熔盐储罐焊接施工方案(修改)

熔盐储罐焊接施工方案(修改)
熔盐储罐焊接施工方案(修改)

目录

1.工程概况 (3)

1.Project Summary (3)

2 编制依据 (3)

2 Compilation Basis (3)

3 施工准备 (4)

3 Construction Preparation (4)

4 焊前准备 (7)

4 Weld Preparation (7)

5 施工工序 (10)

5 Construction process (10)

6 熔盐罐底板组对焊接 (11)

6 Assembly welding for tank bottom plate (11)

7 熔盐储罐壁板的焊接 (16)

7 Welding of tank shell (16)

8 拱顶的焊接 (19)

8 Welding of vault (19)

9焊缝的修补 (20)

9 Repair weld (20)

10焊接检验 (21)

10 Welding inspection (21)

11 质量保证措施 (24)

11Quality assurance measures (24)

12 HSE保证措施 (30)

12 HSE Assurance Measures (30)

13工机具及人力资源 (43)

13 Machines & Tools, and Human Resources (43)

1.工程概况

1.Project Summary

本工程为2台20000m3拱顶冷、热熔盐储罐新建工程,工程所在地位于青海省德令哈市西出口太阳能发电基地内,工程内容包括储罐罐主体制作、安装、防腐、及相关检测。

This work is for two sets of 20000m3vault hot melt salt storage tank new project, the project is located in solar energy base of west exit of Delingha City, Qinghai province, and the project contents include fabrication, installation, anti-corrosion, and relevant inspection of the main body of the storage tank.

储罐结构形式为拱顶固定顶,共由五带壁板组成,壁板材质为Sa-516 Gr.70 N,壁板厚度从下到上依次为42mm、34mm、25mm、16mm、10mm。

The storage tank structure is fixed arch roof which is constituted with five shell plates. The material of shell plate is Sa-516 Gr.70 N,the thickness of shell plate from up to down in sequence is 42mm, 34mm, 25mm, 16mm and 10mm respectively.

2 编制依据

2 Compilation Basis

2.1 中广核德令哈50MW光热项目热传储热系统施工图

2.1 Construction Plan of CGN-Delingha 50MW Solar Thermal Power Generation Project Heat Transmission and Heat Accumulation System

2.2 合同、招标文件;

2.2 Contract, bidding document;

2.3 Q/JH121.11.004-92《安全技术操作规程》

2.3 Q/JH121.11.004-92 Safety Technical Operation Process

2.4 GB50128-2014《立式圆筒形钢制焊接储罐施工及验收规范》

2.4 GB50128-2014 Vertical Cylindrical Steel Storage Tank Welding Construction and Acceptance Specification

2.5 SH/T3530-2011《石油化工立式圆筒形钢制储罐施工工艺标准》

2.5 SH/T3530-2011 Technical Standard for Construction Vertical Cylindrical Steel Storage Tanks for Petrochemical Industry

2.6 GB50341-2003《立式圆筒形钢制焊接油罐设计规范》

2.6 GB50341-2003 Code for Design of Vertical Cylindrical Welded Steel Oil Tanks

2.7 GB/T709-2006《热轧钢板和钢带的尺寸、外形、重量及其允许偏差》

2.7 GB/T709-2006 Dimension, Shape, Weight and Tolerances for Hot-rolled Steel Plates and Sheets

2.8 NB/T47014-2011《承压设备焊接工艺评定》

2.8 NB/T47014-2011 Welding procedure qualification for pressure equipment

2.9 NB/T47015-2011 《压力容器焊接规程》

2.9 NB/T47015-2011 Welding specification for Pressure Vessels

2.10 GB/T985-1998《气焊、手工电弧焊及气体保护焊焊缝坡口基本形式与尺寸》

2.10 GB/T985-1998 Basic forms and sizes of weld grooves for gas welding manual arc welding and gas-Shielded arc weldind

2.11 GB/T986-1998《埋弧焊焊缝坡口的基本形式与尺寸》

2.11 GB/T986-1998 Basic forms and sizes of weld grooves for submerged arc welding 2.12 JB/T4730-2005《承压设备无损检测》

2.12 JB/T4730-2005 Nondestructive Testing of Pressure Equipments

3 施工准备

3 Construction Preparation

3.1 焊工考试

3.1 Welder Examination

3.1.1 所有参加熔盐罐制作安装工程的焊工必须经过严格的审核和正规的岗前培训,持证上岗,对从事埋弧焊、气体保护焊和手工焊的焊工,应按GB50236-2011《现场设备、工艺管道焊接工程施工规范》焊工考核的有关规定进行考试。

3.1.1 All welders who will take participation in the manufacture and installation of the hot melting salt tank must receive strict reviewing and regulated pre-job training and obtain certificates before being appointed the post. The welders who take participation in the submerged welding, gas shielded welding and manual welding should take examination as per relevant regulations for assessment of welders in Field Equipment,

GB50236-2011 Process Pipeline Welding Construction Specification.

3.1.2 对于首次施焊SA-516 Gr.70 N钢板的焊工,必须考试合格,才允许进行相应的焊接工作。

3.1.2 The welder who first welds SA-516 Gr.70 N steel plate must take the examination and then be appointed to conduct the welding work after examination qualification.

3.1.3 根据现场情况,在正式开工前,完成焊工考试情况。按焊工实际焊接类型分别进行考试。考试合格后,方可进行焊接操作。

3.1.3 According to field situation, the welder examination should be completed before formal starting of the construction. The examination should be prepared in line with the actual welding type respectively which will be performed by the welder. The examination qualified welder will be awarded with welder qualification certificate and will be appointed the post in line with certificate. No welding job for welder who failed to be awarded with welder qualification certificate.

3.1.4 焊接工作进行前,焊接技术员要对所有焊工进行焊接技术交底,让焊工熟知焊接工艺方案,熟练掌握所焊部位的材质种类和所采用的工艺方法,如坡口形式、焊材选用、焊接电压电流调节、焊接速度控制等,让焊工了解焊接应力与焊接缺陷的危害与预防措施。

3.1.4 Before welding, the welding technician should deliver technical details disclosure to all welders to make each welder be familiar with the welding technology plan, to perfectly master the materials classification and applicable technology for the welding parts, such as groove shape, welding materials selection, regulation of welding voltage and current, and welding speed control, in order to make the welders understand the hazards and prevention measures of welding stress and welding defects.

3.2焊接设备

3.2 Welding device

直流电焊机、CO2气体保护焊焊机、埋弧自动平(角)焊机等。焊接设备的电流表、电压表、等仪表、仪器以及规范参数调节装置应定期进行检验。上述表、计装置失灵时,不得进行焊接。手工电弧焊、氩弧焊焊机必须集中放置在离焊接区较近的焊机棚内;自动焊根据现场需要进行放置,放置焊接设备的场地必须保持通风良好、干燥、维修方便。Welding equipment: DC welder, CO2gas shielded welding machine, automatic submerged arc flat fillet welder, etc. Ammeter, voltmeter, and other specification parameter adjusting devices shall be inspected periodically. When the aforesaid meter and metering device fail to function, welding shall not be performed. SMAW and GTAW welder must be collectively placed in the weld machine shed, near by the weld zone, the automatic weld machine to be placed according to the site needs. The weld machines shed must be kept well ventilated, dry and easy maintaining.

3.3焊接材料

Welding materials:

焊接材料应具有产品质量证明文件,符合现行国家标准的规定,且实物与证明书上的批号相符,外观检查时,焊条的药皮不得有受潮、脱落或明显的裂纹;焊丝在使用前应清除其表面的油污、锈蚀等;埋弧自动焊丝、焊剂必须放在干燥处妥善保管;低氢型焊材需按照批次、规格不同,分别取样送有资质试验室进行熔敷金属的扩散氢含量检测,

扩散氢含量以不超过4mg/100g为合格。

Welding materials shall have certificate of qualification and shall meet the stipulations of the current national standard, and lot number on the material package shall conform to the certificate; Electrode shall be free of moisture, falling or apparent crack during visual inspection; Welding wire shall be free of oil stain, rust stain and so on prior to usage; Submerged automatic arc welding wire and flux shall keep in a dry place properly;

焊接材料入库前检查其装箱单,出厂质量证明书等文件,检查焊材包装等情况及核对标识后方可入库。焊材入库后应根据焊材种类、型号、批号分类存放,存放焊材的库房应干燥、退风,库内温度应大于50℃,相对湿度不大于60%;焊材应放在焊材架上,离开地面和墙壁的距离不小于300mm,应安放湿度计并做好记录。

Before receiving welding materials, it is required to check its packing list, leave-factory quality certificate and other documents, welding material packages, and identifications. When the welding material is received, it shall be stored as per its category, type, and batch number respectively, and the welding material storage room shall be dry, ventilated, room temperature shall be larger than 50C, relative humidity shall not be larger than 60%; welding materials shall be put on the welding material support, its distance to the ground and wall shall not be less than 300mm, and humidity meter shall be installed and its reading shall be well recorded.

焊接材料设专人保管,掌握焊材库的温度、湿度状况及焊材库存量、出库量,并必须设去湿剂。

Welding materials shall be kept be designated person, temperature, humidity, inventory, distribution amount of the welding material storage room shall be mastered, and the de-wetting agent shall be used.

焊条和焊剂烘干设专职烘干员,并按厂家说明书要求进行烘烤,如无规定按下表要求烘烤。在使及过程中保持干燥,焊条烘干数量要有计划,根据工程的进展情况,适量的进行烘干。烘干时,要经常打开通风孔并打开风扇,驱除潮气,焊条、焊剂放进或取出时,干燥箱内温度不得低于200℃;烘干合格后的焊条放入恒温箱内。焊工取焊条时,必须携带焊条筒,随用随领。同一焊条筒内不准放入两种不同规格的焊条,以免用错。当湿度为80%-90%时,使用时间不超过2小时。湿度小于80%时,使用时间不超过4小时,超过这些时间,应按规定重新烘干,焊条再烘干的次数,一般不超过2次。烘干焊条要使用远红外线式焊条烘干箱和保温箱,箱内不得烘干除焊条、焊剂以外的物品,干湿温度计要定期校验。焊条烘干员应及时做好《焊条烘干记录》、《焊材发放记录》、《焊材库温湿度记录》,记录时写全焊材的使用部位、材料名称、牌号、批号等内容。对于回收的焊条,应分类存放,重新烘干,不得与未使用的焊条混放。

The designated person shall be arranged to ne responsible for drying electrode and flux, and it shall be dried as per the instruction of the manufacturer, if no stipulation is made, below table shall be followed. During usage process, it is required to keep dry, the electrode shall be dried as per the scheduled quantity, and drying operation shall be properly made as per the project progress. During drying process, vent shall be opened and fan shall be used frequently to remove moisture; when electrode and flux are used, temperature in the dryer shall not be less than 200℃; After it is dried thoroughly, the electrode shall be put into thermostat. When the welding operator takes out the electrode, quiver must be carried for placing the electrode. The same quiver shall not be placed with electrode of different specification so as to avoid misapplication. When the humidity is 80%-90%, usage time shall not be more than two hours. When the humidity is less than 80%, the usage time shall not be more than four hours, otherwise, it shall be dried again, but the drying times for the electrode shall not be more twice in general. It is required to use far-infrared electrode drying oven and incubator to dry the electrode,

beside electrode and welding flux, no other article is allowed to be dried in the oven, and dry and wet bulb thermometer shall be calibrated periodically. The electrode drying responsible person shall make Electrode Baking Record, Electrode Issue Record, and Temperature and Humidity Record of Welding Material Storage. Application position, vendor name, brand no., and furnace number of the welding material shall be recorded clearly. The recovered electrode shall be stored as per its classification and dried again, and it is forbidden to put it with the unused electrode together.

药皮受潮、脱落或有明显裂纹的焊条不得使用,焊丝在使用前应清除表面的油污、锈蚀等。

If the coating is moisture, dropped, or significant crack exists, the electrode is not allowed to use; prior to application of welding wire, grease, rust, and other defects shall be removed from its surface.

4 焊前准备

4 Weld Preparation

4.1 坡口形式

4.1 Groove Type

4.2熔盐罐各部位焊接方法

4.2Welding various parts of molten salt tanks

4.3焊接注意事项

4.3 Welding attenation

4.3.1设计图纸中除注明者外,其余角焊缝的焊脚高度均等于两相焊件中较薄件的厚度,且须为连续焊。

4.3.1Unless otherwise noted in the design drawing, other fillet weld's weld joint height shall be equal to the thinner part of the two welded parts, and continuous welding is

required.

4.3.2凡参加储罐焊接的电焊工必须经劳动部门的考试合格并有相应项目和位置焊工担任。

4.3.2Welders who engaged in the storage tank welding must pass the examination of the labor department, and the welding work shall be performed by the welder with corresponding project and position.

4.3.3定位焊应由合格焊工施焊,焊接工艺要求与正式焊接相同。引弧和熄弧不应在母材或完成的焊道上,正式焊接前应将定位焊缝两端修磨成缓坡,保证接头的质量,定位焊长度不小于50mm。

4.3.3Tack-welding shall be performed by the qualified welder, and the welding process requirements shall be identical to formal welding requirements. Run-on tab and run-off tab shall not be applied in parent material or the completed weld pass, prior to formal welding, it is required to trim and grind both ends of the tack weld into slow slope so as to ensure the joint quality, and the tack weld length shall not be less than 50mm.

4.3.4焊缝组装前应清除坡口表面及两侧各20mm范围内的泥沙、铁锈、水分和油污,并充分干燥,露出金属光泽。

4.3.4Prior to assembling weld, bevel surface and 20mm of both sides shall be free of sediment, rust, water, and grease, it shall be fully dried, and it is required to have the metallic luster.

4.3.5焊接中应保证焊道始端和终端质量,始端采用后退起弧法,终端应填满弧坑,多层焊的接头应错开。

4.3.5It is required to ensure starting and finishing end of each weld pass are qualified, the starting end adopts backward arc striking method, the finishing end shall have the crater filled fully, and joint of multilayer welding shall be staggered.

4.3.6双面焊的焊缝背面焊接前,当采用碳弧气刨清根时,应修整刨槽并磨除渗碳层。所有角接及T型接头焊缝,至少焊两遍完成,接头错开,圆滑过渡;板厚大于或等于6mm的搭接角焊缝,至少焊两遍。

4.3.6All corner joint and T joint welds shall be welded at least twice, joints shall be staggered and rounded off; if the plate thickness is larger than or equal to 6mm lapped fillet weld, it shall be welded twice at least.

4.3.7焊接环境出现下列情况之一时,必须采取有效防护措施,否则禁止施焊。

4.3.7If one of following welding condition occurs, effective preventive measures shall be taken, otherwise, it is forbidden to execute welding.

a.手工电弧焊时风速大于8m/s;

b.气体保护焊时风速大于2m/s;

c.大气相对湿度大于85%;

d.雨、雪、大雾环境。

a.When manual arc welding is performed, wind speed is larger than8m/s;

b.When gas shielded welding is made, wind speed is larger than2m/s;

c.Relative humidity of atmosphere is larger than85%;

d.Rain, snow, and fog occur.

4.3.8如出现上述现象时,应针对各条采取以下措施:搭设防风、防雨棚,对初始焊道100mm 内加热,保持焊道干燥;以上措施必须满足此条要求,否则不得施焊。 4.3.8If the above phenomena occur, following measures shall be taken correspondingly: set up wind proofing and rain proofing shed, heat the initial welding pass within 100mm, and keep the welding pass dry; the aforesaid measures must satisfy this requirement; otherwise, execution of welding is not allowed. 5 施工工序 5 Construction process

组装、焊接其余

6 熔盐罐底板组对焊接

6 Assembly welding for tank bottom plate

罐底由中幅板和边缘板组成,罐底板焊缝均采用对接焊。基础验收合格后,确定方位画出中心线,得出中点、画出垫板、边缘板安装位置线,其中边缘板安装铺设按设计直径和基础坡度长度外加收缩余量来确定半径。边缘板之间铺设间隙外侧为8-10mm,内侧为12-14mm。

Tank bottom is composed of center plate and edge plate, the tank bottom plates are all butt welded, before laying the bottom plates, its lower surface should be painted with anti-corrosion coatings, leaving 50mm range of the edge. After foundation inspection & acceptance, the position shall be determined to draw the center line, so as to find the midpoint, draw the mounting position lines of backing board and edge plate, wherein the radius of edge plate mounting and laying is determined as the design diameter and foundation slope length plus shrinkage allowance. The laying gap of edge plates is 6mm of outside and 8mm of inside.

6.1 罐底边缘板焊接

6.1 Weld tank bottom plate

6.1.1弧形边缘板的对接焊采用手工焊。先焊其外侧300mm焊缝,打底焊后进行渗透检查,以第二层开始每层错开50~70mm,焊接完成后上部磨平。为控制焊接引起的角变形,将坡口处用夹具向上提起6~8mm。

6.1.1Manual welding is applied for the butt welding of curved edge plates. First, the outside 300mm weld joint shall be carried out, with penetration inspection after backing welding. Starting from the second layer, each layer shall shift 50~70mm, after welding is completed, the upper part shall be grinded flat. To control the angular distortion caused by welding, the end bevel shall be lifted 6 ~ 8mm up with clamp.

6.1.2边缘板剩余对接焊缝的焊接,焊工应对称分布每隔600mm 隔缝跳焊600mm ,焊缝表面应光滑平整,焊接应加防变形板。

6.1.2For the welding of edge plates butt weld seam, the welder should do the skip sequence welding of 600mm in symmetrical distribution of 600mm.Weld surface should be smooth and anti-deformation plate should be added.

Anti-deformation plate

6.2中幅板焊接

6.2 Center plate welding

6.2.1 中幅板的焊接,采用CO2气体保护焊打底,埋弧自动焊盖面焊接成形。

6.2.1 The welding of center plate uses CO2 gas shielded welding for backing, with submerged automatic arc welding and cosmetic welding.

6.2.2底板中幅板按照先短后长的顺序进行焊接,初层焊道采用分段退焊法施焊。6.2.2 The plate in the bottom plate is welded according to the order of the initial length and the long post, and the primary bead is welded by subsection back welding method.

6.2.3中幅板铺设时,按照排版图从中心向四周铺设,边缘板依安装位置线铺设,垫板与相邻两块底板中的一块先点焊,底板与垫板应贴紧,其间隙不大于1mm。

6.2.3 When laying the center plates, it should be done according to the layout diagram from the center to the edges, with backing plate and one of two adjacent bottom plates spot welded first, the bottom plate and backing plate should be tightly against each other, with the gap not greater than 1mm.

6.2.4中幅板组对时,其间隙控制在6±1mm之间。底板与垫板之间的点焊应按焊接技术措施规定的次序严格执行。

6.2.4 When fitting up the center plates, the gap should be kept between 4-6mm. Spot-welding between the base plate and backing plate should be carried out according to the sequence provided in welding technical specifications strictly.

6.2.5 罐底板中幅板焊接时,按下图顺序进行:

按照上图所示焊接顺序和方向进行分段倒退跳焊,同一组内的焊缝同时焊接,分段长度要一致,焊接层数相同,焊接电流和焊接速度一致,层与层之间的焊接接头要错开,另外中幅板之间丁字口区域200mm预留不焊,待长、短缝自动焊完成后用手工焊接完成。

6.2.6 罐底板焊接时,须采取以下防变形措施:

6.2.6 When doing the tank bottom plate welding, the following anti-deformation measures should be taken:

6.2.6.1焊接短缝时,应在焊缝的两端离边缘150mm处打上背板(背板长度不小于600mm,宽度不小于150mm )。

6.2.6.1When carrying out short seam welding, back panel (with length not less than 600mm and width not less than 150mm) shall be set at 150mm from the edges at both ends of the weld seam.

6.2.6.2焊接长缝时,用龙门板将[20号槽钢固定于焊缝两侧,离焊缝200mm并卡紧。

6.2.6.2When carrying out long seam welding, batter board is used to fix the[22 channel on both sides of the weld, 200mm from the weld, and clamped firmly.

6.3 边缘板剩余对接缝的焊接

6.3 The welding of edge plate remaining butt seams

边缘板剩余的对接缝焊接应在大角焊缝焊接完毕后,收缩缝(中幅板与边缘板的搭接焊缝)焊接之前进行,采用手工电弧焊进行焊接。焊接时由多名焊工对称均匀分布,隔一条缝焊一条,焊接方向由外向内,初层焊可采用分段跳焊法。焊接前将垫板与2块边缘板进行点固,间隙小于1mm,未焊接的焊缝不得将2块边缘板都与底板点焊。焊接时应采用背杠与卡具进行加固。

The remaining butt seam welding of edge plate shall be carried out after the full fillet weld is completed, before the welding of contraction joints (the lap welds of center plates and edge plates), using manual arc welding. A number of welders shall be symmetrical evenly distributed, separated by a weld seam, with the welding direction from outside to inside, and the primary layer welding can adopt the method of segmented wandering sequence . Before welding, the backing plate and two edge plates shall be tack welded, with the gap less than 1mm, the two edge plates and bottom plate

of non-welded seam shall not be spot welded. Fixture and back panel should be used for reinforcement in welding.

6.4 收缩缝(龟甲缝)的焊接

6.4 Welding of contraction weld (tortoise-shell seam)

收缩缝为整个底板的最后一条焊缝,收缩缝的焊接采用埋弧自动焊机焊接,焊前应将边缘板与中幅板之间的卡具松开或磨开定位焊点,焊工应沿圆周均匀分布,分段跳焊Contraction joint is the last weld of the whole base plate. The welding of contraction joint uses automatic submerged fillet arc welding machine, the fixture or the tacked spot between edge plate and center plate shall be loosened or removed before welding and the welding operator shall be evenly distributed circumferentially to carry out segmented skip welding.

6.5 罐底板真空试漏

6.5 Tank bottom plate vacuum leakage test

罐底焊接完毕,检查凹凸度,凹凸变形的深度不应大于变形长度的2% ,且不应大于50mm ,并对所有焊缝进行真空试验。试漏时,先在焊缝表面涂肥皂水,用长方形真空箱压在焊缝上,真空箱底部四周用玻璃高密度海绵密封,用胶管与真空箱泵相通,通过真空箱上盖装有的密封有机玻璃观察箱内渗漏情况,当箱内真空度达到0.053MPa 时,若焊缝表面无气泡出现,证明焊缝无泄漏,即为合格,如发现气泡应立即作好标记,必须用砂轮将缺陷表面磨开,明确渗漏原因后方可修补,坚决不可在缺陷表面进行修补,修补后重新试漏。

After tank bottom welding is completed, check the degree of unevenness, uneven deformation depth should not exceed 2% of the length of the deformation, and not greater than 50mm, and vacuum test shall be carried out on all welds. When doing the leakage test, first apply soapy water on the weld surface, place a rectangular vacuum box on the seam, with the around of box bottom sealed with glass high-density foam, using a hose to connect with vacuum box pump, observe the leakage status inside the box through the sealed plexiglass in the tank top cover, when the inside vacuum reaches 0.053MPa, if no bubbles shown on the weld surface, it proves that without leakage, the weld is qualified, if bubbles are found, it should be immediately marked, using the wheel the open to grind the defected surface, the repair can only be carried out after the cause of leakage is cleared. It is strictly forbidden to carry out the repairing just on the defected surface, and leakage re-test shall be carried out after repairing.

空箱

空泵

注:压力表Pressure gauge 焊缝Weld 真空箱Vacuum tank 胶皮管Flexible hose 真空试验示意图Schematic diagram of vacuum test

7 熔盐储罐壁板的焊接

7 Welding of tank shell

熔盐储罐壁板安装采用倒装法进行,即先安装顶圈壁板及拱顶,然后壁板依次向下安装焊接,最后安装焊接底圈壁板及大脚焊缝。根据这种安装方法,壁板立缝、环缝采取先焊外侧,然后内侧搭设临时操作平台进行焊缝清根和焊接工作。立缝内外侧均采用气电立焊,环缝外侧采用自动焊,内侧手工电弧焊。

7.1 顶圈壁板的焊接

7.1 Welding of tank top shell

顶圈壁板组对完毕后先进行纵缝焊接,焊接方法采用气电立焊,先焊接大坡口,后焊小坡口,然后利用内侧操作平台对焊缝进行清根,清根可采用磨光机或碳弧气刨,但刨后应用角向磨光机将刨槽内的渗碳层和杂物打磨干净。(10mm和16mm壁板可一次焊接成型)为了便于环缝的装配,各条纵缝的上下端各留出150mm,暂不焊接,待环缝装配后再焊接。

After the top ring wallboard is assembled, vertical seam welding shall be performed first, with welding method of manual welding, if the direction of the bevel is at the outside of the wallboard, two backing welding outside the wallboard shall be carried out first (if inside, the welding sequence would be opposite), and then clear the weld root at the back, which can use grinder or carbon arc gouging, but after gouging, angle grinder shall be used to clean the carburized layer and debris. (The shell plate of 10mm and16mm can be welded at once time.)In order to facilitate the assembly of circular seam, 150mm shall be set at the upper and lower ends of each longitudinal seam, and welded after the circular seam assembly.

7.2 其余各层壁板的焊接

7.2 The welding the remaining wallboard of each layer

7.2.1其余各层壁板焊接先焊纵缝,再焊环缝。纵缝焊接前,先焊上定位龙门板,然后拆下纵缝组对卡具,16mm 及以上的壁板纵缝为x型坡口,其余v型坡口。焊接时,先焊外侧,然后内侧清根焊接。

7.2.1For the welding of remaining layers of wallboards, longitudinal seam shall be welded first, and then circular seam, before longitudinal seam welding, the positioning batter board shall be welded, and then the longitudinal seam assembly fixtures shall be removed. 16mm and above wallboard longitudinal seam is x-shape bevel and the rest is v-shape bevel. When welding, the outside shall be welded before inside.

7.2.2壁板环缝的焊接,采用埋弧自动焊和手工焊,焊接程序:先埋弧自动焊焊接外侧,多台埋弧焊机均布同时沿同一方向进行施焊。然后反面进行清根,清根方法同前。然后用手工焊焊接内侧焊缝

7.2.2Welding procedure: first the outside weld with the SAW, then clean the root at the back, with the same method stated above. Then weld inside with SMAW.

7.2.3罐壁板厚度自下而上分别为δ= 42 、34 、25 、16 、10mm共计5圈,采用电动葫芦提升倒装法组装。拆除组装用的工卡具时,不得损伤母材。如有损伤,应按标准进行修补。钢板表面的焊疤应打磨平整。

7.2.3The thickness of tank shell from the upper to the lower is δ= 42, 34, 25, 16 and 10mm with 5 circles in total, the tank shells are installed by means of electric hoist lifting upside-down method. The tooling and clamp shall be disassembled without wearing the base material. If there is any damage, it shall be repaired as per the standards. The crater of the steel plate surface shall be ground to a smooth, uniform finish.

7.2.4组对壁板时,间隙应符合焊接工艺要求。罐壁焊接应先焊纵缝,在上下纵缝全部焊接完后,再焊环缝。环缝焊接时,应采用数台焊机均布施焊。先焊接外侧焊缝,并用电弧气刨清根后,再用手工电弧焊进行内侧焊缝的焊接。

7.2.4When the shell is assembled, clearance shall conform to the welding process requirements. When the tank shell is welded, longitudinal seam shall be welded firstly, and circumferential seam shall be welded after the top and the bottom circumferential seams finish welding. When the circumferential seam is welded, several sets of welding machine shall be used to weld uniformly. The outer welding seams will be welded at first, the back chipping will be done by means of electric arc gouging and then the inner welding seams will be welded with SMAW.

7.2.5为防止焊缝角变形,除应严格执行焊接工艺外,尚应设置必要工装,做好防变形措施。

7.2.5To avoid the deformation of welding seam angle, the welding process should be performed strictly, necessary tooling should be set up and measures for anti-deformation should be taken as well.

7.3大角焊缝的焊接

7.3Welding of Bighorn weld

7.3.1底圈壁板和底板边缘板外缘300mm焊接完成后,进行大角焊缝的焊接。焊接采

用焊条电弧焊打底,埋弧自动焊盖面的方法。焊接坡口形状如下图所示:

7.3.1The bighorn weld should weld after the last shell plate and the 300mm outside of the annular plate finishing. The weld method is GMAW and SAW. The welding groove shape as follow:

7.3.2由于底圈壁板厚度与底板边缘板厚度相差较大,且坡口为全焊透,因此焊接过程中产生的角焊缝变形也比较明显,为了防止产生较大的焊接变形量,因此在焊接过程中需要采取相应措施。焊接工装如下图所示:

7.3.2Since the large thickness difference between the last shell plate and the annular plate, and the groove is full penetration, the welding deformation of the fillet is more obvious. In order to prevent the welding deformation of the fillet, so the welding process needs to take corresponding measures. Welding tooling as shown below:

a.壁板两侧与底板边缘板用角钢做斜撑,来防止底板边缘板翘起与起鼓。

https://www.360docs.net/doc/5314195182.html,e the angle iron to be bracing between the both sides of the shell plate and the annular plate to prevent the annular to tilt.

b.底板边缘板与垫板之间点焊,且点焊焊缝应尽可能长,来防止右侧底板边缘板翘起。

b.The annular plate and the backing plate should be spot welded to prevent the right side of the annular to tilt.

c.焊接顺序为先焊大坡口一侧,后焊小坡口。

c.Weld the side of the big groove first, and then the small groove.

d.焊接由多台埋弧焊机均布同时沿同一方向进行施焊。

d.Make numbers of submerged arc welding machine weld in the same direction at the same tim

e.

8 拱顶的焊接

8 Welding of vault

8.1拱顶的安装是在罐壁顶圈壁板已安装焊接的条件下进行的。顶圈壁板焊接完成后,进行坠板的焊接。

8.1 dome is installed in the tank wall under the top ring wall installed welding carried out. After the top ring wall welding is completed, perform fall plate welding.

8.2拱顶板与加强筋预制完成后,在预制场完成拱顶板与加强筋的焊接工作。然后在临时支撑安装完成后,将拱顶板与加强筋的预制件整体吊装在临时支撑上进行预制焊接。

8.2 dome plate and stiffener prefabricated, precast yard completion in the dome plate and stiffener welding work. After the temporary support then installation is complete, the dome plate and stiffener preforms integral lifting prefabricated welded on temporary support.

8.3已安装的拱顶的焊接程序为:先焊接扇形大板间的纵向焊缝,再焊接中心板与各

扇形大板内沿间的环缝,后焊接扇形大板外沿与罐壁环形角钢圈间的环缝。拱顶的焊接拟采用二氧化碳保护焊,纵向缝施焊时宜由多名焊工采用跳焊法对称同时焊接;外沿环缝施焊时宜由多名焊工均布,同时沿同一方向焊接。

8.3 Dome welding procedures installed as follows: first longitudinal seam welded large sector between the plates, center plate and then welded in each sector girth along the board between the outer edge of the board after the welding sector with the tank wall ring angle girth ring between. Dome welding intends to use carbon dioxide arc welding, longitudinal welding seam welder when advised by a number of symmetric skip welding Simultaneous welding; seam welding at the outer edge of the ring should be evenly distributed by a number of welders, welding simultaneously in the same direction.

8.4顶板在设置短桅杆部分预留出1000*1000mm的空间,待罐顶提升高度超过桅杆高度后补设安装完成

8.4A space of 1000x1000mm should be reserved at the short mast part of the top plate. The reserved space should not be installed until the hoisting height of tank top has exceeded the height of mast.

9焊缝的修补

9 Repair weld

9.1 深度超过0.5mm划伤、电弧擦伤、焊疤等有害缺陷,应打磨平滑。打磨后的钢板厚度不应小于钢板名义厚度扣除负偏差值;缺陷深度或打磨深度超过1mm时,应进行补焊,并打磨平滑;焊道内部的超标缺陷在焊接修补时,应探测缺陷的埋置深度,确定缺陷的清除面,修补长度不应小于50mm,高强钢钢板修补长度不应小于100mm;清除的深度不应大于板厚的2/3当采用碳弧气刨时,缺陷清除后应修磨刨槽,返修的焊缝按原规定的方法进行无损检测,并达到合格标准。

9.1The depth of scratch, scuffing by electric arch, welding scar, crater defect and other defects exceeding 0.5mm should be polished and smoothened. The thickness of polished steel plate should not be less than the nominal thickness where the negative deviation is taken off. When the defect depth or the polishing depth exceeds 1mm, the make-up welding should be conducted and polished. When the unacceptable defects inside the welding beams are repaired, the submerged depth of the defects should be detected to specify the defects on the removal face, and the repairing length shall not be less than 50mm, and the repairing length for high-strength steel plate shall not be less than 100mm. The removal depth is not allowed to exceed 2/3 height of the plate thickness. When the carbon arch gouging applied, the gouging slot should be trimmed after the defects are removed. The non-destructive testing should be carried on the weld to be repaired as per the specified methods, with the goal to meet the qualification standard.

9.2 焊接修补的应按照焊接工艺进行。

Weld repairing work shall be performed as per the welding procedure.

大型储罐施工方案

§1施工方案

§1.1 总体施工方案 1、液压提升倒装自动焊工艺 a、本工程二台20000m3浮顶罐采用液压提升倒装自动焊工艺进行施工,施工工艺流程图如 后图所示。 b、罐底板、罐壁板在本部生产基地进行深度工厂化预制,利用进口的龙门自动切割机,切割 下料和坡口加工一次成型。 c、油罐纵缝和环缝外口采用CO2气体保护自动焊,口采用CO2气体保护半自动焊;油 罐底板采用埋弧焊+碎丝焊。 2、液压提升倒装自动焊施工工艺流程图

§1.2 油罐预制方案 1、罐底预制 a、罐底预制主要是弓形边缘板和中幅板的切割。罐底中幅板、边缘板采用净料预制技术, 用龙门自动切割机切割钢板的直边和坡口,罐底边缘板弧线采用半自动火焰切割机切割。 b、罐底板预程序如下: c、底板预制前应绘制排板图,并应符合下列规定 ●罐底的排板直径,宜按设计直径放大0.1%-0.2%; ●边缘板沿罐底半径方向的最小尺寸,不得小于700mm; ●弓形边缘板的对接接头,宜采用不等间隙,外侧间隙宜为6-7mm;侧间隙宜为 8-12mm; ●中幅板的宽度不得小于1000mm,长度不得小于2000mm; ●底板任意相邻焊逢之间的距离不得小于200mm。 d、中幅板的尺寸允许偏差应符合下表的规定

2、壁板预制 a、壁板预制主要为板料检验、切割下料和滚圆三个过程,进行工厂化施工,壁板预制工艺 流程如下: b、壁板预制前,根据设计要求、施工规及钢板实际到货规格绘制排板图,报设计及监理单 位批准,并应符合下列要求: ●底圈壁板纵缝,宜向同一方向逐圈错开,其间距不得小于500mm; ●底圈壁板纵向焊缝与罐底边缘板的对接缝之间的间距不得小于200mm; ●罐壁开孔接管或开孔接管补强板外缘与罐壁纵向焊缝之间的距离,不得小于200 mm; 与环向焊缝之间的距离,不得小于100 mm; ●包边槽钢对接接头与罐板纵向焊缝之间的距离不得小于200mm; ●壁板宽度为1800mm,长度不得小于6000mm。 ●壁板尺寸的允许偏差应符合下表:

储罐焊接工艺方案

目录 一工程概况 二现场焊接执行标准、规范三坡口加工与接头形式 四一般要求 五焊接施工要点 六防变形措施 七质量检验 八无损探伤程序 九安全技术措施

一、工程概述 上海孚宝漕泾罐储罐区共计47台储罐,详见储罐安装工艺方案: 二、现场焊接执行标准、规范 1、API650标准 2、《立式圆桶形钢制焊接油罐施工及验收规范》GBJ128-90 三、坡口加工与接头形式 坡口加工与接头形式应符合施工图纸的要求,其中坡口、碳钢采用半自动氧烟切割机、不锈钢采用等离子切割机加工,加工后用角向磨光机打磨表面硬化层。碳钢用砂轮片不得与不锈钢混用。 四、一般要求: 1、焊工必须持有技术监督局颁发的焊工证(在有效期内),并通过孚宝现场检验考试,取得孚宝发放的合格证书。焊工施焊的相应位置应与此次考试合格证的合格项目相符。上岗必须佩戴专用标识,并在焊缝附近用记号笔标出焊工编号。 2、焊接设备完好,接线牢固。 3、严格遵守所给定的工艺参数施焊,不得改变和随意突破。 4、储罐主体主要使用三种焊材 碳钢Q235-A采用J422酸性焊条(不需烘烤) 不锈钢304、304L采用A002焊条 碳钢+不锈钢(Q235-A+304L)采用 焊条的烘烤、发放、回收由我公司负责。焊条烘烤温度150℃,烘烤时间1小时。各焊工班组应于前一天下班提出焊条用量,并负责

领出新焊条,放入焊条烘箱内,现场使用焊条(包括J422)必须采用保温筒携带,焊条放在保温筒最多6个小时。当天未用完的焊条应交回焊条库保管或复烘。 5、焊前应将坡口表面及其周边不小于20mm范围内的油、锈迹、漆、垢、水分、毛刺等清理干净,并检查确认其坡口角度、对口间隙、错边量等。 6、引弧、收弧均应在焊道上或用引弧板,禁止随意在母材上打火,试电流。 7、点固焊、工卡具焊接应采用与正式焊接相同的焊条和焊接工艺。工卡具及其他临时焊点拆除时,严禁用大锤强力打下,宜采用氧-乙炔焰切割或砂轮机打磨,避免损伤母材。 8、焊接环境出现下列任一情况时,无有效防护措施,禁止施焊: 风速大于8m/s; 相对湿度大于90%; 气温低于0℃; 雨、雪天气。 附:储罐WPS选用图(见图1) 储罐焊接用WPS

焊接施工方案

焊接作 业 制: 核: 定: 准: 施工单位:枣庄矿业集团元创机电工程公司

焊接施工方案 、焊接概况 1、本工程管道材料主要为碳素钢管。 2、焊接施工执行DL/T869-2004《火力发电厂焊接技术规程》。 二、焊工 1、担任锅炉受压元件焊接的焊工,须持有按《锅炉压力容器压力管道焊工考试与管理规 则》考试合格的合格证,持证焊工所承担的焊接项目必须与持证项目相符。 2、参加焊接的焊工应有较强的责任心,能认真执行国家的各项标准和规范,严格遵守工 艺纪律,按给定的焊接作业指导书或焊接工艺卡的要求施焊。 3、焊工应对所焊焊缝质量负责。当焊口组对不符合要求时,焊工有权拒绝焊接并及时向 焊接检查员报告。当出现重大质量问题时,报告有关人员,不得自行处理。 4、焊缝焊接完毕,应清理焊接飞溅,做好自检工作,并按规定打上焊工钢印,及时填写焊接记录,上报 焊接施工员。 三、焊接材料的管理 1、采用的焊接材料应符合设计文件规定。焊接材料及焊接用的各种气体必须有质量证明 书或合格证,并应符合国家有关标准的规定,本工程中使用的焊条应符合GB5117《碳钢 焊条》;焊丝应符合GB1300《焊接用钢丝》的要求。标准规定或对焊材质量有怀疑时,应进行抽查试验,待试验合格后方可使用。 2、施工现场专门设置焊材室, 并由专职人员负责焊材的管理、验收、烘干、贮存、发放、回收等工 作。焊材室须安装除湿设备,以防焊材受潮(温度宜在5O C以上,相对湿度应小于60%)。 3、焊条按规定的温度烘焙,烘焙时每只烘箱每次只能烘一种牌号的焊条。 4、本工程使用的焊条、焊丝应分类挂牌贮存,焊工应凭焊接施工员签发的领用卡领用焊 材,焊材室按领用卡发放焊材,防止错用焊条、焊丝。 5、焊工领出的焊条必须装入温度保持在100-150 O C的焊条保温筒内,随用随取。 6、焊条、焊丝按根领用,焊工应交回当日未焊完的焊材及焊丝头、焊条头,焊材室应认真做好发放、回收工作,为每个焊工建立台帐,并采取一定的措施以控制焊条头、焊丝头的回收率。 7、焊接用的氩气应符合GB4842《氩气》的规定,纯度应不低于99.96%,氧气纯度应不 低于98.5%,乙炔气纯度应符合GB6819《溶解乙炔》的规定。

机电安装冬季施工方案实用版

YF-ED-J4250 可按资料类型定义编号 机电安装冬季施工方案实 用版 In Order To Ensure The Effective And Safe Operation Of The Department Work Or Production, Relevant Personnel Shall Follow The Procedures In Handling Business Or Operating Equipment. (示范文稿) 二零XX年XX月XX日

机电安装冬季施工方案实用版 提示:该解决方案文档适合使用于从目的、要求、方式、方法、进度等都部署具体、周密,并有很强可操作性的计划,在进行中紧扣进度,实现最大程度完成与接近最初目标。下载后可以对文件进行定制修改,请根据实际需要调整使用。 工程概况 1.1 工程名称及相关单位 项目名称:XX润滑油XX项目 建设单位:XX(XX)润滑油有限公司 总承包单位:中国某设计工程有限公司 监理单位:XXX建工程监理有限责任公司 施工单位:中国化学工程第X建设有限公司 1.2 工程特点 根据《建筑工程冬期施工规程》JGJ104-2011规定:当室外日平均气温连续5天稳定低

于5℃便进入冬期施工,当室外日平均气温连续5天高于5℃,即解除冬施工。 本工程施工地区位于XX市南港工业园区,该地区冬季较长,多西北风,平均风速 3.12m/s。气温较低,降水也少;XX1月最冷,月平均温度-2℃。历史最低温度是-17.8℃。土壤最大冻结深600mm,最大积雪厚度200mm。根据XX的气象资料表明,XX市冬期施工的起止日期一般为11月15日至来年3月15日。 根据本工程进度分析,处于冬季施工的储罐制作与安装、钢结构、管道制作与安装等重点施工步骤的防风、防滑、防冻、防火的等问题较为突出。针对该地区季节特点,根据工程的进度、专业制定了以下冬季施工方案,以确保冬季施工质量及工期。

储罐焊接方案

储罐焊接方案 珠海恒基达鑫国际仓储有限公司 储罐焊接施工方案 编制:刘体义 审核:杨建满 批准:刘冰 中国化学工程第十一建设公司 2003年7月 审批表 建设单位审批意见: 签章: 年月日监理单位审批意见: 签章: 年月日 珠海恒基达鑫二期工程储罐焊接施工方案中国化学工程第十一建设公司 1 编制说明和依据 1.1 编制说明 3由我公司承建的珠海恒基达鑫二期工程罐制作安装工程共有5万米储罐2台,该罐为内浮顶型式,工作介质为成品油。 由于该储罐制安工作量大、施工工期短(约6个月),而储罐的焊接质量是内在质量的关键,也是影响整个工程的质量和进度的重点。为确保本工程储罐制安的焊接质量和进度,特编制本焊接方案。 本方案经审批通过后,即可用于指导本工程的焊接工作,其所述内容与其它文件不符时,一律以本方案为准,各有关人员要严格依照执行,以确保焊接质量和进度。

在工程实施过程中,将以焊接工艺卡的形式对本方案进行进一步细化,并向工人进行技术交底,用于具体地指导具体部位的焊接施工。 本方案在实施过程中若有不合适之处,也将以焊接工艺卡的形式对之进行修改、补充完善,并下发指导施工。 1.2 编制依据 1)工程施工合同 2)设计施工图纸 3)施工组织设计 4)《立式圆筒形钢制焊接油罐施工及验收规范》 GBJ128-90 5)《现场设备、工业管道焊接工程施工及验收规范》 GB50236-98 6)《钢制压力容器焊接工艺评定》 JB/T4708-2000 7)《钢制压力容器焊接规程》 JB/T4709-2000 8)《锅炉压力容器焊工考试规则》劳人锅[1988]1号 第1页共21页 珠海恒基达鑫二期工程储罐焊接施工方案中国化学工程第十一建设公司 9)《焊接材料质量管理规程》 JB/T3223-96 10)《炼油、化工施工安全规程》 SHJ505/HGJ233-87 11)评定合格的焊接工艺评定 2 工程概况 储罐名称:成品油储罐台数:2 储罐直径:50m 罐壁高度:23.5m 结构形式:内浮盘拱顶罐 罐体详细情况: 厚度板幅序号名称材质备注 mm mm 1 16MnR 34 1980 罐壁第1带板

钢筋焊接专项施工方案

观澜上域10#楼工程 钢筋机械连接和焊接施工方案 文件编号: 版本/修订状态: 受控状态: 分发号: 编制人: 审核人: 批准人: 巴中市华兴建筑有限公司 观澜上域10#楼工程 二0一五年一月

施工组织设计(方案)审批表 钢筋机械连接和焊接施工方案 编号: 序号:

1、工程概况 本工程钢筋的连接将有机械连接和焊接,机械连接主要是套筒连接;焊接包括电渣压力焊、闪光对焊、电弧焊。 (1)钢筋连接分为绑扎搭接、机械连接和焊接连接,后两种连接的类型及质量应符合《钢筋机械连接技术规范》(JGJ 107)及《钢筋焊接及验收规程》(JGJ 18)。 (2)当钢筋直径≥22mm时应采用不小于Ⅱ级机械连接,钢筋直径≥20mm时不允许采用闪光对焊和电弧搭结焊。 (3)穿层柱受力纵筋连接应采用Ⅰ级机械连接。 (4)框支梁的纵向钢筋连接:采用Ⅰ级机械连接。框架梁的钢筋连接:一级抗震等级采用Ⅰ级机械连接,二、三、四级可采用焊接或绑扎连接(d≤20mm时)。 (5)框支柱的纵向钢筋连接:采用Ⅰ级机械连接。框架柱纵向钢筋的连接:一、二级抗震等级和三级抗震等级的底层应采用Ⅰ级机械连接;三级抗震等级的其它部位和四级抗震等

级的受力钢筋可采用绑扎搭接或焊接接头(d<20mm时)。 (6)冷扎带肋钢筋的连接严禁采用焊接接头。 (7)“同一连接区段内纵向受拉钢筋绑扎搭接接头”要求、“同一连接区段内纵向受拉钢筋机械连接、焊接接头”要求,详见《11G101-1》。 (8)梁及柱纵向受力钢筋的搭接接头长度范围内应配置加密箍,构造详见《11G101-1》。 2、编制依据: 《建筑工程施工质量验收统一标准》(GB 50300—2001);《混凝土结构工程施工质量验收规范》(GB 50204—2002)(2011版); 《钢筋焊接验收规程》(JGJ18—2012) 《钢筋焊接接头试验方法》(JGJ27—2001) 《钢筋机械连接通用技术规程》(JGJ107—2010) 3、钢筋的机械连接 3.1、钢筋机械连接 (一)施工前准备工作验收 1.套筒:宜使用优质碳素结构钢或合金结构钢,应有供货单位出厂合格证、材质证明书、资料齐全方可使用。 2.主要机具:套丝机、管钳扳手、力矩板手等。 3.凡从事带肋钢筋螺纹连接工作的工人必须经过技术培训,持证上岗,班组成员相对固定。 4.作业场地应有安全防护措施,加强劳动保护,防止发生触电、机械损伤等事故。 (二)操作工艺

储罐等非标设备施工专题方案

工程 储罐非标设备制作安装专题方案 编制: 审核: 审批: 公司 年月

目录 1、编制说明 2、工程项目概况 3、工程项目管理目标和指标 4、项目主要管理人员与管理职责 5、项目执行标准 6、施工平面布置 7、工程项目施工部署 8、主要施工方案及技术措施 9、检验、测量的控制 10、施工平面布置图 11、施工进度计划

1、编制说明 编制说明: 本工程共有31台就地储罐,2台大型卧式储罐(反应槽),其他为小型非标设备(8台塔类设备另编写方案),依据设计要求,结合以往施工经验,编制切实可行的施工专题方案,确保本工段的施工顺利竣工。 编制依据: ⑴设计图纸。 ⑵GB50128-2005 《立式圆筒形钢制焊接储罐施工及验收规范》。 ⑶JB/T4735-1997《钢制焊接常压容器》 ⑶我公司近年来施工的同类工程施工经验及技术总结、工法。 ⑷我公司管理体系的标准 ⑸国家及行业现行环境、安全生产法律、法规。 工程工期:开工后2个月陆续交付安装管道。 2、工程项目质量、环境、职业安全健康目标 工程项目质量目标: 该工程质量目标为交验合格率100%,保证工程质量达到验评标准规定的合格等级。 工程项目环境管理目标、指标:

防污染、节能源。 工作生活污水达标排放; 固体废弃物实现分类管理、无害化; 杜绝油品、化学危险品泄露; 最大限度节约施工材料和水电能源; 对噪音源进行控制:噪音限制执行GB12523—90标准。工程项目职业安全健康管理目标: 重安全、保健康。 杜绝死亡事故和重伤事故,轻伤率不超过10‰; 杜绝火灾事故; 杜绝职业病发病。 3、该工段项目主要管理人员与管理职责 XXXX:安装工程负责人 XXXX:安装工艺技术员 4、项目执行标准 GB50128-2005《立式圆形钢制焊接油罐施工及验收规范》JB/T4735-1997《钢制焊接常压容器》 GB50205《钢结构工程施工质量及验收规范》

储罐施工方案A版

江苏德力化纤20万吨/年聚酯装置及配套工程储罐及料仓制安施工方案 目录 一、工程概况 (2) 二、编制依据 (2) 三、储罐施工工艺 (2) 四、施工准备 (3) 4.1、技术准备 (3) 4.2、场地准备 (3) 4.3、材料检验 (3) 4.4、基础复查 (4) 4.5、工机具材料准备 (4) 4.6、劳动力计划 (4) 五、储罐的制作 (4) 5.1、预制 (4) 5.2、组装工序 (8) 5.3、表面处理 (17) 5.4、焊缝检验和罐体试验 (17) 六、提升方案 (18) 6.1、施工方法 (18) 6.2、桅杆的选择 (19) 6.3、桅杆工作 (20) 七、焊接工艺及主要焊接顺序 (21) 7.1、焊接材料 (21) 7.2、焊接工艺 (21) 7.3、焊接顺序 (23) 7.4、焊缝质量检查 (25) 八、劳动力计划 (25) 8.1、持证上岗。 (25) 8.2、劳动力计划一览表 (25) 九、安全措施 (26) 十、工机具及材料计划 (27) 10.1、工机具计划一览表 (27) 10.2、材料计划一览表 (28)

一、工程概况 本工程为江苏德力化纤2台5000米3乙二醇罐制安工程,单台重量约为150t, 2台150米3的SEG和DEG罐,单台重约为6.5t,材质为不锈钢.预定2010年4月15日开工,2010年6月30日制作安装完成。 二、编制依据 1、GB50128-2005《立式圆筒形钢制焊接油罐施工及验收规范》 2、JB4730-94《压力容器无损检测》 3、GB50341-2003《立式圆筒形钢制焊接储罐设计规范》; 4、SH3406-92《石油化工立式圆筒形钢制焊接储罐设计规范》; 5、JB/T4730-2005《承压设备无损检测》; 6、SH3514-2001《石油化工设备安装工程质量检验评定标准》 7、 SH3505-1999《石油化工施工安全技术规程》 8、JB/T4709-2000《钢制压力容器焊接规程》 9、GB50236-98《现场设备工业管道焊接工程施工及验收规范》 10、设计图纸 三、储罐施工工艺 本工程储罐壁板和顶板采用倒装法施工,汽车吊车、叉车辅助壁板围板、底板和顶板铺设,利用罐内周边等分均匀设置16根提升桅杆,用手拉葫芦提升。胀圈与胀圈之间连接采用焊接固定,每条接头处加三块加强块,防止接头开裂或变形,桅杆沿圈周边等分均匀布置,每条桅杆底圈同底板焊接固定,作八字形加强撑,底板中心处立中心桅杆一条,桅杆顶部焊连接盘,每一根

储罐施工方案(安装)

目录 1.编制说明 1 2.工程概况 1 3.编制依据 2 4.施工方法 2 5.焊接工艺及主要焊接顺序15 6.质量保证措施21 7.资源配置计划23 8.质量保证措施23 9.HSE施工管理计划26

1、编制说明 1.1 为了保证产品罐区及中间罐区17台储罐的施工质量,满足设计和生产对工艺的要求,特编制本方案。 1.2本方案经监理审查通过后,即可用于指导储罐的安装工艺作业,其所规定的内容与其它方案不符时,一律以本方案为准。各有关人员要严格依照执行,加强工艺纪律,以确保储罐的质量和进度。 1.3质量目标计划:单位工程检验合格率100%;分部、分项工程交验合格率90%;设备封闭合格率100%;零质量事故。 2、工程概况 2.1本工程为多伦世腾15万吨/年煤制烯烃副产品芳构项目,储罐制作安装工程包括50m3罐4台、100m3罐2台、200m3罐2台、300m3罐1台、330m3罐1台、500m3罐1台、1000m3罐3台以及2000m3罐3台,其中15台罐结构为固定顶圆筒形立式储罐(内设浮盘),2台罐结构为固定顶圆筒形立式储罐(未设浮盘)。罐体安装采用倒装法,焊接采用手工电弧焊。 设备实物量清单 序号设备位 号 设备名称 规格型号 mm 材质重量Kg 单位数量 1 TK-1352A /B 苯产品检验 罐 DN3800X5400 Q245R 9114 台 2 2 TK-1304 抽余油储罐DN3800X5400 Q235B 8638 台 1 3 TK-1101 甲醇储罐DN3800X5400 Q235B8682 台 1 4 TK-1353A /B 甲苯产品检 验罐 DN5200X5250Q235B11513 台 2 5 TK-1351混合芳烃缓 冲罐 DN5500X1026 Q235B16743 台 1 6 TK-1302新鲜溶剂罐DN5500X1026 Q235B16659 台 1 7 V-1807混合芳烃储 罐 DN7750X7130Q235B18004 台 1 8 TK-1303湿溶剂罐DN6600X1065 Q235B24438 台 1

焊接施工方案

电焊施工技术措施 一、工程概况 二、施工准备 1、材料:根据图纸要求,梁焊接采用J506焊条,柱墙焊接采用HJ431焊剂,使用的焊剂、电焊条、必须有出厂合格证书,施焊前应经过烘焙。严禁使用药皮脱落,焊芯生锈的焊条。 2、焊工在施焊前应检查焊工合格证,应证明焊工所能承接的焊接工作。 3、现场供电应符合焊接用电要求。 4、风力超过4级时,要采取挡风措施。 三、电弧焊施工工艺要求 (一)、操作工艺 1、焊接前进行焊接工艺试验合格后再施焊。搭接焊时,钢筋要预弯,按单面搭接10d+2㎝长度做弯曲以保证两钢筋的轴线在一直线上。 2、将欲焊接的钢筋调直拼拢靠紧后,缝面平直向上。搭接焊采用两点定位焊固定。 3、焊接速度:要求等速焊接,保证焊缝厚度、宽度均匀一致。 4、起焊:在焊缝起焊点前方15—20mm处的焊道内引燃电弧,将电弧拉长4—5mm,对母材进行预热后带回起焊点,开始向前施焊。 5、收弧:每条焊缝到末尾应将弧坑填满后,往焊接方向的反方向带弧,使弧坑甩在焊道里边,以防弧坑咬肉。 6、然后分层施焊,每遍焊接厚度不能过大,且应待冷却后敲去药皮再焊第二遍、三遍,直至符合要求为止。 7、经焊工自检确无问题后方可转移地点继续。 (二)、质量要求: 1、焊缝长度必须达到要求,作料时做成10d+20mm。 2、焊接时电流不可过大,防止烧伤咬肉。 3、焊肉饱满,焊接高度h≥0.3d并不小于4㎜,焊缝宽高b≥0.7d并不小于10㎜。 4、无夹渣,砂眼、孔洞等缺陷。 5、粗钢筋必须分层施焊,且底层药皮应敲干净后方可焊上面的第一层焊缝应有足够的熔深,主焊缝与定位焊缝特别是在定位焊缝的始端与终端,应熔合良好。

储罐焊接冬季施工方案(DOC)

神木首端场站储浆罐制作安装工程 冬季施工方案 编制: 审核: 批准: doc1

神木首端场站项目经理部2014年10月12日 doc2

目录 储浆罐安装工程冬季施工方案 (1) 1、适用范围 (1) 2、编制依据 (1) 《现场设备、工业管道焊接工程施工及验收规范》GB 50236-2011 (1) 3、工程概述 (1) 4、当地气候条件 (2) 5.5技术准备 (3) 5.6生产准备 (3) 5.7资源准备 (3) 5.8人员培训教育准备 (4) 6.储浆罐制安冬季施工技术要求及措施(针对防风保温棚外施工项目) (4) 7、施工临时用电管理 (5)

8、施工机具、设备 (6) 9、车辆管理 (7) 10、HSE管理要求及措施 (8) 10.1高空作业 (8) 10.2吊装作业 (9) 10.3施工用电 (10)

储浆罐安装工程冬季施工方案 1、适用范围 本方案适用于神渭管道输煤项目神木首端场站储浆罐制安工程冬季施工。 2、编制依据 《现场设备、工业管道焊接工程施工及验收规范》GB 50236-2011 《立式圆筒形焊接油罐施工及验收规范》GB50128-2005 《建筑冬期施工规程》JGJ104-2011 3、工程概述 陕西省神木至渭南输煤管线始于神木县红柳林煤矿,截止于渭南市蒲城县。我单位主要承担神木首端场站储浆罐安装工程,其中主要工程量有4台储浆罐(单台容积5700m3),以及其顶端附属机电设备、钢结构,及照明、避雷及接地。 陕北地区冬季来临相对较早,持续时间较长,在气温低于0℃、室外日平均气温连续5天稳定低于5℃时,即正式进入冬季施工。本工程所处地区环境相当恶劣(最低气温能达到-25℃,最高风速10m/S),储罐制安工程关键工作内容为焊接,而焊接质量受环境影响较大。为保证冬季焊接质量,并根据本工程施工的具体情况,特制定相应冬季施工措施,从而保证工程实体质量。

储罐焊接方案

吉林众鑫化工集团有限公司12万吨/年生物法环氧乙烷装置和动力厂及配套公用工程 乙醇储罐焊接施工方案 1、编制说明 1.1 为了保证储罐焊接工程质量,满足设计和生产对工艺的要求,特编制本方案。 1.2 本方案作为施焊过程中必须遵守的焊接技术文件和合格焊接工艺评定一起作为编制焊接工艺卡的依据。 1.3本方案经监理审查通过后,即可用于指导储罐制作的焊接工作,其所规定的内容与其它方案不符时,一律以本方案为准。各有关人员要严格依照执行,加强工艺纪律,以确保储罐焊接质量和进度。 1.3在储罐安装焊接过程中,将以焊接工艺卡的形式对本方案进行进一步细化,并下发作业班组进行技术交底,用于具体地指导具体部位的焊接施工。 1.4本方案在实施过程中若有设计修改或不合适之处,也将以焊接工艺卡的形式对之进行修改,补充完善,并下发指导施焊。 2、工程概况 2.1本工程为吉林众鑫化工集团有限公司12万吨/年生物法环氧乙烷装置和动力厂及配套公用工程项目。制作安装乙醇储罐2台,外形尺寸为φ21000×18375*14/6,重量为139.47吨、材质为Q245R/Q235B。 2.2设计参数一览表

材质:Q245R/Q235B 3、编制依据 3.1. 设计院设计蓝图。 3.2 相关规范 《立式圆筒形钢制焊接油罐设计规范》GB50341-2003 《立式圆筒形钢制焊接储罐施工及验收规范》GB50128-2005 《压力容器焊接规程》JB/T47019-2011 《承压设备无损检测》JB/T4730-2005 《焊接工艺评定规程》 DL/T 868-2004 3.3企业工艺标准的名称及编号: 《施工技术方案管理规定》 Q/JH223.22101.02-2013 《施工技术通用管理标准》 Q/JH222·21100.01-2013 《施工质量通用管理标准》 Q/JH223·21500.01-2013 《质量、环境、职业安全健康综合管理手册》 Q/JH223·20001.2007 《安全生产责任管理规定》 Q/JH223·21801.01 4、施工方法 4.1施工顺序

焊接施工方案81447

目录 11 概述2 2锅炉的主要工作参数为2 3编制依据2 3.6电力建设施工及验收技术规范(火力发电厂焊接篇)DL/T869-2004。 (2) 4焊接主要施工机具2 3.3主要消耗材料使用计划 (3) 5主要管理人员配置和劳动力计划4 6主要施工方案和重大技术措施4 6.1焊接措施 (4) 7施工质量管理9 7.2焊接材料管理员 (9) 8焊接质量标准和质量目标9 9安全文明和环境施工管理10 10危险源辨识《附表》11

1 1 概述 本工程为沧州中铁装备制造材料有限公司煤气发电锅炉安装工程,锅炉为2台额定蒸发量为85t/h自然循环煤气锅炉。锅炉采用唐山信德锅炉集团有限公司XD—85/5.29-Q 型次高温次高压、单锅筒横置式,自然循环,π型布置、全悬吊结构锅炉。 2锅炉的主要工作参数为 锅炉额定蒸发量:85t/h 给水温度:150℃ 额定蒸汽压力:5.29Mpa 额定蒸气温度:4850C 排烟温度:1350C 运转层标高:7000mm 锅筒中心标高:25000mm 水压试验压力:7.23 Mpa 2.1焊接工程量简介: 锅炉钢结构焊接、本体受热面管道及连通管焊接、给水系统管道焊接,主蒸汽管道焊接等。 3编制依据 3.1沧州中铁装备制造材料有限公司煤气发电工程《施工组织总设计》。 3.2唐山信德锅炉厂提供的图纸及资料。 3.3《火力发电工程施工组织设计导册》。 3.4《电力建设安全工作规程》。 3.5现有的焊接施工所需图纸、计划及方案。 3.6电力建设施工及验收技术规范(火力发电厂焊接篇)DL/T869-2004。 3.9《火电施工质量检验及评定标准》(焊接篇)1996年版。 3.10《蒸汽锅炉安全技术监察规程》。 4焊接主要施工机具 4.1焊接主要施工机具一览表 4.2工程主要工器具表

储罐焊接施工方案

储罐焊接施工方案 1.0 工程概况..................... .. (2) 1.1 工程简介 (2) 1.2 储罐金属材质、厚度一览表 (2) 2.0 编制依据..................... .. (5) 3.0 储罐焊接方案.................... .. (6) 3.1 焊接方法 (6) 3.2 焊工资格管理 (6) 3.3 焊接工艺评定 (6) 3.4 焊材及管理 (7) 3.5 焊接的基本要求 (7) 3.5 储罐主体焊接方法 (7) 3.6 焊缝无损检测要求 (11) 3.7 焊缝返工管理 (12) 3.8 焊接质量保证措施 (13) 4.0 施工安全措施.................... .. (16) 5.0 人员计划..................... .. (18)

6.0 施工机具计划.................... .. (18) 1.0 工程概况 1.1 工程简介 罐区储罐安装工程包括MTBE 及苯类罐组、裂解燃料油罐组、乙二醇罐组3 个罐组,其中MTBE 及苯类罐组包括2 台1500m 3裂解轻燃料油储罐、2 台2000m 3C9 储罐、2 台2000m 3MTBE储罐、2台2000m 3二甲苯储罐、2台2000m 3甲苯储罐、3台3000 m3苯储罐共计13台储罐。裂解燃料油罐组包括2台1500m 3裂解燃料油储罐;乙二醇罐组包括2台8000m 3乙二醇储罐、2台1100m 3二乙二醇储罐、1台110m3三乙二醇储罐、1台110m3多乙二醇储罐。 裂解轻燃料油、C9、MTBE、二甲苯、甲苯、苯储罐为内浮顶碳钢罐,其中苯储罐带加热盘管。裂解燃料油储罐为带加热盘管的固定拱顶碳钢罐。乙二醇、二乙二醇为固定拱顶碳钢罐(内喷铝),三乙二醇底板边缘板及第一、二、三、四圈壁板为低合金钢,中幅板及其余壁板为碳钢的固定拱顶罐(内喷铝),多乙二醇储罐为固定拱顶不锈钢罐,带加热盘管。 1.2 储罐金属材质、厚度一览表 储罐金属材质、厚度见下表所示:

非标设备组对焊接施工方案

聚氯乙烯联合一体化项目 非标设备组对焊接施工方案 编制: 审核: 批准: 目录 一.工程概况.......................................... 错误!未指定书签。 二.施工依据.......................................... 错误!未指定书签。 三.焊接工艺评定...................................... 错误!未指定书签。 四.焊工资格管理...................................... 错误!未指定书签。 五.焊接方法及焊接材料 ................................ 错误!未指定书签。 六.焊接材料的管理.................................... 错误!未指定书签。 七.组对定位.......................................... 错误!未指定书签。 八.焊接施焊要求...................................... 错误!未指定书签。 焊接结束或中断时,收弧要慢,弧坑要填满,这样能防止火口裂纹。 . 错误!未指定书签。 16.罐底的焊接:.......................................... 错误!未指定书签。 a.中幅板的焊接,需先焊短焊道,后焊长焊道。初层焊道应采用分段退焊或跳焊法;错误!未指定书签。 b.边缘板的焊接,需首先施焊靠外缘300mm的部位。在罐底与罐壁连接的角焊接接头焊完后,且在边缘板与

储罐安装工程冬季施工组织设计

新体系冷轧作业部酸再生储存罐设备制作工程储罐安装工程冬季施工案 编制: 审核: 批准: 工业安装工程股份有限公司

2014年11月28日

目录 1、适用围 2、编制依据 3、工程概述 4、当地气候条件 5、冬季施工准备工作 6、冬季施工措施 7、HSE措施

1、适用围 本案适用于包钢新体系冷轧作业部酸再生储存罐设备制作安装工程冬季施工。 2、编制依据 《立式圆筒形焊接油罐施工及验收规》GB50128-2005 《建筑冬期施工规程》JGJ104-97 3、工程概述 1#、4#、7 #、8#300m3酸储存罐衬胶施工。在气温低于0℃、室外日平均气温连续5天稳定低于5℃时,进入冬季施工。根据本工程施工的具体情况,制定冬季施工需要采取防护的具体工程项目、工作容,制定相应的冬季施工防护措施,保证工程实体质量。 4、当地气候条件 工程所在地属四季分明,春季干旱多西北风,夏季雨少气温高,秋季凉爽而短暂,冬季寒冷少雪(现在平均气温-8℃左右,最低气温达-17℃)。 5、冬季施工准备工作 5.1项目部成立冬期施工领导小组,负责组织冬期施工工程的生产、技术、质量、安全管理和冬施物资供应,负责冬施工作的协调组织,并明确责任,确保冬施中各项工作及时有效进行,避免由于冬施组织不力给生产进度、工程质量、安全施工造成影响。 5.2进入冬季施工前,组织技术员、质检员、施工员、安全员、资料员及实验员认真学习冬施规程,格按规程要求组织冬施。 5.3项目部设置专人测量施工期间的室外气温、原材料的温度,绘制测温点平面布置图,对测温进行编号,并作好记录。对测温保温人员等组织技术业务

立式圆筒形钢制焊接储罐安装施工方案

立式圆筒形钢制焊接储罐安装施工方案 Document number:WTWYT-WYWY-BTGTT-YTTYU-2018GT

立式圆筒形钢制焊接储罐安装施工方案 1.编制依据: 江门江盈化工有限公司(甲方)提供包含罐体基本尺寸的图纸。《石油化工立式圆筒形钢制焊接储罐设计规范》 《立式圆筒形钢制焊接油罐施工及验收规范》 《石油化工立式圆筒形钢制储罐施工工艺标准》 《钢结构工程施工及验收规范》 《钢制压力容器》 国家质量技术监督局颁发《压力容器安全技术监察规程》99板《管壳式换热器》 T4735-97《钢制常压容器》 T2806-1996《奥氏体不锈钢压力容器制造管理细则》 T4708-2000《钢制压力容器焊接工艺评定》 T4709-2000《钢制压力容器焊接规程》 《压力容器无损检测》 《压力容器油漆、包装、运输》 国家其它有关施工规范和行业标准 2.工程概况: 工程名称:江门江盈化工有限公司大储罐和附属槽罐制造安装 建设单位:江门江盈化工有限公司 总包单位:广东石油化工设计院

设计单位:根据江门江盈化工有限公司(甲方)提供包含罐体基本尺寸的图纸由承包方提供设计图纸,并经业主认可。 施工单位: 本工程位于江门江盈化工有限公司公司,工程内容:15个50~600T 储罐、1个100m2换热器和18台槽罐的制作,包括罐体、上下人孔、液位计、盘梯(带护栏)、罐顶栏杆、盘管等内容。 3指导思想: 严格执行国家有关规范和标准,严密组织,精心设计,精心施工。加强施工现场工程管理,建设文明工地,工程一次性合格100%。优良率达到90%,消除安全、质量事故,缩短工期,降低工程成本。坚持满足用户使用功能,确保结构稳定,降低工程总造价的思想,为用户着想,服务与于用户。 4施工准备 现场施工组织机构 现场以本工程严格按项目法施工,建立必须项目经理为首的项目领导班子,制度项目管理方法,落实岗位责任制,对各个工序的工作作出合理的安排,实行正确的项目经理制度,建立科学的管理制度,对生产实行统一指挥,保证生产经营顺利的进行。详见施工组织机构框图(一) 现场平面布置 根据该工程的现场情况,将合理规划平面图,钢板下料,喷沙,涂刷底漆等工序在施工现场工作区形成流水作业,做到有序不乱。

焊接施工方案

目录 1概述 (2) 2锅炉的主要工作参数为 (2) 3编制依据 (2) 4焊接主要施工机具 (2) 5主要管理人员配置和劳动力计划 (4) 6主要施工方案和重大技术措施 (4) 7施工质量管理 (9) 8焊接质量标准和质量目标 (10) 9安全文明和环境施工管理 (10) 10危险源辨识《附表》 (11) 1

1 概述 本工程为沧州中铁装备制造材料有限公司煤气发电锅炉安装工程,锅炉为2台额定蒸发量为85t/h自然循环煤气锅炉。锅炉采用唐山信德锅炉集团有限公司XD—85/5.29-Q 型次高温次高压、单锅筒横置式,自然循环,π型布置、全悬吊结构锅炉。 2锅炉的主要工作参数为 锅炉额定蒸发量:85t/h 给水温度:150℃ 额定蒸汽压力:5.29Mpa 额定蒸气温度:4850C 排烟温度: 1350C 运转层标高:7000mm 锅筒中心标高:25000mm 水压试验压力:7.23 Mpa 2.1焊接工程量简介: 锅炉钢结构焊接、本体受热面管道及连通管焊接、给水系统管道焊接,主蒸汽管道焊接等。 3编制依据 3.1沧州中铁装备制造材料有限公司煤气发电工程《施工组织总设计》。 3.2唐山信德锅炉厂提供的图纸及资料。 3.3《火力发电工程施工组织设计导册》。 3.4《电力建设安全工作规程》。 3.5现有的焊接施工所需图纸、计划及方案。 3.6电力建设施工及验收技术规范(火力发电厂焊接篇)DL/T869-2004。 3.9《火电施工质量检验及评定标准》(焊接篇)1996年版。 3.10《蒸汽锅炉安全技术监察规程》。 4焊接主要施工机具 4.1焊接主要施工机具一览表

4.2工程主要工器具表 3.3主要消耗材料使用计划

储罐焊接施工方案

1.0 工程概况 1.1 工程简介: 乐山宏亚化工有限公司新增4×500m3甲醛储罐、12×100m3储罐。本工程涉及的设备是以甲方(乐山宏亚化工)提供的尺寸及容积为依据,我项目部承担现场制造。储罐主体材质为国产0Cr18Ni9钢板,罐体爬梯材质为Q235,储罐结构为立式锥顶平底。单条焊缝施工完毕立即进行渗透探伤,坚决执行探伤工作严肃认真、不合格焊缝必须返修原则。因此,我公司项目部决定精心挑选优秀持证焊工,采用手工电弧焊施焊,确保焊接质量。储罐施工焊接工作量大,易产生焊接变形。故编写此施工方案,严格按照焊接工艺进行施工,以确保施工质量。 1.2 500m3立式锥顶平底储罐设计参数 1.2.1设计容积:502m3 1.2.2公称直径:8000mm 1.2.3设计高度:10000mm 1.2.4设计压力:常压 1.2.5使用介质:甲醛 1.2.6结构形式:立式锥顶平底 1.2.7主体材质:0Cr18Ni9 2.0 工程特点 本工程的施工工期位于春末夏初。该时期雨水较多,天气潮湿,焊接环境较为复杂;另外储罐施工焊接工程量巨大,技术要求较高;必须采取有效的的焊接环境保护措施和选用高素质的焊接作业人员,以确保储罐焊接质量和工程按时如期交付。 3.0 编制依据 3.1《立式圆筒形钢制焊接储罐施工及验收规范》 GB50128-2005 3.2《现场设备、工业管道焊接工程施工规范》 GB50236-2008 3.3《压力容器安全技术监察规程》 TSG2004-2009 3.4《钢制压力容器》 GB150-2011 3.5《钢制压力容器制造技术要求》 HG20584-1998 3.6《钢制压力容器焊接工艺评定》 JB/T4708-2000 3.7《钢制压力容器焊接规程》 JB/T4709-2000 3.8《不锈钢焊接容器》 JB/T4730-2005 3.10《304不锈钢焊接工艺评定报告》 PQR0201

机电安装冬季施工方案

仅供参考[整理] 安全管理文书 机电安装冬季施工方案 日期:__________________ 单位:__________________ 第1 页共15 页

机电安装冬季施工方案 1.2工程特点 根据《建筑工程冬期施工规程》JGJ104-2011规定:当室外日平均气温连续5天稳定低于5℃便进入冬期施工,当室外日平均气温连续5天高于5℃,即解除冬施工。 本工程施工地区位于xx市南港工业园区,该地区冬季较长,多西北风,平均风速3.12m/s。气温较低,降水也少;xx1月最冷,月平均温度-2℃。历史最低温度是-17.8℃。土壤最大冻结深600mm,最大积雪厚度200mm。根据xx的气象资料表明,xx市冬期施工的起止日期一般为11月15日至来年3月15日。 根据本工程进度分析,处于冬季施工的储罐制作与安装、钢结构、管道制作与安装等重点施工步骤的防风、防滑、防冻、防火的等问题较为突出。针对该地区季节特点,根据工程的进度、专业制定了以下冬季施工方案,以确保冬季施工质量及工期。 2编制依据 2.1施工图纸中国某设计工程有限公司 2.2《立式圆筒形焊接储罐施工及验收规范》GB50128-2005 2.3《钢结构工程施工质量验收规范》GB50205-2001 2.4《工业金属管道工程施工规范》GB50235-2010 2.5《现场设备、工业管道焊接工程施工及验收规范》GB50236-2011 2.6《建筑工程冬期施工规程》JGJ104-2011 2.7《石油化工施工安全技术规程》SH3505-1999 3冬季施工方法 3.1冬季施工准备工作 第 2 页共 15 页

3.1.1对冬施将要施工的分部分项工程进行图纸复查,列出主要工程实物量,安排好施工进度计划。对不适合冬施要求的分项或部位,及时向建设单位、设计单位提出修改设计建议。 3.1.2编制专题冬施方案,达到技术可靠、经济合理,同时组织有关人员学习,并对有关班组详细进行交底。 3.1.3按照冬施计划,编制切实可行的冬施物资需用计划,尽快落实货源,及时进场。对有毒、易燃、易爆物品应符合相关的管理规定。 3.1.4对冬季施工的计量系统、机械、设备、管线等进行全面检修,更换老化元器件,备用一定量的易损零配件;结合机械设备的换季保养,及时更换润滑油;对使用防冻液的机械设备确保防冻液符合当地防冻要求,未使用防冻液的机械设备采取停机后排放冷却水或进入暖棚车间等防冻措施。 3.2管道安装工程 3.2.1焊接场所尽量安排在室内,避免雨、雪、风、霜的干扰,室内保持干燥、清洁,无灰尘。 3.2.2不锈钢焊接环境温度不得低于5℃,碳钢焊接环境温度不得低于0℃,相对湿度不得大于90%。当焊件温度低于上述温度时,所有钢材的焊缝应在施焊处100mm范围内预热到15℃以上,再开始施焊。 3.2.3当环境温度低于上述规定施焊时,应设置焊接防风保温棚,保温棚采用∠50的角钢焊制,外包一层防火布,内补一层保温毡,提高棚内的环境温度并降低棚内的湿度,使之达到焊接工艺规程要求的环境条件。 3.2.4低温天气焊接时,层间间隔时间不得过长。每道焊缝应一次焊接完成,以确保焊接的层间温度。在整个焊接过程中,层间温度不应 第 3 页共 15 页

16储罐焊接施工方案

储罐焊接施工方案 编制:叶树超 审核:鲁松池 批准:周宗华 中国化学工程第十一建设公司

1储罐焊接一般技术要求 (175) 2储罐底板的焊接 (176) 3储罐壁板的焊接 (177) 4储罐拱顶的焊接 (178) 5储罐附件的焊接 (178) 6焊接检验 (178) 7焊缝返修 (179)

储罐焊接施工方案 1 储罐焊接一般技术要求 1)焊接工艺评定:工程施焊前,应具备按有关规范进行的,能全部覆盖工程项目的经评定合格的焊接工艺评定,并按工艺评定的结果编制焊接工艺卡。 2)焊工:参加施焊的焊工应是经过培训、考试并有与施焊相适应的合格项目。 3)材料:储罐及管道工程所铺设前,应按业主和监理方的要求及有关标准、规范的规定,并经检查确认为合格的方可进行施焊。 4)焊材的使用: 根据材质选用相应的焊条。 5)焊材的管理: 焊材的保管、烘干、发放程序应严格按照《焊材仓库保管制度》、《焊条的烘烤、发放及使用管理规定》、《焊材烘烤规范》等有关规定执行,并认真作好记录,保证良好的追踪性。 6)焊接方法:采用全手工焊. 7)坡口加工与组对:坡口加工采用氧-乙炔焰半自动切割机和等离子切割机切割加工,角向磨光机修磨去除氧化皮的方法进行。坡口角度、尺寸经检查合格后方可进行组对,组对尺寸要求如图所示。 8)焊前清理:焊前应对母材坡口及两侧20mm 的范围进行清理,不得有油、锈、水等污物。 9)焊接:焊工在焊接过程中应严格执行焊接工艺规范的要求;尽量采用窄道 (少于4 倍焊条直径)、短弧、多层焊,多层焊时层间接头应错开;整个焊接过程中始终注意起、收弧的控制和质量,起弧时应采用后退引弧法,使起弧部位在焊接过程中重熔以减少缺陷,收弧时应填满弧坑防止弧坑裂纹的产生,且起、收弧均应在坡口内进行,严禁划伤母材表面。 10)点固焊及工卡具焊接要求:所用焊材、工艺及对焊工的要求应与正式施焊相同;点固焊长度50~80mm、焊点间隔300~500mm为宜,点固焊应注意焊透并应在坡口内引弧和熄弧,不得划伤母材表面、不得损坏坡口钝边。工卡具等临时焊道的焊接应在工卡具或焊道上引弧和熄弧,严禁损伤母材表面,并应注意焊透。 11)工卡具等临时附件拆除除时,应注意不得伤及母材表面,切除后打磨平滑并对表面及厚度进行检查,有缺陷时应进行补焊、修磨至合格要求。 12)焊接环境:当施焊环境出现下列情况之一时,应采取有效防护措施,否则不得施焊。 雨雪环境;相对湿度》90%;手弧焊8M/S。