地铁隧道工程建设承包合同(中英文)
- 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
- 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
- 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。
地铁隧道工程建设承包合同
CONSTRUCTION CONTRACT OF SUBWAY TUNNEL
签约日期:Signature Date of
本合同系中译英翻译:张云军
Translated from Chinese to English
by Mr. Chang Yunejune.
发包人:城市轨道交通(集团)有限公司 Employer: City Railway (Group)., Ltd.
承包人:隧道工程建设有限公司 Contractor: Tunnel Construction Limited Company
鉴于:轨道交通(集团)有限公司(以下简称:发包人)为实施轨道交通六号线隧道土建工程(项目名称),已接受隧道工程建设有限公司(以下简称:承包人)对该项目施工的投标;
鉴于:承包方是具有隧道土建工程资质和技术能力的专业工程公司,愿意接受发包方提出的招标条件并中标;
发包人和承包人依照招标文件共同达成如下协议。
Whereas: City Railway (Group)., Ltd. ( hereinafter referred to as employer), in the expectation of construction of tunnel earthwork for No. 6 railway traffic, has accept the bid of Contractor: Tunnel Construction Limited Company (hereinafter referred to as contractor ).
Whereas: Contractor is a professional engineering company with the quality and technical ability of tunnel civil engineering, willing to accept the bidding conditions which are issued by employer and win the bid;
NOW, THEREFORE, Parties of employer and contractor hereby, in accordance with bidding documents, enter into following agreement:
第一部分协议书 Part One Agreement
1.本协议书与下列文件一起构成合同文件:
Contract documentation is constituted by this agreement and following documents: (1)中标通知书;Notice of Acceptance
(2)投标函及投标函附录;Bid letter and Appendix therewith
(3)专用合同条款及通用合同条款Particular provision and general provision
(4)技术标准和要求及图纸;Technical standard, requirement and drawing
(5)已标价工程量清单;Priced list of project amount
(8)其他合同文件。Other contract documentation
2. 上述文件互相补充和解释,如有不明确或不一致之处,以合同约定次序在先者为准。The documents above should be taken as mutually complementary and explanatory
of one another. In the event of any indefinite, vague or inconsistency among them, the order in front by contract agreement will be prevail.
3. 签约合同价: Contracted price
4. 承包人承诺按合同约定承担工程的实施、完成及缺陷修复。
Contractor promise to undertake pursuant to the stipulation of contract the implement, complement and defect repair of project.
5. 发包人承诺按合同约定的条件、时间和方式向承包人支付合同价款。
Employer promise to effect payment of contracted price pursuant to the conditions, time and ways which stipulated in contract.
6. 承包人应按照监理人指示开工,工期为595日历天。
Contractor should make commencement subject to supervisor’s order. Work’s period is 595 calendar days.
7. 本协议书一式壹拾伍份,合同双方各执柒份,公证机关壹份。
This agreement in made fifteen original copies, each party hold seven copies and notarization authority hold one copy.
8. 合同未尽事宜,双方另行签订补充协议。补充协议是合同的组成部分。Outstanding issues herein will be with supplementary agreement by parties separately. Supplementary agreement is the integral part of contract.
第二部分专用合同条款 Part Two Particular Provision
1.一般约定 General Provision
1.1.工程和设备 Project and Equipment
永久工程:隧道工程(包括局部路基段、区间)、隧道入洞口区间工程、出入段线工程以及施工进出场道路的拓宽和施工用水、电的安装等辅助工程。
Permanent Works: tunnel engineering including local roadbed, interval zones, the interval zones of tunnel entrance, entry section, road expanding to construction site, and auxiliary projects such as installation of water, power for work, and so on.
临时工程:隧道、高架区间、路基工程及出入段线的主体工程及附属工程,以及实施以上工程必须的施工进出场道路的拓宽和施工用水、电的安装等临时工程。Temporary Projects: Tunnel, elevated section, roadbed, main project and auxiliary project for in and out of section / line, and road expanding to construction site, and temporary projects such as installation of water, power , which are necessary for Work implementation, and so on.
1.1.2 缺陷责任期:结构工程两年,防水工程五年。
Defect Liability Period: Two years for structure project and five years for water proof project.
1.2 合同生效的条件 Effective Condition
合同生效的条件:经双方法定代表人或委托代理人签字盖章且承包人提供合同总价款12%的履约担保后生效。
Effective condition: This contract will come into force and effect upon the signature and seal by legal representatives of parties or authorized agent in addition to Performance Guarantee issued by contractor, of 12% of total contract price.