不可抗力条款示例

合集下载
  1. 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
  2. 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
  3. 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。

1. Force Majeure

1.1 Force Majeure Event only means any of the following events:

a) acts of God, flood, drought, earthquake or other catastrophic natural disaster

(but excluding adverse weather conditions);

b) epidemic or pandemic;

c) terrorist attack, civil war, civil commotion or riots, war, threat of or preparation

for war, armed conflict, imposition of sanctions, embargo, or breaking off of

diplomatic relations;

d) nuclear, chemical or biological contamination or sonic boom;

e) fire or explosion;

f) any labour or trade dispute, strikes, industrial action or lockouts (other than in

each case by the party seeking to rely on this clause, including its

subcontractors or suppliers); or

g) Interruption or failure of major utility services (other than in each case where

the interruption or failure is caused by the party seeking to reply on this cause

including its subcontractors or suppliers).

[Any Force Majeure event shall be evidenced by the relevant authority of the

country where the relevant event occurs.]

1.2 Provided it has complied with clause 1.4, if a party is prevented from performing

any of its obligations under this contract by a Force Majeure Event (Affected

Party), the Affected Party shall not be deemed in breach of this contract or

otherwise liable for any such failure or delay in the performance of such

obligations.

1.3 The corresponding obligations of the other party will be suspended, and its time

for performance of such obligations extended, to the same extent as those of

the Affected Party.

1.4 The Affected Party shall:

a) as soon as reasonably practicable after the start of the Force Majeure

Event [but no later than [NUMBER] days from its start], notify the other

party in writing of the Force Majeure Event, the date on which it started,

its likely or potential duration, and the effect of the Force Majeure Event

on its ability to perform any of its obligations under the contract; and

b) use all reasonable endeavours to mitigate the effect of the Force

Majeure Event on the performance of its obligations.

1.5 Once the Force Majeure Event ceases to exist, the Affected Party must as soon

as reasonably practicable resume the performance of its obligations under this

contract. Where the Affected Party is the contractor, the contractor must

provide a revised programme rescheduling the works to minimise the effects of

the prevention or delay caused by the Force Majeure Event.

1.6 A Force Majeure Event does not relieve a party from the liability for an

obligation which arose before the occurrence of that event.

1.7 The contractor has no entitlement and the employer has no liability for any

extension of time or costs in any way incurred by the contractor due to a Force

Majeure Event.

1.8 If the Force Majeure Event prevents the Affected Party's performance of its

obligations for a continuous period of more than [NUMBER] [weeks], the party

not affected by the Force Majeure Event may terminate this contract by giving

[NUMBER] [weeks'] written notice to the Affected Party.

相关文档
最新文档