括:

a) Machine exterior inspection and accessory inspection 机床外观及配置检查。

b) Equipment installation设备安装调试:

c) Accuracy inspection according to Horizontal Machining center Test Record (Attachment 4) provided by

mamufacturer.

机床精度检验按照制造商精度检验书(附件4)验收。

d) Dry-run 8 hours to check machine performance 空运转8小时,检查机床性能。

e) Provide the report of the pre-acceptance include the above items.

提供包括以上各项检测报告。

f) Should machine 30 pieces of work-pieces per pallet continuously for detecting machine performance

during final acceptance period,machining process refer to attachment files.

终验收期间连续加工30件/每工作台工件用于机床性能检测已满足图纸要求,加工内容见附件。

g )When the machine is sent to buyer site, will be in charge for final acceptance. At the same time, must

train the buyer’s operators which is held in the buyer’s site, the maker is responsible for mechanical

相关文档
最新文档