拜耳异氰酸酯和聚醚项目MDI联合装置罐区储罐防腐施工技术措施
- 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
- 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
- 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。
目录
CONTENTS
1.0适用范围 (1)
1.0SCOPE (1)
2.0工程概况 (1)
2.0 GENERAL (1)
3.0编制依据 (2)
3.0 REFERENCES (2)
4.0施工和检测程序 (3)
4.0APPLICATION OF CONSTRUCTION AND TEST (3)
5.0施工前准备 (3)
5.0PREPARATION FOR CONSTRUCTION (3)
6.0抛丸(喷砂)及喷涂作业 (8)
6.0SHOTBLASTING(SAND BLASTING) AND SPRAYING (8)
7.0检查与验收 (25)
7.0 INSPECTION AND ACCEPTANCE (25)
8.0 作业环境要求 (26)
8.0 WORKING CONDITIONS (26)
9.0产品的标识与防护 (27)
9.0 SIGNS AND PROTECTION OF THE PRUDUCT (27)
10.0 HSE管理 (27)
10.0 HSE MANAGEMENT (27)
11.0附件 (28)
11.0 ACCESSORIES (28)
1.0 适用范围SCOPE
本专业方案适用于拜耳异氰酸酯和聚醚项目MDI联合装置罐区设备(V911、V912、V913)防腐油漆工程施工。This scheme is for the anti-corrosive painting engineering of the pipeline of Bayer Isocyanate & PET Project MDI Train-Tank Farm(V911,V912,V913).
2.0 工程概况GENERAL
该项目罐防腐为3号系统(system 3),分底漆,中间漆和面漆三层涂装,不锈钢(保温)罐为4号系统(system 4),分环氧清漆、面漆三层涂装,涂层总干膜厚度不低于200微米。This project, Bayer Isocyanate & PET Project MDI Train-Tank Farm has nineteen carbon steel tanks and six stainless steel tanks to be
antisepsis. The soleplates of carbon steel should be carried to the anti-corrosive place to do blast cleaning and painting (the components that can’t be derusted by the abrator should be derusted by blasting copper ore). Carry it to the construction scene after primary coat finished. Then, barrior paint and finish coat shall be covered when pressure has been tested and qualified(carbon steel tanks below 120℃). Below 120℃, the carbon steel tanks with derusting rating Sa2.5 is System 3. It should be covered with three coats including primary coat, barrior paint and finish coat. The epoxy zinc-rich primer should be thick 80 polyurethane finish coat60 thick. The dry coating should be 240 Stainless steel tanks below 120℃ is System 4. They should be covered with three coats. They are epoxy varnish, polyurethane finish coat.
3.0 编制依据PREFERENCES
3.1拜耳规定CSA0056-Corrosion Protection
Bayer Regulation CSA0056-Corrosion Protection
3.2拜耳规定BISS-ES-50-001
Bayer Regulation BISS-ES-50-001
3.3 工程设计图纸Figures of the Project Design
3.4 DIN EN ISO12944
3.5“油漆工程规定”(中国石化集团南京设计院)Regulations of the Painting
Projects(Sinopec Nanjing Design Institute)
4.0 施工和检验程序Application of the Construction and Test
4.2贮罐施工检验程序Application of Testing Tanks Construction
4.2.1预制厂施工程序Application of the Prefabricate Plant
施工前的准备贮罐底板和基础涂装前表面处理与检查底漆喷涂
底漆检查与验收中间漆喷涂与验收面漆喷涂检查验收Preparation before application, removing the identifications →disposing and testing the surface before coating →checking and acceptance of primary coat→checking and acceptance of barrior paint→painting finish coat →checking and affirmance