道路工程施工概况英文
- 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
- 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
- 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。
Overview
Construction quality is crucial to the long-term pavement performance. Construction factors such as surface preparation, placement, joint construction and
compaction/consolidation have an overwhelming effect on pavement performance, which cannot be ignored or compensated for in mix or structural design.
Compaction
Compaction is the process by which the volume of air in an HMA mixture is reduced by using external forces to reorient the constituent aggregate particles into a more closely spaced arrangement. This reduction of air volume produces a corresponding increase in HMA density (Roberts et al., 1996[1]).
Figure 1: A Steel Wheel and a Pneumatic Tire Roller Working Side-by-Side.
Compaction is the greatest determining factor in dense graded pavement performance (Scherocman and Martenson, 1984[2]; Scherocman, 1984[3]; Geller, 1984[4]; Brown, 1984[5]; Bell et. al., 1984[6]; Hughes, 1984[7]; Hughes, 1989[8]). Inadequate compaction results in a pavement with decreased stiffness, reduced fatigue life, accelerated aging/decreased durability, rutting, raveling, and moisture susceptibility (Hughes, 1984[7]; Hughes, 1989[8]).
Compaction Measurement and Reporting
Compaction reduces the volume of air in HMA. Therefore, the characteristic of concern is the volume of air within the compacted pavement, which is typically quantified as a percentage of air voids in relat ion to total volume and expressed as “percent air voids”. Percent air voids is calculated by comparing a test specimen’s density with the density it would theoretically have if all the air voids were removed, known as “theoretical maximum density” (TMD) or “Rice density” after the test procedure inventor.
Although percent air voids is the HMA characteristic of interest, measurements are usually reported as a measured density in relation to a reference density. This is done by reporting density as:
•Percentage of TMD (or “percent Rice”). This expression of density is easy to convert to air voids because any volume that is not asphalt binder or aggregate is assumed to be air. For example, a density reported as 93 percent Rice means that there are 7 percent air voids (100% – 93% = 7%).
•Percentage of a laboratory-determined density. The laboratory density is usually a density obtained during mix design.
•Percentage of a control strip density. A control strip is a short pavement section that is compacted to the desired value under close scrutiny then used as the
compaction standard for a particular job.
Pavement air voids are measured in the field by one of two principal methods:
•Cores (Figures 2 and 3). A small pavement core is extracted from the compacted HMA and sent to a laboratory to determine its density. Usually, core density
results are available the next day at the earliest. This type of air voids testing is
generally considered the most accurate but is also the most time consuming and expensive.
•Nuclear gauges (Figures 4 and 5). A nuclear density gauge measures in-place HMA density using gamma radiation. Gauges usually contain a small gamma
source (about 10 mCi) such as Cesium-137 located in the tip of a small probe,
which is either placed on the surface of the pavement or inserted into the
pavement. Readings are obtained in about 2 – 3 minutes. Nuclear gauges require calibration to the specific mixture being tested. Usually nuclear gauges are
calibrated to core densities at the beginning of a project and at regular intervals
during the project to ensure accuracy.
Each contracting agency or owner usually specifies the compaction measurement methods and equipment to be used on contracts under their jurisdiction.