2021年体育中心游泳馆屋面系统工程施工组织设计方案

合集下载

体育馆、游泳馆工程主要分部、分项工程施工方案

体育馆、游泳馆工程主要分部、分项工程施工方案

体育馆、游泳馆工程主要分部、分项工程施工方案1、基坑(槽)土方开挖与回填(1)施工方法基坑(槽)开挖采用反铲挖掘机挖装、自卸汽车运输,基底预留30cm人工清基。

基坑(槽)回填采用装载机或手推车运土,人工分层回填,每层填土25~30cm,手扶振动碾或蛙夯夯实。

基坑降排水视水文地质情况采取井点管或管井降水,或基底周边设排水沟、集水坑泵排积水。

部分遇有中、弱风化岩层时,采用浅孔、密排距松动爆破法挖除。

(2)工艺流程测量定位放线→机械开挖基坑槽(降、排水)→人工清基底→验坑(槽)→浇筑垫层→基础钢筋砼→基坑(槽)分层回填土、夯实。

(3)施工要点开挖前认真察明地下管线等隐蔽设施,如有时采取改移或保护措施。

开挖据基础深度、结构特点及施组安排进行,先深后浅,先集中后分散。

准确进行土方量调配核算,适于回填的土方存放于体育馆场地中部,余土外运至甲方指定地点。

体育馆根据基础挖深、间距采用大开挖的方法,集中挖至基础底标高处,大开挖施工据施组进度安排进行,随挖随施作垫层、基础。

开挖边坡视地层土质而定(1:0.33~1.0)。

游泳馆地下室在基坑底周边设排水沟、集水坑,及时泵排地下水或雨水,保持地下水位在底板垫层下50cm,持续至回填土完毕,防止水浸危害地基承载力和地下水压力造成地下室上浮。

开挖过程中经常测量和核查平面位置及边坡坡度,控制好标高避免超挖或扰动地基原状土。

挖至设计标高后及时请监理与设计单位进行验坑(槽)并尽快施作基础垫层,防止长期晾晒表面风化或遭雨水浸泡危害地基承载力。

如遇地基岩性与设计不符或承载力不足时,即时报告监理与设计人员处理;如需加深换填时,采用C10砼。

雨期施工时,基坑(槽)应分段开挖,挖好一段浇筑一段垫层,并在基坑(槽)上口周边设土埝或截水沟,以防地面雨水流入,同时应经常检查边坡和支护情况,以防止坑壁受水浸泡造成塌方。

游泳馆地基持力层为石灰岩,如机械挖不动时采用浅孔密排距松动爆破法挖除。

基槽开挖后,应对基础下岩溶发育情况进行探测,如遇基岩表面溶沟、溶槽较发育,应将填充物清理干净后再浇筑砼处理,确保在基础下一倍基础宽度深度范围内无>10cm岩溶发育,基础下二倍基础宽度深度范围内岩溶累计厚度≯30cm。

游泳馆施工组织设计

游泳馆施工组织设计

游泳馆施工组织设计一、工程概述本次游泳馆建设项目位于具体地点,总建筑面积为X平方米。

游泳馆主体结构为结构形式,包括游泳池、更衣室、淋浴间、休息区等功能区域。

该游泳馆的设计旨在为广大市民提供一个舒适、安全、卫生的游泳健身场所。

二、施工部署(一)施工目标1、质量目标:确保工程质量达到国家验收合格标准,力争优质工程。

2、工期目标:计划在具体工期内完成全部施工任务。

3、安全目标:杜绝重大伤亡事故,轻伤事故发生率控制在X%以内。

(二)施工组织机构成立项目经理部,项目经理全面负责工程的施工管理工作。

项目部下设工程技术部、质量安全部、物资设备部、综合办公室等部门,各部门分工明确,协同工作。

(三)施工顺序1、先进行基础工程施工,包括土方开挖、基础垫层、基础钢筋混凝土施工等。

2、主体结构施工,依次进行柱、梁、板的钢筋混凝土施工。

3、安装工程穿插进行,包括给排水、电气、暖通等。

4、装饰装修工程在主体结构验收合格后进行,包括内外墙抹灰、地面铺贴、吊顶安装等。

三、施工准备(一)技术准备1、熟悉施工图纸,进行图纸会审,编制施工组织设计和专项施工方案。

2、做好技术交底工作,将施工技术要求和质量标准传达给施工人员。

(二)现场准备1、平整施工场地,修筑临时道路,搭建临时设施。

2、布置施工用水、用电线路,保证施工正常进行。

(三)材料准备1、根据施工进度计划,编制材料采购计划,提前采购所需材料。

2、对进场材料进行检验,确保材料质量符合要求。

(四)劳动力准备1、根据工程规模和施工进度要求,组织足够的劳动力进场。

2、对施工人员进行培训,提高其技术水平和质量意识。

四、主要分部分项工程施工方法(一)基础工程1、土方开挖采用机械开挖为主,人工配合清底的方式。

开挖过程中注意控制基底标高和边坡坡度,防止超挖和塌方。

2、基础钢筋混凝土施工钢筋在加工场加工成型,运至现场绑扎。

混凝土采用商品混凝土,泵送浇筑,振捣密实。

(二)主体结构工程1、钢筋工程钢筋的品种、规格、数量和位置必须符合设计要求。

体育中心施工组织设计

体育中心施工组织设计

体育中心施工组织设计一、项目背景和目标体育中心是一个综合性的体育场馆,用于举办体育比赛、培训和文化活动等。

本次施工组织设计旨在确保项目按时、按质、按量完成,使体育中心成为一个具有现代化设备和设施的理想场所。

二、施工组织机构1.总包单位:负责整体施工管理和协调各分包单位的工作。

2.分包单位:负责具体施工任务,根据总包单位的要求完成各项工作。

三、施工方案1.场地准备:清理、平整工地,确定场地边界,进行管线布置等工作。

2.地基工程:进行土方开挖、填筑、夯实等工作,确保地基的承载能力和稳定性。

3.主体结构施工:按照设计图纸进行钢筋加工、混凝土浇筑、模板安装等工序,确保主体结构的牢固和精确。

4.建筑装饰工程:进行室内外墙体的砌筑、抹灰、粉刷等工作,安装门窗、地板、天花板等装饰材料。

5.道路与管道工程:进行道路硬化、排水管道的安装等工作,确保交通畅通和设施的正常使用。

6.电力与通信工程:进行电力线路的敷设、电缆的连接、弱电系统的安装等工作,保证供电和通信设施的完善。

7.机电设备安装:按照相关要求进行机电设备的安装、调试和运行,确保设备能正常运行。

8.环境美化工程:进行园林景观的设计和施工,种植草坪、树木和花卉等,增加场馆的美观性。

四、施工进度安排1.制定详细的施工计划,明确各项工程的时间节点和工期。

2.实施科学合理的施工组织,合理分配工作力量和资源,确保各项工作的顺利进行。

3.在施工过程中的关键节点,安排预备队伍和备用设备,以应对可能出现的问题和延误。

五、施工安全措施1.制定施工安全管理制度,明确各岗位的责任和职责。

2.加强现场安全监测,确保施工现场的安全环境。

3.定期组织安全培训和教育,提高员工的安全意识和应急处理能力。

六、质量控制措施1.制定施工质量管理制度,明确各项工作的质量要求和验收标准。

2.对于关键的工序和节点,进行全程、全过程的监督和检查,确保施工质量。

3.加强施工现场的质量检测和监控,及时纠正和处理质量问题。

游泳馆工程施工组织设计方案

游泳馆工程施工组织设计方案

编制说明一、编制指导思想本工程位于龙岩市连城县莲峰镇交通方便。

因该工程是连城县重点项目,根据本工程的招标文件的精神,工程质量、进度工期、安全生产、环境保护、标化现场及文明施工要求很高。

为此,我公司针对本工程施工,采用国内外新技术、新工艺成果以及我公司多年来积累的一整套施工的完善、先进、科学的施工工法和施工经验来指导工程施工。

严格按照公司的ISO9001质量标准进行质量目标贯彻;成立工程质量创优组织管理、控制体系,按照PDCA循环的质量管理过程,从人、机、料、法、环、测六大因素着手,成立QC小组对工程质量进行攻关;制订针对本工程的质量通病的有效防治措施。

成立最强的项目经理部,同时配备具有施工经验丰富的项目经理及管理人员进行组织管理。

优化并组织劳动力、机械设备配备计划及合理的物料供应计划,确保工程质量并降低工程造价。

针对工程特点及现场情况,制订相应的工程质量保证体系、工期保证措施体系及安全生产保证体系。

合理进行施工现场平面布置,建立对应的文明施工、标化现场及环境保护方案。

二、编制范围连城县体育中心室内游泳馆工程土建及水电安装工程。

三、编制依据1、招标单位提供的连城县体育中心室内游泳馆工程合同文件、图纸、图纸会审等补充文件。

2、福建省唯冠工程设计有限公司设计的建筑、结构、水电等设计图纸。

3、国家及福建省现行的施工及验收规范、操作规程、验收标准。

4、福建省及龙岩市现行的建筑工程预算定额与估价表及现行配套文件。

5、福建省和龙岩市工程建设现行有关指令性文件规定。

6、国家推广应用的新技术、新工艺、新材料。

7、《多层建筑施工手册》、《建筑施工模板设计手册》8、施工现场和周围环境勘察情况。

四、编制说明1、本工程为设计、招标、施工同时进行的项目管理模式,许多专业施工及装修施工等未明确,因此施工中将根据工程进度编制更为详细的专项施工组织设计和特殊部位专项施工方案,对人、材、物、法、环、测六方面质量管理、施工部署、施工进度计划、现场平面布置等全过程进行细化,并报业主、监理审批。

最新版体育中心游泳馆屋面系统工程施工组织设计方案

最新版体育中心游泳馆屋面系统工程施工组织设计方案

最新版体育中心游泳馆屋面系统工程施工组织设计方案第一章编制依据一、编制依据本施工组织设计编制依据为下列有关文件;1.南京**体育中心游泳馆屋面系统工程招标文件;2.南京**体育中心游泳馆屋面系统工程补充通知;3.由招标单位提供的本工程相关图纸;4.现行的国家和行业颁布的有关设计和施工规范、标准;5.国家及当地的有关法律、行政法规;6.结合企业内部标准,质量手册及程序文件的有关规定;7.业主、总包对质量、工期的要求;8.本工程现场施工条件。

二、选用技术标准及规范我们承诺在本工程的施工中严格按照以下国家及当地的一切有关法规的要求执行,如下述标准及规范要求与标准要求有出入,则采用较为严格的标准及规范。

在实际的施工过程中如遇到暂无标准或规范的项目,则结合我们企业的标准或推荐国际公认的同等或更高的标准作为依据;如若在施工期间有新的国家行业标准及规范颁布,我们还将保证满足新的标准和规范要求去做。

(1)金属屋面技术规范《金属屋面工程技术规范》JGJ102-96《金属与石材幕墙工程技术规程》JGJ133-2001(2)建筑设计规范《高层民用建筑设计防火规范》GB50045-952001版《建筑设计防火规范》GBJ16-872001版《建筑抗震设计规范》GB50011-2001《建筑防雷设计规范》GB50057-94《钢结构设计规范》GB50017-2002《建筑结构荷载规范》GB50009-2001(3)材料标准《铝合金建筑型材》GB/T5237-2000《铝及铝合金加工产品的化学成分》GB/T3190《碳素结构钢》GB700-88《低合金高强度结构钢》GB1597《平面钢化玻璃》GB/T9963-1998《铝及铝合金板材》GB/T3880-1997《建筑用铝型材铝板氟碳涂层》JC133-2000《建筑橡胶密封垫预成型实芯硫化的结构密封垫用材料》GB10711《聚氨酯硬泡体防水保温工程技术规程》JCJ14-1999《建筑用硅酮结构密封胶》GB16776(4)检测方法《硬质泡沫塑料吸水率试验方法》(GB8801-88)《绝缘材料稳态热阴及有关特性的测定》(GB10294-88)《泡沫塑料和橡胶表观(体积)密度的测定》(GB/T6343-95)《硬质泡沫塑料尺寸稳定性试验方法》(GB8811-88)《硬质泡沫塑料压缩试验方法》(GB8813-88)(5)其他规范及要求《建筑施工高处作业安全技术规范》JG80-91《施工现场临时用电安全技术规范》JGJ46-88一、工程概述南京**体育中心为第*届**运动会的主赛场。

游泳馆项目工程施工方案

游泳馆项目工程施工方案

一、工程概况游泳馆项目位于某市某区,占地面积约为10000平方米,总建筑面积约为10000平方米。

工程主要包括游泳馆、淋浴间、更衣室、休息区、设备间等。

本工程采用钢筋混凝土结构,建筑层数为地上3层,地下1层。

二、施工组织设计1. 施工总平面布置(1)施工场地:根据施工现场实际情况,合理划分施工区域,包括材料堆场、施工临时道路、施工生活区等。

(2)施工临时道路:确保施工场地内道路畅通,方便材料运输和人员通行。

(3)施工生活区:设置宿舍、食堂、卫生间等设施,满足施工人员生活需求。

2. 施工进度计划(1)施工阶段:分为基础施工、主体结构施工、装饰装修施工、设备安装施工等。

(2)施工顺序:按照施工总平面布置,依次进行基础施工、主体结构施工、装饰装修施工、设备安装施工。

(3)施工时间:基础施工为3个月,主体结构施工为6个月,装饰装修施工为3个月,设备安装施工为2个月,总工期为14个月。

三、施工方法及工艺1. 基础施工(1)采用钢筋混凝土基础,按照设计要求进行施工。

(2)基础垫层采用碎石垫层,厚度不小于100mm。

(3)基础混凝土采用商品混凝土,强度等级不小于C20。

2. 主体结构施工(1)采用钢筋混凝土框架结构,按照设计要求进行施工。

(2)主体结构混凝土采用商品混凝土,强度等级不小于C25。

(3)主体结构钢筋绑扎、焊接、安装等按照规范要求进行。

3. 装饰装修施工(1)墙面、地面采用瓷砖、大理石等装饰材料,按照设计要求进行施工。

(2)吊顶采用轻钢龙骨石膏板,按照设计要求进行施工。

(3)门窗安装按照规范要求进行。

4. 设备安装施工(1)游泳池、淋浴间、更衣室等设备按照设计要求进行安装。

(2)设备安装完成后,进行调试和试运行。

四、施工质量控制1. 施工材料:严格按照设计要求和规范要求选用材料,确保材料质量。

2. 施工工艺:严格按照施工规范和操作规程进行施工,确保施工质量。

3. 施工过程:加强施工过程中的质量控制,对关键工序进行验收。

多功能游泳池工程施工方案

多功能游泳池工程施工方案

一、工程概况本项目为多功能游泳池工程,位于某城市体育中心内,占地面积约为2000平方米。

游泳池尺寸为50米×25米,深度为2米,设有比赛池、训练池、儿童戏水区等功能区域。

游泳池结构采用钢筋混凝土框架结构,池壁厚度为250px,底板厚度为300px,砼强度等级为C30,抗渗等级为S8。

游泳池内装修采用泳池专用瓷砖贴面,池外四周地面为防滑地砖面层。

游泳池配套设备包括给水、排水、供配电设施等。

二、施工部署1. 成立工程项目组,设项目经理兼技术负责人1人,施工员2人,质检员、安全员、材料员各1人。

选用木工、钢筋、砼及装饰、水电5个班组,负责各自施工任务。

2. 施工流程:施工准备→土方工程→基础工程→主体结构工程→池体防水工程→设备安装工程→给排水工程→电气工程→装修工程→验收交付。

3. 施工期限:本工程计划工期为6个月,包括土方工程、基础工程、主体结构工程、池体防水工程、设备安装工程、给排水工程、电气工程、装修工程等。

三、施工准备1. 施工现场平整:对施工现场进行平整,清除杂物、障碍物,满足施工要求。

2. 施工材料:根据工程量清单,提前准备所需的建筑材料、设备及配件,如钢筋、水泥、砂石、瓷砖、给水排水管道、电气设备等。

3. 施工设备:配置足够的施工设备,如挖掘机、推土机、混凝土泵、搅拌机、模板、脚手架等。

4. 技术交底:组织施工人员学习施工图纸、施工方案、技术规范等,确保施工人员熟悉工程要求。

四、施工方法及质量要求1. 土方工程:采用挖掘机、推土机等设备进行土方开挖、回填,确保施工安全、进度和质量。

2. 基础工程:按照设计图纸进行基础施工,包括垫层、底板、池壁等,确保基础牢固、平整。

3. 主体结构工程:采用钢筋混凝土框架结构,严格把控钢筋焊接、混凝土浇筑、养护等环节,确保结构安全、耐用。

4. 池体防水工程:采用防水砂浆、防水涂料等材料进行池体防水,确保游泳池内部不渗水。

5. 设备安装工程:按照设计要求安装给水、排水、供电等设备,确保设备安装规范、功能正常。

游泳馆施工组织设计方案

游泳馆施工组织设计方案

游泳馆施工组织设计方案第八章±0.000以上主体结构工程施工1、主体结构施工顺序平台放线→墙、柱钢筋连接→墙、柱钢筋绑扎→墙、柱水电预埋→模板支撑搭设→墙、柱支模→墙、柱砼浇筑→平台梁、板支模→水电预埋→平台板面筋绑扎→梁筋、平台板底筋绑扎→局部吊模→墙、柱上端砼浇筑→养护→平台砼浇筑→转上层2、主体结构主要项目施工方法2.1 钢筋工程钢筋采用集中配料,每一流水段,每根柱、平台、墙钢筋编好号后捆成束集中吊运,现场绑扎、冷挤压连接、立焊连接的施工方法。

2.1.1 钢筋原材料、随质保书、送验要求同地下室部分。

2.1.2 钢筋接头选用根据设计要求,结合规范、实际施工情况,钢筋接头连接选择(进入支座锚固除外)仍同地下室部分。

2.1.3 钢筋几种主要接头工艺施工要求钢筋的几种接头形式同地下室部分。

2.1.4 钢筋绑扎质量保证措施(1)核对成品钢筋的级别、直径、形状、尺寸和数量等是否和料单、料牌相符,如有错、漏应纠正增补。

(2)准备必须数量的铁丝和保护层垫块以及常见的绑扎工具,如钢筋钩、带板口的小撬棍、绑扎架及柱、墙绑扎用鹰架等。

(3)现场就位绑扎时,首先应将模板内刨花、碎木块及垃圾等清除干净。

(4)划出钢筋位置线:平板或墙板的钢筋,在模板上划线;柱的箍筋,在两根对角线主筋上划点;梁的箍筋,应在架立筋上划点,基础的钢筋,在两向各取一根钢筋划点或在垫层上划线。

(5)钢筋接头的位置,应根据来料规格,结合规范对接头位置、数量的规定,使其错开,在模板上划线。

(6)梁、板、柱等类型较多,应在模板上分别标明各种型号构件钢筋规格、形状和数量。

(7)绑扎形式复杂的结构部位,应事先制定钢筋穿插就位的顺序,支模和绑扎钢筋的先后次序。

(8)预先浇筑好砼垫块,垫块均采用粗砂浇制,且均插18号扎筋丝。

2.1.5 预埋、预留措施(1)楼板内下层受力筋必须放在电线管道的下面;(2)板上圆孔洞直径及方形孔洞宽度(b)(b为垂直与板跨度方向孔洞宽度)小于300mm时,受力钢筋绕过孔洞边不可切断;大于300mm时应按设计要求在孔洞周围采取加固措施。

体育场游泳馆安装施工方案

体育场游泳馆安装施工方案

体育场游泳馆安装施工方案
一、前言
体育场游泳馆是一个重要的运动场馆,游泳馆的安装施工是确保游泳馆正常运行的重要环节。

本文将针对体育场游泳馆安装施工进行详细的方案设计。

二、施工准备
1. 人员组织
施工前需要确定施工队伍的人员组织架构,包括负责人、施工人员、监理人员等角色,确保各个岗位职责明确。

2. 施工材料
准备好游泳馆安装所需的各种材料,包括管道、设备、电缆等。

3. 工程设备
根据施工需要,准备好相应的工程设备,确保施工顺利进行。

三、施工流程
1. 安装准备
在施工现场进行勘察,确定管道、设备的安装位置,并进行标记。

2. 管道安装
按照设计要求,先安装游泳馆的主要管道,包括进水管道、排水管道等。

3. 设备安装
安装各种游泳馆设备,包括泳池过滤设备、水泵等,确保设备安装正确,能够正常运行。

4. 电气布线
进行游泳馆的电气布线工作,确保正常用电和设备的安全运行。

5. 系统调试
安装完成后,对游泳馆的管道、设备进行系统调试,检查系统是否正常运行。

四、安全保障
在施工过程中,要遵守相关的安全操作规程,确保施工人员和场馆设备的安全,避免发生意外事故。

五、质量检验
施工完成后,要对游泳馆的安装情况进行全面检查,确保安装质量符合相关标
准和要求。

总结
体育场游泳馆安装施工是一个细致、复杂的工程,施工方案的合理性和施工质
量的优良程度直接影响到游泳馆的使用效果和安全性。

只有严格按照施工方案进行施工,确保施工质量,才能保证游泳馆的正常运行。

游泳馆施工组织设计

游泳馆施工组织设计

游泳馆施工组织设计1. 引言本文档旨在设计游泳馆施工组织,确保施工过程顺利进行。

游泳馆施工组织设计应注重安全、高效和质量,同时合理管理资源和人员。

2. 施工组织方案2.1 施工步骤安排按照施工过程的逻辑顺序,制定详细的施工步骤安排,包括下列内容:- 土建施工:包括地基处理、混凝土浇筑、建筑结构施工等;- 设备安装:包括游泳池设备、通风系统、照明系统等的安装;- 室内装修:包括墙面装修、地面铺设、洁净度要求等;- 配套设施:包括防火设施、安全设备、卫生设施等的安装和调试;- 竣工验收:包括施工质量检查、设备运行测试、安全检查等。

2.2 施工周期预估结合施工步骤安排,合理预估游泳馆施工周期,全面考虑施工各阶段的工期和任务交叉情况。

2.3 人员组织管理安排专业施工团队,包括工长、施工人员、质检员等,保证施工场地的专业管理和施工质量控制。

设立项目经理,协调各施工阶段工作,确保施工进度顺利推进。

2.4 安全措施制定安全施工措施,确保施工过程中的人员安全和设备安全。

包括设置安全警示标识、明确安全操作规程、定期进行安全培训等。

2.5 资源管理合理安排施工所需的各类资源,包括材料、设备和人力资源。

确保施工过程中资源的及时供应和有效利用。

3. 施工组织流程图设计一个施工组织流程图,清晰展示施工过程中各个步骤的关系和依赖关系,方便项目管理和监控。

4. 施工组织风险评估对施工组织中可能存在的风险进行评估和分析,制定相应的应对措施,降低风险对施工进度和质量的影响。

5. 结论本文档设计了游泳馆施工组织,包括施工步骤安排、施工周期预估、人员组织管理、安全措施、资源管理等方面。

通过合理的组织和管理,能够确保游泳馆施工过程的顺利进行,保证施工质量和工期的达到预期目标。

2021年体育中心游泳馆工程施工组织设计方案

2021年体育中心游泳馆工程施工组织设计方案

2021年体育中心游泳馆工程施工组织设计方案目录第一章编制依据 (1)第二章工程概况 (1)第三章管理方针和目标 (5)第四章施工条件 (6)第五章施工组织 (7)第六章施工部署 (8)第七章施工方案 (9)第八章冬期施工措施 (59)第九章质量保证措施 (61)第十章工期保证措施 (68)第十一章安全保证措施 (69)第十二章环境保护措施 (80)第十三章降低成本措施 (82)第十四章文明施工和防止扰民措施 (83)第十五章信息管理 (83)第十六章项目风险管理 (86)附表一、施工机具设备表 (89)附表二、劳动力计划表 (90)附图三、施工网络计划 (91)附图四、施工总平面布置图 (92)第一章编制依据1.1 本工程设计施工图和其他相关设计文件;1.2 《建筑法》、《建设工程质量管理条例》;1.3 国家及地方相关法律法规和规章;相关标准、规范及规程;1.4 公司编制的《质量、环境及职业健康安全管理手册》(QG/ZYDJ-00-2007);1.5 建筑工程公司编制的《质量、环境及职业健康安全管理体系程序文件》(QG/DBJS·JG-2007);1.6 《**市游泳馆岩土工程勘察报告》;1.7 类似工程的施工经验。

第二章工程概况2.1 工程名称:体育中心游泳馆。

2.2 建设单位:建设委员会。

2.3 建设地点:位于西部新区,西路,盛达大道,南侧和西侧为规划地块。

2.4 建设规模:总建筑面积:15492.8m2;地上:13643.24m2;地下:1849.56m2 ;总高度:结构上弦杆轴线标高26.10m;座席数量:2022座。

2.5 施工范围:游泳馆的建筑、结构及给排水工程。

2.6 工期要求:2.7 工程内容简述:2.7.1 本工程房屋高度11.25m,地面以上三层,地下一层。

2.7.2 结构形式:地上:看台部分为现浇混凝土结构,看台罩棚为钢结构桁架。

地下:外墙为自防水钢筋混凝土墙体。

最新版体育训练中心维修改造工程施工组织设计方案

最新版体育训练中心维修改造工程施工组织设计方案

最新版体育训练中心维修改造工程施工组织设计方案项目背景体育训练中心为保障高水平运动员的日常训练和国际大型体育赛事的需要,经过多年使用,已出现多处老化和损坏问题,需要进行维修改造。

本次维修改造工程的规模较大,包括了场馆设施、供水排水、电力及通讯设施、消防安全设施等多个方面。

施工组织设计方案本次维修改造工程施工组织设计方案如下:1. 施工方案(1)场馆设施维修改造方案场馆设施维修改造主要包括体育馆、游泳馆、跳水馆和羽毛球馆等多个场馆。

- 首先进行拆除工作,包括旧的比赛场地、照明灯、声光控制器等。

在拆除过程中,要保证既不破坏现有结构,又不影响施工进度。

- 其次进行土建工程。

在土建工程中,要尽可能地保留现有的基础设施,避免对基础设施的破坏和改变。

同时,还要针对现有的设施,进行细节上的完善升级。

- 最后进行装饰和设施安装。

在这个阶段中,要尽可能保持装饰风格的一致性,以及实现现代化的装饰效果。

(2)供水排水方案供水排水方案中主要包括了给水系统和排水系统的维护和更换。

- 针对给水系统的改造,要考虑水质和供水量,并在工程设计中考虑接入城市自来水管道,使其水质优良,同时供水量充足。

- 针对排水系统的改造,要对现有的污水管道进行检查、修复和更换,保证排水的畅通。

(3)电力及通讯设施方案电力及通讯设施方案中主要包括了电缆和互联网设施的更换。

- 针对电缆的更换,要根据现有容量进行规划,确保电缆满足当前和未来的需求。

- 针对互联网设施的更换,要在设计时考虑当前使用设备的数量和未来增加的数量,避免设备不足的状况出现。

2. 安全防护措施在施工期间,安全是第一位的。

因此,在制定“施工组织设计方案”时,要充分考虑相关的安全防护措施,保障人员的人身安全和设施的安全。

- 在拆除工程中,要做好物品移动的保护工作,避免碰撞和损坏。

- 在土建工程中,要设置坍塌预留通道,保障人员的安全;同时,在进行高空作业时,要设置扶手和保护网,防止材料坠落。

泳池游泳馆工程施工方案

泳池游泳馆工程施工方案

一、工程概况本工程位于我国某城市,总建筑面积约10000平方米,包括室内游泳池、室外游泳池、更衣室、淋浴室、休息区、管理办公室等设施。

游泳池分为标准游泳池和儿童游泳池,其中标准游泳池尺寸为50m×25m,儿童游泳池尺寸为20m×10m。

游泳池深度分别为1.8m和1.2m。

本工程采用钢筋混凝土结构,外立面采用玻璃幕墙,具有现代化的设计风格。

二、施工部署1. 施工组织(1)成立泳池游泳馆工程项目组,设项目经理1人,施工员2人,质检员、安全员、材料员各1人,以及钢筋、混凝土、装饰、水电安装等5个班组。

(2)施工过程中,严格执行国家有关施工规范、标准和质量要求,确保工程质量和安全。

2. 施工进度安排(1)基础工程:预计工期为60天。

(2)主体结构工程:预计工期为90天。

(3)装饰装修工程:预计工期为120天。

(4)配套设施安装:预计工期为60天。

(5)竣工验收:预计工期为30天。

3. 施工方法(1)基础工程1)采用钢筋混凝土灌注桩基础,桩径为600mm,桩长为15m。

2)基础混凝土采用C25等级,桩顶承台混凝土采用C30等级。

(2)主体结构工程1)采用钢筋混凝土框架结构,梁、板、柱采用C30等级混凝土。

2)梁、板、柱尺寸及配筋按照设计要求进行施工。

(3)装饰装修工程1)外立面采用玻璃幕墙,室内墙面、地面、天花采用瓷砖、涂料等材料。

2)室内游泳池采用抗渗混凝土,池壁、池底厚度分别为300mm和300mm。

(4)配套设施安装1)游泳池设备:包括水泵、过滤器、消毒设备等。

2)给排水、电气、通风空调等配套设施按照设计要求进行安装。

三、施工质量保证措施1. 施工前,对施工人员进行技术交底,确保施工人员熟悉施工工艺和质量要求。

2. 施工过程中,加强质量检查,发现问题及时整改。

3. 施工结束后,进行竣工验收,确保工程质量符合国家标准。

四、施工安全保证措施1. 施工现场设立安全警示标志,确保施工人员安全。

体育馆游泳馆工程施工设计方案

体育馆游泳馆工程施工设计方案

Ⅵ施工组织设计目录一、工程概况1、工程名称与规模······················································2、工程围与容··························································3、建筑与结构··························································4、主要工程量··························································5、工期要求····························································6、质量要求····························································7、安全与环保要求······················································8、自然条件····························································9、施工条件····························································10、相关单位···························································二、施工总体组织与规划1、总体主导思路························································2、项目管理组织························································3、施工队伍部署与任务划分··············································4、施工总平面布置······················································5、总体施工组织方案····················································6、主要分项工程施工顺序················································7、施工工期目标规划····················································8、工程质量目标规划····················································9、安全、文明施工与环保目标规划········································三、施工进度计划安排1、总工期计划安排······················································2、工程项目阶段性目标计划··············································3、施工进度计划横道图、网络图··········································四、劳动力计划安排·····················································五、主要施工机械设备配备···············································六、主要材料(设备)供应进度计划·········································七、主要分部、分项工程施工方案·········································1、基坑(槽)土方开挖与回填··············································2、钢筋砼基础··························································3、游泳馆地下室(含游泳池) ··············································4、钢筋砼框架··························································5、体操、排球训练馆屋面预应力框架梁····································6、卷材防水保温屋面····················································7、脚手架······························································8、钢筋制安····························································9、砼制运、浇捣、养护··················································10、水泥炉渣空心砌块填充墙·············································11、楼地面·····························································12、墙与顶棚饰面·······················································13、外墙干挂花岗岩施工·················································14、散水、踏步、坡道···················································15、电气系统···························································16、给排水、消防系统···················································17、暖通、空调系统·····················································八、保证工期的主要措施·················································九、工程质量保证措施···················································十、保证安全措施·······················································十一、环境保护、文明施工与文物保护措施·································Ⅵ施工组织设计一、工程概况1、工程名称与规模本标工程系师大学体育馆、游泳馆工程,建筑面积分别为13300、10240m2,合计23540m2。

体育中心游泳馆项目总承包施工组织设计

体育中心游泳馆项目总承包施工组织设计

浙江黄龙体育中心游泳跳水馆项目施工组织设计目录第一章编制说明··········································································································· - 1 -1.1编制简述 (1)1.2编制依据及原则 (1)1.2.1 编制依据····································································································- 1 -1.2.2 编制原则····································································································- 5 -第二章工程概况··········································································································· - 5 -2.1工程简介 (5)2.2设计简介 (6)2.2.1 建筑概况····································································································- 6 -2.2.2 结构概况····································································································- 7 -2.2.3 专业概况····································································································- 7 -2.3水文地质条件 (12)第三章工程特点及施工重点、难点分析与对策 ·························································- 12 -3.1工程特点 (12)3.2施工重点、难点分析与对策 (13)第四章施工部署··········································································································- 16 -4.1项目管理目标 (16)4.1.1 质量管理目标··························································································- 16 -4.1.2 工期管理目标··························································································- 16 -4.1.3 职业健康安全和环境管理目标······························································- 17 -4.2项目管理架构 (17)4.2.1 项目组织机构··························································································- 17 -4.2.2 项目组织机构职责分工··········································································- 18 -4.3区段划分与总体施工组织 (22)4.3.1 施工作业区和流水段划分······································································- 22 -4.3.2 施工程序部署··························································································- 22 -中国建筑第八工程局有限公司ML-1浙江黄龙体育中心游泳跳水馆项目施工组织设计4.4施工计划准备 (22)4.4.1 施工技术准备工作计划··········································································- 22 -4.4.2 施工机械准备工作计划··········································································- 24 -4.4.3 物资材料准备工作计划··········································································- 24 -4.4.4 施工队伍准备工作计划··········································································- 24 -4.4.5 临时设施准备工作计划··········································································- 25 -4.4.6 作业条件准备工作计划··········································································- 25 -第五章施工进度计划 ··································································································- 25 -5.1施工进度编制原则 (26)5.1.1 响应性原则······························································································- 26 -5.1.2 实施性原则······························································································- 26 -5.1.3 经济性原则······························································································- 26 -5.1.4 层层控制原则··························································································- 26 -5.1.5 适时调整原则··························································································- 27 -5.1.6 奖先罚后原则··························································································- 27 -5.2施工工期目标 (27)5.2.1 施工进度计划各阶段控制要点······························································- 27 -5.3施工进度组织方法 (28)5.3.1 交叉作业··································································································- 28 -5.3.2 确保进度的施工要素组织······································································- 28 -5.4主要人、机、料进场计划 (31)5.4.1 劳动力进场计划······················································································- 31 -5.4.2 主要施工机械的进场计划······································································- 31 -5.4.3 主要工程材料进场计划··········································································- 31 -5.5施工进度保证措施 (32)5.5.1 施工准备期间保证措施··········································································- 32 -5.5.2 施工期间保证措施··················································································- 33 -5.5.3 农忙、春节期间保证措施······································································- 34 -5.5.4 机械及工器具保证措施··········································································- 35 -中国建筑第八工程局有限公司ML-2浙江黄龙体育中心游泳跳水馆项目施工组织设计5.5.5 施工经济保障措施··················································································- 35 -5.5.6 施工技术保障措施··················································································- 35 -5.5.7 外部环境保障措施··················································································- 35 -5.5.8 夜间施工保障措施··················································································- 36 -5.5.9 季节性和高温季节施工保障措施··························································- 36 -5.5.10 施工方案保障措施················································································- 36 -5.5.11 管理与控制手段保障措施····································································- 37 -第六章拟投入资源计划 ······························································································- 38 -6.1劳动力配置 (38)6.2.1 劳动力计划考虑因素··············································································- 38 -6.2.2 劳动力计划表··························································································- 39 -6.2.3 拟投入最高人数和平均人数··································································- 39 -6.2.4 劳动力计划保证措施··············································································- 39 -6.3主要机械设备计划 (40)6.3.1 塔吊的选择······························································································- 40 -6.3.2 混凝土运输设备的选择··········································································- 41 -6.3.3 装修垂直运输机械的选择······································································- 41 -6.3.4 钢筋加工机械选择··················································································- 41 -6.3.5 木工加工机械选择··················································································- 42 -6.3.6 砂浆搅拌设备选择··················································································- 42 -6.3.7 水泵、打夯机和发电机等选择······························································- 42 -6.3.8 土建阶段主要施工机具配置计划··························································- 42 -6.4测量和试验仪器设备配置 (43)6.4.1 测量仪器的配置······················································································- 43 -6.4.2 试验仪器设备配置··················································································- 44 -6.4.3 测量试验仪器设备表··············································································- 44 -6.4.4 测量实验仪器设备的注意事项······························································- 44 -6.5原材料 (44)6.5.1 保证计划实现的措施··············································································- 45 -中国建筑第八工程局有限公司ML-3。

游泳馆施工组织设计方案

游泳馆施工组织设计方案

第八章±0以上主体结构工程施工1、主体结构施工顺序平台放线→墙、柱钢筋连接→墙、柱钢筋绑扎→墙、柱水电预埋→模板支撑搭设→墙、柱支模→墙、柱砼浇筑→平台梁、板支模→水电预埋→平台板面筋绑扎→梁筋、平台板底筋绑扎→局部吊模→墙、柱上端砼浇筑→养护→平台砼浇筑→转上层2、主体结构主要工程施工方法2.1 钢筋工程钢筋采用集中配料,每一流水段,每根柱、平台、墙钢筋编好号后捆成束集中吊运,现场绑扎、冷挤压连接、立焊连接的施工方法。

2.1.1 钢筋原材料、随质保书、送验要求同地下室局部。

2 钢筋接头选用根据设计要求,结合标准、实际施工情况,钢筋接头连接选择(进入支座锚固除外)仍同地下室局部。

2.1.3 钢筋几种主要接头工艺施工要求钢筋的几种接头形式同地下室局部。

2.1.4 钢筋绑扎质量保证措施(1)核对成品钢筋的级别、直径、形状、尺寸和数量等是否和料单、料牌相符,如有错、漏应纠正增补。

(2)准备必需数量的铁丝和保护层垫块以及常用的绑扎工具,如钢筋钩、带板口的小撬棍、绑扎架及柱、墙绑扎用鹰架等。

(3)现场就位绑扎时,首先应将模板内刨花、碎木块及垃圾等去除干净。

(4)划出钢筋位置线:平板或墙板的钢筋,在模板上划线;柱的箍筋,在两根对角线主筋上划点;梁的箍筋,应在架立筋上划点,根底的钢筋,在两向各取一根钢筋划点或在垫层上划线。

(5)钢筋接头的位置,应根据来料规格,结合标准对接头位置、数量的规定,使其错开,在模板上划线。

(6)梁、板、柱等类型较多,应在模板上分别标明各种型号构件钢筋规格、形状和数量。

(7)绑扎形式复杂的结构部位,应事先制定钢筋穿插就位的顺序,支模和绑扎钢筋的先后次序。

(8)预先浇筑好砼垫块,垫块均采用粗砂浇制,且均插18号扎筋丝。

2.1.5 预埋、预留措施(1)楼板内下层受力筋必须放在电线管道的下面;(2)板上圆孔洞直径及方形孔洞宽度(b)(b为垂直与板跨度方向孔洞宽度)小于300mm时,受力钢筋绕过孔洞边不可切断;大于300mm时应按设计要求在孔洞周围采取加固措施。

体育场游泳馆安装施工方案

体育场游泳馆安装施工方案

体育场游泳馆安装施工方案一、前期准备工作1.安全保障:在施工前,要对施工现场进行安全评估和环境检测,并制定应急预案。

2.人员组织:成立施工团队,并组织培训以确保施工人员具备专业技能和安全知识。

3.施工材料准备:根据设计方案和工程要求,购买合适的材料,并进行验收。

4.设备准备:购买所需的设备,并进行检测和调试。

5.工期计划:制定详细的施工工期计划,并进行合理的资源分配。

二、游泳池安装1.准备施工现场:清理现场,确保施工区域干净整洁,并设置安全警示标志。

2.建造池壳:按照设计方案,在地面上进行地基的施工,并建造池壳。

3.安装管道系统:根据设计图纸,进行管道的安装和连接,包括进水管道、排水管道和循环水管道等。

4.安装过滤系统:按照设计要求,安装过滤器、水泵、消毒设备等。

5.安装辅助设施:安装池边护栏、跳台、观众席等。

6.安装照明系统:安装适当的照明设备,以确保游泳场馆在夜间正常运行。

三、设备调试1.检查设备安装情况:对于已安装的设备进行检查,确保其安装正确、固定稳定,且与管道系统连接良好。

2.设备调试:按照设备使用说明书,对设备进行调试,确保其运行正常。

3.检查安全设备:检查安全设备,如救生圈、游泳圈等,确保其数量和位置合理,并易于使用。

4.进行水质检测:使用专业水质检测设备,对游泳池的水质进行检测,确保水质符合卫生标准。

四、完善细节1.进行环境美化:在游泳馆周围种植草坪、树木等植被,提供舒适的环境。

2.安装标识牌:在适当的位置安装标识牌,包括游泳馆名称、安全提示等。

3.安装监控设备:根据安全要求,安装视频监控设备,确保游泳馆的安全。

五、验收工作1.进行综合检查:对游泳场馆进行全面检查,确保施工符合设计要求和相关标准。

2.环境卫生检查:检查游泳池和周边环境的卫生情况,并进行清洁和消毒。

3.相关部门验收:安排相关部门对游泳场馆进行验收,确保符合相关法规和卫生标准。

4.整理资料:整理施工记录和相关资料,做好归档和备份。

  1. 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
  2. 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
  3. 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。

2021年
体育中心游泳馆屋面系统工程施工组织设计方案
第一章编制依据
一、编制依据
本施工组织设计编制依据为下列有关文件;
1.南京**体育中心游泳馆屋面系统工程招标文件;
2.南京**体育中心游泳馆屋面系统工程补充通知;
3.由招标单位提供的本工程相关图纸;
4.现行的国家和行业颁布的有关设计和施工规范、标准;
5.国家及当地的有关法律、行政法规;
6.结合企业内部标准,质量手册及程序文件的有关规定;
7.业主、总包对质量、工期的要求;
8.本工程现场施工条件。

二、选用技术标准及规范
我们承诺在本工程的施工中严格按照以下国家及当地的一切有关法规的要求执行,如下述标准及规范要求与标准要求有出入,则采用较为严格的标准及规范。

在实际的施工过程中如遇到暂无标准或规范的项目,则结合我们企业的标准或推荐国际公认的同等或更高的标准作为依据;如若在施工期间有新的国家行业标准及规范颁布,我们还将保证满足新的标准和规范要求去做。

(1)金属屋面技术规范
《金属屋面工程技术规范》JGJ102-96
《金属与石材幕墙工程技术规程》JGJ133-2001
(2)建筑设计规范
《高层民用建筑设计防火规范》GB50045-952001版
《建筑设计防火规范》GBJ16-872001版
《建筑抗震设计规范》GB50011-2001
《建筑防雷设计规范》GB50057-94
《钢结构设计规范》GB50017-2002
《建筑结构荷载规范》GB50009-2001
(3)材料标准
《铝合金建筑型材》GB/T5237-2000
《铝及铝合金加工产品的化学成分》GB/T3190
《碳素结构钢》GB700-88
《低合金高强度结构钢》GB1597
《平面钢化玻璃》GB/T9963-1998
《铝及铝合金板材》GB/T3880-1997
《建筑用铝型材铝板氟碳涂层》JC133-2000
《建筑橡胶密封垫预成型实芯硫化的结构密封垫用材料》GB10711
《聚氨酯硬泡体防水保温工程技术规程》JCJ14-1999
《建筑用硅酮结构密封胶》GB16776
(4)检测方法
《硬质泡沫塑料吸水率试验方法》(GB8801-88)
《绝缘材料稳态热阴及有关特性的测定》(GB10294-88)
《泡沫塑料和橡胶表观(体积)密度的测定》(GB/T6343-95)《硬质泡沫塑料尺寸稳定性试验方法》(GB8811-88)
《硬质泡沫塑料压缩试验方法》(GB8813-88)
(5)其他规范及要求
《建筑施工高处作业安全技术规范》JG80-91
《施工现场临时用电安全技术规范》JGJ46-88
一、工程概述
南京**体育中心为第*届**运动会的主赛场。

中心位于南京**区,占地1300亩,主体建筑包括容纳8万人的主体育场,1.5万席的体育馆,4个池的游泳中心,20片网球场的网球中心以及一些附属配套设施,计划于2005年全部建成。

建成后的南京**体育中心,将成为集竞技体育、业余体育、群众健身、文化娱乐、旅游休闲于一体的设施一流、环境优美的大型体育公园。

也将成为该南京市新的标志性建筑之一。

游泳馆构建在体育中心东南入口处,内设国际标准的50米长的比赛池、25X25米的跳水池、50X15米的训练池和600平方米的休闲池,观众区设有3000个席位。

游泳馆大空间部分一层,观众区部分二层(局部有夹层),在泳池下部设有设备层(地下室),建筑面积约25200平方米,外观呈海螺状。

二、项目总体要求
本工程对工期的要求为:开工日期为2003年11月1日,竣工日期为2003年12月31日。

共61日历天。

本工程的质量要求为合格,质量目标为创“鲁班奖”;文明施工要求为创“省级文明工地”。

一、项目目标
(一)施工质量目标
本工程的施工质量目标:质量完全符合施工验收规范,达优良标准,争创“鲁班奖”。

(二)施工进度目标
我方将本工程的施工工期目标订为61日历天,于2003年11月1日开工,于2003年12月31日竣工。

我方将确保在目标工期内完成招标文件规定的招标范围内的全部施工任务,并交付使用。

(三)成本目标
在工程进行过程中,通过开源节流,对工程中人力资源、物质资源和费用开支,进行指导、监督、调节和限制,以劳动定额为基础,制定各个工序成本控制定额及经济技术指标,从而降低项目成本,提高经济效益。

本工程的成本目标是:成本降低率为5%。

(四)安全目标
公司的安全目标是在每个员工的努力和安全意识的基础上,严格遵守安全和环保规章制度及操作规程,积极参加安全教育培训,正确佩戴个人防护用品,以预防事故,实现安全生产零事故的目标,注意安全生产,采取安全标准化措施,杜绝发生重大伤亡事故。

二、项目管理体系与人员数量
(一)项目管理体系
根据本工程量大、结构复杂、工种工序繁多、立体交叉作业、
平行流水施工的特点,为了保证工程的顺利实施,我司将集中具有丰富施工经验的优秀管理人员,组成项目经理部,从而使幕墙工程能在施工管理、施工技术上充分体现精品意识。

本工程项目经理由多年从事幕墙施工的国家一级项目经理担任,实行项目经理负责制。

项目经理代表公司对外接收业主和监理的指令和调度,协调外部各方关系及事务;对内负责协调公司各种资源的调度,配合工程进展,指挥和管理项目部内部各事务。

(系统组织机构图见下页)
(二)项目管理体系组织说明
1.项目经理职能
(1)全面管理工程施工过程,对工程项目质量、安全、文明施工、工期和工程成本等全面负责。

(2)贯彻执行国家、省、市有关法律、法规和政策,执行企业的各项管理制度。

(3)负责主持项目部日常工作。

(4)根据施工进度情况,调整资金流动、材料设备供应、人力机械使用等计划。

(5)组织制定项目施工管理机构各类管理人员的职责、权限和项目管理的规章制度并监督执行。

(6)执行经济责任书中项目经理负责履行的各项条款。

(7)对工程项目施工进行有效控制,执行有关技术规范和标准,积极推广应用新技术,确保工程质量和工期,实现安全、文明生产,努力提高经济效益。

(8)运用现代化管理办法和应用新技术进行计划、组织、指挥、协调、控制,实现项目管理目标。

(9)主持项目施工、质量例会,签署开、竣工报告。

(10)组织指挥本工程项目的生产经营活动,调配并管理进入工程项目的人力、资金、物资、机械设备等生产要素。

(11)安排施工作业队伍,并把好持证上岗关。

(12)负责制定项目质量目标,并落实目标的贯彻、实施。

(13)向项目指挥部及工程总监汇报项目部工作,按公司有关规定对项目实施管理。

(14)负责监督执行质量检查规程。

(15)负责质量三检,分析质量状况,掌握质量动态。

各分项工程开工前作好质量规范要求布置会。

(16)制定安全生产规章制度,监督安全生产规章制度的贯彻落实,定期进行安全大检查。

(17)组织三检制度,主持质量检查验评,督促工程验收手续的工作,对不合格品要及时返工,发生问题及时上报。

2.技术总负责职能
(1)具体主持本工程的现场图纸变更工作。

(2)负责本工程技术管理工作,组织重大技术方案的审核,解决施工过程中出现的重大技术问题。

(3)负责施工全过程技术指导与监控,负责监督执行ISO9001质量体系,组织施工图纸会审和技术交底。

(4)与业主、设计单位、监理公司保持密切沟通,保证设计、监理的要求与指令在各工种中贯彻落实。

(5)组织技术骨干对本项目的关键技术难题进行科研攻关,落实加工制作、施工安装工艺,确保施工顺利进行。

(6)负责组织玻璃幕墙各项性能指标检测的工作。

3.项目总调度职能
(1)负责组织和调度生产过程中所需工厂内加工的人员、设备和
材料。

(2)负责组织和调度生产,在确保质量的前提下,全面完成铝型材加工、复合铝板加工、玻璃加工、钢结构加工、外协件加工等各项生产任务。

(3)负责按照施工进度要求,保证材料及时运输到位,以保工期。

(4)负责外协加工合同的签订、管理及履行。

4.项目副经理职能
(1)对项目经理负责,负责监督协调现场的施工安装工作。

(2)认真贯彻公司及项目经理针对本工程制订的整体方案和技术措施,对工程成本、进度、质量和施工工艺严格把关。

(3)领导工人按图纸、施工规范进行施工,并经常进行检查,认真实施变更,及时提供局部结构优化的方案,完善图纸确认手续。

5.质控组职能
(1)收集整理质量资料,对现场情况随时、随地进行监控,及时填报分项工程质量检查评定报表,协助建立质量档案。

(2)按质量标准及时对工程质量进行验评,对不合格的有权责令返工、停工,并将发生的质量问题及经济损失如实上报。

(3)参加质量会议及质量检查,参加工程质量问题的分析、调查和处理。

(4)积极协助领导开展全面质量管理,严格掌握质量标准,对检查评定的工程质量负责,认真实行目标管理和全面质量管理。

(5)严格按设计图纸、施工规范、施工程序组织施工,按照质量。