北京企业电动汽车充电桩申请用电的报装流程
下载温馨提示:该文档是我店铺精心编制而成,希望大家下载以后,能够帮助大家解决实际的问题。

文档下载后可定制随意修改,请根据实际需要进行相应的调整和使用,谢谢!
并且,本店铺为大家提供各种各样类型的实用资料,如教育随笔、日记赏析、句子摘抄、古诗大全、经典美文、话题作文、工作总结、词语解析、文案摘录、其他资料等等,如想了解不同资料格式和写法,敬请关注!
Download tips: This document is carefully compiled by theeditor. I hope that after you download them,they can help yousolve practical problems. The document can be customized andmodified after downloading,please adjust and use it according toactual needs, thank you!
In addition, our shop provides you with various types ofpractical materials,such as educational essays, diaryappreciation,sentence excerpts,ancient poems,classic articles,topic composition,work summary,word parsing,copy excerpts,other materials and so on,want to know different data formats andwriting methods,please pay attention!
1. 准备材料
在申请北京企业电动汽车充电桩用电报装之前,需要准备以下材料:
- 企业营业执照副本原件及复印件;
- 企业法定代表人身份证原件及复印件;
- 充电桩项目批准文件;
- 充电桩设备清单及技术参数;
- 用电负荷计算书及用电方案设计;
- 用电申请人身份证原件及复印件;
- 若有租赁场地,需提供租赁合同及出租方身份证明。

2. 提交申请
携带准备好的材料,前往所在地区的电力营业厅或通过网上电力营业厅提交电动汽车充电桩用电报装申请。

填写《电力用户用电申请表》,并提供相关材料。

3. 供电方案答复
电力公司收到申请后,将在5个工作日内对用电申请进行审核。

若审核通过,电力公司将提供供电方案,包括供电电压、容量、线路等,并答复申请人。

4. 签订供电合同
申请人应在收到供电方案后5个工作日内与电力公司签订《电力供应合同》。

合同签订后,电力公司将安排施工。

5. 施工及验收
申请人应按照供电方案要求进行充电桩的施工。

施工完成后,申请人需向电力公司申请验收。

电力公司将安排工作人员对充电桩进行验收,验收合格后,充电桩方可投入使用。

6. 办理用电手续
在验收合格后,申请人还需要办理一些用电手续,如办理电表安装、开通用电等。

电力公司将根据申请人提供的信息进行办理。

注意事项:
1. 申请人应对充电桩设备的安全、质量、合规性负责,确保设备符合国家相关标准和要求。

2. 申请人应按照电力公司的供电方案进行施工,不得擅自更改供电电压、容量等参数。

3. 充电桩施工验收合格后,申请人应及时办理用电手续,确保充电桩正常投入使用。

4. 在办理过程中,申请人应保证提供的材料真实、完整、有效,如有虚假信息,将承担相应法律责任。

5. 若申请人对办理进度或结果有疑问,可随时向电力公司咨询,电力公司将及时解答。