Garment PP meeting guideline
- 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
- 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
- 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。
PRE PRODUCTION MEETINGS
GUIDELINES
Clothing Only
August 2009
Version 1
Pre Production Meetings
Guidelines
Contents
Introduction
P. 3
Meeting Details
P. 4
Meeting Arrangements P. 4 Attendees
P. 4
Meeting Requirements P. 5 Meeting Procedure P. 6 Minutes
P. 6
Meeting Paperwork P. 7 Special Points to Review in Meeting P. 8
Pre Production Check List P. 8 Styling/Artwork concerns P. 9
Construction Comments P. 9
Workmanship Comments P. 10 Critical Area Comments P. 10 Children’s wear Critical Area Comments P. 11
Packaging and Labeling P. 11-12
Additional Comments P. 12 Production Sample
P. 12
Final Inspection
P. 12
Signature
P. 12
INTRODUCTION
This manual has been produced as a clear point of reference for our Tesco PT and suppliers in order to create a uniform pre-production meetings process across the whole supply base.
All Tesco products must now undergo a pre production meeting conducted by Tesco PT team .This applies to initial orders only.
The information in this manual is very comprehensive but it is not definitive and is subject to change.
Suppliers are responsible for their own quality standards. Suppliers must perform their own in house pre production meetings. It is the main responsibility of the supplier to ensure product quality conforms to Tesco requirements
If you have any queries on the contents of this manual please contact your relevant PT or TM.
Arranging Meeting
It is the responsibility of the Tesco PT technologist to contact the supplier and arrange the location, date and time for the pre production meeting
The meeting should be held at one of the following locations – these are listed in order of preference:-
•At suppliers factory
•At suppliers office
•At Tesco office
Ideally all meetings should take place approximately 2 weeks after approval of Red Seal sample. However, if this is not possible then a more appropriate date should be agreed between the Tesco PT technologist and supplier.
Attendees
People to be present at meeting are:-
•Relevant Tesco PT and (if possible) TM
•Relevant Tesco merchandiser
•Supplier merchandiser
•Supplier QA technologist
•Supplier QC
Meeting Requirements
Each meeting attendee should bring with them the following information:- •Relevant Tesco PT
Blank meeting minutes and any updated information since approval of Red Seal sample Tesco PT must complete all basic information on the minutes prior to meeting:- Meeting date, style number, etc.
•Relevant Tesco merchandiser
Product File, including:-
o Approved lab dips,
o Approved base fabric hanger and test report
o Contract
o Size and quality breakdown
o Wash panel
o Approved WEB PDM paperwork inc. size chart and approval comments
o Approved trims
o Any buyer and supplier critical comments
•Supplier merchandiser
Approved Red Seal sample or reference sample
Trim Cards
Production schedule
Lead time information for fabric, trims etc.
Any outstanding submissions for approval e.g. Wash panels etc •Supplier technologist
Any technical information required e.g. patterns, print position information etc.
•Supplier QC